Dear Sir or Madam,

Could you please let me know the cost of the re-organisation process to date that Westminster is currently undertaking?

Yours faithfully,

R Brown

Westminster City Council

Confirmation of Freedom Of Information Request

Thank you for your request for information.

Your request details have now been recorded and will be passed on to the
appropriate Divisional Records Officer for action.

This Freedom Of Information Request was based on the following
information:

Name: R Brown
Address: see email address
Email: [FOI #21952 email]
Telephone:
Request Details: Could you please let me know the cost of the
re-organisation process to date that Westminster is currently undertaking?

FOI Reference Number: 4560
Target Completion Date: 23/11/2009

Please do not reply to this email.
This is an automatic response to your request, and replies to this message
will not be actioned.

If you need to contact Westminster City Council regarding your request,
please contact:

mailto:[Westminster City Council request email]
Tel:020 7641 3921

dangos adrannau a ddyfynnir

Shasha, Jolekha, Westminster City Council

Dear R Brown

You recently wrote to Westminster City Council asking us to respond to two
questions, which you submitted under the Freedom of Information Act 2000.

Please find our responses below.
I hope this information is useful to you.
Your sincerely
Jolekha Shasha
Westminster City Council
Human Resources
.

Could you please let me know the cost of the re-organisation process to
date that Westminster is currently undertaking?
The council's restructuring is planned over three phases. Phase one will
complete at the end of December 2009, phase two will complete by the end
of March 2010. The current proposal is that phase three will be complete
by the end of September 2010 . The plans are on track and will deliver a
range of operational benefits, customer service improvements and full year
annual savings of £11.8m. The changes are significant and will result in
a reduction of staff of around 10% of the establishment (non-schools) i.e.
around 270 posts. This will include some redundancies, the majority of
which are in phase one . The restructuring will put the council in a
strong position to continue to provide excellent front line services
despite the well publicised reductions in public expenditure, which will
take effect from 2011. The council has earmarked a one-off reserve of
£10m to cover the cost of restructuring (including associated redundancy
costs), and costs incurred in transforming to a new operating model. To
date the cost of restructuring excluding redundancies is approximately
£0.5m, covering additional HR support and office move costs. Estimated
redundancy costs for staff leaving in phase one are around £3.5m.

Could you please let me know the budget for the upcoming (November 2009)
Westminster management conference at Ashridge?
The budget for the forthcoming management conference at Ashridge
Management Centre is £28,000. The cost to the city council will be in the
region of £8,000. The majority of the costs are funded from trading
surplus generated over the course of 2008/09 by WestCo.