Question 1. How you procure Construction Consultancy Services?

Answer 1. Construction Consultancy is procured via Kirklees Council's current Framework Agreement for Construction Consultancy Services.

Question 2. How you procure Construction Contractors?

Answer 2. Construction Contractors Services are procured via Kirklees Council's current Framework Agreement for Construction Contractor Services.

Question 3. If by your own framework, please tell me:

  1. The titles and content of the relevant frameworks

Answer 3a. Consultancy Services Framework

The framework covers the following service provision:

Architects

Building Surveying

Condition Surveying

Electrical

Landscape

Mechanical

CDM

Project Management

Q.S. Bill of Quantities

Q.S. Schedule of Works

Q.S. Design & Build

Structures

Construction Services

Minor Capital Works Framework

Major Capital Works Framework

Question 3b. Who is on the current Framework's

Answer 3b.

Consultancy Services Framework

Architects:

Bradshaw Gass & Hope

Faber Maunsell

Halcrow Yolles

JNP Group

KMN Group Ltd

Mason Clark Assoc

NPS NE Ltd

Robinson Consulting

Urbanvision

White Young Green

Wright Mottershaw Lydon

Building Surveying

Aedas

Bradshaw Gass & Hope

Davies Langdon

Hall & Partners

HBS Business Services

Mason Clark Assoc

Nicol Thomas

Urbanvision

Watson Battye

Condition Surveying

Aedas

Bradshaw Gass & Hope

Davies Langdon

Hall & Partners

HBS Business Services

Mason Clark Assoc

Nicol Thomas

Urbanvision

Watson Battye

Electrical

Brentwood Design

Faber Maunsell

Halcrow Yolles

HSB Business Services

NPS NE Ltd

Operon

Sheffield City Council

Urbanvision

White Young Green

Landscape

Austin Smith Lord

Baily Garner

Insite Environments

NPS North East

Robinson Architects

Sheffield City Council

Urbanvision

Weddle Landscape

White Young Green

Mechanical

Brentwood Design

Faber Maunsell

Halcrow Yolles

HSB Business Services

NPS NE Ltd

Operon

Sheffield City Council

Urbanvision

White Young Green

CDM

Aedas

Baily-Garner

Hall & Partners

HSB Business Services

Mason Clark Assoc

NPS NE Ltd

Sheffield City Council

Urbanvision

Watson Battye

White Young Green

Project Management

Cyril Sweett

Faithful & Gould

Mason Clark Assoc

NPS North East Ltd

Rider Hunt

Sheffield City Council

White Young Green

Q.S. Bill of Quantities

Baily-Garner

Cyril Sweett

Edmond Shipway

Faithful & Gould

Hall & Partners

HSB Business Services

Nisbet

NPS NE Ltd

Sheffield City Council

Stephen Davies Assoc

Todd & Ledson

Urbanvision

Q.S. Schedule of Works

Baily-Garner

Currie & Brown

Edmond Shipway

Faithful & Gould

HSB Business Services

Nisbet

NPS NE Ltd

Sheffield City Council

Stephen Davies Assoc

Todd & Ledson

Urbanvision

Q.S. Design & Build

Baily-Garner

Faithful & Gould

HSB Business Services

Nisbet

NPS NE Ltd

Sheffield City Council

Todd & Ledson

Urbanvision

Structurers

Bradshaw Gass & Hope

Faber Maunsell

Halcrow Yolles

JNP Group

KMN Group Ltd

Mason Clark Assoc

NPS NE Ltd

Robinson Consulting

Urbanvision

White Young Green

Wright Mottershaw Lydon

Minor Capital Works Framework

Bermar Building Company Limited

Strategic Team Group

Torpoint Limited

Triton Construction Limited

Major Capital Works Framework

Bramall Construction Ltd

Morgan Ashurst

Clugston Construction

Question 3 c. The start and end dates of the framework

Question 3 d. Any possible extension period to the framework

Answer 3 c. Minor Capital Works Framework

Major Capital Works Framework

Start Date 1.1.2009 End Date 31.3.2013

Answer 3 d. There is an option to extend for a period of 12 months.

Answer 3 c. Consultancy Services Framework

Start Date 1.7.06 End Date 30.6.10

Question 3 e. The name and contact e-mail of person responsible for the frameworks

Answer 3 e. Paul Walsh

[email address]