This is an HTML version of an attachment to the Freedom of Information request 'Islington Town Hall Auditorium refurbishment'.
 
SECTION  7 
PRE-CONSTRUCTION INFORMATION 
 
 
Issue Date :  Oct 00 
 
 
Rev. No. :  0 
 
 
DMS-613 
P:\ProjectFiles-Al  Clients\Islington\739553-Auditorium\05 QS Info\Tender 
documents\Section 7 Pre Con Info.doc 
 

  F303h                                                                                                  
   
  Pre-Construction Information 
 
LBI- Auditorium 
 
Pre-Construction 
Information 
For; London Borough of Islington 
Upper Street 
London 
N1 2UD 
T:  020 7527 3807 
F:  020 7527 3152 
 

  F303h                                                                                                  
   
  Pre-Construction Information
 
Document Control Sheet 
Project Title 
 
Document Title 
Pre-Construction Information 
Revision 
01 
Status 
Issue 1 
Control Date 
31 October 2008 
Record of Issue 
 Issue 
Status  Author 
Date 
Check 
Date 
Authorised 
Date 
01 
Issue 1  J lLeyden 
31/10/08  R Stong 
31/10/08  O Taiwo 
31/10/08 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Distribution 
Organisation 
Contact 
Copies  Date 
Mouchel  
File Copy 

31/10/08 
Tender 
 
 
 
 
 
 
 
 
 
 
 
 
 
Version: 4.0 
Prepared by: Group Health & Safety 
Date of Issue: 01/08   

Authorised by: Oliver Gilmore 

  F303h                                                                                                  
   
  Pre-Construction Information
 
Contents 
Document Control Sheet _____________________________________________ i 
Contents __________________________________________________________1 
Introduction________________________________________________________3 
1  Description of the Project _________________________________________4 
1.1  Project description and programme details 

1.2  Location details:  Site Name 

1.3  Location Map 

1.4  Whether or not the structure wil  be used as a workplace 

1.5  The minimum time to be al owed between appointment of the principal  
 
contractor and instruction to commence work on site 

1.6  Extent and location of existing records and plans 

2  Client’s Considerations & Management Requirements _________________7 
2.1  Structure and organisation 

2.2  Planning and management of the construction work, including health and safety goals  7 
2.3  Client’s permit to work systems 

2.4  Emergency procedures and means of escape 

2.5  Site transport arrangements or vehicle movement restrictions 

2.6  Activities on, or adjacent to the site during the works 

2.7  Arrangements for communication and liaison between parties 

2.8  Security arrangements 

2.9  ‘No-go’ areas or other authorisation requirements for those involved in the  project 

2.10 Welfare provisions 

2.11 Site hoarding requirements 

2.12 Fire precautions 

2.13 Any areas the client has designated as confined spaces 

2.14 Smoking and parking restrictions 

2.15 Health and Safety of the Client’s Employees or those involved in the Project 

3  Environmental Restrictions and Existing On Site Risks _______________11 
3.1  Safety Hazards: 
11 
3.2  Health Hazards 
13 
4  Significant Design and Construction Hazards _______________________14 
4.1  Significant Design Assumptions and Suggested Work Methods 
14 
4.2  Arrangements for Co-ordination of Ongoing Design Work and Design Changes 
14 
Version: 4.0 
Prepared by: Group Health & Safety 
Date of Issue: 01/08   

Authorised by: Oliver Gilmore 

  F303h                                                                                                  
   
  Pre-Construction Information
 
 
4.3  Information on Significant Risks Identified During Design 
14 
4.4  4Materials Requiring Particular Precautions 
15 
5  The Health and Safety File _______________________________________17 
5.1  Layout and format 
17 
Version: 4.0 
Prepared by: Group Health & Safety 
Date of Issue: 01/08   

Authorised by: Oliver Gilmore 
 
 

  F303h                                                                                                  
   
  Pre-Construction Information
 
Introduction 
Objectives 
The Pre-Construction Information provides the health and safety focus for the design and construction 
phase of a project.  It sets out to ensure that the design and construction of the works are effected in a 
safe way that complies with current health and safety legislation, in particular the requirements of the 
Construction (Design and Management) Regulations 2007 and associated Approved Code of Practice. 
This information is included as part of the documentation issued to designers and contractors and is to 
be developed by the successful y appointed Principal Contractor prior to work commencing.  No work is 
to  commence  until  the  Principal  Contractor's  Construction  Phase  Plan  has  been  assessed  for  its 
adequacy. 
On  receipt  of  instructions  to  proceed  the  Principal  Contractor  is  under  a  legal  duty  to  administer, 
implement  and  update  the  Construction  Phase  Plan  throughout  the  contract  period  as  required  by 
changes in design or circumstances. 
Health and Safety Information 
During the pre-construction phase of a project, the Pre-Construction Information brings together health 
and safety information obtained from the Client and, where appropriate, Designers and the CDM Co-
ordinator. 
The  Construction  Phase  Plan  during  construction  wil   draw  on  the  Principal  Contractor's  health  and 
safety  policy  and  assessments,  the  Pre-Construction  Information  prepared  by  the  CDM  Co-ordinator 
and the details on the management and prevention of health and safety risks created by contractors 
and sub-contractors.  The Construction Phase Plan wil  continue to provide a co-ordinating mechanism 
as  construction  progresses.  The  Principal  Contractor  wil   be  required  to  maintain  the  Construction 
Phase Plan up to date for the duration of the Contract. 
Hazard Identification 
The hazards identified in this Pre-Construction Information are those identified during the initial design 
stage of the project.  Further risk assessments must be prepared by the Principal Contractor. 
The  hazards  identified  as  a  result  of  these  risk  management  procedures  shal   be  considered  by  the 
Principal Contractor during the development of the Construction Phase Plan that shal  be submitted for 
review prior to any works commencing. 
The Principal Contractor is required to take appropriate measures to control the risks created by these 
hazards, and any others he might recognise, and to prepare detailed method statements for managing 
these aspects of the works throughout the Contract. 
Version: 4.0 
Prepared by: Group Health & Safety 
Date of Issue: 01/08   

Authorised by: Oliver Gilmore 

  F303h                                                                                                  
   
  Pre-Construction Information
 
 
1  Description of the Project 

1.1  Project description and programme details 
The project is the refurbishment of the London Borough of Islington Town Hal  Auditorium.  Built in the 
Victorian  period  the  Town  Hal   is  an  excel ent  example  of  the  period  and  the  task  is  to  restore  the 
auditorium to its former glory.  The depth of the works is basical y an upgrade of the existing facility but 
with  the  addition  of  a  clear  glass  lift  in  the  foyer  for  disabled  access  and  smal   building  works  to 
accommodate the structure. The addition of a disabled toilet is also in the plans as wel  as a light and 
electrical upgrade. Some new carpets and upholstery works to the gal ery seating are also required.  
1.1.1 Key dates  
Design is ongoing and tender applications are expected by __ 31 Oct 08. 
The project is not expected to start until March 2009 with a contractors lead in time of 4 weeks. 
1.1.2 Name of Client: 
 
 
Mr John Roberts 
   
 
 
 
 
London Borough of Islington 
   
 
 
 
 
Islington Town Hal  
   
 
 
 
 
Upper Street 
   
 
 
 
 
Islington 
   
 
 
 
 
London N1 2UD 
 
 
Name of CDM Co-ordinator:   
James Leyden 
 
   
 
 
 
 
Mouchel Government and Business Services Limited 
 
   
 
 
 
 
Mount Pleasant House 
 
   
 
 
 
 
2 Mount Pleasant 
 
   
 
 
 
 
Cambridge 
 
   
 
 
 
 
CB3 0RN 
 
 
Name of Designers: 
 
Mr Roger Stong 
 
 
 
Mouchel Government and Business Services Limited  
 
 
 
 
 
 
Unit 311 Highgate Studios 
 
 
 
 
 
 
53-79 Highgate Road 
 
 
 
 
 
 
London 
 
 
 
 
 
 
NW5 1TL 
 
1.2  Location details: 
 
 
Islington Town hal  
   
 
 
 
 
Upper Street 
   
 
 
 
 
Islington 
   
 
 
 
 
London N1 
Version: 4.0 
Prepared by: Group Health & Safety 
Date of Issue: 01/08   

Authorised by: Oliver Gilmore 
 
 

  F303h                                                                                                  
   
  Pre-Construction Information
 
 
 
1.3  Location Map 
N   
 
  London Borough of Islington Town Hal  
Version: 4.0 
Prepared by: Group Health & Safety 
Date of Issue: 01/08   

Authorised by: Oliver Gilmore 
 
 

  F303h                                                                                                  
   
  Pre-Construction Information
 
 
 
1.4  Whether or not the structure will be used as a workplace 
The  structure  is  to  be  used  as  a  workplace  and  the  finished  design  wil   need  to  take  account  of the 
relevant requirements of the Workplace (Health, Safety and Welfare) Regulations 1992. 
1.5  The minimum time to be allowed between appointment of the principal contractor and 
instruction to commence work on site 
4  weeks  have  been  al owed  for  mobilisation  commencing  January  2009  and  is  to  be  completed  by 
February 2009. 
1.6  Extent and location of existing records and plans 
Other  Documents  can  be  obtained  from  the  Facilities  Manager  during  normal  office  hours.  He  is 
contactable on 0207-527-3107. These documents include the Asbestos log.  
The Health and Safety File in relation to other works and alterations carried out at the Town Hal  can 
also be obtained via the Facilities Manager, contactable on the number above at the Town Hal . 
 
Version: 4.0 
Prepared by: Group Health & Safety 
Date of Issue: 01/08   

Authorised by: Oliver Gilmore 
 
 

  F303h                                                                                                  
   
  Pre-Construction Information
 
 
2  Client’s Considerations & Management Requirements 

2.1  Structure and organisation 
The Town Hal  is the headquarters of the Council of the London Borough of Islington and as such has a 
complete management structure.  The Site Facilities Team Manager Mr Gareth Jenkins is responsible 
for the management of al  internal works. 
2.2   Planning and management of the construction work, including and health and   safety 
goals 
A designated Site Safety Officer is to be appointed by the Principal Contractor.  A copy of their CV is to 
be included with any tender documentation. 
Al  persons  working on or visiting the Works Site shal  receive a briefing concerning their health and 
safety by the Principal Contractor who shal  maintain a record of briefing to each individual. 
High visibility jackets, safety helmets and safety footwear must be worn by al  operatives and shal  be 
provided  by  the  Principal  Contractor  to  al   visitors  to  the  site.    Other  Personal  Protective  Equipment 
(PPE) shal  be worn to suit the task in hand. 
The Site shal  be kept clean and tidy and spoil and waste shal  be removed regularly in accordance with 
current regulations.  Burning of waste material is not permitted. 
Noise and dust shal  be kept to a reasonable minimum by the implementation of appropriate measures, 
so as not to interfere with the sites ongoing activities adjacent to the site. 
Workpeople shal  not trespass on land adjacent to the Site. 
Drinking and eating wil  only be permitted within the site accommodation and only after hand washing. 
Smoking onsite is strictly prohibited.  Arrangements for smoking should be discussed with the council 
representatives. 
Radios and cd/cassette players are not permitted on the Site. 
Plant  and  machinery  shal   be  adequately  silenced  and  appropriate  for  the  activity  being  undertaken.  
Large items of plant shal  be immobilized when not in use. 
The Principal Contractor shal  ensure al  workers receive site induction training covering, site access & 
egress routes, site rules, vehicles and storage, emergency and first aid conditions. 
Storage wil  only be permitted within the works site boundary, or as agreed with the Engineer. 
No alcohol is to be consumed by workpeople during normal working hours including rest breaks. 
Al  existing site features that are to remain shal  be adequately protected. 
Version: 4.0 
Prepared by: Group Health & Safety 
Date of Issue: 01/08   

Authorised by: Oliver Gilmore 
 
 

  F303h                                                                                                  
   
  Pre-Construction Information
 
 
2.3  Client’s permit to work systems 

Permits  to  Work  must  be  arranged  through  the  facilities  management  team  headed  by  Mr  Gareth 
Jenkins. 
2.4  Emergency procedures and means of escape 
The  Principal  Contractor  must  adopt  the  existing  building  safety  systems.    Information  on  these 
systems is available from the facilities team manager Mr Gareth Jenkins. 
2.5  Site transport arrangements or vehicle movement restrictions 
At present the forecourt to the rear of the auditorium is being renovated.  The pre contract meeting wil  
discuss the arrangements for parking and siting of PC’s cabins. 
2.6  Activities on, or adjacent to the site during the works 
The facilities manager has an up to date list of al  ongoing works.  The PC is asked to consult with him 
daily so that his programme can proceed safely. 
2.7  Arrangements for communication and liaison between parties 
The Principal Contractor shal  liaise with al  major stakeholders who wil  be affected or inconvenienced 
by the works. 
2.8  Security arrangements 
On set up the PC shal  receive notice of the needed security protection measures he must adopt. 
2.9   ‘No-go’ areas or other authorisation requirements for those involved in the project 
Areas not part of the works or welfare provision are out of bounds to the Principal Contractor and his 
staff. 
2.10  Welfare provisions 
The Principal Contractor wil  provide al  necessary welfare facilities for the workforce including messing, 
drying,  water  supply  and  telephone.    Toilet  facilities  can  be  arranged  but  only  subject  to  certain 
conditions that must be met.  The facilities manager wil  brief the PC accordingly. 
2.11  Site hoarding requirements 
Al   areas  should  be  secured  at  cease  work.    This  includes  access  to  the  hal   as  wel   as  access  to 
climbing towers.   
 
Version: 4.0 
Prepared by: Group Health & Safety 
Date of Issue: 01/08   

Authorised by: Oliver Gilmore 
 
 

  F303h                                                                                                  
   
  Pre-Construction Information
 
 
2.12  Fire precautions 

Adequate  first  aid  fire  appliances  should  be  provided  for  the  duration  of  the  works  by  the  PC.    Site  
Induction should include; the first aid appliances available, their suitability of use and details of how to 
activate.  Also a description of evacuation procedures and details of how to raise the alarm internal y 
which should match the systems already in place in the building. 
2.13  Any areas the client has designated as confined spaces 
The  only  recognised  areas  of  confined  spaces  are  in  the  hal   ceiling  voids.  These  areas  may  be 
accessed during the works period and if so a permit of work must be in place. 
2.14  Smoking and parking restrictions 
No smoking in Public buildings.  Parking is to be discussed at the first pre contract meeting. 
2.15  Health and Safety of the Client’s Employees or those involved in the Project 
The  Principal  Contractor  shal   ensure  strict  adherence  with  any  pre-determined  traffic/movement 
routes,  delivery  times  or  restrictions  identified  at  the  Contract  commencement,  and  shal   implement 
traffic/route management and safety measures to protect al  operatives, vehicles and pedestrians in the 
vicinity of the works. 
Pedestrian access is also to be control ed using appropriate signage. 
The Principal Contractor shal  appoint a dedicated Traffic Safety Officer who shal  be responsible for 
the operation and effectiveness of any traffic and pedestrian safety and management measures. 
The  Principal  Contractor  is  to  ensure  subcontractors  make  adequate  provision  for  the  selection  of 
drivers and general vehicle safety. 
A Client’s permit to work system operates on site for electrical work, confined spaces, work at height, 
hot works etc.  
The  Principal  Contractor  is  to  develop  a  fire  evacuation  procedure  that  is  compatible  with  the  fire 
evacuation  procedures  for  the  main  site.    The  Principal  Contractor  shal   provide  details  of  First  Aid 
cover on site and the name of the responsible person for fire safety. 
Areas of the main site outside the contractor’s construction area are no smoking zones. 
There are parking restrictions on site, constructors vehicles are only to be parked in designated areas 
as agreed. 
The  Principal  Contractor  wil   be  required  to  liaise  closely  with  al   major  stakeholders  to  ensure  that 
health and safety interfaces between the stakeholders activities and those of the Principal Contractor 
are ful y understood and adequately addressed in advance of the works being carried out. 
Version: 4.0 
Prepared by: Group Health & Safety 
Date of Issue: 01/08   

Authorised by: Oliver Gilmore 
 
 

  F303h                                                                                                  
   
  Pre-Construction Information
 
 
Working hours are to be 08.00 to 17.00 Monday to Friday.  There is to be no Saturday, Sunday or bank 
holiday working. 
The Principal Contractor is required to carry out risk assessments, and to prepare method statements 
explaining  the  proposed  measures  for  control ing  the  risks  created  by  the  interface  with  the  existing 
operations, and for managing these aspects of the works.  These are to be included in the Construction 
Phase Plan. 
Version: 4.0 
Prepared by: Group Health & Safety 
Date of Issue: 01/08   
10 
Authorised by: Oliver Gilmore 
 
 

  F303h                                                                                                  
   
  Pre-Construction Information
 
 
3  Environmental Restrictions and Existing On Site Risks 

3.1  Safety Hazards: 
3.1.1 Boundaries and access, including temporary access 
Access to the site wil  be where possible from the main front entrance. Security checks are in operation 
and  anything  brought  into  the  building  wil   be  security  checked.    Arrangements  are  to  be  made  with 
security staff for access and egress restrictions throughout the term of the contract.   
It is envisaged that the site compound wil  be located in the main hal . 
3.1.2 Adjacent land uses 
There is a primary school on the East elevation. 
Residential housing borders the north and south elevations 
There is a public footpath on the South elevation 
There is a public footpath on the West elevation along with a car park for staff and visitors 
There is a rear car park on the east elevation in continual use during office hours 
3.1.3 Existing storage of hazardous materials 
There  are  a  number  of  storage  facilities  on  site,  there  location  and  contents  wil   be  identified 
beforehand.  The  facilities  manager  wil   have  up  to  date  information  on  any  storage  of  hazardous 
materials. 
Any  petrol,  diesel  or  paints  are  to  be  kept  in  a  bunded  area,  gas  bottles  and  flammables  are  to  be 
stored in a lockable cage away from the build area. 
3.1.4 Location of existing services – water, electricity, gas etc.  
Existing  service  plans  location  of  existing  meters  and  any  relevant  O  &  M  documents  wil   be  made 
available prior to work commencing, these wil  be provided by Mr Gareth Jenkins. 
Details  of  existing  underground  services  are  held  on  site.    No  guarantee  can  be  given  as  to  the 
accuracy  of  the  services  information,  the  Principal  Contractor  shal   carry  out  investigations  as 
appropriate by locating the precise routes of known services prior to any ground works, to ensure that 
risks from foreseeable health and safety hazards are minimised or eliminated. 
3.1.5 Ground conditions 
N/A 
Version: 4.0 
Prepared by: Group Health & Safety 
Date of Issue: 01/08   
11 
Authorised by: Oliver Gilmore 
 
 

  F303h                                                                                                  
   
  Pre-Construction Information
 
 
3.1.6 Any restrictions on deliveries or waste col ection or storage 
Information wil  be given at the first pre-contract meeting. 
3.1.7 Previous structural modifications, including weakening or strengthening of the structure 
Existing  structures  may  be  subject  to  conservation  requirements,  advice  wil   be  given  prior  to  work 
commencing. These wil  include doors/glass screens/fixtures and fittings and other items deemed to 
be of architectural interest. 
Some  wal s  may  be  live.  Floors  are  to  be  protected  during  al   phases  of  work.  These  consist  of 
Terrazzo/Marble/Tile and Grano. 
3.1.8 Fire  damage,  ground  shrinkage,  movement  or  poor  maintenance  which  may  have  adversely 
affected the structure 
None known. The facilities manager should be consulted if any doubt exists.  
3.1.9 Any difficulties relating to plant and equipment in the premises, such as overhead gantries whose 
height restricts access 
No access for mechanical plant. Suitable scaffolding towers with sufficient protection required.  Lev ‘s 
required to remove dust.  
3.1.10  Health  and  safety  information  contained  in  earlier  design,  construction  or  ‘as-built’  drawings, 
such as details of pre-stressed or post-tensioned structures. 
None known contact the facilities manager for further details. 
 
 

Version: 4.0 
Prepared by: Group Health & Safety 
Date of Issue: 01/08   
12 
Authorised by: Oliver Gilmore 
 
 

  F303h                                                                                                  
   
  Pre-Construction Information
 
 
 
3.2  Health Hazards 
3.2.1   Asbestos, including results of surveys 
An  asbestos  management  pack  is  held  by  Mr  Jenkins,  there  wil   also  be  support  from  the  Councils 
Asbestos  data  base  manager.  The  management  pack  contains  al   information  to  date  on  asbestos 
surveys carried out on the site. 
3.2.2   Existing storage of hazardous materials 
There  are  a  number  of  storage  facilities  on  site,  there  location  and  contents  wil   be  identified 
beforehand should this project take you into close proximity. 
3.2.3 Contaminated land, including results of surveys 
None known. 
3.2.4 Existing structures containing hazardous materials 
Existing  structures  may  be  subject  to  conservation  requirements,  advice  wil   be  given  prior  to  work 
commencing. These wil  include doors/glass screens/fixtures and fittings and other items deemed to 
be of architectural interest. 
Some  wal s  may  be  live.  Floors  are  to  be  protected  during  al   phases  of  work.  These  consist  of 
Terrazzo/Marble/Tile and Grano. 
Records of hazardous materials contained in the existing structures are held on site and wil  be made 
available to the Principal Contractor by the facilities manager. 
3.2.5 Health risks arising from Client’s activities 
Building wil  be occupied by staff and visitors. There may also be other Contractors on site carrying out 
day to day maintenance. 
The Principal Contractor is required to take appropriate measures to control the risks created by these 
hazards,  to  explain  the  proposed  methods  in  his  Construction  Phase  Plan  and  to  prepare  detailed 
method statements for managing these aspects of the works. 
Version: 4.0 
Prepared by: Group Health & Safety 
Date of Issue: 01/08   
13 
Authorised by: Oliver Gilmore 
 
 

  F303h                                                                                                  
   
  Pre-Construction Information
 
 
4  Significant Design and Construction Hazards 

4.1  Significant Design Assumptions and Suggested Work Methods 
The works take place in an area of historic interest. Particular care is required to ensure no damage to 
existing features. 
No  internal  safety,  communication,  or  other  systems  are  to  be  modified  or  removed  without  prior 
permission of the facilities manager.   
4.2   Arrangements for Co-ordination of Ongoing Design Work and Design Changes 
The  procedures  for  the  consideration  and  acceptability  of  the  health  and  safety  implications  of 
contractor  prepared  designs  shal   fol ow  the  principles  of  prevention  and  protection  and  take  into 
account those issues highlighted in this Pre-Construction Information. 
Details of health and safety hazards, which cannot be eliminated, are to be submitted to the CDM Co-
ordinator,  together  with  the  proposals  for  mitigation  or  control,  in  sufficient  time  to  al ow  adequate 
consideration by the CDM Co-ordinator. 
Procedures  for  dealing  with  unforeseen  events  during  the  project  which  result  in  substantial  design 
changes and which might affect the project are as fol ows: 
•  The  CDM  Co-ordinator  is  to  be  immediately  informed  by  the  Principal  Contractor  of  the 
circumstances relating to the event. 
•  The health and safety issues arising from any unforeseen occurrence are to be submitted to the 
CDM Co-ordinator as soon as is practicable. 
•  In the event that any re-design is required, for whatever reason, the health and safety implications 
of the modified design shal  be submitted for consideration to the CDM  Co-ordinator in due time 
before execution. 
The Principal Contractor is to confirm the arrangements for monitoring and reviewing the compliance 
with health and safety issues in the Construction Phase Plan. 
4.3  Information on Significant Risks Identified During Design 
The  Principal  Contractors  designers  are  to  provide  information  with  the  design,  of  where  significant 
risks remain, to ensure that the CDM Co-ordinator, other designers and contractors are aware of these 
risks and can take account of them. 
The fol owing hazards have been identified that may pose a risk to the health and safety of construction 
workers  and  others  authorised  to  be  on  the  Site.    The  Principal  Contractor  is  required  to  control  the 
risks  from  these  hazards,  and  to  prepare  detailed  risk  assessments  and  method  statements  for 
managing these aspects of the works. 
Version: 4.0 
Prepared by: Group Health & Safety 
Date of Issue: 01/08   
14 
Authorised by: Oliver Gilmore 
 
 

  F303h                                                                                                  
   
  Pre-Construction Information
 
 
4.3.1 Identified Hazards 
•  Working adjacent to live site. 
•  Working on site adjacent to other contractors. 
•  Working in the vicinity of live services. 
•  Movement of plant / delivery of materials. 
•  Working in close vicinity of the General Public 
•  Working at Height 
•  Working in dust rich atmosphere. 
•  Working with unknown materials/Paints/finishes etc 
•  Noise 
•  Restricted light. 
•  Manual Handling. 
•  Confined spaces. 
•  Puwer 
•  Loler 
•  Mobile plant (LEV) 
If material is discovered during excavation that the Principal Contractor considers may be a hazard to 
the  workforce  the  Client  and  CDM  Co-ordinator  shal   be  informed  immediately  and  an  appropriate 
course of action agreed. 
4.3.2 Common place Hazards 
Commonplace  site  hazards  not  identified  above  are  considered  to  be  within  the  expertise  of  a 
competent contractor and must be control ed by normal good site management practice. 
4.3.3 Method Statements 
The  Principal  Contractor  wil   be  required  to  demonstrate  by  safety  method  statements  incorporating 
appropriate Safety Management Systems and Procedures, his assessment of the risks to employees 
and others arising from the above hazards (and any others he might recognise) and how he intends to 
manage and control these risks. 
The Construction Phase Plan and / or method statements shal  also include the Contractor’s proposed 
sequencing of the works for consideration and acceptance by the Client.  This should include a typical 
traffic management layout, and the overal  proposed phasing of the works. 
4.4  Materials Requiring Particular Precautions 
4.4.1 Existing asbestos. 
The Islington Town Hal  should have a ful y up to date Asbestos register.  The register is to be signed 
by the Principal contractor before any work has started. 
 
Version: 4.0 
Prepared by: Group Health & Safety 
Date of Issue: 01/08   
15 
Authorised by: Oliver Gilmore 
 
 

  F303h                                                                                                  
   
  Pre-Construction Information
 
 
4.4.2  Common materials 
Common materials (such as concrete, mortar) and substances and plant fuels used during construction 
wil   present  health  and/or  safety  hazards.    These  are  considered  to  be  within  the  experience  of  a 
competent contractor, and should be control ed by the application of COSHH procedures. 
4.4.2 Unusual or dated materials 
Care  should  be  taken  to  identify  the  original  materials  used  in  the  original  features  of  this  very  old 
building. A ful  assessment of any materials should be considered before sanding, stripping or other 
dust provoking actions are carried out. Lead pipework is stil  in use in water and sewage systems. 
 
Version: 4.0 
Prepared by: Group Health & Safety 
Date of Issue: 01/08   
16 
Authorised by: Oliver Gilmore 
 
 

  F303h                                                                                                  
   
  Pre-Construction Information
 
 
5  The Health and Safety File 

5.1  Layout and format 
Two  hard  copies  of  the  Health  and  Safety  File  shal   be  prepared  as  the  works  progress  and  wil   be 
delivered to the Client at the completion of the works. 
The  contents  of  the  Health  and  Safety  File  wil   record  the  works  carried  out  on  the  project  and  wil  
provide  relevant  as  built  information  to  enable  the  Client  to  establish  appropriate  procedures  for  the 
future repair, maintenance or dismantling of the works without risks to persons health and safety. 
Two copies of al  information should also be issued in an electronic format.  The format of the electronic 
data issued is to be as fol ows:  Al  documents and product data sheets are to be in PDF format, Design 
Team drawings are to be in PDF and Autocad DWG format. 
The Principal Contractor shal  col ate al  appropriate information as it becomes available, and this shal  
subsequently be passed to the CDM Co-ordinator for inclusion in the File. 
The  Principal  Contractor  is  urged  to  implement  an  early  procedure  that  advises  contractors  and 
materials suppliers of the detailed requirements for this record information. 
This Pre-construction information has been prepared by; 
Mouchel Government and Business Services Limited  
Unit 311 Highgate Studios 
53-79 Highgate Road 
London 
NW5 1TL 
 
from information col ected from the client and project designers. 
 
It is approved for issue on behalf of Mouchel  by : 
 
 
 
 
Mr J Leyden  RMaps 
CDM Co-ordinator 
 
 
 
 
Date: 31sth October 2008 
 
Version: 4.0 
Prepared by: Group Health & Safety 
Date of Issue: 01/08   
17 
Authorised by: Oliver Gilmore 
 
 

Document Outline