This is an HTML version of an attachment to the Freedom of Information request 'Non Stop Gov software issues'.

PROJECT: FOI (Freedom of Information) & DPA (Data Protection Act) process re-engineering

Date: 9th December 2008

Project Sponsor: Andrea Glanville

Project Manager: Stuart Flanagan and Chris Jones

Project Objectives: To investigate the functionality of the Non Stop Gov system in line with current FOI and DPA processes.

Project Scope:

Project Team: Stuart Flanagan, Chris Jones

Project Approach: To meet with key stakeholders including NSG system administrator.

Project Deliverables: To look at system module ability of the NSG in line with FOI and DPA processes and requirements including

Communication Plan: All relevant parties when identified.

Risk Register: Resources unable to meet due to Christmas Period and leave

Timescales: 16th January 2009

Sign Off:

______________ _______________ ______________

Project Sponsor Project Manager Programme Manager

Project Initiation Document

Printed on 22/04/2009 Page 2 of 2 File: PID for FOI and DPA.doc

Form: PMTK 06 Issue 01

0x01 graphic
Project Initiation Document

Printed on 22/04/2009 Page 1 of 1 File: PID for FOI and DPA.doc

Form:- PMTK 06 Issue 01