1) How many GHA properties and any associated properties such as cube etc( only if GHA oversees those and hence responsible for planning their smoke alarms too if applicable) (dwellings: flats, houses etc etc) in Glasgow are still yet to be installed with Smoke Alarms in accordance to the new Scottish Government law?

2) With reference to the number given in question one above, considering that smoke alarm installation will take around 2 hours per home/flat/dwelling etc to install how many working days or months would this approximately be expected to take (for all GHA social housing including any associated housing stock such as cube = if GHA is responsible for overseeing that) for all installations to be complete? (I refer also to the fact that I am aware that Scottish Government have indeed included flexibility for this purpose regarding their current deadline).

Thank you

Yours faithfully,

Sarah Summers

Information Requests, Wheatley Homes Glasgow Limited

Our Ref: FOI19122Summers

Date: 19/01/2022

Dear Ms Summers

Your Request for Information
Freedom of Information (Scotland) Act 2002

I refer to your e-mails dated 19 January 2022 which I am treating as a request for information under the provisions of the Freedom of Information (Scotland) Act 2002.

You requested the following information:

1) How many GHA properties and any associated properties such as cube etc( only if GHA oversees those and hence responsible for planning their smoke alarms too if applicable) (dwellings: flats, houses etc etc) in Glasgow are still yet to be installed with Smoke Alarms in accordance to the new Scottish Government law?

2) With reference to the number given in question one above, considering that smoke alarm installation will take around 2 hours per home/flat/dwelling etc to install how many working days or months would this approximately be expected to take (for all GHA social housing including any associated housing stock such as cube = if GHA is responsible for overseeing that) for all installations to be complete? (I refer also to the fact that I am aware that Scottish Government have indeed included flexibility for this purpose regarding their current deadline).

I will look into this request and establish if any information can be released to you.

A response to your request for information will be sent to you promptly; and in any event not later than 16 February 2022.

Yours sincerely,

Information Governance Team

show quoted sections

Information Requests, Wheatley Homes Glasgow Limited

1 Attachment

Dear Ms Summers

Please see the response to your information request.

I trust that you find this in order.

Regards

Information Governance Team

show quoted sections