Central Station Refurbishment Cost Breakdown

Roedd y cais yn llwyddiannus.

Dear Tyne and Wear Passenger Transport Executive,

With the £6 million refurbishment of Central Station Metro now fully completed I'd be grateful if a detailed breakdown of the costs involved in this project could be sent over.

Yours faithfully

Freedom Info, Tyne and Wear Passenger Transport Executive

Dear Jason,

Thank you for your email which has been passed to me as the person responsible for responding to Freedom of Information requests at Nexus. I will provide a response within the statutory timescales.

Regards
Michael

Michael Hunt
Administration Manager
 
Nexus, Nexus House, St James' Boulevard, Newcastle Upon Tyne, NE1 4AX
Telephone 0191 2033243 / Fax 0191 2033180

dangos adrannau a ddyfynnir

Dear Freedom Info,

I would like to make you aware you have past the deadline in which I should have received a response to my request, by law.

Due to this I am requesting a full internal review and I would like a response to my request ASAP.

Yours sincerely

Freedom Info, Tyne and Wear Passenger Transport Executive

Dear Jason,

Yes, apologies for this. I'm busy getting a detailed breakdown for you. The project has just recently finished and I have a total cost but just awaiting the detailed breakdown for you. I have just chased this again for you and it will be with you asap.

Regards
Michael

Michael Hunt
Administration Manager
 
Nexus, Nexus House, St James' Boulevard, Newcastle Upon Tyne, NE1 4AX
Telephone 0191 2033243 / Fax 0191 2033180

dangos adrannau a ddyfynnir

Freedom Info, Tyne and Wear Passenger Transport Executive

Dear Jason,

 

First of all please accept my apologies for the late distribution of this
information. 

 

Please find below a detailed breakdown of costs relating to the
refurbishment of Central Station.

 

Regards

Michael

 

Element Total Cost
   
Substructure £0.00
   
Superstructure £146,417.18
Frame £0.00
Upper Floors £0.00
Roof £0.00
Stairs and Ramps £99,505.00
External Walls £0.00
Windows and External Doors £0.00
Internal Walls and Partitions £13,982.25
Internal Doors £32,929.93
   
Internal Finishes £1,456,779.39
Wall Finishes £500,862.30
Floor Finishes £653,662.22
Ceiling Finishes £302,254.87
   
Fittings, Furnishings and Equipment £61,473.43
   
Services £1,293,169.43
Sanitary Installations £2,315.33
Services Equipment £150.00
Disposal Installations £12,470.28
Water Installations £20,201.12
Heat Source £0.00
Space Heating and Air Conditioning £0.00
Ventilation Systems £0.00
Electrical Installations £689,484.80
Fuel Installations £0.00
Lift Conveyor Installations £390,324.00
Fire and Lightning Protection £49,113.51
Communication, Security and Control Installations £51,631.40
Specialist Installations £43,607.75
Builder's Work in Connection with Services £33,871.24
   
Prefabricated Buildings and Building Units £0.00
   
Work to Existing Building £46,805.26
Minor Demolition and Alteration Works £46,805.26
   
External Works £0.00
Site Preparation Works £0.00
Roads, Paths, Pavings and Surfacings £0.00
Soft Landscaping, Planting and Irrigation Systems £0.00
Fencing, Railings and Walls £0.00
External Fixtures £0.00
External Drainage £0.00
External Services £0.00
Minor Building Works and Ancillary Buildings £0.00
   
Facilitating Works £625,465.38
Toxic/Hazardous/Contaminated Material Treatment £625,465.38
Major Demolition Works £0.00
Temporary Supports to Adjacent Structures £0.00
Specialist Ground Works £0.00
Temporary Diversion Works £0.00
Extraordinary Site Investigations £0.00
   
Main Contractor Preliminaries £537,669.27
   
Main Contractor's Overhead & Profit £0.00
   
Project/Design Team Fees  
   
Other Development/Project Costs £1,908,569.00
   
Risk (Client's Contingencies) £0.00
   
Current Contract/Project Cost £6,076,348.34

 

 

Michael Hunt

Administration Manager

 

Nexus, Nexus House, St James' Boulevard, Newcastle Upon Tyne, NE1 4AX

Telephone 0191 2033243 / Fax 0191 2033180

 