Dear FOI Team,

I would be most grateful if you would provide me, under the Freedom of Information Act, details in respect to the contract below.

Crawley Borough Council — Property Partnering Contract.:
http://ted.europa.eu/udl?uri=TED:NOTICE:...

The details we require are:
• Suppliers who applied for inclusion on each framework/contract and were successful & not successful at the PQQ & ITT stages
• Actual spend on this contract/framework (and any sub lots), from the start of the contract to the current date
• Start date & duration of framework
• Is there an extension clause in the framework(s)/contract(s) and, if so, the duration of the extension?
• Has a decision been made yet on whether the framework(s)/contract(s) are being either extended or renewed?
• Who is the senior officer (outside of procurement) responsible for this contract?

Thank you for your help.

Yours sincerely
Richard Samson

Freedom Of Information, Crawley Borough Council

Dear Sir,

 

Thank you for your request for information which is being considered under
the Freedom of Information Act 2000.

 

The Council will endeavour to respond to your request within 20 working
days, however our services are under unprecedented pressure due to the
COVID-19 pandemic and therefore delays are possible as resources are being
diverted away from usual compliance of information rights work. Please
bear with us during this challenging time.

 

Please remember to quote the above reference number in any future
communications.

 

Yours faithfully,    

     

Nirvana Kidwell

Freedom of Information Officer • Audit and Risk

Crawley Borough Council

 

01293 438000

[1]http://www.crawley.gov.uk

 

Monday to Friday

 

Please note I am working from home, therefore please contact me via Email
or Teams.

 

FOI: 8057

 

 

 

show quoted sections

Freedom Of Information, Crawley Borough Council

Dear Sir,

Further to your email below, we are writing to you to apologise for the
delay in responding to your request under the Freedom of Information Act
2000. Work is still ongoing in collating the information you have
requested, and we will forward a response at the earliest opportunity.

Please remember to quote the above FOI reference number in any future
communications.

Yours sincerely,

Nirvana Kidwell

Freedom of Information Officer • Audit and Risk

Crawley Borough Council

 

01293 438000

[1]http://www.crawley.gov.uk

 

Monday to Friday

 

Please note I am working from home, therefore please contact me via Email
or Teams.

 

 

 

From: Freedom Of Information
Sent: 02 June 2021 11:33
To: 'Richard Samson' <[FOI #761500 email]>
Subject: FOI 8057 - Acknowledgement

 

Dear Sir,

 

Thank you for your request for information which is being considered under
the Freedom of Information Act 2000.

 

The Council will endeavour to respond to your request within 20 working
days, however our services are under unprecedented pressure due to the
COVID-19 pandemic and therefore delays are possible as resources are being
diverted away from usual compliance of information rights work. Please
bear with us during this challenging time.

 

Please remember to quote the above reference number in any future
communications.

 

Yours faithfully,    

     

Nirvana Kidwell

Freedom of Information Officer • Audit and Risk

Crawley Borough Council

 

01293 438000

[2]http://www.crawley.gov.uk

 

Monday to Friday

 

Please note I am working from home, therefore please contact me via Email
or Teams.

 

FOI: 8057

 

 

 

show quoted sections

Freedom Of Information, Crawley Borough Council

1 Attachment

Dear Sir,

 

Please see attached for Crawley Borough Council’s response.

 

Regards,

 

Gillian Edwards

Audit and Risk Manager

Crawley Borough Council

 

01293 438384

[1]www.crawley.gov.uk

 

 

FOI request No: 8057

 

From: Richard Samson
[[2]mailto:[FOI #761500 email]]
Sent: 01 June 2021 16:49
To: Freedom Of Information <[3][email address]>
Subject: Freedom of Information request - Crawley Borough Council —
Property Partnering Contract

 

 

Dear FOI Team,

 

I would be most grateful if you would provide me, under the Freedom of
Information Act, details in respect to the contract below.

 

Crawley Borough Council — Property Partnering Contract.:

 

[4]http://ted.europa.eu/udl?uri=TED:NOTICE:...

 

The details we require are:

 

• Suppliers who applied for inclusion on each framework/contract and were
successful & not successful at the PQQ & ITT stages

 

• Actual spend on this contract/framework (and any sub lots), from the
start of the contract to the current date

 

• Start date & duration of framework

 

• Is there an extension clause in the framework(s)/contract(s) and, if so,
the duration of the extension?

 

• Has a decision been made yet on whether the framework(s)/contract(s) are
being either extended or renewed?

 

• Who is the senior officer (outside of procurement) responsible for this
contract?

 

 

Richard Samson

 

show quoted sections

The information contained in this email may be subject to public
disclosure under the Freedom of Information Act 2000. Unless the
information contained in this email is legally exempt from disclosure, we
cannot guarantee that we will not provide the whole or part of this email
to a third party making a request for information about the subject matter
of this email.

This email and any attachments may contain confidential information and is
intended only to be seen and used by the named addressee(s). If you are
not the named addressee, any use, disclosure, copying, alteration or
forwarding of this email and any attachments is unauthorised. If you have
received this email in error please advise the sender immediately and
permanently delete this email and any attachments from your system.

The views expressed within this email and any attachments are not
necessarily the views or policies of Crawley Borough Council. We have
taken precautions to minimise the risk of transmitting software viruses,
but we advise you to carry out your own virus checks before accessing this
email and any attachments. Except as required by law, we shall not be
responsible for any damage, loss or liability of any kind suffered in
connection with this email and any attachments, or which may result from
reliance on the contents of this email and any attachments.

**********************************************************************

References

Visible links
1. http://www.crawley.gov.uk/
2. mailto:[FOI #761500 email]
3. mailto:[email address]
4. http://ted.europa.eu/udl?uri=TED:NOTICE:...
5. Keep Crawley Safe
https://crawley.gov.uk/coronavirus