This is an HTML version of an attachment to the Freedom of Information request 'How many times projects in Hart and Rushmoor have been delayed.'.

Road name 
What the project was for? 
Where the work took 
Was there a 
Reason for the delay? 
Duration of the delay? 
place? 
delay? 
Ash Road, 
This work was to secure water 
Within Ash Road, Aldershot  The scheme 
N/A 
N/A 
Aldershot 
supplies, improve water pressure and  between the Lower 
completed on 
reduce the number of bursts in the 
Farnham Road junction and  time, however  
Aldershot area.  
Church Hill. 
further work to 
complete a 
connection 
took place 
overnight on 
the 17th March 
and on the 20th 
March 2013.  
Selborne 
A new 118 metre long water main 
Within Selborne Avenue 
No 
N/A 
N/A 
Avenue, 
was laid to enable water to service 
between Overton Close 
Aldershot 
new properties. 
and Morland Road. 
Hawley Lane, 
Trial holes to investigate the water 
Within Hawley Lane just 
No 
N/A 
N/A 
Farnborough 
main within the road. 
north of the M3 crossing. 
Fernhill Road, 
Installation of a new 1.6km water 
Within Fernhill Road 
No 
N/A 
N/A 
Farnborough 
main was required to ensure we can 
between the Mayfield 
 
 
continue to supply the growing 
Road junction, along 
 
 
population of Farnborough over the 
Fernhill Road to a point 
coming years. The new pipeline will 
past Hawley Place School. 
also help us move water around our 
 
network ensuring it gets to the areas 
   
which need it. 

Reading Road, 
A new 1.4km water main was 
Within Reading Road 
Yes 
Initially there were 
Originally the work was 
Frogmore 
installed along Reading Road, 
between the A30 
more services within 
due to finish 1st October 
Frogmore to deliver a more secure, 
roundabout junction and 
the ground which the 
2011 but completed in 
robust water supply to the area as 
Darby Green Road. 
Company needed to 
September 2012 once 
the old water main is reaching 
weave the new pipe 
the repairs had been 
capacity and will not cope with future 
around. Following the 
completed during the 
demand. 
installation of the new 
school holiday periods 
pipeline a series of 
(between the holiday 
small leaks were 
periods the road was re-
discovered during the 
opened). 
testing phase which 
 
needed to be repaired 
 
before we put the 
pipeline into operation. 
These repairs took 
place during school 
holiday periods. 
Gally Hill Road,  This work was to install a new 1.5km 
Within Gally Hill Road 
No 
N/A 
N/A 
Church 
water main in Gally Hill Road to 
between the Gally Hill 
Crookham 
supply new housing developments in 
Road/Farmhouse 
the area. 
Way/Malthouse Close 
Roundabout and the 
junction with Aldershot 
Road.