Costs of repairs to Plimsoll Bridge
Dear Bristol City Council,
1. What hydraulic modeling work has already been undertaken to estimate the cost to the Plimsoll Bridge? Please provide any reports conducted, meeting notes available, and any appropriate emails.
2. If separate to the question 1-- the mayor mentioned at Cabinet on October 1 that the original survey assessment and the Treasury green book assessment was for repair cost of £38m to £42m. Please provide the reports of the 'original survey assessment' and the 'Treasury green book assessment'.
Yours faithfully,
Joanna
Dear Joanna .
Case 1287753
Thank you for your enquiry received on 4 October 2019. Your enquiry will
be forwarded to the relevant service and you'll receive a response from
them in due course.
Yours sincerely
Customer Relations Team
NOTE: Please do not edit the subject line when replying to this email.
Bristol City Council
This email contains proprietary confidential information some or all of
which may be legally privileged and/or subject to the provisions of
privacy legislation. It is intended solely for the addressee. If you are
not the intended recipient, an addressing or transmission error has
misdirected this e-mail; you must not use, disclose, copy, print or
disseminate the information contained within this e-mail. Please notify
the author immediately by replying to this email. Any views expressed in
this email are those of the individual sender, except where the sender
specifically states these to be the views of Bristol City Council.
This email has been scanned for all viruses and all reasonable precautions
have been taken to ensure that no viruses are present. Bristol City
Council cannot accept responsibility for any loss or damage arising from
the use of this email or attachments.
--------------------------------------------------------------------------
Council services: http://www.bristol.gov.uk/service
Latest council news: http://www.bristol.gov.uk/ournews
Consultations: http://www.bristol.gov.uk/consult
Dear Bristol City Council,
This response is now delayed. By law you should have responded so please can I have an answer to my question.
Yours sincerely,
Joanna Booth
Dear Ms Booth
Apologies for the delay with this FOI.
Despite the FOI concerning Plimsoll bridge the information was not held by
our Bridges team and was provided by BCC Transport Planning. Please see
the attached document and the text below to answer your enquiry.
The Plimsoll Bridge cost of £40m was based on an initial engineering
estimate of £27m which was increased to account for contingency and
optimism bias to an estimate of £40m. The working behind this was checked
recently as per treasury guidance and confirmed to be within a range of
£37.5m to £43m. The attached details the works and the process. These are
all essential works.
Yours sincerely
Robin
Robin Cane
Bridges and Highway Structures Officer
Bristol City Council
Growth and Regeneration
Transport
Traffic and Highways Maintenance
100 Temple Street
Bristol
BS1 6AN
Postal Address: PO Box 3176
Tel: 0117 35 74386
Email: [1][email address]
--------------------------------------------------------------------------
Council services: http://www.bristol.gov.uk/service
Latest council news: http://www.bristol.gov.uk/ournews
Consultations: http://www.bristol.gov.uk/consult
References