This is an HTML version of an attachment to the Freedom of Information request 'INTERNAL AUDIT - REPORT OF INTERNAL AUDIT ACTIVITY FOR THE PERIOD 1st DECEMBER 2008 - 28th FEBRUARY 2009'.
This report contains information relating to
matters which could prejudice current or 
potential future legal proceedings and are not 
for publication by virtue of paragraph  7 of Part 1 
of Schedule 12A to the Local Government Act 1972.  

BRISTOL CITY COUNCIL
Audit Committee 
3rd April 2009
Report of:  Acting Strategic Director (Resources)
Report Title
Internal Audit - Report of Internal Audit Activity for the Period 
 1st December 2008 - 28th February 2009

Ward: Citywide
Officer presenting report: 
Richard Powell, Chief Internal Auditor
Contract Telephone Number: 0117 92 22448
RECOMMENDATION
The   Audit  Committee   note  the  activities  carried out  by Internal  Audit during the 
period 1st December 2008 - 28th February 2009.  
This report was submitted to the Efficiency and Value for Money Executive Member 
at his meeting on 1st April 2009
SUMMARY
This report provides a summary of the audit activity during 2008/09 to date.
The significant issues in the report are:
• Activity and performance (section 2 - 5)
• Follow up activity (section 6)
• Partnerships (Section 7)
Policy
This   report   is   submitted   in   accordance   with   the   Audit   Committee's   Terms   of 
Reference and Internal Audit's Charter and Strategy
Consultation:
Internal:
None necessary
External:
None necessary
1

Introduction
1.
Introduction
1.1
The Accounts and Audit Regulations 2006 require the City Council to review 
the effectiveness of the Council's system of internal audit.  This responsibility 
has been assigned to the Audit Committee who continually review the 
effectiveness of Internal Audit itself by consideration of periodic and other 
reports by the Chief Internal Auditor. The purpose of this report is to provide 
details of Internal Audit activity during the period 1st December 2008 to 28th 
February 2009 to assist the Executive Member and the Committee in 
discharging this responsibility.  
2.
Internal Audit Activity and Performance - Summary
Activity
2.1
During the period 01/04/2008 - 28/02/2009, Internal Audit Productive Activity 
was as follows:
Area of Activity
Actual  Full Year  Pro-rata 
Days
Planned  Plan Days
Days
Assurance Work (Key and non key including 
2543
2871
2632
work brought forward from 2007/08)
Planning and Reporting
128
105
96
Planned Anti-fraud work
131
112
103
Fraud and Irregularity - Responsive work
224
117
107
Unplanned work
396
432
396
Liaison and Advice
204
275
252
Fol ow Up
60
105
96
Risk Management
129
113
104
Audit Standards and Development
271
336
308
HB Fraud Team Management
22
20
18
Total
4108
4486
4112
2.2
The above table demonstrates that assurance work is slightly below that 
planned for year to date, this is in part due to the need to complete a number 
of assurance audits in the final quarter of the year. The Fraud and Irregularity 
budget has been exceeded by 110% of that planned for year to date, see 
section 5 for details.  Overall, the  level of work delivered is stil  in line with that 
planned for at this point in the year.
2.3
Follow up work has continued following the implementation of the Internal 
Audit follow up and escalation procedure.  However, due to the requirement 
for additional work in areas such as Fraud and Irregularity the level of follow 
2

up work is below that planned at this time. Details of follow up work completed 
is provided in section 6 of this report.   
Performance
2.4
Key performance targets included in Internal Audit's Service Delivery Plan 
include percentage completion of  planned assurance work.  These targets 
are calculated and reported quarterly and are provided below together with 
updated figures to the end of February 2009 and previous year comparative 
data.  It should be noted that many assurance assignments included in the 
audit plan are not finite in nature and take place throughout the year.  As 
such,  assignments in progress are included as wel  as those completed. 
Additionally, those items no longer required are included, as Audit 
involvement may be dependent on the progress made by others or on other 
external factors. Without these caveats, the indicator is of little value.  
Actual Performance
Indicator
Target 
11 
Q3
Q2
 11 
Q3 
Q2 
2008/09
months  2008/09 2008/09 months to  2007/08 2007/08
to 
29/02/08
28/02/09
% of key audits 
95%
87.7%
63.2%
45.6%
89.4%
80.3%
67.2%
completed
% of non key audits 
75%
87.3%
73.9%
59.9%
75.9%
66.5%
50.8%
completed
2.5
Performance figures to date highlight that coverage on key audits is only 
marginal y below that at this point last year, this is in part due to the need to 
delay a number of key audits until the last quarter for strategic reasons and at 
the request of External Audit. The coverage of non key audits is up on last 
year at this time and as such is also in part responsible for the reduced key 
audit coverage.  This increased coverage is in part due to the need to 
complete a high number of school audits in preparation for FMSiS 
assessments which are currently underway.
2.6
Other service delivery plan targets include: 
Indicator
Target
 Actual
Q3 
2008/09
2008/09
11 months 
to 28/02/09
Actual
Customer Satisfaction Survey - % Returning 
90%
99%
99%
a Satisfactory Response.
Final Reports Issued within 3 weeks of 
80%
74%
74%%
completion of field work
% of significant recommendations from key 
100%
100%
100%
audit work either implemented or escalated.
(Paragraph 6 
below refers)
3

Resource Issues
2.7
Resourcing concerns have been alleviated to some extend with the return of 
one member of staff from maternity leave on a part-time basis (0.5 FTE). 
However the section remains under resourced against the original 2008/09 
Plan, by 2 FTE posts.  A limited number of agency staff have continued to be 
retained to assist with delivering the Audit Plan, the costs of which can be 
contained within the current year's budget. 
3.
Planned Work - Reports Issued and Matters Arising
3.1
The Internal Audit Strategy includes the requirement to report any changes to 
the plan approved by the Audit Committee.  No amendments have been 
made to the agreed plan to date.
3.2
Internal Audit Planned work has progressed in line with the approved plan.  A 
list of work completed or in progress during the period, together with the audit 
opinions for any completed work during the period is provided at Appendix A. 
Internal Audit provide standard opinions with each audit report within the 
range of 'very good' to 'poor' as follows:
Very Good
Al  controls were in place and operating effectively. No weaknesses in 
control were identified.
Good
Al  significant controls were in place and operating effectively.  Only minor 
weaknesses in control were identified.  
Satisfactory Most significant controls were in place and operating effectively.  There 
were however areas where improvements are required.
Needs 
Some significant weaknesses in control have been identified and/or some 
Improvement controls were not working effectively.  Management can only have limited 
assurance that the matters covered by this review are properly managed 
and control ed.
Poor
There are no/inadequate controls in place.  Management cannot be 
assured that the matters covered by this review are properly managed and 
control ed.
3.4
Given the nature and breadth of the Council's activities, it is inevitable that 
areas for control improvement are identified by Internal Audit work.  In some 
cases the level of improvements identified means that the existing control 
environment is rated as poor or needs improvement.  Appendix B provides a 
brief summary of work completed during the period, where this was the case. 
For each audit, action plans for control improvements have been agreed with 
relevant officers and it is anticipated that recommendations wil  be 
implemented. Progress against these action plans will be monitored in line 
with Internal Audit's follow up procedure.  Where improvements are not 
satisfactory, matters wil  be escalated to management and the Audit 
Committee notified. The appendix also includes areas of concern where 
Internal Audit staff contribute to pieces of work going on elsewhere in the 
4

Council.  The following table details the number of audit assignments 
completed during 2008/09 to date together with a summary of the opinions 
issued:
Period 3 
YTD Total
1/12/08 - 28/02/09
Total Audits 
Key
Non Key
Key
Non Key
Completed
4
25
13
92
Audit Opinion
Satisfactory or better
2
12
6
44
Needs Improvement
2
10
4
30
Poor
0
1
0
3
No Opinion 
0
2
3
15
Necessary
4.
Unplanned Assignments
4.1
Details of  unplanned work completed during the period can be seen at 
Appendix C.  These include assignments completed or continuing from the 
previous year where significant continued work was not foreseen when 
compiling the audit plan. 
4.2
The nature of these assignments is such that it was not possible to foresee 
the need for the work at the time of preparing the annual Internal Audit plan. 
However upon consideration of the issue, Internal Audit involvement with the 
work was considered necessary as the circumstances indicate a breakdown in 
the control environment.  
4.3
Resources of 432 days are provided in the Audit Plan to accommodate such 
work.  To date, 396 Days  (92% of those planned) have been used .
5.
Fraud and Irregularity 
5.1
Internal Audit have responsibility for the investigation of fraud and irregularity. 
Again, a contingency provision is made in the annual audit plan each year for 
this type of work and this year the provision was 117 days.  However, to date 
224 days (191% of those planned) have been used in work in this area since 
the beginning of the year. As mentioned in the previous report a considerable 
amount of that time has been spent on a fraud investigation concerning 
irregularities within Parking Services, part of the City Development 
Directorate.
5.2
Full details of the fraud responsive work can be seen at appendix D.  This 
includes investigations continuing from previous periods where they are not 
included in the annual plan as wel  as new cases during the current period 
5

which are endorsed in bold in the appendix. 
6.
Follow up and Escalation Matters
6.1
In accordance with Internal Audit's Fol ow up and Escalation Procedure, which 
was introduced in April 2007.  Fol ow up on significant recommendations 
made following key audits has been completed.  Please see paragraphs 6.2 
for details.
Follow Up of Significant Findings From Key Audits
6.2
To date 16 significant recommendations have been made in relation to key 
systems. Details of these and an update on significant recommendations 
which were outstanding at the close of 2007/08 are set out in Appendix E.
Other Follow Up Work Completed:
6.3
In addition to follow up of significant recommendations, follow up work has 
been completed in those areas identified in our previous periodic reports as 
attracting a poor or needs improvement opinion, details of action taken is also 
set out in Appendix E. 
Matters for Escalation
6.4
The follow up and escalation procedure includes the requirement/facility to 
inform the Audit Committee of occasions where escalation of control matters 
or audit access matters through the City Council's management structure has 
not successfully resolved issues.  No matters have occurred during the 
current period.
7.
Other Issues
7.1
Partnerships
7.1.1 Partnership working is an important part of the Council's core aims and 
objectives in order to ensure it maximises the outcomes for the community.  It 
is a government expectation that Councils will increasingly participate in 
partnership working to meet the needs of the community.
7.1.2 The role of Internal Audit within partnership working is to provide an 
independent opinion on the governance arrangements within the partnership, 
ensuring that these arrangements are in line with the Council's own 
governance framework.  Audit will also examine financial responsibilities and 
accountabilities, and performance information.
7.1.3 A review of the governance arrangements in place for the Children & Young 
People's Partnership has recently been completed, and resulted in a 
'Satisfactory' Audit opinion.  However, there were a number of areas identified 
6

where improvement is required, the main one being the need to prepare a 
Risk Register which identifies the risks specific to the Children's Partnership.
7.1.4 The Risk Register for the Children's Partnership was due to be brought to the 
3rd April 2009 Committee meeting, however the Partnership Board decided 
that, having reviewed the Register earlier in the year, there were areas where 
further work was required and requested that the register be brought back to 
them in May.  Therefore, the Risk Register wil  be presented to the Audit 
Committee once that further Partnership Board consideration has taken place.
7.1.5 A review of the governance arrangements within the Bristol Partnership and 
Safer Bristol Partnership is currently underway, as is an overal  review of 
Partnership working within the Bristol Partnership.  A review of the West of 
England Partnership is also ongoing.
7.2
Business Transformation 
7.2.1 Internal Audit are periodical y called upon to either actively participate or 
provide input and guidance on particular projects throughout the Council and 
as such are currently involved with the following project boards:
● Corporate Online Procurement System (COPS)
● Payroll e-Forms
● Housing and Council Tax Benefits Lean Thinking
● Shared Transactional Services
● Project Management Centre of Excel ence.
7.2.2 It is anticipate that Internal Audit wil  continue to provide support and guidance 
to all of the proposed changes as a result of the Transforming Bristol Plan and 
as such have made corporate Business Transformation provision in the 
annual Audit Plans for both 2008/9 and 2009/10.
7.3
External Reports
7.3.1 As well as internal audit work, the Audit Committee is able to draw assurance 
from external inspections and the recommendations they make.  So far this 
year there have not been a considerable number of external inspections, 
however the Committee wil  wish to be aware that the following external 
reports were received:
7

Report Received
Key Outcomes 
Ofsted - Annual 
Overall effectiveness of Children's Services was 
Performance 
graded as a 2 (Adequate) with 3/6 of the sub-sections 
Assessment letter for  scoring a 2 and 2/6 scoring a 3 (Good).  Areas for 
Children and Young  improvement have been identified in all 6 sections.
People in Bristol. 
This Performance Assessment is based on a self-
(2008)
assessment submission made by Children, Young 
People and Skil s Directorate.
The letter was brought to the attention of the 
Executive Member for Children's Services in 
December 2008.
CSCI - Annual 
There are two key judgements in this assessment, 
Performance 
Delivering Outcomes and Capacity to Improve.  For 
Assessment of Adult  2008 the Council rated as 'Good' for Delivering 
Social Care Services.  Outcomes and 'Promising' for Capacity to Improve, 
(2008)
with an overal  performance rating of 2 stars.  Key 
areas for development have been identified and wil  
be monitored throughout the year.
Report presented to the Care and Safer Communities 
Scrutiny Commission on 6th January 2009
I&DeA - Strategic 
This review concentrated on four key themes:
Housing Peer Review 
(October 2008)
● Leadership and Corporate Working
● Service User Focus and Resident Engagement
● Achieving Effective and Sustainable Outcomes
● People, Performance and Resource Management
Report presented to the Quality of Life Scrutiny 
Commission on 23rd March 2009.
8.
Other Options Considered
8.1 None necessary
9.
Risk Assessment
9.1 There are no risks arising directly from this report, although clearly the work of 
Internal   Audit   minimises   the   risk   of   failures   in   the   Council's   internal   control 
environment and governance arrangements, reduces the risk of fraud and other 
losses and increases the potential for prevention and detection of such issues.
10. Equalities Impact Assessment
10.1 None necessary for this report
8

11. Legal and Resource Implications
11.1 Legal - none sought
11.2 Resources  - none arising from this report 
Appendices
Appendix A Audit Work Completed and In Progress during the period 
01/12/2008 to 28/02/2009
Appendix B Summary of Audit Work Completed During the Period where 
Controls are not Adequate 
Appendix C Summary of Unplanned Work 
Appendix D Summary of Fraud and Irregularity
Appendix E Audit Fol ow Up Activity
LOCAL GOVERNMENT ACCESS TO INFORMATION
Background Papers
Exempt
9