SCHEDULE V 
AUTHORITY’S RESPONSIBILITIES 
 
Schedule V (Authority’s Responsibilities) 
 
CCN050 
Version 4.0  
 
RESTRICTED – COMMERCIAL 

NPIA 
IDENT1 CONTRACT 
Northrop Grumman
 
RESTRICTED – COMMERCIAL 
 
CONTENTS 
 
 
1. 
SCOPE ...................................................................................................................................... 2 
2. 
AUTHORITY’S RESPONSIBILITIES................................................................................. 2 
3. 
AUTHORITY’S RESPONSIBILITIES FOR LANTERN PILOT PHASE 2 .................. 10 
4. 
AUTHORITY’S RESPONSIBILITIES FOR IDENT1 SERVICES FOR UKVISAS..... 10 
5. 
AUTHORITY'S RESPONSIBILITIES FOR LANTERN SERVICE EXPANSION…..10 
 
 
Schedule V (Authority’s Responsibilities) 

15 January  2007 
Version 3.3 CCN040R4 
 
 
 
 
RESTRICTED – COMMERCIAL 

NPIA 
IDENT1 CONTRACT 
Northrop Grumman
 
RESTRICTED – COMMERCIAL 
 
SCHEDULE V 
 
AUTHORITY’S RESPONSIBILITIES  
1. 
SCOPE 
1.1 
The Authority shall comply with its responsibilities regarding the information, data, materials 
and  manpower  as  described  in  the  table  set  out  in  Clause  2  below  (the  “Authority’s 
Responsibilities”).   
1.2 
If the Authority fails to perform the Authority’s Responsibilities set out in this Schedule, the 
provisions of Clause 45 of Schedule B (Conditions of Contract) shall apply. 
2. 
AUTHORITY’S RESPONSIBILITIES 
CATEGORY 
AUTHORITY’S 
QUANTITY 
COMPLIANCE 
RESPONSIBILITY – 
DEADLINE FOR 
THE AUTHORITY 
PERFORMANCE OF 
SHALL PROVIDE: 
THE RELEVANT 
AUTHORITY’S 
RESPONSIBILITY 
DATA AND 
 
 
 
DOCUMENTATION 
- FOR ENGLAND 
AND WALES 
 
1.  Appropriate access 
All marks, ten prints  At Effective Date. 
and rights to use  
and palms that 
Operational NAFIS 
comprise the 
central databases, 
national collection. 
subject to the data 
protection provisions 
set out in Clause 31 
of Schedule B 
(Conditions of 
Contract).  
 
2.  Appropriate access 
All marks, ten prints  At Effective Date. 
and rights to use 
and palms that are 
Operational NAFIS 
maintained at the 
bureaux databases, 
individual bureau. 
subject to the data 
protection provisions 
set out in Clause 31 
of Schedule B 
(Conditions of 
Contract).   
 
3.The Authority shall 
All MOUs 
At Effective Date for 
use its Commercially 
developed during 
NAFIS Bureaus and with 
Reasonable 
the delivery and 
effect of CCN010 
Endeavours to ensure 
support of NAFIS 
“National Livescan 
that the NAFIS 
and NAFIS 
Services” for NAFIS 
Bureaux MOUs 
Livescan. 
Livescan until EOS1 by 
(existing prior to the 
which time the Contractor 
Effective Date) and 
will have developed and 
NAFIS Livescan 
delivered new IDENT1 
MOUs  (existing 
MOU’s to all Forces.  
Schedule V (Authority’s Responsibilities) 
2  
CCN050 
Version 4.0  
 
 
 
 
RESTRICTED – COMMERCIAL 

NPIA 
IDENT1 CONTRACT 
Northrop Grumman
 
RESTRICTED – COMMERCIAL 
 
CATEGORY 
AUTHORITY’S 
QUANTITY 
COMPLIANCE 
RESPONSIBILITY – 
DEADLINE FOR 
THE AUTHORITY 
PERFORMANCE OF 
SHALL PROVIDE: 
THE RELEVANT 
AUTHORITY’S 
RESPONSIBILITY 
prior to CCN010, 
“National Livescan 
Services”) continue 
until the Contractor 
enters into new 
MOUs by EOS1.  If  
the Authority is 
unable to comply 
with this Authority’s 
Responsibility due to 
any issue(s) raised by 
a Police Force, the 
Parties will work 
together with the 
relevant Police Force 
to resolve such 
issue(s) or, if 
appropriate, the 
Parties may amend 
the relevant existing 
NAFIS Bureau and / 
or NAFIS Livescan 
MOU(s) to address 
such issue(s).  If the 
Parties are unable to 
resolve any issue 
raised by the relevant 
Police Force, the 
Parties will escalate 
the matter in 
accordance with 
Schedule P (Dispute 
Resolution 
Procedure). 
 
4. Relevant benchmark 
1M records (fingers 
At Effective Date and to 
data sets. 
and palms) and 
be available for use 
corresponding set of  throughout the IDENT1 
search marks, prints 
programme, subject to the 
and palms. 
Contractor complying 
with the data protection 
provisions set out in 
Clause 31 of Schedule B 
(Conditions of 
Contract). 
 
5. Relevant Palm Test 
Palm test data 
20 days after the 
Data. 
(background 
Effective Date subject to 
database and 
the data protection 
corresponding 
provisions set out in 
Schedule V (Authority’s Responsibilities) 
3  
CCN050 
Version 4.0  
 
 
 
 
RESTRICTED – COMMERCIAL 

NPIA 
IDENT1 CONTRACT 
Northrop Grumman
 
RESTRICTED – COMMERCIAL 
 
CATEGORY 
AUTHORITY’S 
QUANTITY 
COMPLIANCE 
RESPONSIBILITY – 
DEADLINE FOR 
THE AUTHORITY 
PERFORMANCE OF 
SHALL PROVIDE: 
THE RELEVANT 
AUTHORITY’S 
RESPONSIBILITY 
search palms) to be 
Clause 31 of Schedule B 
used in the Fairfax 
(Conditions of 
Test Facility. 
Contract). 
FACILITIES – FOR 
 
 
 
ENGLAND AND 
WALES 
 
 
1.  NAFIS operations 
Lease of 
At Effective Date. 
and computer hall 
Contractor’s 
work area at Hendon 
existing space at 
Data Centre. 
Hendon Data Centre 
to be continued until 
EOS1 with options 
to extend in yearly 
increments to the 
end of the Contract, 
subject to the terms 
and conditions 
(including any 
termination rights) 
of the lease for the 
Hendon Data 
Centre.   
 
 
 
2.  NAFIS and NAFIS 
All relevant NAFIS 
At Effective Date and up 
Livescan facilities at 
and NAFIS 
until expiry of the MOU.  
existing bureau 
Livescan equipment 
 
locations.  
and facility space 
(to include 
communications, 
electrical cabling 
and UPS, where 
currently provided 
by the forces) to be 
provided as detailed 
within the then 
current MOU. 
 
3.  MIS workstation 
Desktop workspace 
Effective Date + 30 days.   
space at NKBH and 
and access to power 
Hendon. 
and 
communications for 
MIS workstation.  
Subject to the 
provisions of Clause 
45 of Schedule B 
(Conditions of 
Contract), the 
Schedule V (Authority’s Responsibilities) 
4  
CCN050 
Version 4.0  
 
 
 
 
RESTRICTED – COMMERCIAL 

NPIA 
IDENT1 CONTRACT 
Northrop Grumman
 
RESTRICTED – COMMERCIAL 
 
CATEGORY 
AUTHORITY’S 
QUANTITY 
COMPLIANCE 
RESPONSIBILITY – 
DEADLINE FOR 
THE AUTHORITY 
PERFORMANCE OF 
SHALL PROVIDE: 
THE RELEVANT 
AUTHORITY’S 
RESPONSIBILITY 
liability to the 
Authority under this 
Authority 
Responsibility, 
should NKBH and 
Hendon facilities 
not be available, is 
solely limited to the 
provision of the 
MIS workstation at 
NKBH and Hendon. 
 
4.  Appropriate 
 
Monthly PSRs, and 
conference room 
formally schedule design 
space for monthly 
reviews. 
programme reviews 
at an appropriate 
location, including 
locations in 
Scotland.  Where it 
is mutually agreed to 
use a Contractor’s 
facility, the 
Contractor shall be 
liable for all costs of 
providing the 
facility, excluding 
the Authority’s 
travel, 
accommodation and 
staff costs. 
 
5.  Agreed facility space  The Authority will 
As the Parties agree to 
at all National 
use its reasonable 
meet CCN010 “National 
Livescan Services 
endeavours to 
Livescan Services” 
locations for 
provide space at 
proposed roll out 
installation of 
each of the 
schedule. 
Livescan / EIUs 
proposed National 
subject to site 
Livescan Services 
survey. 
sites. This space 
will be subject to 
the site survey as 
detailed in Schedule 
Q (Contractor’s 
Solution). 
LABOUR - FOR 
 
 
 
ENGLAND AND 
WALES 
 
1.  An appropriate 
Such number of 
As the Parties agree to 
number of 
fingerprint offices to  meet the relevant 
Schedule V (Authority’s Responsibilities) 
5  
CCN050 
Version 4.0  
 
 
 
 
RESTRICTED – COMMERCIAL 

NPIA 
IDENT1 CONTRACT 
Northrop Grumman
 
RESTRICTED – COMMERCIAL 
 
CATEGORY 
AUTHORITY’S 
QUANTITY 
COMPLIANCE 
RESPONSIBILITY – 
DEADLINE FOR 
THE AUTHORITY 
PERFORMANCE OF 
SHALL PROVIDE: 
THE RELEVANT 
AUTHORITY’S 
RESPONSIBILITY 
fingerprint officers to  be determined by 
Milestones in Schedule G 
participate at UK 
the Authority, as 
(Transition). 
Prototyping 
detailed in Schedule 
Laboratory to 
G (Transition) and 
evaluate HCI. 
Schedule Q 
(Contractor’s 
Solution). 
 
2.  An appropriate 
Such number of the 
 As the Parties agree to 
number of Authority 
Authority personnel 
meet the relevant 
personnel to 
to be determined by 
Milestones in Schedule G 
participate in 
the Authority and 
(Transition). 
operational tests in 
detailed in Schedule 
the UK prior to 
H (Acceptance 
deployment of 
Procedures). 
releases. 
 
3.  Appropriate number 
As detailed in 
 As the Parties agree to 
of PNC staff to 
Schedule H 
meet the relevant 
support regression 
(Acceptance 
Milestones in Schedule G 
and integration test 
Procedures). 
(Transition). 
of new IDENT1 
functionality and 
testing of 
enhancements to 
existing 
functionality. 
DATA AND 
 
 
 
DOCUMENTATION 
– FOR SCOTLAND 
 
1.  Relevant legacy 
 
As the Parties agree to 
SAFR tenprint, palm 
meet the relevant 
and mark data 
Milestones in Schedule G 
subject to the data 
(Transition). 
protection provisions 
set out in Clause 31 
of Schedule B 
(Conditions of 
Contract). 
 
2.  Provide the approval   
As the Parties agree to 
to obtain the 
meet the relevant 
Livescan to SAFR 
Milestones in Schedule G 
“Interface Contract 
(Transition). 
Document”. 
 
3.  Pre-existing CHS 
Access to technical 
As the Parties agree to 
Interface 
staff to define the 
meet the relevant 
Specification 
interface. 
Milestones in Schedule G 
information. 
(Transition). 
Schedule V (Authority’s Responsibilities) 
6  
CCN050 
Version 4.0  
 
 
 
 
RESTRICTED – COMMERCIAL 

NPIA 
IDENT1 CONTRACT 
Northrop Grumman
 
RESTRICTED – COMMERCIAL 
 
CATEGORY 
AUTHORITY’S 
QUANTITY 
COMPLIANCE 
RESPONSIBILITY – 
DEADLINE FOR 
THE AUTHORITY 
PERFORMANCE OF 
SHALL PROVIDE: 
THE RELEVANT 
AUTHORITY’S 
RESPONSIBILITY 
 
4.  Make available Palm   
As the Parties agree to 
prints maintained in 
meet the relevant 
paper collection with 
Milestones in Schedule G 
URNs to identify the 
(Transition). 
related ten print 
subject to agreed 
management 
processes. 
 
5.  Provide reasonable 
The Authority shall 
As the Parties agree to 
assistance in the 
submit the 
meet the relevant 
submittal of IDENT1  documentation / 
Milestones in Schedule G 
Livescan EIU for 
specification 
(Transition). 
device approvals.  
provided by the 
For the avoidance of 
Contractor 
doubt, the Authority 
regarding IDENT1 
is not responsible for 
Livescan / EIU’s to 
the subsequent 
the appropriate 
approval or length of 
Minister in 
the approval period.  
Scotland. 
It is the Contractor’s 
responsibility to 
meet the relevant 
specification. 
 
6.  No less than a dozen 
The Authority will 
As the Parties agree to 
samples of Scottish 
provide such 
meet the relevant 
ten print forms, with 
fingerprint data as 
Milestones in Schedule G 
sample 
agreed in a sanitised  (Transition). 
representative CHS 
/ generic form for 
data for use in 
training.  In addition 
developing IDENT1 
the Authority will 
training, subject to 
provide 
the data protection 
representative 
provisions set out in 
examples of CHS 
Clause 31 of 
data from one or 
Schedule B 
both of the two 
(Conditions of 
CHS training 
Contract). 
databases. 
FACILITIES - FOR 
 
 
 
SCOTLAND 
 
1.  Agreed facility space  The Authority will 
As the Parties agree to 
for IDENT1 
use its reasonable 
meet the relevant 
operational Bureaux 
endeavours to 
Milestones in Schedule G 
system in Scotland 
provide space at the 
(Transition). 
(for the avoidance of 
SCRO site at Pacific 
doubt, this shall not 
Quay. This space 
apply for the parallel 
will be subject to 
Bureau). 
the site survey as 
detailed in Schedule 
Schedule V (Authority’s Responsibilities) 
7  
CCN050 
Version 4.0  
 
 
 
 
RESTRICTED – COMMERCIAL 

NPIA 
IDENT1 CONTRACT 
Northrop Grumman
 
RESTRICTED – COMMERCIAL 
 
CATEGORY 
AUTHORITY’S 
QUANTITY 
COMPLIANCE 
RESPONSIBILITY – 
DEADLINE FOR 
THE AUTHORITY 
PERFORMANCE OF 
SHALL PROVIDE: 
THE RELEVANT 
AUTHORITY’S 
RESPONSIBILITY 
Q (Contractor’s 
Solution). 
 
2.  Agreed facility space  The Authority will 
As the Parties agree to 
at all Scottish 
use its reasonable 
meet the relevant 
Livescan locations 
endeavours to 
Milestones in Schedule G 
for installation of 
provide space at 
(Transition). 
Livescan / EIUs 
each of the 
subject to site 
proposed sites. This 
survey. 
space will be 
subject to the site 
survey as detailed in 
Schedule Q 
(Contractor’s 
Solution). 
 
3.  Pre-existing facility 
 
As the Parties agree to 
layouts, including 
meet the relevant 
appropriate pre-
Milestones in Schedule G 
existing wiring 
(Transition). 
diagrams for power 
and communications 
to support equipment 
installations at the 4 
Bureau in Scotland. 
LABOUR - FOR 
 
 
 
SCOTLAND 
 
1.  Reasonable number 
As detailed in 
As the Parties agree to 
of fingerprint staff 
Schedule G 
meet the relevant 
(as agreed with the 
(Transition) and 
Milestones in Schedule G 
Authority) to 
Schedule Q 
(Transition). 
confirm 
(Contractor’s 
identification of 
Solution). 
respondents from 
IDENT1 search prior 
to adding to unified 
collection. 
 
2.  Reasonable number 
 
As the Parties agree to 
of Staff (as agreed 
meet the relevant 
with the Authority) 
Milestones in Schedule G 
to support design, 
(Transition). 
development and 
testing of the 
integrated SCRO 
CHS into IDENT1. 
 
3.  Post EOS1 – 
As detailed in 
Post EOS1 as agreed by 
reasonable number 
Schedule H 
both parties. 
of SCRO CHS staff 
(Acceptance 
to support testing 
Procedures). 
and regression 
Schedule V (Authority’s Responsibilities) 
8  
CCN050 
Version 4.0  
 
 
 
 
RESTRICTED – COMMERCIAL 

NPIA 
IDENT1 CONTRACT 
Northrop Grumman
 
RESTRICTED – COMMERCIAL 
 
CATEGORY 
AUTHORITY’S 
QUANTITY 
COMPLIANCE 
RESPONSIBILITY – 
DEADLINE FOR 
THE AUTHORITY 
PERFORMANCE OF 
SHALL PROVIDE: 
THE RELEVANT 
AUTHORITY’S 
RESPONSIBILITY 
testing of new and 
enhanced IDENT1 
capabilities. 
EOS2 
 
 
 
 
Schedule G, Annex G-
 
As the Parties agree to 
5, Item 40 SLA 
meet the relevant 
between Contractor 
Milestones in Schedule G 
and third parties. 
(Transition) 
Coordination of MOU 
agreement and signature 
(i.e. must broker) 
between the Contractor 
and external service 
providers (list of 
external service 
providers to be provided 
by Contractor). 
Schedule V (Authority’s Responsibilities) 
9  
CCN050 
Version 4.0  
 
 
 
 
RESTRICTED – COMMERCIAL 

NPIA 
IDENT1 CONTRACT 
Northrop Grumman
 
RESTRICTED – COMMERCIAL 
 
 
3. 
AUTHORITY’S RESPONSIBILITIES FOR LANTERN PILOT PHASE 2 
The Authority is responsible for delivery of all CFE/CFI required under this CCN014R2, including 
the following CFE/CFI required for this CCN014R2 “LANTERN Pilot Phase 2 - Implementation 
Phase”: 
•  the C&W PDA SRAS functionality as defined in Cable & Wireless Proposal "CJX Remote 
Access for PDA's - Version for Northrop Grumman", version 2.3, dated 18th October 2005', 
•  all C&W SRAS deliverables, including approved SRAS software and the next version of the 
Aventail SSL VPN for an enhancement to simplify start-up for the operator and to fix to a 
current fault that prevents operation of the full SRAS stack,  
•  liaison with the Police Forces, and  
•  all Force GPRS hardware and software for GPRS connectivity. 
The Authority is responsible for delivery of all CFE/CFI from its contractors to Northrop Grumman: 
•  that satisfy and meet the LANTERN Pilot Phase 2 requirements, and 
•  on or before the critical dates as set out in the proposed roll-out schedule. 
 
4. 
AUTHORITY’S RESPONSIBILITIES FOR IDENT1 SERVICES FOR UKVISAS 
The additional Authority’s Responsibilities in respect of IDENT1 Services for UKvisas are set out in 
Annex V-1. 
5. 
AUTHORITY’S RESPONSIBILITIES FOR LANTERN SERVICE EXPANSION 
The Authority is responsible for delivery of all CFE/CFI required under this LANTERN Service 
Expansion: 
•  All C&W SRAS deliverables, including approved SRAS software,  
•  Provision of all C&W Certificate Authority capability for LANTERN, 
•  Liaison with the Police Forces, and  
•  All Force GPRS hardware and software for GPRS connectivity. 
 
Schedule V (Authority’s Responsibilities) 
10  
CCN050 
Version 4.0  
 
 
 
 
RESTRICTED – COMMERCIAL