I have spoken to peter card our head of building control an he confirmed that you will need to apply for a section 
30 temporary structure notice . BC will primarily want to understand the structure of the building but as the public 
are accessing it they are also likely to want to assess emergency lighting, means of escape, and fire safety 
issues . peter is happy to have an initial discussion and I suggest you make contact with him asap as some early 
input from him might help save time later on. I am ccing him into this. 
  
I have also confirmed planning will be required however i think that this won't be too onerous in terms of 
information as their view is that its there for a short period and there no residents directly affected by it. One issue 
however that you need to keep an eye on are trees and they will need to see root protection measures as we 
discussed.  
  
regards 
  
Jon 
 
From: Rees, Matthew  
Sent: 01 July 2013 16:35 
To: '
; Abbott, Jon; 
 
Cc: Whittle, Adrian; 
 
Subject: RE: Artangel/Heygate 
 
Good afternoon all, 
  
I thought this mornings meeting on the exciting 
 art installation was very helpful for all parties and 
raised issues for each to take away. 
  
The key actions that I noted are as follows: 
  
Artangel 
1) To liaise with 
 at Treeworks regarding root protection requirements for those trees in close proximity 
to the site 
2) To re-examine the crane requirements and consider potential implications in terms of blocking Deacon Way 
and Crossway's Church access. 
3) To consider site security and fencing 
4) To appoint a production manager and progress work on contruction methodology, procurement and design 
issues 
5) To arrange a meeting between Squib and Lend Lease to discuss demolition methodology 
  
E&C Regeneration Team 
1) To confirm planning and building control requirements 
2) To prepare a land licence that will be issued to Artangel for the site. 
3) To arrange briefing with Cllr Veronica Ward (Culture and Leisure) and Cllr Fiona Colley (Regeneration) 
  
Lend Lease 
1) To provide demolition requirements to Artangel and also global minimum requirements for demo / construction 
06/03/2014

Page 2 of 2
works 
2) To share range of demolition tender costs for the block in question (not with contractor names) 
3) To meet with Squib and Artangel to discuss demolition methodology. 
  
Given the extremely tight programme that 
 are working to can I suggest we look to programme a 
further meeting or conference call towards the middle or end of next week? Would Wednesday 10th July be too 
soon to report back on above? 
  
Regards 
  
Matthew Rees  
Senior Project Manager  
Elephant & Castle Development Team  
London Borough of Southwark  
0207 5254926  
[mobile number]  
  
 
From:
@artangel.org.uk]  
Sent: 28 June 2013 16:39 
To: Abbott, Jon; Rees, Matthew; 
 
Cc: Whittle, Adrian; 
 
Subject: Artangel/Heygate 
 
Apologies to all. The link to download the attachment is correct. But the document attached to my email 
was not. 
 
This is the right version, please disregard the previous attachment. 
 
 
 
06/03/2014

Page 1 of 1
Wannop, Laura 
From: 
Rees, Matthew
Sent: 
28 August 2013 15:54
To: 
Subject: Art Angel / Planning
Good afternoon gents 
  
Bad news is that 
 is not available for a meeting next Friday (6th). I am 
hoping to brief
 on Monday though - i've spoken with Bridin O'Connor (
boss) who is 
now aware of the proposal and has recommended that we speak directly to 

  
Once i've had a chance to update 
 I will look to confirm a date whilst i'm away. I'll 
make sure that Jon attends this first session  
  
Please can you confirm any times / dates you intend to attend site  
  
Thanks 
  
Matt 
 
03/03/2014

Page 1 of 2
Wannop, Laura 
From: 
artangel.org.uk]
Sent: 
20 September 2013 15:34
To: 
Nakendo, Fahad
Cc: 
Abbott, Jon
Subject: Re: Artangel Heygate project
Dear Fahad, 
 
I just thought I would drop you a quick note to check that you have all the information that you need to 
prepare this license. It would be good at least to be looking at a draft of this next week if possible. 
 
best, 
 
 
 
 
 
Artangel 
31 Eyre Street Hill 
London EC1R 5EW 
T: 020 7713 1400 
 
artangel.org.uk 
 
 
On 10 Sep 2013, at 13:48, "Nakendo, Fahad" <[email address]> wrote: 
 
Hi 
  
Could you please re-forward plan over to me. I will be preparing the licence for this site. 
Kind Regards, 
Fahad 
  
From: 
artangel.org.uk]  
Sent: 09 September 2013 12:31 
To: Abbott, Jon 
Subject: Re: Artangel Heygate project 
 
Dear Jon, 
 
Further to emails with Matthew of last week: 
 
1) Attached my final comments on HoT's - can you help us find a way of getting those 
formalised? 
 
2) Can I assume that you'll also be able to give Fahad the appropriate signal to move on 
with the licence?... 
 
3) …On which subject, I've dropboxed a pdf of the red-line boundary I've now re-proposed 
drawn on the Lendlease plan (though it could also be redrawn on a different scale plan if 
needed?). 
 
03/03/2014

Page 2 of 2
 
It's not the original I sent through to Matt, nor precisely what he sent back to me because it 
reverts the boundary to use n existing adjacent building as a boundary which is inherently 
more economical and more secure.  If there's some issue I haven't thought of in this, we 
should discuss it but I hope it is not problematic. 
 
Has there been any development in relation to the CPO process since the date for appeal 
passed? I ask because I am in intermittent contact with 
 and need to figure out how 
best to communicate at this point. (I met 
 last week and shared very vague 
details, but enough to understand he knows what we're about and is fine with it.) 
 
very best
 
 
The email you received and any files transmitted with it are confidential, may be covered 
by legal and/or professional privilege and are intended solely for the use of the individual 
or entity to whom they are addressed. If you have received this in error please notify us 
immediately. If you are not the intended recipient of the email or the person responsible for 
delivering it to them you may not copy it, forward it or otherwise use it for any purpose or 
disclose its contents to any other person. To do so may be unlawful. Where opinions are 
expressed in the email they are not necessarily those of Southwark Council and Southwark 
Council is not responsible for any changes made to the message after it has been sent.  
 
03/03/2014

Page 1 of 1
Wannop, Laura 
From: 
artangel.org.uk]
Sent: 
23 September 2013 15:35
To: 
Nakendo, Fahad
Cc: 
Abbott, Jon; Rees, Matthew
Subject: 
Re: Artangel Heygate project
Importance:  High
Attachments: RedLinePlan_Artangel_Excerpt.pdf; ATT728553.htm; Public liability document 13-14.pdf; 
ATT728554.htm
Dear Fahad, 
 
Apologies, the message I thought I had sent didn't make it out of my drafts on Friday evening.  
 
1) Attached is a copy of the coversheet for our annual PL and EL in amt of £5m and £10m 
respectively. 
 
2) Having spoken to you now, I would propose to summarise the project for the purpose of license in 
something like the following way in order to avoid waiting for the full 100-page manual. 
 
1. Outline description of project 
2. Overview of Sequence of works, with timeline 
3. Operational controls 
Line of Control 
Controls during Public access phase 
5. Insurance 
6. Risk Assessments 
 
Does that sound adequate? (I don't propose to make it too complex at this point.) 
 
3) In terms of red-line boundary, I proposed a plan which I tried to send you and Jon on 10/9 but I 
guess it didn't arrive because it was about 9MB. It showed the retention of my suggestion that we use 
the adjacent building as the west boundary of the area. This is a sensible thing to do from our point of 
view for practical and security reasons. 
 
Here, attached, is a reduced size excerpt, and the full file is available from this link to my Dropbox. 
 
 
 
Please let me know if you have any trouble reading any of this. 
 
best wishes,  
 
 
 
 
 
Artangel 
31 Eyre Street Hill 
London EC1R 5EW 
 
 
@artangel.org.uk 
 
 
06/03/2014



Page 1 of 2
Wannop, Laura 
From: 
Nakendo, Fahad
Sent: 
02 October 2013 12:38
To: 
Subject: 
RE: overview
Attachments: Artangel authorised site and access route020913.pdf
 
Please find attached plan as requested showing the licence area and access route as advised by Lend Lease. 
Kind Regards, 
Fahad 
  
 
From: 
@artangel.org.uk]  
Sent: 25 September 2013 10:20 
To: Nakendo, Fahad 
Cc: Rees, Matthew 
Subject: Re: overview 
 
Thanks Fahad. Happy that the document is fit for purpose. 
 
If you've sent a copy to
, it may be that we're waiting until after the end of the week for their 
comments, because I understand that 
 is away….? 
 
best wishes, 
 
 
 
 
 
Artangel 
31 Eyre Street Hill 
London EC1R 5EW 
 
 
@artangel.org.uk 
 
 
On 25 Sep 2013, at 09:32, "Nakendo, Fahad" <[email address]> wrote: 
 
 
This will do for licence purposes. Just to mention, I have forwarded the draft licence to Lend Lease 
for their comments. 
Kind Regards 
Fahad 
 
From: 
@artangel.org.uk]  
Sent: 24 September 2013 20:55 
To: Nakendo, Fahad 
Cc: Rees, Matthew 
Subject: overview 
03/03/2014

Page 2 of 2
 
Dear Fahad, 
 
I wonder what you think of this as a somewhat 'high-level' overview of the principles of 
delivering this project. 
 
Will it provide what you need in terms of the issuing of the licence? Please let me know 
tomorrow, if you can, as I would like to have the chance to add to this—if necessary— in 
time for us to have a draft licence in place at the end of this week. I hope this is acheivable. 
 
best wishes, 
 
 
 
The email you received and any files transmitted with it are confidential, may be covered 
by legal and/or professional privilege and are intended solely for the use of the individual 
or entity to whom they are addressed. If you have received this in error please notify us 
immediately. If you are not the intended recipient of the email or the person responsible for 
delivering it to them you may not copy it, forward it or otherwise use it for any purpose or 
disclose its contents to any other person. To do so may be unlawful. Where opinions are 
expressed in the email they are not necessarily those of Southwark Council and Southwark 
Council is not responsible for any changes made to the message after it has been sent.  
 
03/03/2014

Artangel Heygate Commission 
Method Overview 
ARTANGEL HEYGATE COMMISSION 
Method Overview 
Description of activity 
Artangel is commissioning a new, temporary art instal ation to be created and presented in situ on the Heygate Estate, 
a large 1970s housing estate in Elephant and Castle currently awaiting demolition and redevelopment.The project is the 
work of the artist Mike Nelson. 
 
The work to be created ad presentedis an architectural constructionmade from the fabric of a four-storey building 
situated on the north side of Heygate Street, 61-72 Chearsley. 
 
Thisbuilding wil  be cleared of its contents, stripped of asbestos, professional y deconstructed, and the constituent 
concrete panels wil  be stockpiled, before being reassembled to create the form of a stepped pyramid. 
 
The process of demolition wil  be filmed, and the film wil  be shown in the interior of the new building, which visitors wil  
be able to access during a visit to the project. 
Delivery Team 
Artangel is producing and commissioningtheproject, working on the site under license from Southwark Council with the 
co-operation of the developer Lend Lease. 
 
The project team is led by Artangel’s Head of Production, Rob Bowman, supported by project management from 
McLennan, and complemented by Quantity Surveying from Boyden Group, and CDM from Butler & Young. 
 
Artangel wil  appoint reputable contractors to undertake specific processes involved in the project,including demolition 
and construction.The principal contractor wil  be Squibb Group, who wil  directly deliver the soft-strip,removal of 
asbestos, post-strip, and the deconstruction of the building. Specific services wil  be subcontracted to ArcTec who wil  
fabricate, supply, and instal  the steels needed for stabilization and construction. Al  fabrications and instal ations wil  
conform to plans drawn up by the appointed engineers, Atelier One. 
Methodological principles 
Al  works to be undertaken wil be detailedin a comprehensive delivery plan which wil  include method statements and 
risk assessments for each phase of activity drawn up by the relevant contractor. This wil  be circulated to key 
stakeholders (Southwark Borough Council, Lend Lease) in advance. Al  site operations during construction phases wil  
meet Lend Lease’s Global Minimum Requirements. 
 
The demised site is defined by a red-line plan drawn up and appended to the license to be issued by Southwark Borough 
Council.  
 
Page 1 of 4 































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































Artangel Heygate Commission 
Method Overview 
The site defined by this plan wil  be separated from surrounding areas by a physical boundary made from a combination 
of hoarding, ‘heras’ fencing, and existing structures. This wil  al ow effective control of the site, access management 
andmitigate risks to public safety. The site wil  be managed professional y, with appropriate welfare and security, and 
safety measures and risk controls identified 
in advance in order to ensure an incident and injury-free site. 
 
The strip and demolition of the building wil  be undertaken under planning consent already given by Southwark Council 
(subject to specific conditions to be discharged by Lend Lease by 30 September 2013).Demolition consent is contingent 
onfurther specific measures to protect trees onsite, which Artangel wil  provide for in the written plan.Implementation 
wil  include fencing and root protection measures. No pruning or fel ing wil  take place without advicethat such 
measures are acceptable within the requirements of Tree Protection conditional to planning consent. 
 
Thenewly constructed building wil  be subject to its own planning approval from Southwark Council, a process involving 
consultation with and review by Building Control, and the notification of and submission of a planning application. 
Artangel wil  prepare and seek this consent with the input of others in the delivery team, and al  construction plans wil  
be contingent on receiving the necessary approvals. 
Sequence of operations 
Instal ation of fencing and welfare provisions 
1-Oct-2013; 1 week 
Soft strip of building, asbestos removal;  
7-Oct-2013; 3.5 weeks 
Demolition of link bridges and garages to 
16-Oct-2013; 8 days 
south of building, to enable access 
Instal ation of temporary steelwork and 
21-Oct-2013; 3.5 weeks 
props as per design 
Demolition of one balcony and instal ation 
28-Oct-2013; 1 week 
of reinforced concrete slab 
Demolition of remaining balcony, instal  
6-Nov-2013; 10 days 
slab, instal ation of scaffold staircase 
Structural demolition works, and 
18-Nov-2013; 6 weeks 
subsequent construction 
Internal fit out of building 
30-Dec-2013; 3 weeks 
Preparation of site for public access 
20-Jan-2014; 3 weeks 
Page 2 of 4 







































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































Artangel Heygate Commission 
Method Overview 
Launches & public presentation 
12-Feb—1-Jun-2014; 15 weeks 
 
Operational controls: Construction phase 
Artangel wil  assume responsibility for ensuring that there is an effective team structure in place to implement each 
phase of the project during the period of its construction. 
 
The delivery plan wil  show a Line of Control that identifies Designated Responsible Individuals, their areas of direct 
responsibility and their reporting relationships to others in the project team. 
 
Operational controls and the implementation of agreed EH&S policies during the processes of demolition and 
construction wil  be the responsibility of a DRI appointed by the principal contractor. This person wil  ensure that the 
project plan is implemented effectively, and ensure that al  contractors and service providers are work to support 
EH&S risk management. S/he wil  report in turn to Artangel’s project management team in reviewing the effectiveness 
of onsite controls. 
 
Lend Lease’s GMRs require that onsite operations are periodical y reviewed by a third party contractor, and Artangel 
and any appointed party wil  co-operate ful y in ensuring this process of review is effective. 
Operational controls: Public presentation 
Artangel wil  assume responsibility for the secure and safe operation of the demised site during the period in which the 
project is open to the public. 
 
The project wil  be presented to the public from 12 February 2014 to 1 June 2014 inclusive, open five days per week(Wed-
Sun) between 10am and 7pm. Other, programmed activities may be arranged outside of these hours including special 
viewings for community groups; outreach activity; and visits from stakeholders and funders. A programme of these 
activities wil  be made maintained by Artangel. 
 
Artangel wil  employ a team of trained Front of House staff to manage the site during opening hours and during any 
eventsto ensure that al  visitorsenjoy a safe, enjoyable and engaging experience. They wil  be the primary point of 
contact and information for visitors to Artangel’s project. 
 
A Duty Front of House Managerwil  oversee al  public-facing operations. S/he wil  ensure that Artangel’s Health & 
Safety and Fire Evacuation plans are implemented, and manage the team of staff to provide a helpful and engaging 
service to visitors. 
 
Designated access routes into and out of the site and the building itself wil  be identified and agreed uponat the 
completion of the structure and finalisation of site arrangements. Routes of access wil  be subject to ful  risk 
assessment. The Front of House team wil  facilitate visitor access, includingmaking specific provision for visitorshaving 
to cross Deacon Wayin order to mitigate any risk presented by the use of this road forconstruction traffic. 
Page 3 of 4 

Artangel Heygate Commission 
Method Overview 
Insurance 
Artangel has an annual insurance policy for its activities as a commissioner and producer of contemporary artworks in 
the public realm, providing cover for Public Liability and Employers Liability of £5 and £10m respectively. 
 
Our underwriters review our working methods and endorsements or additions to our policies are included where risks 
are identified. 
 
Artangel also holds additional insurance policies for specific risks (eg hired in equipment used on site) and wil  take 
further cover out where it is deemed necessary. 
 
--End-- 
Page 4 of 4 

Page 1 of 1
Wannop, Laura 
From: 
Nakendo, Fahad
Sent: 
03 October 2013 10:29
To: 
Subject: 
RE: license
Attachments: Artangel authorised site and access route031013.pdf
 
Please find attached revised plan. Please let me know that you are happy with the red line boundary. 
Kind Regards, 
Fahad 
  
 
From: Rob Bowman [mailto:[email address]]  
Sent: 02 October 2013 13:44 
To: Nakendo, Fahad 
Subject: license 
 
Dear Fahad, 
 
Red line plan attached, please let me know if you are able to access it. 
 
best, Rob 
 
03/03/2014


Wannop, Laura
From:
Nakendo, Fahad
Sent:
08 October 2013 11:21
To:
Subject:

131008_AH_Art Angel-site compound licence- Final Version
Attachments:
131008_AH_Art Angel-site compound licence_LL Comments (2).doc
Hi
Please find final version of licence for your review. This includes the issues of the events licence that i mentioned in 
my previous email.
Kind Regards,
Fahad Nakendo MRICS
131008_AH_Art 
Angel-site compo...
1

Page 1 of 2
Wannop, Laura 
From: 
@artangel.org.uk]
Sent: 
09 October 2013 11:33
To: 
Nakendo, Fahad
Cc: 
Rees, Matthew; Abbott, Jon
Subject: Re: License
Dear Fahad, 
 
Wonderful, I'm happy apart from the tiny detail that it is Artangel (all one word), and that there is a date 
that needs to be put in under section 5. If it makes no difference (and I've assured Matthew that he will 
know our plans and that we will not simpy turn up on site with crew on Monday!!) perhaps we could 
date this from next week. 
 
Once this done, will you print and post, or do you want me to see it again and print and send you back 
copies? 
 
best, 
 
 
 
 
 
Artangel 
31 Eyre Street Hill 
London EC1R 5EW 
 
 
@artangel.org.uk 
 
 
On 9 Oct 2013, at 10:54, "Nakendo, Fahad" <[email address]> wrote: 
 
Dear 
 
Please find attached a revised version of the licence and plan taking into account of your comments 
below. 
Kind Regards, 
Fahad 
  
 
From: 
@artangel.org.uk]  
Sent: 08 October 2013 16:42 
To: Nakendo, Fahad 
Cc: Rees, Matthew 
Subject: License 
 
Dear Fahad, 
 
Apologies for this but we've picked up on a discrepancy with the red line on the attached in 
our meeting today. The boundary on the south edge runs through the middle of some built 
structures and it really needs to be at the far edge (southmost) of this drawn area. That 
03/03/2014

Page 2 of 2
would mean it butts up to the hatched area for access, and follows the outside of the curve… 
 
Very crudely tried to show this in purple on the attached. 
 
My error here. 
 
Further three comments on the license before I am happy. 
 
At 2. can you refer to us as The Artangel Trust including the other name by which we're 
known parathentically if you wish to later refer to us otherwise ("Artangel") 
 
at 11. you are missing an s at the end of agree on line 4. 
 
At 24 can you change 'Principal Contractor' to 'Client' which is how Artangel should be 
designated, and being such does  indeed comply us to appoint a CDM coordinator. 
 
best, 
 
 
The email you received and any files transmitted with it are confidential, may be covered 
by legal and/or professional privilege and are intended solely for the use of the individual 
or entity to whom they are addressed. If you have received this in error please notify us 
immediately. If you are not the intended recipient of the email or the person responsible for 
delivering it to them you may not copy it, forward it or otherwise use it for any purpose or 
disclose its contents to any other person. To do so may be unlawful. Where opinions are 
expressed in the email they are not necessarily those of Southwark Council and Southwark 
Council is not responsible for any changes made to the message after it has been sent.  
<131009_AH_Art Angel-site compound licence_Final.doc><Artangel authorised site and 
access route091013.pdf> 
 
03/03/2014

Page 1 of 1
Wannop, Laura 
From: 
@artangel.org.uk]
Sent: 
23 October 2013 16:39
To: 
Rees, Matthew
Subject: 
app form revised
Attachments: Application Form Filled.pdf; ATT27222.htm
03/03/2014

Page 1 of 5
Wannop, Laura 
From: 
@artangel.org.uk]
Sent: 
27 November 2013 16:52
To: 
Nakendo, Fahad
Cc: 
Rees, Matthew
Subject: 
Re: Artangel Lease
Importance: 
High
Follow Up Flag: Follow up
Flag Status: 
Red
Dear Fahad, 
 
1.Could you correct Art Angel (which should always be one word 'Artangel’) on all this paperwork. 
 
2. Para 23 should read: The Tenant shall be the Client under the CDM Regulations and shall 
appoint a CDM Coordinator.
 
 
Can we have a copy of the DEMP please. 
 
Following these corrections or your instruction for me to make the changes accordingly, I will forward 
on copies for signing by two of our Directors. 
 
 
 
 
 
 
Artangel 
31 Eyre Street Hill 
London EC1R 5EW 
 
 
@artangel.org.uk 
 
 
On 26 Nov 2013, at 15:03, Nakendo, Fahad <[email address]> wrote: 
 
Dear
 
Please find attached revised lease for your comments if any and statutory declaration for your 
signature before lease engrossment. 
Kind Regards, 
Fahad 
  
 
From: 
@artangel.org.uk]  
Sent: 15 October 2013 15:57 
To: 
; Nakendo, Fahad 
Cc: Rees, Matthew; 
 
Subject: Re: Artangel -  
 
03/03/2014

Page 2 of 5
. thanks, that's helpful. 
 
Fahad, would you be able to change the plan accordingly? Give me a ring if you need. 
 
best, 
 
 
 
 
 
Artangel 
31 Eyre Street Hill 
London EC1R 5EW 
 
 
@artangel.org.uk 
 
 
On 15 Oct 2013, at 15:51, 
 wrote: 
 
  
  
 
 
  
 
 
  
 
 
  
 Please consider the environment before printing this e-mail 
  
  
  
  
From: 
@artangel.org.uk]  
Sent: 15 October 2013 15:41 
To: 
 
Cc: Matthew Rees; Fahad Nakendo 
Subject: now with attachment 
Dear 
 
Okay, my apologies (and to Farhad for this further delay). This arose from not 
fully apprehending what the hatched area represents.  
Ideally, we would have a vehicular access to the end of garages (purple line) 
but also beyond as marked to the blue line. Clearly a vehicle following that 
route would need to be properly provided for in terms of a banksman, and that 
would be written into the TMP which we have now drafted. I should also say 
that this would be a very rare occurence, if it were to be acceptable to Lend 
Lease to provide for this. 
Equally, if you see a significant issue with it I can discuss it with Squibb and 
we will find another way, just working up to the purple line. 
03/03/2014

Page 3 of 5
Perhaps you could advise so that we can finalise this plan, and I will ensure 
you get an amended copy back for DP9. 
best, 
 
 
 
 
Artangel 
31 Eyre Street Hill 
London EC1R 5EW 
 
 
@artangel.org.uk 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
  
 
 
 
 
 
 
 
 
 
  
03/03/2014

Page 4 of 5
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 Please consider the environment before printing this e-mail 
From: 
@artangel.org.uk]  
Sent: 08 October 2013 16:28 
To: Matthew Rees; 
 
Subject: Red line 
I've looked again at the plans. 
The redline on the site plan for the license is wrong. 
However, I believe the fencing plan shows the hoarding in the the right place, 
assuming it is intended to runalong the line of the existing fronts of the 
existing garages rather than to the front edge of the pavement. 
I can't see a strong reason why it should need to be at the front edge of the 
pavement, doing so creates a disconnection between existing structures and the 
proposed line of the hoarding, and it narrows the effective width of the access 
way (though trucks presumably won't regularly mount the pavement). 
I drew this conclusion from looking at the position of the column in the image 
and on the plan here where the curved section of wall is. The column is clearly 
on the pavement... 
Hope that's clear. New plans will follow. 
 
<image001.jpg> 
 
 
 
Artangel 
31 Eyre Street Hill 
London EC1R 5EW 
 
 
@artangel.org.uk 
<Artangel authorised site and access route031013.pdf> 
  
<Artangel authorised site and access route091013.pdf> 
 
The email you received and any files transmitted with it are confidential, may be covered 
by legal and/or professional privilege and are intended solely for the use of the individual 
or entity to whom they are addressed. If you have received this in error please notify us 
immediately. If you are not the intended recipient of the email or the person responsible for 
03/03/2014

Page 5 of 5
delivering it to them you may not copy it, forward it or otherwise use it for any purpose or 
disclose its contents to any other person. To do so may be unlawful. Where opinions are 
expressed in the email they are not necessarily those of Southwark Council and Southwark 
Council is not responsible for any changes made to the message after it has been sent.  
<20131126 KR Lease to Art Angel clean.doc><Artangel Lease Plan.pdf><20131115 
Notice under 1954 Act.doc><20131115 Stat Dec.doc> 
 
03/03/2014

FW: Artangel
Page 1 of 2
Wannop, Laura 
From: 
Nakendo, Fahad
Sent: 
05 December 2013 15:17
To: 
'
Cc: 
Reed, Katharine; 
Subject: RE: Artangel
Dear 
 
Please mark for 
 
Kind Regards, 
Fahad 
 
From: 
@artangel.org.uk]  
Sent: 05 December 2013 14:47 
To: Nakendo, Fahad 
Cc: Reed, Katharine; 
 
Subject: Re: Artangel 
 
Dear Fahad, 
 
Does this paperwork come back to you, or shall I mark them for 

 
I’m going to get three copies sent to you tomorrow. Can you return one copy to me once it has been 
countersigned by other parties please, as I would like a signed copy on our records. The other two can 
be retained by LBS and Lend Lease as Katharine suggests. 
 
My colleague 
is helping me with this tomorrow so could you cc her if there is a response. 
 
Best, 
 
 
 
 
 
Artangel 
31 Eyre Street Hill 
London EC1R 5EW 
 
 
@artangel.org.uk 
 
 
On 3 Dec 2013, at 13:57, Nakendo, Fahad <[email address]> wrote: 
 
Dear 
  
Please see email below. I will be grateful if you could sign and return two copies of lease and also 
get stat dec signed at your solicitors as instructed belwo. 
Kind Regards,  
Fahad  
______________________________________________  
   
   
03/03/2014

FW: Artangel
Page 2 of 2
   
  
     
  
     
  
        
  
  
 
 
 
 
 
 
  
 
 
 
  
  
  
  
  
  
  
  
  
  
  
  
 
The email you received and any files transmitted with it are confidential, may be covered 
by legal and/or professional privilege and are intended solely for the use of the individual 
or entity to whom they are addressed. If you have received this in error please notify us 
immediately. If you are not the intended recipient of the email or the person responsible for 
delivering it to them you may not copy it, forward it or otherwise use it for any purpose or 
disclose its contents to any other person. To do so may be unlawful. Where opinions are 
expressed in the email they are not necessarily those of Southwark Council and Southwark 
Council is not responsible for any changes made to the message after it has been sent.  
<20131115 Stat Dec.doc><20131203 KR Lease to Art Angel final.doc><Artangel Lease 
Plan-281113 (2).pdf><20131115 Notice under 1954 Act.doc> 
 
03/03/2014