This is an HTML version of an attachment to the Freedom of Information request 'Vehicles movements to and from Viridor Beddington Energy Recovery Facility'.


 
 
London Borough of Sutton   
Environment & Neighbourhoods Directorate 
Executive Head of Commissioning -  
Brendon Hills 

Your Ref: 
 
Direct Line:  020-8770-6116 
My Ref: 
 
e-mail: 
 
 
 
 
 
       Date:  
20th February 2015 
 
Ms Maeve Tomlinson 
By email 
Please reply to: 
xxxxxxxxxxxxxxxxxxxxxxx@xxxxxxxxxxxxxx.xxx 
 
 
London Borough of 
 
Sutton 
24 Denmark Road 
 
CARSHALTON 
Please ask for 
Matt Clubb 
Surrey SM5 2JG 
 
 
www.sutton.gov.uk 
 
 
 
 
 
 
Dear Ms Tomlinson 
 
Re: FREEDOM OF INFORMATION ACT 2000 - INFORMATION 
REQUEST - REF NO - F7453  
  
I refer to your request for information received on 26th January 2015 
concerning vehicles movements to and from Viridor Beddington Energy 
Recovery Facility. 
  
Your questions have been answered below.  
  
Q.1 Please could I have a breakdown of the number of trucks/vehicles 
per day that will be going to the Viridor Beddington Energy Recovery 
Facility site?
 
  
The Transport Assessment submitted by the Viridor as part of the 
planning application provided an estimate of 666 daily two way trips (all 
vehicles) to and from the site.  The Transport Assessment can be found 
here: 
http://www.viridor.co.uk/assets/Uploads/SouthLondonERF/Environment
al_Statement/Environmental_statement_main/Technical_Appendices/T
A_A_Scoping/A3%20Traffic%20Assessment%20Scoping.pdf 
 
 
Q.2 How many trucks/vehicles will be leaving the site with ash? 
  
Ash will be removed from Beddington Farmlands through 26 daily two-
way vehicle movements. For more information please see Table 5-26 
Strategic Director - 
and Table 5-27 in Viridor’s Transport Assessment.  
Environment & 
  
Neighbourhoods 
Directorate 
Mary Morrissey 
 
 

Chief Executive 
 
Niall Bolger 


 
Q.3 What will be the size of trucks/serving the above? 
  
The vehicles transporting ash from Beddington Farmlands will have a 
20 tonne payload.   
  
Q.4 How far will the trucks be travelling? 
  
The distance the vehicles transporting ash from Beddington Farmlands 
will depend on the end uses for the ash. Therefore, this information can 
not be provided at this stage.  
  
Q.5 How much diesel is required to run the Viridor Beddington Energy 
Recovery Facility? 
  
The London Borough of Sutton does not hold this information. The 
information can be ascertained but not within the FOI timeframe. 
 
The information regarding how much diesel is required to run the Viridor 
Beddington Energy Recovery Facility has been requested and will be 
forwarded to you when available.    
 
If you are unhappy with the way in which your request has been 
handled you have the right to ask for an internal review.  Please notify 
us in writing as soon as possible with the grounds upon which you feel 
the appeal is justified to : xxx@xxxxxx.xxx.xx  or by post to Corporate 
Customer Care Team, Civic Offices, St Nicholas Way, Sutton, Surrey, 
SM1 1EA.  
 
We aim to respond to you within 20 working days of receiving your 
request. If it is going to take longer we will let you know.  
  
Should you still be dissatisfied with the outcome you have the right to 
refer to the Information Commissioner: Wycliffe House, Water Lane, 
Wilmslow, Cheshire, SK9 5AF www.ico.org.uk  
  
Yours sincerely 
 
 
 
 
 
Matt Clubb  
Head of Commissioning and Contract Performance 
 
F7453 Viridor