Surveys for major works programme, Partridge Way, 2019; and subsequent correspondence, etc.

Roedd y cais yn rhannol lwyddiannus.

Dear Homes for Haringey,

Partridge Way N22 consists of two tower blocks (Newbury House and Finsbury House), the houses 2-70 Partridge Way; and surrounding land.

Homes for Haringey wrote to residents on 08 November 2019 advising that a survey was being carried out (by Ridge and Partners) related to the External and Communal Major Works programme, including windows, roof, rainwater goods, concrete, brickworks repairs and fencing works.

The letter said, 'We will write to all residents to inform you of what has been included in the programme following the outcome of the surveys'.

For information, I received this letter addressed to me personally, and I live in Newbury House at Partridge Way.

(1) Can you please confirm whether the letter, referred to above, was delivered to all residents of the estate, both the tower blocks and the houses?

(2) Please provide full copy of all survey reports produced by Ridge as a result of the survey work referred to; with all appendices and any financial estimates.

(3) Please provide copies of all letters sent to any part of the estate following decisions about what was included in the programme following the outcome of the surveys.

(4) Please provide full copy of all written and illustrative materials used at the relevant drop in session on held on 31 January 2020.

With thanks.

Yours faithfully,

Paul Burnham

ComplaintsHFH, Homes for Haringey

Dear Paul Burnham

 

Freedom of Information Request: Reference LBH/10995121

 

I acknowledge your request for information received on 16 April 2021.

 

This information request will be dealt with in accordance with the Freedom
of Information Act 2000 and we will send the response by 17 May 2021.

 

Yours sincerely,

 

 

Lara Taiwo

Feedback Officer

Business Improvement Team

Homes for Haringey

4th Floor | 48 Station Road | London | N22 7TY

Customer Services: 0208 489 5611

Direct Number: 020 8489 4469

E: [1][email address]

 

From: Paul Burnham <[FOI #747899 email]>
Sent: 15 April 2021 21:05
To: FeedbackHFH <[Homes for Haringey request email]>
Subject: Freedom of Information request - Surveys for major works
programme, Partridge Way, 2019; and subsequent correspondence, etc.

 

 

Dear Homes for Haringey,

 

Partridge Way N22 consists of two tower blocks (Newbury House and Finsbury
House), the houses 2-70 Partridge Way; and surrounding land.

 

Homes for Haringey wrote to residents on 08 November 2019 advising that a
survey was being carried out (by Ridge and Partners) related to the
External and Communal Major Works programme, including windows, roof,
rainwater goods, concrete, brickworks repairs and fencing works.

 

The letter said, 'We will write to all residents to inform you of what has
been included in the programme following the outcome of the surveys'.

 

For information, I received this letter addressed to me personally, and I
live in Newbury House at Partridge Way.

 

(1) Can you please confirm whether the letter, referred to above, was
delivered to all residents of the estate, both the tower blocks and the
houses?

 

(2) Please provide full copy of all survey reports produced by Ridge as a
result of the survey work referred to; with all appendices and any
financial estimates.

 

(3) Please provide copies of all letters sent to any part of the estate
following decisions about what was included in the programme following the
outcome of the surveys.

 

(4) Please provide full copy of all written and illustrative materials
used at the relevant drop in session on held on 31 January 2020.

 

With thanks.

 

Yours faithfully,

 

Paul Burnham

 

-------------------------------------------------------------------

 

Please use this email address for all replies to this request:

[2][FOI #747899 email]

 

Is [3][Homes for Haringey request email] the wrong address for Freedom of
Information requests to Homes for Haringey? If so, please contact us using
this form:

[4]https://www.whatdotheyknow.com/change_re...

 

Disclaimer: This message and any reply that you make will be published on
the internet. Our privacy and copyright policies:

[5]https://www.whatdotheyknow.com/help/offi...

 

For more detailed guidance on safely disclosing information, read the
latest advice from the ICO:

[6]https://www.whatdotheyknow.com/help/ico-...

 

Please note that in some cases publication of requests and responses will
be delayed.

 

If you find this service useful as an FOI officer, please ask your web
manager to link to us from your organisation's FOI page.

 

 

dangos adrannau a ddyfynnir

Gadawodd Paul Burnham anodiad ()

Response by 17 May 2021

Loomes Kevin, Homes for Haringey

1 Atodiad

 

Dear Paul Burnham,

LBH/10995121 Freedom of Information Request

 

I am writing further to your email dated 15 April 2021.

 

You requested :

 

(1) Can you please confirm whether the letter, referred to above, was
delivered to all residents of the estate, both the tower blocks and the
houses?

 

(2) Please provide full copy of all survey reports produced by Ridge as a
result of the survey work referred to; with all appendices and any
financial estimates.

 

(3) Please provide copies of all letters sent to any part of the estate
following decisions about what was included in the programme following the
outcome of the surveys.

 

(4) Please provide full copy of all written and illustrative materials
used at the relevant drop in session on held on 31 January 2020.

 

 

 

Please see my response set out below:

 

(1)           I can confirm that the letter dated 08 November 2019 was
sent to all dwellings of the estate (ie, Finsbury House, Newbury House,
Trinity Road and Partridge Way houses)

 

(2)           No information was produced regarding the works package.
 This is because as the works to the estate as originally set out was
changed and some of the addresses were subsumed into another package –
these addresses did not include Finsbury House or Newbury House

 

(3)           No letters were sent out regards this works package as
originally planned regards Finsbury House or Newbury House

 

(4)           I have been informed by the Resident Liaison Officer that
there was no illustrative materials used at the drop in session, only the
invite letter, which I have attached for your reference

 

 

 

If you have any queries please do not hesitate to email at
[1][email address]

If you are unhappy with how we have responded to your request, you can ask
us to conduct an Internal Review. If so, please contact the [2]Corporate
Feedback Team  (please note you should do so within two months of this
response).

 

You may also complain to the Information Commissioner's office, which may
be able to help you.  However, they would normally expect the local
authority to have undertaken a complaint investigation or Internal Review
of the request before they will accept the referral. 

 

You can contact the Commissioner at:

 

Information Commissioner

Wycliffe House

Water Lane

Wilmslow

Cheshire

SK9 5AF

Phone help line:    0303 123 1113

Fax:  01625 545510

Website:     [3]www.ico.gov.uk

  

Yours sincerely,

 

Kevin Loomes

Data Manager

Asset Management/Property Services

 

Homes for Haringey

E: [4][email address]

[5]www.homesforharingey.org

[6]@homes4haringey

 

From: Paul Burnham <[FOI #747899 email]>
Sent: 15 April 2021 21:05
To: FeedbackHFH <[Homes for Haringey request email]>
Subject: Freedom of Information request - Surveys for major works
programme, Partridge Way, 2019; and subsequent correspondence, etc.

 

 

Dear Homes for Haringey,

 

Partridge Way N22 consists of two tower blocks (Newbury House and Finsbury
House), the houses 2-70 Partridge Way; and surrounding land.

 

Homes for Haringey wrote to residents on 08 November 2019 advising that a
survey was being carried out (by Ridge and Partners) related to the
External and Communal Major Works programme, including windows, roof,
rainwater goods, concrete, brickworks repairs and fencing works.

 

The letter said, 'We will write to all residents to inform you of what has
been included in the programme following the outcome of the surveys'.

 

For information, I received this letter addressed to me personally, and I
live in Newbury House at Partridge Way.

 

(1) Can you please confirm whether the letter, referred to above, was
delivered to all residents of the estate, both the tower blocks and the
houses?

 

(2) Please provide full copy of all survey reports produced by Ridge as a
result of the survey work referred to; with all appendices and any
financial estimates.

 

(3) Please provide copies of all letters sent to any part of the estate
following decisions about what was included in the programme following the
outcome of the surveys.

 

(4) Please provide full copy of all written and illustrative materials
used at the relevant drop in session on held on 31 January 2020.

 

With thanks.

 

Yours faithfully,

 

Paul Burnham

 

-------------------------------------------------------------------

 

Please use this email address for all replies to this request:

[7][FOI #747899 email]

 

Is [8][Homes for Haringey request email] the wrong address for Freedom of
Information requests to Homes for Haringey? If so, please contact us using
this form:

[9]https://www.whatdotheyknow.com/change_re...

 

Disclaimer: This message and any reply that you make will be published on
the internet. Our privacy and copyright policies:

[10]https://www.whatdotheyknow.com/help/offi...

 

For more detailed guidance on safely disclosing information, read the
latest advice from the ICO:

[11]https://www.whatdotheyknow.com/help/ico-...

 

Please note that in some cases publication of requests and responses will
be delayed.

 

If you find this service useful as an FOI officer, please ask your web
manager to link to us from your organisation's FOI page.

 

 

dangos adrannau a ddyfynnir