Valuation Valuation Date Date Issued
Task Order
Address
Valuation
Difference
68
16/06/2014
24/06/2014 Task Order South 3-3E PETERS PATH 17 - 30
£ 2 3,012.39 £ -
74
15/09/2014
24/09/2014 Task Order South 3-3E PETERS PATH 17 - 30
£ 4 6,329.58 £ 2
3,317.19
75
06/10/2014
14/10/2014 Task Order South 3-3E PETERS PATH 17 - 30
£ 5 9,926.53 £ 1
3,596.95
77
03/11/2014
11/11/2014 Task Order South 3-3E PETERS PATH 17 - 30
£ 6 8,841.68 £ 8,915.15
78
17/11/2014
28/11/2014 Task Order South 3-3E PETERS PATH 17 - 30
£ 1 28,828.16 £ 5
9,986.48
79
01/12/2014
09/12/2014 Task Order South 3-3E PETERS PATH 17 - 30
£ 1 10,493.69 -£ 1
8,334.47
80
12/12/2014
22/12/2014 Task Order South 3-3E PETERS PATH 17 - 30
£ 1 10,534.27 £ 4
0.58
81
16/01/2015
27/01/2015 Task Order South 3-3E PETERS PATH 17 - 30
£ 1 18,578.03 £ 8,043.75
82
30/01/2015
09/02/2015 Task Order South 3-3E PETERS PATH 17 - 30
£ 1 19,616.59 £ 1,038.56
83
13/02/2015
20/02/2015 Task Order South 3-3E PETERS PATH 17 - 30
£ 1 35,145.28 £ 1
5,528.69
84
06/03/2015
16/03/2015 Task Order South 3-3E PETERS PATH 17 - 30
£ 1 44,163.73 £ 9,018.45
85
20/03/2015
26/03/2015 Task Order South 3-3E PETERS PATH 17 - 30
£ 1 61,499.08 £ 1
7,335.35
86
31/03/2015
07/04/2015 Task Order South 3-3E PETERS PATH 17 - 30
£ 1 62,323.82 £ 824.73
88
01/05/2015
08/05/2015 Task Order South 3-3E PETERS PATH 17 - 30
£ 1 64,488.27 £ 2,164.45
92
22/07/2015
24/07/2015 Task Order South 3-3E PETERS PATH 17 - 30
£ 1 67,343.12 £ 2,854.85
101
08/12/2015
15/12/2015 Task Order South 3-3E PETERS PATH 17 - 30
£ 1 57,195.05 -£ 1
0,148.07
106
26/02/2016
11/03/2016 Task Order South 3-3E PETERS PATH 17 - 30
£ 1 57,563.60 £ 368.55
112
31/05/2016
20/06/2016 Task Order South 3-3E PETERS PATH 17 - 30
£ 1 60,195.64 £ 2,632.04
142
17/07/2017
20/07/2017 Task Order South 3-3E PETERS PATH 17 - 30
£ 1 60,195.64 £ -
Valuation Valuation Date Date Issued
Task Order
Address
Valuation
68
16/06/2014
24/06/2014 Task Order South 3-3E PETERS PATH 17 - 30
£ 2 3,012.39
68
16/06/2014
24/06/2014 Task Order South 3-3E PETERS PATH 45 - 58
£ 2 2,375.18
68
16/06/2014
24/06/2014 Task Order South 3-3E PETERS PATH 59 - 72
£ 1 6,426.29
Total:
£ 61,813.85
Less Previously Certified:
£ 201.60
Amount Due in Valuation:
£ 61,612.25
74
15/09/2014
24/09/2014 Task Order South 3-3E PETERS PATH 1 - 16
£ 5 8,248.85
74
15/09/2014
24/09/2014 Task Order South 3-3E PETERS PATH 17 - 30
£ 4 6,329.58
74
15/09/2014
24/09/2014 Task Order South 3-3E PETERS PATH 31 - 44
£ 2 9,876.20
74
15/09/2014
24/09/2014 Task Order South 3-3E PETERS PATH 45 - 58
£ 7 5,337.93
74
15/09/2014
24/09/2014 Task Order South 3-3E PETERS PATH 59 - 72
£ 4 9,500.06
Total:
£ 259,292.63
Less Previously Certified:
£ 174,471.86
Amount Due in Valuation:
£ 84,820.77
75
06/10/2014
14/10/2014 Task Order South 3-3E PETERS PATH 1 - 16
£ 7 5,031.40
75
06/10/2014
14/10/2014 Task Order South 3-3E PETERS PATH 17 - 30
£ 5 9,926.53
75
06/10/2014
14/10/2014 Task Order South 3-3E PETERS PATH 31 - 44
£ 7 3,195.00
75
06/10/2014
14/10/2014 Task Order South 3-3E PETERS PATH 45 - 58
£ 7 9,070.11
75
06/10/2014
14/10/2014 Task Order South 3-3E PETERS PATH 59 - 72
£ 5 0,120.04
Total:
£ 337,343.08
Less Previously Certified:
£ 259,292.63
Amount Due in Valuation:
£ 78,050.45
77
03/11/2014
11/11/2014 Task Order South 3-3E PETERS PATH 1 - 16
£ 8 0,507.14
77
03/11/2014
11/11/2014 Task Order South 3-3E PETERS PATH 17 - 30
£ 6 8,841.68
77
03/11/2014
11/11/2014 Task Order South 3-3E PETERS PATH 31 - 44
£ 7 4,370.62
77
03/11/2014
11/11/2014 Task Order South 3-3E PETERS PATH 45 - 58
£ 8 0,386.19
77
03/11/2014
11/11/2014 Task Order South 3-3E PETERS PATH 59 - 72
£ 4 9,986.89
Total:
£ 354,092.52
Less Previously Certified:
£ 337,343.08
Amount Due in Valuation:
£ 16,749.44
78
17/11/2014
28/11/2014 Task Order South 3-3E PETERS PATH 1 - 16
£ 1 43,989.79
78
17/11/2014
28/11/2014 Task Order South 3-3E PETERS PATH 17 - 30
£ 1 28,828.16
78
17/11/2014
28/11/2014 Task Order South 3-3E PETERS PATH 31 - 44
£ 1 29,462.77
78
17/11/2014
28/11/2014 Task Order South 3-3E PETERS PATH 45 - 58
£ 1 36,456.03
78
17/11/2014
28/11/2014 Task Order South 3-3E PETERS PATH 59 - 72
£ 6 9,219.57
Total:
£ 607,956.32
Less Previously Certified:
£ 354,092.52
Amount Due in Valuation:
£ 253,863.80
79
01/12/2014
09/12/2014 Task Order South 3-3E PETERS PATH 1 - 16
£ 1 24,401.21
79
01/12/2014
09/12/2014 Task Order South 3-3E PETERS PATH 17 - 30
£ 1 10,493.69
79
01/12/2014
09/12/2014 Task Order South 3-3E PETERS PATH 31 - 44
£ 1 21,072.96
79
01/12/2014
09/12/2014 Task Order South 3-3E PETERS PATH 45 - 58
£ 1 30,315.13
79
01/12/2014
09/12/2014 Task Order South 3-3E PETERS PATH 59 - 72
£ 6 6,646.34
Total:
£ 552,929.34
Less Previously Certified:
£ 607,956.32
Amount Due in Valuation:
-£ 55,026.98
80
12/12/2014
22/12/2014 Task Order South 3-3E PETERS PATH 1 - 16
£ 1 25,603.50
80
12/12/2014
22/12/2014 Task Order South 3-3E PETERS PATH 17 - 30
£ 1 10,534.27
80
12/12/2014
22/12/2014 Task Order South 3-3E PETERS PATH 31 - 44
£ 1 21,129.33
80
12/12/2014
22/12/2014 Task Order South 3-3E PETERS PATH 45 - 58
£ 1 30,315.13
80
12/12/2014
22/12/2014 Task Order South 3-3E PETERS PATH 59 - 72
£ 6 6,646.34
Total:
£ 554,228.57
Less Previously Certified:
£ 552,929.34
Amount Due in Valuation:
£ 1,299.23
Valuation Valuation Date Date Issued
Task Order
Address
Valuation
81
16/01/2015
27/01/2015 Task Order South 3-3E PETERS PATH 1 - 16
£ 1 35,824.74
81
16/01/2015
27/01/2015 Task Order South 3-3E PETERS PATH 17 - 30
£ 1 18,578.03
81
16/01/2015
27/01/2015 Task Order South 3-3E PETERS PATH 31 - 44
£ 1 32,580.41
81
16/01/2015
27/01/2015 Task Order South 3-3E PETERS PATH 45 - 58
£ 1 45,072.95
81
16/01/2015
27/01/2015 Task Order South 3-3E PETERS PATH 59 - 72
£ 7 4,499.24
Total:
£ 606,555.36
Less Previously Certified:
£ 552,929.34
Amount Due in Valuation:
£ 53,626.02
82
30/01/2015
09/02/2015 Task Order South 3-3E PETERS PATH 1 - 16
£ 1 45,974.22
82
30/01/2015
09/02/2015 Task Order South 3-3E PETERS PATH 17 - 30
£ 1 19,616.59
82
30/01/2015
09/02/2015 Task Order South 3-3E PETERS PATH 31 - 44
£ 1 33,974.07
82
30/01/2015
09/02/2015 Task Order South 3-3E PETERS PATH 45 - 58
£ 1 47,801.20
82
30/01/2015
09/02/2015 Task Order South 3-3E PETERS PATH 59 - 72
£ 8 7,970.94
Total:
£ 635,337.02
Less Previously Certified:
£ 606,555.36
Amount Due in Valuation:
£ 28,781.66
83
13/02/2015
20/02/2015 Task Order South 3-3E PETERS PATH 1 - 16
£ 1 55,268.12
83
13/02/2015
20/02/2015 Task Order South 3-3E PETERS PATH 17 - 30
£ 1 35,145.28
83
13/02/2015
20/02/2015 Task Order South 3-3E PETERS PATH 31 - 44
£ 1 53,282.14
83
13/02/2015
20/02/2015 Task Order South 3-3E PETERS PATH 45 - 58
£ 1 68,086.92
83
13/02/2015
20/02/2015 Task Order South 3-3E PETERS PATH 59 - 72
£ 9 2,285.99
Total:
£ 704,068.45
Less Previously Certified:
£ 635,337.02
Amount Due in Valuation:
£ 68,731.43
84
06/03/2015
16/03/2015 Task Order South 3-3E PETERS PATH 1 - 16
£ 1 69,027.99
84
06/03/2015
16/03/2015 Task Order South 3-3E PETERS PATH 17 - 30
£ 1 44,163.73
84
06/03/2015
16/03/2015 Task Order South 3-3E PETERS PATH 31 - 44
£ 1 61,179.26
84
06/03/2015
16/03/2015 Task Order South 3-3E PETERS PATH 45 - 58
£ 1 66,961.11
84
06/03/2015
16/03/2015 Task Order South 3-3E PETERS PATH 59 - 72
£ 9 1,190.66
Total:
£ 732,522.75
Less Previously Certified:
£ 704,068.45
Amount Due in Valuation:
£ 28,454.30
85
20/03/2015
26/03/2015 Task Order South 3-3E PETERS PATH 1 - 16
£ 1 88,054.06
85
20/03/2015
26/03/2015 Task Order South 3-3E PETERS PATH 17 - 30
£ 1 61,499.08
85
20/03/2015
26/03/2015 Task Order South 3-3E PETERS PATH 31 - 44
£ 1 79,840.80
85
20/03/2015
26/03/2015 Task Order South 3-3E PETERS PATH 45 - 58
£ 1 83,909.45
85
20/03/2015
26/03/2015 Task Order South 3-3E PETERS PATH 59 - 72
£ 9 7,275.13
Total:
£ 810,578.54
Less Previously Certified:
£ 732,522.75
Amount Due in Valuation:
£ 78,055.78
86
31/03/2015
07/04/2015 Task Order South 3-3E PETERS PATH 1 - 16
£ 1 89,918.61
86
31/03/2015
07/04/2015 Task Order South 3-3E PETERS PATH 17 - 30
£ 1 62,323.82
86
31/03/2015
07/04/2015 Task Order South 3-3E PETERS PATH 31 - 44
£ 1 82,844.14
86
31/03/2015
07/04/2015 Task Order South 3-3E PETERS PATH 45 - 58
£ 1 86,198.31
86
31/03/2015
07/04/2015 Task Order South 3-3E PETERS PATH 59 - 72
£ 9 9,006.79
Total:
£ 820,291.66
Less Previously Certified:
£ 810,578.54
Amount Due in Valuation:
£ 9,713.13
Valuation Valuation Date Date Issued
Task Order
Address
Valuation
88
01/05/2015
08/05/2015 Task Order South 3-3E PETERS PATH 1 - 16
£ 1 96,413.98
88
01/05/2015
08/05/2015 Task Order South 3-3E PETERS PATH 17 - 30
£ 1 64,488.27
88
01/05/2015
08/05/2015 Task Order South 3-3E PETERS PATH 31 - 44
£ 1 82,844.14
88
01/05/2015
08/05/2015 Task Order South 3-3E PETERS PATH 45 - 58
£ 1 86,198.31
88
01/05/2015
08/05/2015 Task Order South 3-3E PETERS PATH 59 - 72
£ 1 00,376.94
Total:
£ 830,321.63
Less Previously Certified:
£ 820,291.66
Amount Due in Valuation:
£ 10,029.97
92
22/07/2015
24/07/2015 Task Order South 3-3E PETERS PATH 1 - 16
£ 1 97,060.39
92
22/07/2015
24/07/2015 Task Order South 3-3E PETERS PATH 17 - 30
£ 1 67,343.12
92
22/07/2015
24/07/2015 Task Order South 3-3E PETERS PATH 31 - 44
£ 1 85,666.05
92
22/07/2015
24/07/2015 Task Order South 3-3E PETERS PATH 45 - 58
£ 1 87,941.16
92
22/07/2015
24/07/2015 Task Order South 3-3E PETERS PATH 59 - 72
£ 1 02,420.66
Total:
£ 840,431.38
Less Previously Certified:
£ 830,321.63
Amount Due in Valuation:
£ 10,109.74
101
08/12/2015
15/12/2015 Task Order South 3-3E PETERS PATH 1 - 16
£ 1 87,705.17
101
08/12/2015
15/12/2015 Task Order South 3-3E PETERS PATH 17 - 30
£ 1 57,195.05
101
08/12/2015
15/12/2015 Task Order South 3-3E PETERS PATH 31 - 44
£ 1 72,548.50
101
08/12/2015
15/12/2015 Task Order South 3-3E PETERS PATH 45 - 58
£ 1 71,941.28
101
08/12/2015
15/12/2015 Task Order South 3-3E PETERS PATH 59 - 72
£ 1 03,043.39
Total:
£ 792,433.39
Less Previously Certified:
£ 840,431.38
Amount Due in Valuation:
-£ 47,997.99
106
26/02/2016
11/03/2016 Task Order South 3-3E PETERS PATH 1 - 16
£ 1 88,163.75
106
26/02/2016
11/03/2016 Task Order South 3-3E PETERS PATH 17 - 30
£ 1 57,563.60
106
26/02/2016
11/03/2016 Task Order South 3-3E PETERS PATH 31 - 44
£ 1 72,952.19
106
26/02/2016
11/03/2016 Task Order South 3-3E PETERS PATH 45 - 58
£ 1 72,295.29
106
26/02/2016
11/03/2016 Task Order South 3-3E PETERS PATH 59 - 72
£ 1 03,330.86
Total:
£ 794,305.69
Less Previously Certified:
£ 792,433.39
Amount Due in Valuation:
£ 1,872.30
112
31/05/2016
20/06/2016 Task Order South 3-3E PETERS PATH 1 - 16
£ 1 89,694.08
112
31/05/2016
20/06/2016 Task Order South 3-3E PETERS PATH 17 - 30
£ 1 60,195.64
112
31/05/2016
20/06/2016 Task Order South 3-3E PETERS PATH 31 - 44
£ 1 72,952.19
112
31/05/2016
20/06/2016 Task Order South 3-3E PETERS PATH 45 - 58
£ 1 72,295.29
112
31/05/2016
20/06/2016 Task Order South 3-3E PETERS PATH 59 - 72
£ 1 03,740.36
Total:
£ 798,877.56
Less Previously Certified:
£ 794,715.19
Amount Due in Valuation:
£ 4,162.37
142
17/07/2017
20/07/2017 Task Order South 3-3E PETERS PATH 1 - 16
£ 189,694.08
142
17/07/2017
20/07/2017 Task Order South 3-3E PETERS PATH 17 - 30
£ 160,195.64
142
17/07/2017
20/07/2017 Task Order South 3-3E PETERS PATH 31 - 44
£ 172,952.19
142
17/07/2017
20/07/2017 Task Order South 3-3E PETERS PATH 45 - 58
£ 172,295.29
142
17/07/2017
20/07/2017 Task Order South 3-3E PETERS PATH 59 - 72
£ 103,740.36
Total:
£ 798,877.56
Less Previously Certified:
£ 798,877.56
Amount Due in Valuation:
£ -