Andrew 2nd email on progress - I am now on holiday until 2nd Sept. Will you please contact Richard on any issues while I am away
Sunday and Eve Project
Progress
· TRO should have run to 29th Aug and in the meantime objections should have been processed by the 16th September
· .There is now a three week delay on the project because of the delay in posting the TRO. The golive is likely to be 18th Nov any more slippage and the income expected from the Christmas peak will be missed.
· Still waiting to know if there is an approvals process to go through after objections – NH to update – RB to chase
TRO Progress
Legal response
o “Just to keep you up to date but as the email below shows, legal services are hesitant to advertise the weekend and evening charges order given the Barnet ruling. I am not convinced the Barnet case has much bearing for this particular proposals and feel we have a strong defense to justify the need for the changes and the benefit for the evening economy”.
A Mason update to the above
o “Following on from our conversation this morning I’ve discussed this with Helen Atkinson who has been advising on this and asked her to provide a written considered view for you on the decisions taken on both the Sunday and evening car parking and the residents permit scheme in the light of the Barnet decision. We should be able to provide this by Monday at the latest. I understand the need to raise this with CLT asap and hope that’s acceptable”
Comms
Maggie is compiling a list of places and routes to disseminate the information once the advertising period is completed at the end of August