This is an HTML version of an attachment to the Freedom of Information request 'Procurement of Contractors and Construction Consultancy Services'.
 
SNH News and Information Notice 
 
 
 
Subject  :  Procurement Procedures for Contracts 
£10,000 and over - Tender Timescales & 
Introduction of 10 Day Standstill Period 
Name  :  Information Notice No 249 - Procurement Procedures for 
Contracts £10,000 and over and the introduction of the 
Standstill Period 
Custodian Unit  :  Business Support Services (036) 
Internal Audience  :  All Staff 
Approved by  :  Head Of Business Support Services 
Date Valid  :  26/02/2010 
Date for Review  :  26/02/2011 
 
 
 
Notice Sub-Types 
1.  Instruction Note. 
Issued on behalf of Management Team, it must be applied as directed, except where a section is 
clearly marked as ‘Advisory’ when an element of local judgement can be applied. You must get in 
touch with the Custodian Unit if for any reason you think that circumstances make it inappropriate to 
implement the mandatory content of an Instruction Note. Please also let the Custodian Unit know if 
you have any suggestions for improving an Instruction Note. 
2.  Advice Note. 
Issued as advice to staff.  Flexibility and judgement can be exercised in deciding how best to apply 
content in local circumstances. You should get in touch with the Custodian Team if you have any 
questions or doubts about implementing the content of an Advice Note or if you have suggestions for 
improving it. 
3.  News and Information Notice. 
Communications issued on an ad hoc basis to inform staff of specific facts or events.  
This document is uncontrolled when stored in hard copy or an electronic 
format other than eRDMS.  Please do not save copies, and only print where 
absolutely necessary. 
eRDMS File: Procurement Information Notices  
Document ID: B527144 
 
Page 1 of 6 

 
Table Of Contents 
Page 
 
TIMETABLE FOR CONTRACTS £10,000 AND OVER...................................................... 2 
Steps, Time-scales and Awarding a Contract................................................................. 2 
  
TIMETABLE FOR CONTRACTS £10,000 AND OVER 
 
The purpose of this News and Information Notice is to remind staff of the procurement 
processes and the time-scales to advertise, tender and award a contract that exceeds the 
value of £10,000.00. 
If you have had approval of a bid that is £10,000 or more to take forward in financial year 
2010-11, you are required to carry out a full competitive tendering exercise.  It is important 
that you plan ahead and take the following information into account when planning your 
projects, this will also ensure that the procurement team can help you achieve the required 
time-scales. 
Introduction of 10 Day Standstill Period: What is the 10 day standstill period and how 
does it affect my project? 
As mentioned above a 10 day standstill period is being implemented with immediate effect, 
this applies to all contracts that are awarded through the procurement team.  The standstill 
period is applied once the nominated officer has selected their preferred supplier.  All 
bidders are e-mailed informing them of who SNH intends to award the contract to.  The 
unsuccessful bidders are then given 10 working days to appeal the decision.   
PLEASE NOTE: The standstill period is not applicable if you are using an already 
established framework agreement and / or contract to appoint a supplier. 
Steps, Time-scales and Awarding a Contract 
£1,000 to £4,999.99 inc. VAT 
X 3 Telephone Quotes 
£5,000 to £9,999.99 inc. VAT 
X 3 Written Quotes 
£10,000 to £24,999.99 net VAT 
All Paperwork to Procurement 
Full Competitive Tendering Exercise 
Up to 8 Weeks 
£25,000 to £156,442 net VAT 
Full Competitive Tendering Exercise 
Up to 10 Weeks 
£156,442 and Over 
Full European Tendering Exercise 
Very Minimum of 3 months 
 
eRDMS File: Procurement Information Notices  
Document ID: B527144 
 
Page 2 of 6 

 
NB: Please remember to take account of Public Holidays and Privilege Holidays. 
The table below sets out the steps and time-scales to carry out a full competitive tendering 
exercise.   
Time is of the essence.  Forward planning and remembering to give your chosen supplier 
sufficient time to carry out the services / works you have contracted them to do. 
Stage 
Action 
Time 
 
New Contract 
Nominated officer forward all documentation to 
Up to 8 weeks 
Opportunities between 
Procurement.  Please provide procurement with 
the value of : 
the following information / documentation: 
£10,000 and 
Requisition (listing all suppliers being invited to 
£24,999.99 
tender (ITT), providing full contact details i.e. 
names, addresses etc); 
Statement of Requirements (SoR); 
Any other documents relevant to what you are 
procuring. 
Procurement carry out full competitive tendering 
exercise on behalf of the nominated officer. 
Please note: if you are trained in using the new 
iBuy purchasing system you will complete a 
requisition on-line and provide procurement with 
objective reference nos. for all the above-
mentioned documents. 
New Contract 
New contract opportunities are advertised using  It is 
Opportunities 
the Public Contracts Scotland portal.  
recommended 
between the value of : 
that a Contract 
http://www.publiccontractsscotland.gov.uk/ 
Notice (advert) is 
£25,000 and 
When you have completed your Contract Notice  advertised for a 
£156,442.00 need to 
(advert) you should e-mail either:  
minimum of 10 
be advertised. 
[email address]  or 
working days (2 
Nominated Officer 
[email address] 
weeks). 
advertises the contract 
This will allow procurement  to publish the 
opportunity 
notice,  please provide us with the following 
Advertising Helpdesk 
information: 
No. 01463 725086 or 
The Title and Contract Notice ID no.   
725085 
Please note: Procurement recommend that at 
this stage we give an indicative number of how 
many bidders we will eventually invite to tender 
– please discuss with Procurement.   
Evaluating the Pre 
Once the deadline date of your Contract Notice 
This is really 
Qualification 
has expired, you evaluate the PQQs.  PLEASE 
dependant on 
Questionnaires 
NOTE: You don’t have to wait until the deadline 
you the 
(PQQs) 
date to have passed to evaluate the PQQs you 
nominated 
receive, you can evaluate them as & when you 
officer and on 
receive them.   
how many PQQs 
you receive. 
You will be given an Objective file to save all 
your PQQs into (This will help ease your e-mail 
(Minimum 1 
eRDMS File: Procurement Information Notices  
Document ID: B527144 
 
Page 3 of 6 

 
box).  An evaluation matrix can be found on the 
week (5 working 
Procurement Microsite under Advertising. 
days). 
NB: Please provide a name of an alternative 
 
contact who can answer any queries / questions   
in your absence. 
Please remember to send a courtesy e-mail to 
all the suppliers, who registered an interest & 
returned a completed PQQ but were not 
successful in being short-listed to be Invited to 
Tender). 
After the PQQs have 
Send to procurement a list of the suppliers you 
Procurement 
been Evaluated 
have shortlisted to be Invited to Tender (ITT) 
always aim to 
along with any other documents necessary for 
issue ITTs within 
the issuing of the ITT.  
a 48 hour 
turnaround. This 
Ensure you provide us with full contact details of  is providing we 
each Supplier being invited to tender (names, 
are in receipt of 
addresses, e-mail addresses etc.).   
all the relevant 
If trained in using iBuy you complete your 
documents & all 
requisition on-line and provide procurement with  paperwork is in 
objective reference nos. for all other documents.  order. 
Issuing the 
Procurement will issue the ITTs - providing we 
A minimum of 
Invitations to Tender 
are in receipt of all the necessary documents. 
15 working 
(ITT) 
days is usually 
NB: Should you the nominated officer receive 
recommended 
any questions / queries from the bidders, please  for bidders to 
consult with Procurement first.  ALL answers to 
return their bids.  
queries etc must be put out via procurement & 
These time-
NOT the nominated officer.  Procurement may 
scales can be 
have to consult with nominated officer 
altered – please 
dependant on the nature of the question / query 
discuss with 
being asked. 
procurement. 
NB: Please provide the details of an alternative 
contact who in your absence can answer any 
queries / questions received not of a 
procurement nature.  
 
Return of Tender 
Procurement will conduct a Tender Board on 
The Tender 
Submissions (Bids) 
the tender return date & forward all bids to the 
Submission may 
nominated officer.   
take a few days 
to be delivered 
The bids received may not be posted out on the  depending on 
day the Tender Board is conducted. This may 
your location.   
be due to circumstances beyond our control.  In 
the case of Great Glen House, the bids will be 
delivered by hand. 
Evaluation of Tender 
On receipt of the bids, you the nominated 
Evaluation of 
Submissions 
officer, & if appropriate the evaluation panel will 
bids – 
evaluate all the bids submitted & select your 
dependant on 
eRDMS File: Procurement Information Notices  
Document ID: B527144 
 
Page 4 of 6 

 
preferred supplier(s).  
the nominated 
officer & 
An evaluation matrix can be found on the 
evaluation panel. 
Procurement Microsite, it is located under 
Evaluations.   
Once the evaluation has been completed & the 
preferred supplier(s) selected, complete the 
back of the Tender Summary sheet with your 
preferred supplier(s) details & return the 
summary sheet along with all the originals of the 
bids to procurement.   
Should you select the Other Than Lowest 
Tender (OTLT), you need to provide 
procurement with a justification, in the format of 
a standard SNH memo.  Clearly stating your 
reasons why you have opted for the OTLT.  
Reasons need to be robust in order to allow 
procurement in the absence of the nominated 
officer to provide constructive & meaningful 
feedback to any unsuccessful contractor who 
makes such request. 
Standstill Period 
Once procurement receive your 
10 working days 
recommendation.  Procurement will e-mail all 
(2 weeks).  The 
bidders stating who SNH intend awarding the 
day the e-mail is 
contract to.  There will then be 10 working days 
issued is classed 
for the unsuccessful bidders to appeal the 
as Day 0 (zero) 
decision. 
NB: The 10 day standstill period is a standard 
requirement when conducting an EU tendering 
exercise, to ensure compliance this requirement 
is now being applied to sub-threshold contract 
opportunities. 
Contract Award 
As soon as the 10 day standstill period has 
Procurement’s 
Letter/Purchase 
expired & none of the unsuccessful bidders 
aim is to issue 
Order 
have logged an appeal, procurement will go 
the award within 
ahead & issue the contract award / purchase 
48 hrs of the 
order. 
expiry of the 
standstill period 
or as soon after. 
Contract Start Date & 
Please bear in mind the following hints & tips 
 
Forward Planning 
when planning to take forward a project: 
(Hints & Tips) 
Contract Notices (adverts) & Statement of 
Requirements (SoRs) should always clearly 
state when you would expect works to 
commence, this allows interested suppliers & / 
or invited suppliers to plan their workloads & 
give them as much lead-in time as possible; 
Select an alternative contact to answer any 
eRDMS File: Procurement Information Notices  
Document ID: B527144 
 
Page 5 of 6 

 
queries etc. in your absence & provide these 
details in both your contract notice & at ITT 
stage. 
These hints & tips are based on feedback we 
received after attending a “Meet the Research 
Contractors day” held at BBY in 2008.  
  
If you have any queries please contract: 
 
Procurement Help Desk 01463 725097, or 
Public Contracts Scotland Portal Helpdesk: 01463 725086 – 01463 725085 
E-mail: [email address] or [email address]  respectively. 
 
eRDMS File: Procurement Information Notices  
Document ID: B527144 
 
Page 6 of 6