| Building 1000 Remedial Works Relating to non-DDA Items - Provisional Programme | |||||||||||||||||||
| Note: Timings are subject to change when contractors proposals are received. Some items will depend upon contractors proposals and cannot be programmed at this time. | |||||||||||||||||||
| ID | Task | June | July | August | September | October | |||||||||||||
| 25 | 2 | 9 | 16 | 23 | 30 | 6 | 13 | 20 | 27 | 3 | 10 | 17 | 24 | 1 | 8 | 15 | 22 | ||
| 1 | Bowmer and Kirkland Items | ||||||||||||||||||
| 2 | |||||||||||||||||||
| 3 | Podium deck waterproofing, cracked slabs and steelwork, mastic repairs | ||||||||||||||||||
| 4 | Fosroc site visit to agree details | ||||||||||||||||||
| 5 | Fabers drainage details to be prepared | ||||||||||||||||||
| 6 | Auketts movement joint proposals to be prepared | ||||||||||||||||||
| 7 | Procure subcontractor | ||||||||||||||||||
| 8 | Mobilisation / lead-in | ||||||||||||||||||
| 9 | Order spare paving slabs and delivery | ||||||||||||||||||
| 10 | Site works - entrance area | ||||||||||||||||||
| 11 | Site works - north walkway | ||||||||||||||||||
| 12 | Site works - west podium | ||||||||||||||||||
| 13 | Site works - east podium | ||||||||||||||||||
| 14 | |||||||||||||||||||
| 15 | Replace other cracked paving slabs | ||||||||||||||||||
| 16 | |||||||||||||||||||
| 17 | Renew mastic to joints in retaining wall at SE/SW corners | ||||||||||||||||||
| 18 | Apply mastic to ends of stair treads at NW/NE/SE/SW corners | ||||||||||||||||||
| 19 | |||||||||||||||||||
| 20 | Inspection of cracked steelwork by original installer and reporting | ||||||||||||||||||
| 21 | Prepare remedial proposals | ||||||||||||||||||
| 22 | Undertake repairs | ||||||||||||||||||
| 23 | |||||||||||||||||||
| 24 | Glazing gasket repairs | ||||||||||||||||||
| 25 | Schedule works | ||||||||||||||||||
| 26 | Carry out survey and repairs | ||||||||||||||||||
| 27 | |||||||||||||||||||
| 28 | Improve plant room ventilation | ||||||||||||||||||
| 29 | Place order and lead-in | ||||||||||||||||||
| 30 | Delivery and installlation of fans/ducting | ||||||||||||||||||
| 31 | |||||||||||||||||||
| 32 | Decomo rainscreen stone panel repairs | ||||||||||||||||||
| 33 | Site inspection by Decomo and reporting | ||||||||||||||||||
| 34 | Prepare full remedial proposal | ||||||||||||||||||
| 35 | Undertake site repairs or replace cracked panels | ||||||||||||||||||
| 36 | |||||||||||||||||||
| 37 | Roof walkway and latchway systems | ||||||||||||||||||
| 38 | Site visit by original installer (Keybemo) and report | ||||||||||||||||||
| 39 | Remedial works as appropriate | ||||||||||||||||||
| 40 | |||||||||||||||||||
| Building 1000 Remedial Works Relating to DDA Priority 4 Items - Provisional Programme (numbers in brackets cross-reference to agreed outline method statement) | |||||||||||||||||||
| Note: Timings are subject to change when contractors proposals are received. Some items will depend upon contractors proposals and cannot be programmed at this time. | |||||||||||||||||||
| ID | Task | June | July | August | September | October | |||||||||||||
| 25 | 2 | 9 | 16 | 23 | 30 | 6 | 13 | 20 | 27 | 3 | 10 | 17 | 24 | 1 | 8 | 15 | 22 | ||
| 41 | DDA Items | ||||||||||||||||||
| 42 | |||||||||||||||||||
| 43 | Ark to re-visit site and confirm issues and remedial preferences | ||||||||||||||||||
| 44 | |||||||||||||||||||
| 45 | High visibility strip required to bollards (1) | ||||||||||||||||||
| 46 | Identify suitable product | ||||||||||||||||||
| 47 | Apply product where needed | ||||||||||||||||||
| 48 | |||||||||||||||||||
| 49 | Relocate and re-sign disabled car park spaces (2 & 3) | ||||||||||||||||||
| 50 | Identify suitable product | ||||||||||||||||||
| 51 | Apply product where needed | ||||||||||||||||||
| 52 | |||||||||||||||||||
| 53 | Handrails on ramp too high (4) | ||||||||||||||||||
| 54 | Original installer (Hubbard) to review design drawings and propose action | ||||||||||||||||||
| 55 | Fabrication | ||||||||||||||||||
| 56 | Installation | ||||||||||||||||||
| 57 | |||||||||||||||||||
| 58 | Lift issues (5, 6 & 7) | ||||||||||||||||||
| 59 | Initial visit from lift engineer to review requirements | ||||||||||||||||||
| 609 | Fitting of improved parts | ||||||||||||||||||
| 61 | |||||||||||||||||||
| 62 | Disabled toilet issues (8-9) | ||||||||||||||||||
| 63 | Identify new door locks, procure and replace | ||||||||||||||||||
| 64 | Relocate emergency call cords | ||||||||||||||||||
| 65 | |||||||||||||||||||
| 66 | Call points at external doors (9) | ||||||||||||||||||
| 67 | Change call point to meet Ark requirements | ||||||||||||||||||
| 68 | |||||||||||||||||||
| 69 | Signage re fire lifts (10) | ||||||||||||||||||
| 70 | Identify suitable product | ||||||||||||||||||
| 71 | Apply product where needed | ||||||||||||||||||
| 72 | |||||||||||||||||||
| 73 | Refuge points to be marked and signed (11) | ||||||||||||||||||
| 74 | Identify suitable product | ||||||||||||||||||
| 75 | Apply product where needed | ||||||||||||||||||
| 76 | |||||||||||||||||||
| 77 | Policies and plans (12, 13 & 14) | ||||||||||||||||||
| 78 | Prepare policies and plans where required (tenants to prepare their own policies if needed) | ||||||||||||||||||
| 79 | |||||||||||||||||||
| 80 | Staff training (15) | ||||||||||||||||||
| 81 | Identify suitable courses (tenants will also likely be required to train staff) | ||||||||||||||||||