Dunstable Football Development Breakdown 2009 to 2015
Pavilion & Pitches 2009-2011
           4,425.00  Building & Planning fees Total
   2,697,883.17  Construction costs Total
Payment to DTC to cover rates and centre manager salary for the 
       111,000.00  1st year as part of ageement. 
         19,363.88  Equipment Total
         16,288.34  Furniture Total
         41,647.00  Landscape services Total
       260,925.26  Professional Services/Salaries Total
         31,047.12  Security Services Total
         68,415.05  Site set up services Total
         11,271.50  Surveys & assessments Total
           1,802.60  Utility connection Total
Total
   3,264,068.92 
Car Park 2014-2015
         11,932.59  Feasibility study
       198,124.19  Car park construction costs total
           3,278.34  Salary costs Total
Total
       213,335.12 
GRAND TOTAL
   3,477,404.04