Dear Merton Borough Council,

Please will you provide a copy of the documents governing the current works and demolition of Bishopsford Road bridge, including the method statement and relevant drawings.

Yours faithfully,

Tony Burton

foi, Merton Borough Council

Thank you for your email message. We aim to respond to all requests under
the Freedom of Information Act 2000 and Environmental Information
Regulations 2004 within 20 working days however during the current
Coronavirus crisis there may be a delay in responding to you.  More
information about the way we deal with information requests is on our web
site at [1]www.merton.gov.uk/foi​

References

Visible links
1. http://www.merton.gov.uk/foi

foi, Merton Borough Council

"Thank you for your email message. We aim to respond to all requests under
the Freedom of Information Act 2000 and Environmental Information
Regulations 2004 within 20 working days however during the current
Coronavirus crisis there may be a delay in responding to you.  More
information about the way we deal with information requests is on our web
site at [1]www.merton.gov.uk/foi
 
Information Governance Team
London Borough of Merton.
020 8545 4634
 
 
 

dangos adrannau a ddyfynnir

References

Visible links
1. http://www.merton.gov.uk/foi

Dear Merton Borough Council,

This is to ask for an internal review of my request which has not been responded to within the period expected.

Yours faithfully,

Tony Burton

foi, Merton Borough Council

"Thank you for your email message. We aim to respond to all requests under
the Freedom of Information Act 2000 and Environmental Information
Regulations 2004 within 20 working days however during the current
Coronavirus crisis there may be a delay in responding to you.  More
information about the way we deal with information requests is on our web
site at [1]www.merton.gov.uk/foi
 
Information Governance Team
London Borough of Merton.
020 8545 4634
 
 
 

dangos adrannau a ddyfynnir

References

Visible links
1. http://www.merton.gov.uk/foi

foi, Merton Borough Council

Dear Mr Burton,

 

Thank you for your email. At this time we are unable to accept your
request for an internal review due to the delay in responding. I note from
our records that your request was due for a response on 3 June. Whilst we
appreciate that we have failed to meet this deadline as you are no doubt
aware the council is currently managing the covid-19 situation and as such
response times to FOI requests may be delayed.

 

Please accept our apologies for the delay in responding.

 

Kind regards

 

Michael Cook

 

Michael Cook

Information Governance Officer

Information Governance Team

Merton Council

www.merton.gov.uk

 

dangos adrannau a ddyfynnir

Dear foi,

Thank you for the update. I appreciate the additional demands caused by COVID-19. Nevertheless, the request relates to "essential works" which are underway during lockdown and so I would appreciate a timely response.

Yours sincerely,

Tony Burton

foi, Merton Borough Council

"Thank you for your email message. We aim to respond to all requests under
the Freedom of Information Act 2000 and Environmental Information
Regulations 2004 within 20 working days however during the current
Coronavirus crisis there may be a delay in responding to you.  More
information about the way we deal with information requests is on our web
site at [1]www.merton.gov.uk/foi
 
Information Governance Team
London Borough of Merton.
020 8545 4634
 
 
 

dangos adrannau a ddyfynnir

References

Visible links
1. http://www.merton.gov.uk/foi

foi, Merton Borough Council

2 Atodiad

Dear Mr Burton

Freedom of Information Act 2000 / Environmental Information Regulations
2004 Information request F14065

 

We have now considered your information request as set out below.  Please
accept my apologies for the late response to your request.

 

You asked:

 

Please will you provide a copy of the documents governing the current
works and demolition of Bishopsford Road bridge, including the method
statement and relevant drawings.

 

Please find attached the Flood Risk Activity Permit for this work,
including the documents, method statement and drawings which govern the
current works and demolition of Bishopford Bridge

 

Please note that the personal details of individuals has been redacted.
This information is exempt under section 40(2) of the Freedom of
Information Act, 2000.  This is because it is personal data and disclosure
would contravene the Data Protection Act. This applies because the
individual(s) are below the level of Assistant Director and as such do not
expect their personal details to be revealed to the world at large, which
disclosure under the FOIA has to be considered as. 

 

In accordance with the Freedom of Information Act 2000 this is a Refusal
Notice to provide the names and contact details of individuals. You have
the right of appeal against the decision, as set out below

 

If you have any queries or concerns about this please contact me.

 

If you are dissatisfied with the handling of your request, please contact
the Head of Information Governance at Merton Council, Civic Centre,
Morden, SM4 5DX or e-mail [1][Merton Borough Council request email].

 

If you remain dissatisfied with the handling of your request or complaint,
you have a right to appeal to the Information Commissioner at:

 

The Information Commissioner's Office, Wycliffe House, Water Lane,
Wilmslow, Cheshire, SK9 5AF.

 

Telephone: 0303 123 1113

 

Website: [2]www.ico.org.uk

 

There is no charge for making an appeal.

 

Yours sincerely

 

[3]TB Email Signature Template 2019

 

dangos adrannau a ddyfynnir