WML-A14-E6A&E6b – WORK SCHEDULE FOR GREAT CRESTED NEWT  
ANNEXED LICENCES 
 
 
Site name and address (as stated on the application form or licence granted):  Thingley Bridge 
 
E6 Work schedule for all new applications from end of April 2013:  
Please ensure that this work schedule is S.M.A.R.T and appropriate timescales 
are provided for each activity, to fit with order of events. 
 
Mandatory  for  all  projects.
  Complete  these  schedules  to  show  timings  for  all  major  categories  of  work  (mitigation  and  compensation  measures),  and  to 
show the main construction period. The most common activities are listed here, and you can add up to 6 more if needed. Leave blank if not applicable. Enter 
timing  by  stating  start  and  end  dates,  to  nearest  month  and  year  (see  first  line  for  example).  Enter  comments  if  you  need  to  clarify  timings.  For  very 
complex schemes (e.g. high impact or phased development schemes) if additional lines are needed please do add in. This work schedule will form part of any 
annexed licence. 
 
PLEASE INCLUDE DATE OF SUBMISSION (e.g. 1 April 2013).  
This will be referenced in the licence  
 23 July 2014 
A) Pre-development and mid-development 
Activity 
Timing 
Comments 
Example: Receptor site pond creation 
Nov-12 to Dec-12 
Also plant pond up with native 
species in January 2013 

Receptor site pond creation 
            
            
Receptor site pond enhancement or restoration 
            
            
Receptor site terrestrial hab works - general e.g. reseeding, hedge planting 
            
            
Receptor site terrestrial hab works - features e.g. hibernacula, refuges 
 Aug 2014-Sept 2014 
 Coincides with exc fence 
installation 
Construction of permanent fences/walls 
            
            
Construction of underpass/tunnel/culvert (and installation of 'guide' fencing) 
            
            
Newt fence installation (to include drift or ring fencing if applicable – specify 
 Aug 2014-Sept 2014 
            
WML-A14a-E6A&E6B (vs. October 2013) 
Page 1 
 

which) 
Newt capture (pitfall trapping etc - outside hibernation/dormancy periods only) 
 Aug 2014-Oct 2014 
            
Pond draining and pond destruction (please indicate when each will occur) 
            
            
Hand searches 
 Aug 2014-Oct 2014 
            
Destructive searches (following completion of all other capture efforts) 
 Sept 2014-Nov 2014 
 Only into the beginning of Nov if 
conditions are suitable 
Construction period (start and end dates) 
 Oct 2014 - Aug 2015 
 Following completion of trapping 
and destructive searches 
Site checks & maintenance during construction 
 Oct 2014-Aug 2015 
 Weekly checks during 
construction period 
Drift fence removal (not to be undertaken during hibernation/dormancy periods) 
            
            
Newt fence removal (not to be undertaken during hibernation/dormancy periods)   Mar 2015-Aug 2015 
 Following completion of all site 
works during spring/summer 
Ring fence removal (not to be undertaken during the hibernation/dormancy 
            
            
periods) 
Habitat reinstatement (for temporary impact schemes only) 
Mar 2015-Aug 2015 
Following completion of 
construction activities 
Post construction mitigation/compensation on dev't site or other (provide details)               
            
            
            
            
            
            
            
            
            
            
            
            
            
           
           
           
           
           
           
  
 
 
B) Post-development works - type a "Y" where each activity will occur for a given year and leave blank for no activity.  
Year: 
2014 
2015 
2016 
2017 
2018 
2019 
2020 
2021 
2022 
2023 
2024 
2025 
Population monitoring 
            
            
            
            
            
            
            
            
            
            
                         
Habitat management  
            
            
            
            
            
            
            
            
            
            
                         
Site maintenance 
            
            
            
            
            
            
            
            
            
            
                         
 
WML-A14a-E6A&E6B (vs. October 2013) 
Page 2