i) Who are the incumbent suppliers of the "basic connectivity
(Layer 2)" for your Wide Area Network Services? Are any contracts
due for renewal in the next six months?

ii) How many sites are there on your network and how many require
high speed (greater than 1Gig) connections?

iii) Do you build and operate your own network or do you use a
Systems Integrator or Outsourcing company to do that? If so, please
specify who and when the contract expires.

iv) How many Data Centres do you use and are they on council
premises or third party premises? Please specify post codes for DC
locations. If third party please specify the company and when the
contract expires.

v) Do you operate your own Data Centres or do you use a
Systems Integrator or Outsourcing company for that? If so, please
specify who and when the contract expires.

vi) Do you use "Co-location" Services ? If yes who is the supplier
and when do the contracts need to be renewed?

Yours faithfully,

Joe Hellard

Link to this

Greater London Authority

16 February 2010

From: [FOI #29101 email]
To: [Greater London Authority request email]
Subject: Freedom of Information request - ICT Implementation

The Mayor would like to thank you for your interest in his work and he is
keen to answer your query as quickly and fully as possible. As you will
appreciate, he receives very large amount of correspondence but he is
committed to responding to your query within 20 working days.

However, the Greater London Authority (GLA) will only respond to queries
that relate to its work and will refer relevant queries to the appropriate
functional body for them to reply e.g. transport related queries will be
referred to Transport for London (TfL).

Please note that the GLA does not accept unsolicited job applications or
C.V's. Information on current vacancies is available on our website at:
[1]http://www.london.gov.uk/jobs.jsp

Thank you for taking the time to write to the Mayor of London, Boris
Johnson.

Yours truly

Public Liaison Unit

References

Visible links
1. http://www.london.gov.uk/jobs.jsp

Link to this

From: Mayor of London
Greater London Authority

18 February 2010

Dear Mr Hellard

Thank you for your recent email to the Greater London Authority (GLA) seeking information about our ICT implementation.

In answer to your questions please note the following:

i) Fujitsu are the suppliers for the GLA and are not due renewal.
ii) There are two sites on the GLA network and both require high speed connections.
iii) The GLA has an external network that is run by Fujitsu. The contract is overseen by Transport for London and is ongoing.
iv) The GLA uses one data centre - on GLA premises - SE1 2AA.
v) The GLA runs its own data centre.
vi) The GLA does not use co-location services.

Yours sincerely

Katya Phillip
Public Liaison Officer

If you are unhappy with the way the GLA has handled your request, you may complain using the GLA's comments and complaints procedure, available at http://www.london.gov.uk/gla/comments/in...

Dear Greater London Authority,

i) Who are the incumbent suppliers of the "basic connectivity
(Layer 2)" for your Wide Area Network Services? Are any contracts
due for renewal in the next six months?

ii) How many sites are there on your network and how many require
high speed (greater than 1Gig) connections?

iii) Do you build and operate your own network or do you use a
Systems Integrator or Outsourcing company to do that? If so, please
specify who and when the contract expires.

iv) How many Data Centres do you use and are they on council
premises or third party premises? Please specify post codes for DC
locations. If third party please specify the company and when the
contract expires.

v) Do you operate your own Data Centres or do you use a
Systems Integrator or Outsourcing company for that? If so, please
specify who and when the contract expires.

vi) Do you use "Co-location" Services ? If yes who is the supplier
and when do the contracts need to be renewed?

Yours faithfully,

Joe Hellard

show quoted sections

Back London's bid to the FA to be a host city for the 2018 World Cup.
Visit http://www.england2018bid.com and choose London as your
favourite host city when registering your support for bringing
the World Cup to England.

GREATER LONDON AUTHORITY
------------------------------------------------------------------------------------
EMAIL NOTICE:
The information in this email may contain confidential or privileged materials.
Please read the full email notice at http://www.london.gov.uk/email-notice.jsp
------------------------------------------------------------------------------------

Link to this

From: Joe Hellard

24 February 2010

Dear Mayor of London,

Thank you for your reply.

I am slightly confused. "there are two sites on the GLA" network.
And "Fujitsu run and external network for GLA".

What sites are in the external network?

Yours sincerely,

Joe Hellard

Link to this

Greater London Authority

24 February 2010

From: [FOI #29101 email]
To: [Greater London Authority request email]
Subject: RE: MGLA160210-4318 Freedom of Information request - ICT
Implementation

The Mayor would like to thank you for your interest in his work and he is
keen to answer your query as quickly and fully as possible. As you will
appreciate, he receives very large amount of correspondence but he is
committed to responding to your query within 20 working days.

However, the Greater London Authority (GLA) will only respond to queries
that relate to its work and will refer relevant queries to the appropriate
functional body for them to reply e.g. transport related queries will be
referred to Transport for London (TfL).

Please note that the GLA does not accept unsolicited job applications or
C.V's. Information on current vacancies is available on our website at:
http://www.london.gov.uk/jobs

Thank you for taking the time to write to the Mayor of London, Boris
Johnson.

Yours truly

Public Liaison Unit

Link to this

From: Mayor of London
Greater London Authority

3 March 2010

Dear Mr Hellard

Thank you for your follow up email to the Mayor of London about the Greater London Authority's (GLA) ICT implementation. I have been asked to reply to you on his behalf.

I am sorry about any confusion in my earlier reply. Please note that the GLA is based at City Hall, its main network (within the confines of City Hall) is run by the GLA IT Unit.

However, it is connected by a high speed link to Transport for London's data centre (the other site on our network). From there, the GLA access some of TFL's Business Systems (e.g. Finance and Procurement).
The high speed link to TFL is run by Fujitsu on behalf of TFL.

I hope that this now clears up any misunderstanding.

Yours sincerely

Katya Phillip
Public Liaison Officer

If you are unhappy with the way the GLA has handled your request,
you may complain using the GLA's comments and complaints procedure,
available at http://www.london.gov.uk/gla/comments/in...

Dear Mayor of London,

Thank you for your reply.

I am slightly confused. "there are two sites on the GLA" network.
And "Fujitsu run and external network for GLA".

What sites are in the external network?

Yours sincerely,

Joe Hellard

show quoted sections

Link to this

From: Joe Hellard

4 March 2010

Dear Mayor of London,

Thanks very much for the Clarification.

Yours sincerely,

Joe Hellard

Link to this

Greater London Authority

4 March 2010

From: [FOI #29101 email]
To: [Greater London Authority request email]
Subject: RE: MGLA240210-4930 RE: MGLA160210-4318 Freedom of
Information request - ICT Implementation

The Mayor would like to thank you for your interest in his work and he is
keen to answer your query as quickly and fully as possible. As you will
appreciate, he receives very large amount of correspondence but he is
committed to responding to your query within 20 working days.

However, the Greater London Authority (GLA) will only respond to queries
that relate to its work and will refer relevant queries to the appropriate
functional body for them to reply e.g. transport related queries will be
referred to Transport for London (TfL).

Please note that the GLA does not accept unsolicited job applications or
C.V's. Information on current vacancies is available on our website at:
http://www.london.gov.uk/jobs

Thank you for taking the time to write to the Mayor of London, Boris
Johnson.

Yours truly

Public Liaison Unit

Link to this

Things to do with this request

Anyone:
Greater London Authority only: