Hello! (Sign in or sign up)

Track this request

Act on what you've learnt

Similar requests

Planning applications online I made a FOI request on 4th July. I sent a reminder on 6th August. Can you please answer my request - see below? Yours sincerely, Darryl Collin... Response overdue.
Follow up sent to Land and Property Services (Northern Ireland) by Darryl Collins on 25 August 2008.
Crime statistics by ward level for NI Thank you for your prompt reply. I have had a look at the web site you directed me to and I would like to clarify/refine my initial question: *... Partially successful.
Follow up sent to Police Service of Northern Ireland by Darryl Collins on 17 July 2008.
Traffic arrangements for CLA game fair, Blenheim Palace 25-27 July Dear Mr Munro Document as requested. As you will see there are some blank spaces within the document. The reasons for these blanks are that they re... Successful.
Response by West Oxfordshire District Council to Robert (Jamie) Munro on 8 September 2008.

More similar requests

Cost of large traffic sign Carnbane Hill, Hillsborough

A Freedom of Information request to Roads Service Northern Ireland by Darryl Collins

The request was successful.

Darryl Collins

8 July 2008

Dear Sir or Madam,

Can you please tell me the total cost of the purchase, erection,
commissioning and annual operation (inc. service contract) of the
large two sided electronic sign in the middle of the carriageway on
Carnbane Hill between Sprucefield and Hillsborough?

And is there a plan to put useful traffic information on these
signs instead of inane slogans like "wise up slow down"?

Thank you for your help.

Yours faithfully,

Darryl Collins

Link to this | Send follow up

Davison, Michael
Roads Service Northern Ireland

10 July 2008

Dear Mr Collins,

Thank you for your email.

Your request is being dealt with and you will receive a formal reponse
within 20 days.

Regards,

Michael Davison
Traffic Information and Control Centre
1b Airport Road
Belfast
BT9 3DY

show quoted sections

Link to this | Reply to this message

Davison, Michael
Roads Service Northern Ireland

25 July 2008

Dear Mr Collins

In response to your email of 8 July 2008 and further to my email of 10 July 2008.

The total cost for the supply and installation, including civils works, of the two signs referred to in your email is £176404.73.

The operational costs for the signs will be in the region of £3240 per annum. It is not possible to give an exact cost as it is dependant upon usage of power and communications.

The capital costs have been part funded by EU as part of a joint cross border project called Instant involving the National Roads Authority in the Republic of Ireland and Roads Service in Northern Ireland.

One of the objectives of project is to provide timely and consistent travel information along the A1/M1 corridor between Belfast and Dublin.

The legend you mention forms part of a UK wide road safety campaign and, at the moment, we are using it to test the signs.

Legends appropriate to the prevailing traffic conditions will be used once testing and commissioning has been completed and the project launched.

I trust you find this useful.

Regards,

Michael Davison
Traffic Information & Control Centre
1b Airport Road
Belfast
BT3 9DY

Tel 028 9025 4507

Chris,

Please log as FoI and remove, thanks.

show quoted sections

Link to this | Reply to this message

Darryl Collins

4 August 2008

Dear Mr Davison

Many thanks for your full response to my FOI request. I certainly
hope that the sign will be used for something useful rather than
the inane slogans it currently displays!

Yours sincerely, Darryl Collins

Link to this | Send follow up

Things to do with this request

Add an annotation (to help the requester or others)

Darryl Collins only: Reply to Davison, Michael | Request an internal review
Roads Service Northern Ireland only: Respond to request