Full Council meeting 6 November 2015: Norwich Northern Distributor Road 
Responses to details/questions submitted ahead of the meeting 
Wensum Valley Alliance letters received via email on 4 and 5 November 2015 to all 
Members 
 
1.0 
Stopping at the A140 
1.1 
The points raised under the heading of ‘Financial Exposure to the Council’ are 
assuming that the Development Consent Order (DCO) can be amended 
within a reasonable timescale.  The Wensum Valley Alliance suggests that 
changes brought about by the Infrastructure Act 2015 make material 
amendments “much simpler, cheaper and more efficient” and that the Council 
has not “seriously investigated this possibility”. 
1.2 
This issue is discussed in paragraph 4.1(c) within the 6 November Full 
Council report.  The merits of constructing a road scheme from the A47(T) at 
Postwick to the A140 at Norwich International Airport were also considered in 
the Examination in Public process, completed during 2014, that culminated in 
the making of the DCO. The Examining Authority considered this option at 
length in their report (in particular at paragraphs 4.20, 4.146 to 4.158, 4.179, 
4.495, 6.34 to 6.36, 6.246 to 6.254, and 8.3).  
 
The Examining Authority rejected this option (and the other alternatives that 
were considered), and reached the overall conclusion that “there are no 
reasonable practicable alternatives that would achieve the objectives sought” 
(paragraph 8.3).  
 
The Secretary of State for Transport accepted this conclusion (paragraph 14 
of the DCO decision).   
1.3 
The County Council has looked into the recent legislative changes and taken 
legal advice on the practical implications of them. The position is that the new 
Infrastructure Act 2015 (and associated amending regulations) does not 
substantially change existing provisions. 
 
Stopping at the A140 would constitute a ‘material change’ to the DCO, and 
due to the different environmental, traffic and land impacts, the timescales 
and process required under the legislation (as amended) could be very similar 
to that for the original (or a new) NDR application.  
1.4 
The County Council would need to carry out further design and assessment 
work, consult on the proposals and consider the consultation responses, 
before submitting an application to change the DCO, then enter the 
acceptance, pre-examination and examination periods. Whilst potentially the 
Secretary of State can decide to omit the examination stage, this cannot be 
decided in advance and is not something the Council can rely on. In any 
sensible project planning it would not be reasonable to assume this step could 
be omitted. In a realistic scenario this process would take approximately two 
years to complete (but it could be considerably longer), not allowing for any 

 

subsequent legal challenge.  This would result in an earliest start date for the 
NDR of Autumn 2018, with completion around autumn 2020. 
1.5 
Cabinet carefully considered the option to stop the project at the A140. Details 
were provided in a report on 2 April 2012.  A link to this report is provided in 
the Full Council (6 November) report. 
  
 
The report raised a specific question for Cabinet about whether to stop the 
NDR at the A140 or continue to the A1067, and, further questions were raised 
about whether the A140 to A1067 section should be single or dual 
carriageway.  The minutes of the meeting (a link to these is also provided in 
the 6 November report
) captured the decision of Cabinet, which was: 

to submit a planning application for the NDR to the A1067 

to progress a dual carriageway NDR between the A140 and A1067 as 
part of the planning submission 

to deliver the construction of the NDR as a single project to A1067 
 
2.0 
Funding the NDR 
2.1 
The further financial exposure that the County Council directly faces to deliver 
the NDR is summarised below.   
Funding Source 
Total Contribution 
DfT (including additional £10m 
£96.49m 
and £19m towards Postwick Hub) 
Community Infrastructure Levy 
£40.00m 
(underwritten by NCC but 
supported by legal agreement with 
GNGB authorities) 
NCC (direct funding contribution 
£30.75m 
including additional £10.4m) 
New Anglia LEP (underwritten by 
£10.00m 
NCC but approved by the LEP 
Board) 
Growth Point funds to facilitate 
£ 1.71m 
accelerated housing (previous 
2012/13 provision) 
Total 
£178.95m 
 
2.2 
The provision of CIL funding is discussed in paragraph 3.10 of the Full 
Council report.
  In view of the CIL receipts forecast over time and the 
provision of the legal agreement already signed by all 4 authorities that form 
the Greater Norwich Growth Board, the risk to the County Council in terms of 

 

failure to service the borrowing is considered to be very low.  Appendix 7a of 
the Joint Core Strategy identifies the NDR as priority 1 infrastructure. 
2.3 
The issue of NDR cost increases has been discussed in the Full Council 
 
report in section 3
2.4 
There is no evidence to suggest that the project costs will over-run.  The 
target cost contract arrangement with Balfour Beatty is discussed in section 
5.2 of the Full Council report

2.5 
The provision of £20.25m for ‘Preparation, Risk and Contingency’ is for the 
County Council’s costs in delivering the project since 2012/13, through its 
statutory processes.  It includes the Council’s risk and contingency during the 
construction phase of the project.  
2.6 
Reference is also made to the Postwick Hub costs.  Members have received 
regular updates on the progress of Postwick Hub, most recently this is 
explained and considered at EDT Committee on 10 July 2015

3.0 
NAO position with DfT   
3.1 
DfT has confirmed they were made aware of the submission to NAO on 29 
October.  NCC was not aware of the NAO process.  DfT have confirmed they 
have met with NAO to discuss the case and they are awaiting the outcome of 
the NAO’s decision based on their findings.  DfT have confirmed that the 
additional funding is being considered as part of its ‘full approval’ evaluation 
process for the project. 
4.0 
Crushed Rock 
4.1 
Our reference made in the full council report (6 November) to crushed rock is 
there to illustrate one of the changes that has impacted on the pricing 
between 2013 and 2015.  In 2013 the budget pricing included a reduction for 
material supply due to the potential to generate a range of suitable materials 
from Coltishall airfield.  Site testing had been completed to assess and 
confirm this potential.  This was subsequently discounted as a possibility. 
5.0 
A11 comparison 
5.1 
Postwick Hub is exclusive of the NDR project as it is already being 
constructed and it is therefore not appropriate to include this when comparing 
project costs.  
 
6.0 
Joint Core Strategy 
6.1 
Not providing the NDR west of the A140 will undermine the Local Plan (the 
JCS plus Site Allocations DPD) and the sustainable delivery of much needed 
economic and housing growth.  The JCS Policy 9 also includes a requirement 
for 2,000 dwellings on unspecified smaller sites in the Broadland part of the 
Norwich Policy area.  

 

6.2 
Most of these 2,000 dwellings are coming forward in the area affected by the 
NDR west of the A140. In particular, Broadland District Council’s Site 
Allocations Development Plan Document, which is reaching the final stages of 
its examination process, allocates land for a total of at around 1,500 dwellings 
on the A1067 corridor (200 dwellings in Drayton which have permission, 300 
dwellings and B1 employment on part of the Hellesdon Hospital site and 800-
1,000 dwellings on the golf club). The policies require the 2 larger sites 
totalling 1,000-1,300 dwellings to be phased with delivery of the NDR. 
6.3 
The Norwich International Airport (NIA) area is specifically identified in the 
JCS as a strategic employment location. NIA is the focus but clearly the wider 
area including the existing airport industrial estates, contributes to the 
strategic importance of this location for employment. In addition to the very 
significant amount of employment in this area, planned expansion includes 
40ha with planning permission for an Aeropark and a further 35ha is being 
allocated for more general employment. The NDR west of the A140 will 
significantly enhance access for businesses and for workers and customers 
from the west and northwest to the airport area. Similarly, access from these 
villages and suburbs will be enhanced to the employment areas further east 
on the NDR. 
6.4 
As part of the overall spatial strategy, the JCS includes a Bus Rapid Transit 
route on the A1067 corridor. This is to serve the existing population as well as 
new growth. Implementation of this scheme will be dependent on the NDR 
west of the A140. 
 
7.0 
Land Compensation Act (1973) 
7.1 
Details were provided in the previous Full Council report.  These are repeated 
here to set out the potential future implications for the Council. 
“Under Part 1 of the Act compensation can be sought by people who own and 
also occupy certain property that has been reduced in value by physical 
factors caused by the use of a new or altered road but have not had any land 
acquired for the scheme itself.  The physical factors are noise, vibration, 
smell, fumes, smoke and artificial lighting and the discharge on to the property 
of any solid or liquid substance. Other factors such as the loss of view or 
privacy cannot be included in the claim for compensation.  
The DfT process specifically requires that the application for funding excludes 
any budget allowance for potential Part 1 claims and so they are not included 
in the budget figures.  The NDR scheme has been designed to minimise the 
impact of physical factors where possible. For example extensive earth 
bunding is proposed along the route. A low noise road surface is proposed 
and new road lighting has been kept to a minimum. 
Claims can be made after the road has been open to traffic for 1 year and 
must be settled within the six years following the first claim day.  Details will 
not be known until any claims are made.  It is expected that future Highways 

 

capital budget may need to absorb any costs which could be up to £1m per 
annum from 2018/19 to 2024/25 if received.” 
 
Questions raised by Cllr Kemp (via email to Wendy Thomson) 
Each question raised is set out with a response: 
1.  Is the statement made below, in the letter Councillors received today, true?  “The 
National Audit Office are investigating the £10m from the DfT, so it cannot 
currently be guaranteed” If so, why weren't Councillors told? Who will make up 
the shortfall if the DfT cannot pay? More cuts from our highways budget? 
Response as per section 3 above. 
2. Why is the BB contract based on estimates and not fixed-price? How is exposure 
to such a massive financial risk justifiable for this Council? What provision in the 
risk register has been made for future increased costs?  
Response as per para 2.4 above. 
3.  Why have fewer precise figures been given in the new briefing for the increased 
costs than for the last EGM? Why is this Council being asked to vote for even 
more money, an extra £0.5 m?  
The Full Council report sets out the issues relating to provision of a comparison in 
paragraphs 3.2 and 3.3.  The additional £0.5m funding is discussed in paragraph 
3.7.  
4.  I queried the supra- inflationary increases on 2 December, now officers claim 
they could indeed have “misled” councillors on the viability of construction cost 
increases.  
The Full Council report at paragraph 2.1 covers this point.   
5.  So who can vote on Friday based on the sparsity of information officers have 
provided? How much does the provision of the new extra expense “crushed rock” 
cost? Why was this and the true extent of archaeological investigations not 
quantified in 2013?  Isn't this going to lead to another challenge? 
It is considered that there is sufficient detail in the report for Members to take a 
decision on whether or not to agree the extra funding for the project and whether to 
instruct the works with Balfour Beatty.  However, Members are also made aware of 
alternatives and options in section 4 of the report.  
The reference made in the full council report (6 November) to crushed rock is 
discussed in section 4 above.  The change in scope of the project, including the 
scope of the archaeology, are discussed in paragraph 3.1 of the Full Council report.