This is an HTML version of an attachment to the Freedom of Information request 'DNSR safety Improvement Notice'.
UNCLASSIFIED 
 
MINISTRY OF DEFENCE 
DEFENCE NUCLEAR SAFETY REGULATOR 
NUCLEAR PROPULSION REGULATOR 
XXXXXXXXXXXXX 
 
DNSR/ 17/9/891 
Yew 2 c 
#1254 Abbey Wood 
Bristol, BS34 8JH 
See distribution 
Direct line: 
XXXXXXXX 
 
Fax 
XXXXXXXX 
 
e-mail: 
XXXXXXXXXXXXX 
 
 
 
 
Date : 22 April 2010 
 
Dear Sirs, 
 
DNSR SAFETY IMPROVEMENT NOTICE - BABCOCK EVENT No 19720 : FAILURE TO 
REINSTATE PRIMARY SAFETY SYSTEMS 
 
REFERENCES:  
  
A. 
DNSR/17/9/883 dated 16 April 2010, DNSR INVESTIGATION INTO BABCOCK EVENT No 
19720: FAILURE TO REINSTATE PRIMARY SYSTEMS. 
B. 
Babcock Marine / DE&S Interim Report of Joint Investigation – 12 March 2010 
 
1. 
This is a Safety Improvement Notice, following from a DNSR investigation into Babcock 
Event no 19720 (Reference A), which led to the extended operation of 2 platforms with a disabled 
primary safety system on a Nuclear Safety Implicated pressure system.  
  
2. 
The key failing in the sequence of events was that the BM Nuclear Procedure allowed hull 
valve blanks to remain fitted after the Nuclear Procedure was closed, without explicitly including a 
control to ensure their removal.  However, the TXB facility operator and NRPA as joint operators 
are considered responsible as those in control when the reactor was taken critical.  
 
3. 
That the information on the blanks fit was captured and then lost by all 3 parties on more 
than one occasion indicates a failure of safety culture as defined by the IAEA, and shortfalls 
against  Authorisation/ Licence Conditions 17, 21 and 22.  
 
4. 
BM are required to amend their business processes, such that safety significant changes 
cannot be introduced to nuclear procedures without an associated step to confirm that the 
additional hazard has been removed or mitigated, prior to closure of the Nuclear Procedure. This 
should be completed by the time of the undocking of HMS Trenchant. 
 
5. 
 BM and the TXB Facility Operator are required to review their documentation to identify the 
potential for other similar, open ended procedural changes, and to provide appropriate assurance 
to the Regulators that the risk is appropriately managed, prior to the undocking of HMS Trenchant. 
 
6. 
BM, TXB and NRPA are required to review their procedures to ensure that key safety 
information is clearly identified when transferred at handover from procedure to procedure, or PAG 
to PAG. This should be completed by end of July, 2010. 
 
7. 
Prior to plant start up, NRPA  as operator, and the TXB Facility Operator are required to 
review the close out of their processes to assure themselves that they do all that could reasonably 
be expected to mitigate the risks to plant and platform from the work completed in that 
maintenance period. This should complete by the end of July 2010.  
 
 
 
UNCLASSIFIED 
 
 

UNCLASSIFIED 
 
8. 
NRPA and BM are required to present their interface arrangements to the Regulators, and to 
clarify how they relate to the identification and management of safety issues in practice, by end of 
June, 2010. 
 
9. 
The content of this letter has been agreed with HSE-NII. 
 
 
 
 
 
(Signed on original) 
 
 
 
XXXXXXXXXXXXX 
Nuclear Propulsion Regulator 
Defence Nuclear Safety Regulator 
 
Distribution 
 
To: 
 
NRPA , Cdre S Dearden, RN 
Babcock Marine for the attention of Mr. Mike Homer 
HMNB Devonport NBCD, Cdre I Jess, RN 
 
Copies: 
 
 
Internal External 
 
 
SM IS-Hd 
 
FLEETXXXX SM X CSOE XXXXXX 
 
NRPA NP-Safety, XXXXXXXXXXXXX 
NII Div.3 Propulsion SI, XXXXXXXXXXXXX 
NBCD CBS, XXXXXXXXXXXXX 
NII Div.3 DRDL PI, XXXXXXXXXXXXX  
DNSR-Hd  
DNSR I(CD) 
Babcock Marine, XXXXXXXXXXXXX 
DNSR I(OR) 
Babcock Marine, XXXXXXXXXXXXX 
DNSR I(CD)-a 
Babcock Marine, XXXXXXXXXXXXX 
File 
Babcock Marine, XXXXXXXXXXXXX 
 
 
 
 
 
 
 
 
 
UNCLASSIFIED 
 
 

Document Outline