This is an HTML version of an attachment to the Freedom of Information request 'Contract with Thales for National ID Scheme'.
Final 
Internal review of response to requests under the Freedom of Information (FoI) Act 
2000 by Mr Peter Collingbourne (reference 10676 and 11863)  
 
Responding Unit:  Identity and Passport Service 
 
Chronology 
 
Request 10676 (Thales contract)
Original FoI request: 
 
 
28 November 2008  
 
Acknowledgement: 
   5 
December 
2008 
 
 
IPS letter explaining delay: 
 
28 December 2008 
 
Request for internal review (time delay): 28 March 2009 
 
Internal review (time delay) response:  29 May 2009 
 
IPS response: 
 
 
 
9 July 2009 
 
Follow-up questions 
 
 
10 July 2009 
 
IPS response to follow-up questions 
17 August 2009 
 
Request 11863 (CSC contract)
Original FoI request: 
 
 
12 May 2009 
 
Acknowledgement: 
   19 
May 
2009 
 
PIT extension letter  
 
 
11 June 2009 
 
IPS response: 
 
 
 
10 July 2009 
 
Request for internal review: 
 
19 August 2009 
(both requests) 
 
Subject of requests 
 
1.  In his request of 28 November 2008, Mr Collingbourne asked for a copy of the 
following documents, which he said formed part of a contract signed on 1 August 
2008 with Thales Information Systems to support IPS in delivering early releases 
of the National Identity Scheme (NIS): 
 
• The thirty-six Service Agreement Schedules and annexes (in the order 1-36, or 
2-36 followed by 1 if Schedule/Annex 1 is entitled "Definitions"). 
 
1

Final 
• The Service Agreement which contains conditions specific to a contract. 
• The Framework Agreement which sets out the core terms for contracts 
awarded. 
• Any and all other documents which form a part of this contract, in ascending 
order of the number of pages within the document. For documents with the 
same number of pages, the documents should be considered in ascending 
alphabetical order of their titles. 
 
2.  Mr Collingbourne asked that IPS should supply â€œas many pages as possible, 
starting with page 1 of the document appearing first in the ordering as specified 
above, and proceeding sequentially through the pages of this document followed 
by the remainder of the above listed documents, in order, to the extent that my 
request would not be subject to exemption under section 12 of the FOIA”. 
 
3.  Mr Collingbourne made a similar request on 12 May 2009, for documents which 
he said formed part of a contract awarded on 7 April 2009 to CSC to upgrade the 
application and enrolment system in IPS: 
 
• The Service Agreement Schedules and annexes (in the order 1-x, or 2-x 
followed by 1 if Schedule/Annex 1 is entitled "Definitions", where x is the 
number of documents). 
• The Service Agreement which contains conditions specific to a contract. 
• The Framework Agreement which sets out the core terms for contracts 
awarded, if different to the Framework Agreement with Thales. 
• Any and all other documents which form a part of this contract, in ascending 
order of the number of pages within the document. For documents with the 
same number of pages, the documents should be considered in ascending 
alphabetical order of their titles. 
 
4.  Mr Collingbourne again asked that IPS should “supply as many pages as possible, 
starting with page 1 of the document appearing first in the ordering as specified 
above, and proceeding sequentially through the pages of this document followed 
by the remainder of the above listed documents, in order, to the extent that my 
request would not be subject to exemption under section 12 of the FOIA”. 
 
Procedural issues 
 
5.  IPS acknowledged Mr Collingbourne’s first request (relating to the Thales contract) 
on 5 December 2008.  On 28 December 2008 IPS wrote to Mr Collingbourne to 
say that they were unable to provide a full response to the request within 20 
working days, as required by the FoI Act, but were dealing with the request as a 
matter of urgency and would aim to send a substantive reply by 26 January 2009. 
On 28 March 2009, not having received a reply, Mr Collingbourne wrote to ask for 
an internal review of the IPS handling of his request.  That internal review, which 
was carried out by the Information Access Team and sent to Mr Collingbourne on 
29 May 2009, concluded that section 10(1) of the FoI Act had been breached.  A 
reply to Mr Collingbourne’s first request was finally sent by IPS on 3 July and 
again on 9 July 2009 (as the e-mail of 3 July did not reach Mr Collingbourne). 
 
 
2

Final 
6.  IPS acknowledged Mr Collingbourne’s second request (relating to CSC) on 19 
May 2009 and on 11 June sent a Public Interest Test extension letter, explaining 
that the requested information had to be considered under the exemption in 
section 43 of the FoI Act (Commercial interests) and that they aimed to respond by 
8 July.  The response to Mr Collingbourne’s second request was sent on 10 July. 
 
7.  It is good practice to acknowledge FoI requests, even though this is not a 
requirement of the FoI Act.  I note that IPS did so in both these cases, although 
the acknowledgements might have been sent a little sooner. Acknowledgements 
should wherever possible be sent within one or two days of receipt of an FoI 
request. 
 
8.  The IPS letter of 28 December 2008, while it was helpful in providing Mr 
Collingbourne with a progress report on his first request, did not say explicitly that 
the public interest was being considered in relation to any part of the request. The 
letter therefore did not constitute a notice under section 17(1) of the FoI Act and it 
did not provide a valid public interest extension of the time allowed for a response 
under section 10(3) of the Act.  I agree with the conclusion of the internal review 
(time delay) of May 2009, which concluded that section 10(1) of the FoI Act was 
breached in relation to the first of Mr Collingbourne’s two requests. 
 
9.  The IPS letter of 11 June 2009 was a properly worded notice under section 17(1) 
of the Act and gave Mr Collingbourne notice that the public interest was being 
considered in relation to his second request.  As such it provided a proper 
extension of the time al owed for a response under section 10(1).  I would add the 
caveat that it was sent one day outside the time limit for sending a notice under 
section 17(1) (i.e. 20 working days, the same time for responding to a request 
under section 10(1)).  I also note that the letter of 11 June referred to section 43 of 
the Act (Commercial interests) rather than to sections 12 and 22 under which the 
information was eventually withheld. 
 
The responses by IPS 
 
10. The IPS response to Mr Collingbourne’s first request (Thales) was that the 
information requested is exempt from disclosure under sections 12(1) and 22(1) of 
the FoI Act (relating to cost and intention to publish respectively). In applying these 
exemptions, IPS acknowledged that there is public interest in disclosure because 
IPS are committed to providing as much transparency on contracts for the 
National Identity Scheme as they can. IPS explained to Mr Collingbourne that an 
exercise had been commissioned within IPS to release further contractual 
information, under which IPS would publish summaries of the contracts for the 
Scheme including those to be awarded in the coming months. IPS said that this 
would provide as much information as IPS was able, without prejudicing 
commercial interests, personal data or security interests. The information would be 
made available on the IPS website and a copy would be sent to Mr Collingbourne. 
 
11. IPS said that the section 12(1) exemption applied to Mr Collingbourne’s first 
request as a whole, not on an 'incremental' basis. The case against disclosure 
was that, in order for IPS to comply with the request without incurring excessive 
cost, a more refined request would be required to understand the exact 
 
3

Final 
information Mr Collingbourne required. A public interest test could then be 
conducted in regard of any potential commercial, technical or security information 
within the documentation. IPS nevertheless believed that the summary contracts 
they intended to publish would, as far as practically possible, provide the 
information Mr Collingbourne had requested. 
 
12. The IPS response to Mr Collingbourne’s second request (CSC) was essentially 
the same as that to the first. 
 
Mr Collingbourne’s follow-up questions and requests for internal review 
 
13. On 10 July 2009 Mr Collingbourne asked a number of questions in respect of the 
IPS response to his first request.  These questions, which were treated by IPS as 
a new FoI request, are set out in the attached Annex.
14. IPS replied to these points on 17 August 2009.  The IPS response is set out below 
each question in the Annex.
15. On 19 August 2009 Mr Collingbourne asked for an internal review of the IPS 
response to his first request, in the following terms: 
 
“I disagree that IPS is able to apply the section 22(1) exemption. The language 
of this exemption refers to an intention to publish that existed "at the time when 
the request for information was made" (FOIA s.22(1)(b)). However, according 
to a further response received from IPS (ref FOICR 12395/09), the decision to 
prepare the information to be published was made on 1 July 2009, well after 
my request was made on 28 November 2008. 
Even if this were not the case, IPS does not have an apparent intention to 
publish the information I requested in all cases. According to the same 
response from IPS, the intention to publish does not exist for documents with 
"commercial, security or technical sensitivity". Instead of the redacted 
documentation being released, IPS only plans to release a summary which 
may not contain all releasable information in the document. 
Turning to the section 12 exemption, I disagree that this applies at all due to Mr 
J Jenkins v Information Commissioner and Department for Environment, Food 
and Rural Affairs, EA/2006/0067. Please remember that your own policy 
cannot override the decisions of the Information Tribunal which in our common 
law legal system should be considered law. Even if the exemption did apply, I 
also disagree that a refined request is necessary to "understand the exact 
information [I] require". In my original request I have been very specific about 
which documents and even which pages I would like you to consider and in 
which order and I fail to see how I can be more specific than this.” 
 
16. On the same date, 19 August 2009, Mr Collingbourne also asked for an internal 
review of his second request (CSC) in similar terms. 
 
Consideration of the response 
 
17. The two requests were similar in form, albeit in respect of different information, 
and the responses were the same in each case.  The main point at issue in this 
 
4

Final 
review is therefore whether sections 12(1) and 22(1) of the FoI Act were properly 
applied in withholding the information which Mr Collingbourne requested in the two 
requests. 
 
Section 12(1)
18. Section 12(1) exempts a public authority from complying with a request for 
information if the authority estimates that the cost of complying with the request 
would exceed the appropriate limit.  The factors which may be taken into account 
when estimating the cost are set out in regulation 4(3) of the Freedom of 
Information and Data Protection (Appropriate Limit and Fees) Regulations 2004.  
Under regulation 4(3) a public authority make take account only of the costs it 
reasonably expects to incur in: 
 
(a) determining whether it holds the information; 
(b) locating the information, or a document which may contain the information; 
(c)  retrieving the information, or a document which may contain the information; 
and 
(d) extracting the information from a document which may contain it. 
 
19. The full information which Mr Collingbourne requested is, I understand, held in a 
discrete and readily accessible document or set of documents.  It therefore seems 
clear that none of the factors at (a) â€“ (c) in paragraph 18 apply in this case.  It is 
less clear whether (d) can be said to apply.  In citing section 12(1) in response to 
these two requests, IPS based their estimate on the cost of physically removing 
information which is exempt from disclosure under one or more of the exemptions 
in Part II of the FoI Act. 
 
20. The Information Tribunal case (Jenkins) to which Mr Collingbourne refers in his 
request for an internal review considered, among other things, whether the words 
“extracting the information from a document containing it” (in regulation 4(3)(d)) 
include the redaction of exempt information containing it. In that case the Tribunal 
found that â€œthe removal of what may be thought to be exempt material, even at the 
stage at which the exercise is carried out, cannot sensibly be viewed as coming 
within the provisions of regulation 4(3)(d) as it is presently drafted” and that â€œthe 
exercise which a public authority may embark on in order to consider whether an 
exemption applies and the extent to which material otherwise disclosable may be 
subject to an exemption, is a separate exercise”.  It should be pointed out that the 
Tribunal did also say in its judgement that â€œthe point is not entirely free from 
doubt”. 
 
21. It is well established that the estimated cost of examining documents in order to 
identify exempt information may not be taken into account in estimating costs for 
the purpose of section 12.  This was fully recognised when the responses to the 
two requests were first formulated.  The position established by IPS at the time 
was that removal of exempt information, even where it had already been identified, 
would mostly have to be done on a line by line basis and would exceed the cost 
limit if it were carried out for the entire documents. 
 
 
5

Final 
22. The Government recognises the position of the Information Commissioner and the 
Information Tribunal that the cost of physically removing exempt information may 
not be taken into account in estimating costs for the purposes of section 12(1), but 
does not necessarily accept it.  The Government’s position, reflected in existing 
Ministry of Justice (MoJ) guidance on FoI, is that the cost of physical redaction can 
and should be taken into account where appropriate and this wil  remain the 
position until such time as it is tested in the courts. 
 
23. There is clearly room for disagreement on this point, but given that the use by IPS 
of section 12(1) in this case was based on the costs of physical redaction and 
reflected the Government’s current interpretation of the legislation and MoJ 
guidance, it is difficult to conclude that it was in principle unreasonable.  However, 
the use of section 12(1) was not based on a detailed assessment of the cost of 
redacting material from the two contracts.  At that stage, IPS had not identified 
what parts of the documents were exempt from disclosure, so any estimate of the 
costs involved in redacting such information would necessarily have been broad.  
The documents are very large and the cost of physically redacting exempt 
information might well have been over the limit, but in general the use of section 
12(1) in responding to an FoI request should be backed up by evidence of the 
costs involved. In the absence of a more detailed estimate than was provided at 
time, the use of section 12(1) at the time is difficult to uphold.  
 
24. Mr Collingbourne specifically asked that extracts from the two contracts should be 
provided on a progressive basis up to the point at which the cost limit was 
incurred.  IPS were not obliged to do this, although it is not entirely clear what was 
meant by the statement that the section 12(1) exemption applied to the requests 
“as a whole, not on an 'incremental' basis” or by the suggestion that a more 
refined request was required to understand the exact information that Mr 
Collingbourne required.   
 
Section 22(1)
25. Information is exempt from disclosure under section 22(1) if the following three 
conditions are met: 
 
(a) the information is held with a view to future publication; 
(b) the information was already held with a view to such publication at the time the 
request was made; and 
(c)  it is reasonable in all the circumstances that the information should be withheld 
until the publication date. 
 
26. IPS have stated that they intend to publish summaries of the contracts with Thales 
and CSC for the National Identity Scheme by the end of February 2010. I 
understand that these summaries wil  provide as much information as IPS are able 
to publish without prejudicing commercial interests, personal data or security 
interests.  I also understand that the summaries wil  where possible use the 
documents themselves, unaltered.  Where this is not possible, due to commercial, 
security or technical sensitivities, a summary wil  be provided (the summaries wil  
not be redacted versions of the originals).  IPS wil  publish the reasons for 
 
6

Final 
withholding any information which is not released, citing the relevant sections of 
the FoI Act. 
 
27. By definition a summary does not constitute the full information in the two 
contracts which Mr Collingbourne requested.  Publication of the summaries 
cannot, therefore, in itself be used as a basis on which to withhold under section 
22(1) all the information which has been requested.  Any information not included 
in the summaries wil , I understand, be exempt from disclosure under some other 
section of the Act because of the commercial, security or other considerations to 
which IPS have referred, but if so exemption must be on those grounds rather 
than section 22(1).  Exemption under section 22(1) can by definition only apply to 
information which wil  be published. 
 
28. It is questionable whether the condition at section 22(1)(c) was met in this case, 
i.e. whether there was an intention to publish at the time the requests were made.  
IPS have said explicitly, in response to a question from Mr Collingbourne, that the 
decision to publish the contract summaries was made following Ministerial 
approval on 1 July 2009.  Both requests were made before that date and it 
therefore seems clear that the condition is not met. 
 
29. The fact that summaries of the contracts are to be published at some stage is, 
clearly, relevant to Mr Collingbourne’s requests and it was quite right that IPS 
should explain this to Mr Collingbourne, not least in order to provide the ‘advice 
and assistance’ required by section 16 of the FoI Act.  For the reasons considered 
in paragraphs 27 and 28, such publication cannot in itself be used as a reason for 
withholding under section 22(1) all the requested information. The correct course 
would have been to apply section 22(1) to the information which is to be published 
and the relevant sections of the Act to the information which is to be withheld 
because of commercial, security or other sensitivities. 
 
Other exemptions
30. The responses to both of Mr Collingbourne’s requests relied wholly on sections 
12(1) and 22(1) to withhold information.  As mentioned in paragraph 9, however, 
the public interest extension letter sent to Mr Collingbourne in respect of his 
second request referred to section 43 of the Act (Commercial interests), 
suggesting that this exemption was at least under consideration at some stage.  It 
would be surprising if some parts of two contracts of this nature were not 
commercially sensitive and hence exempt under section 43.  Moreover, IPS have 
referred to commercial sensitivity in their responses to the two requests, in the 
context of the summaries which are to be published. 
 
31. IPS have also referred, in the context of the summaries, to personal data and 
security and technical considerations, which suggests that other exemptions in the 
FoI Act are relevant to some parts of the two contracts.  IPS did not rely on section 
43 or these other exemptions presumably because that would have required a 
detailed examination of the documents which had not yet been completed.  
 
32. I understand that a detailed examination of the contracts for information which is 
sensitive from a personal, commercial, security or other point of view has been 
 
7

Final 
undertaken in order to prepare the summaries which IPS intend to publish. IPS 
have stated that, although they do not intend to publish a redacted version of the 
actual contracts, they wil  nevertheless use the documents themselves unaltered 
where possible and wil  provide a summary where it is not. IPS have also said that 
they will include the reasons for not releasing information and under which part of 
the FoI Act information has been withheld. The summaries which will be 
published, together with the references to the sections of the FoI Act under which 
information is withheld, will in terms of the information which they provide (if not 
the exact format) be that which would be provided in a full and proper response to 
an FoI request such as those which Mr Collingbourne has made. 
 
Conclusions 
 
33. The IPS response to Mr Collingbourne’s first request was provided well outside 
the 20-working day limit and, in the absence of a public interest extension, was in 
breach of section 10(1) of the FoI Act. 
 
34. The IPS response to Mr Collingbourne’s second request was subject to a proper 
public interest extension, subject to the caveat that the extension letter was sent 
one day outside the 20-working day limit and that it referred to section 43 of the 
FoI Act when the final response relied on completely different exemptions. 
 
35. The use of section 12(1) of the FoI Act in responding to Mr Collingbourne’s 
requests reflected the current Government position and MoJ advice that the cost 
of physically redacting exempt information may be taken into account. However, in 
the absence of a detailed estimate of the costs involved, based on the cost of 
redacting information which had been identified as being exempt, the use of 
section 12(1) should not have been relied upon.  
 
36. IPS were not obliged to provide extracts from the two contracts up to the point at 
which the cost limit was incurred. IPS should have considered whether to provide 
some information to Mr Collingbourne to help him refine his request, but this has 
now been rendered unnecessary by the intention to publish the summaries.  
 
37. Section 22(1) of the FoI Act was used incorrectly in responding to Mr 
Collingbourne requests, first because the published information wil  not cover all 
the information which he requested and secondly because the decision to publish 
was not taken until after the requests were made. The relevant sections of the Act 
should have been applied to the information which is to be withheld because of 
commercial, security or other sensitivities. 
 
38. IPS should send a revised response to Mr Collingbourne’s requests, based on the 
summaries which wil  be published together with the references to the sections of 
the FoI Act under which information is withheld.  
 
Information Access Team 
Home Office 
4 February 2010

 
8

Final 
Annex: Mr Collingbourne’s follow-up points on request 10676 and the IPS 
response 
 

Mr Collingbourne’s question: 
 
“You mention an exercise commissioned within IPS to release further contractual 
information. On what date did IPS make a decision to embark on this exercise? 
 
IPS response: 
 
“IPS gained Ministerial approval to embark on this exercise on 1 July 2009.” 
 
Mr Collingbourne’s question: 
 
“You mention contract summaries. Are these planned to be redacted versions of the 
full contracts or separately drafted documents? If the former, are the redactions 
planned to be only those allowed by the Freedom of Information Act? Please state the 
date on which the plans referred to in this question were made.” 
 
IPS response: 
“The documents wil  be summaries of the contracts awarded. Where possible this wil  
use the documents themselves unaltered and where this is not possible due to a 
commercial, security or technical sensitivity we would provide a prĂŠcis of the relevant 
document. We wil  also include the reasons for not releasing the information, under 
which part of the Freedom of Information Act this has been made and an indication of 
how long such a position is likely to be maintained. We do not intend to publish a 
redacted version of the actual contract documentation. The decision to produce the 
contract summaries was, as stated earlier, made following Ministerial approval on the 
1st July 2009.”  
 
Mr Collingbourne’s question: 
 
“Please confirm or deny whether IPS holds a draft of its summary of the Thales 
contract.” 
 
IPS response: 
 
“IPS does not hold a draft summary of the Thales contract. Work has already been 
commissioned to produce the summaries and this work continues.” 
 
 
9