This is an HTML version of an attachment to the Freedom of Information request 'Victoria Pier Colwyn Bay Costs and Details of Structural Survey'.
 
 
 
 
REPORT ON PRELIMINARY STRUCTURAL 
INSPECTION  
 
VICTORIA PIER, COLWYN BAY 
 
Prepared for: 

 
Prepared by: 
Design & Engineering Services 
 
Datrys 
Conwy County Borough Council 
Consulting Engineers 
Library Building 
3-5 Church Street 
Caernarfon 
Mostyn Street 
Gwynedd 
Llandudno 
LL55 1SW 
LL30 2RP 
 
 
Tel 
01286 671027 
 
 
E mail 
[email address] 
 
 
 
 
09205/B02 
 
Date 
9 December 2009 
PDF created with pdfFactory Pro trial version www.pdffactory.com

REPORT ON PRELIMINARY STRUCTURAL INSPECTION OF 
 VICTORIA PIER, COLWYN BAY 
 
 
1.0 

Introduction 
 
1.1. 
In  November  2009  Datrys  were  instructed  by  Conwy  County  Borough 
Council to undertake a preliminary condition survey of the structure of 
Victoria  Pier,  Colwyn  Bay.  The  purpose  of  the  inspection  was  to 
determine  the  form  and  general  condition  of the  pier  structure  so  that 
the  scope  of  remedial  works  that  might  be  required  to  bring  to  an 
acceptable condition for public access could be outlined.  
 
1.2 
The inspection  of  the  fabric  of  the  buildings and  their  services did  not 
form a part of the brief. 
 
 
2.0 

Location 
 
2.1. 
Victoria  Pier  extends  from  the  Promenade  at  Colwyn  Bay  to  a  point 
some  80m  from  mean  low  water.  The  whole  pier  length  is  therefore 
exposed  at  low  tide.  The  location  is  sheltered  from  the  predominant 
winds from the  west by Rhos Point but has a 165km long fetch to the 
north. The  site is  susceptible  therefore  to  wind  generated  waves  from 
this  direction  with  a  potential  significant  wave  height  of  4m  ignoring 
local beach effects. 
 
2.3 
The beach is generally sandy although coarse gravel and cobbles are 
located  beneath  the  Promenade  wall.  The  coastline  forms  a  shallow 
embayment  from  Rhos  Point in  the  west  to the limestone  headland  at 
Penmaen  Rhos  near  Llysfaen  in  the  east.  The  beach  has  been 
stabilised by the installation of timber groynes.  
 
2.4 
The general arrangement of the Pier is illustrated in the accompanying 
drawings. Its construction is described in greater detail below but may 
be  summarised  as  comprising  of  timber  decking  on  timber  joists 
supported  on  longitudinal  steel  lattice  girders.  The  girders  span 
approximately  12m  onto  braced  cast  iron  columns  fixed  into  cast  iron 
piles embedded in the beach.  
 
2.5 
The  Pier  supports  two  areas  of  buildings.  The  retail  area  dating  from 
the 1970’s which links with the Main Entrance; these occupy the first 3 
bays  of  the  Pier.  The  buildings  are  single  storey  and  of  recent  steel 
construction.  The  Pavilion  is  a  much  larger  and  more  elaborate 
structure constructed in the 1930’s. 
 
2.6 
The  Pier  may  be  divided  into  3  distinct  areas  (all  dimensions  are 
approximate): 
 
•  The Promenade End of 3 bays measuring 40 x 15m. 
PDF created with pdfFactory Pro trial version www.pdffactory.com

•  The  widened  Pavilion  Area  of  8  bays length  and  9  bays  width 
measuring 52 x 47m. 
•  The Seaward End of 14 bays length measuring 128 x 10m. 
 
The  structural  form  of  each  area  comprises  the  same  basic 
construction  as  described  above  with  local  strengthening  beneath  the 
buildings.  
 
 
3.0 

History 
 
3.1 
The  Pier  was  opened  in  1900  and  from  historic  photographs  and 
written  descriptions  appears  originally  to  have  extended only  as  far  ar 
grid line 12 as shown on the appended drawings being approximately 
half  its  present  length.  The  widened  Pavilion  area  was  an  original 
feature although it may have been 1 bay narrower and shorter than at 
present.  The  seaward  area  was  constructed  from  1903  and 
photographic evidence indicated that this reached as far as grid line 22 
some 40m short of the present Pier Head. A 600 seat theatre was then 
constructed at the Pier Head in 1917 extending the Pier to its present 
length. It is possible that the Pavilion area was widened at this time to 
its present dimensions.   
 
3.2 
The  Pier  suffered from  a  several  fires  during  its lifetime  which  caused 
the  loss  of  the  original  Pavilion  and  its  replacement  building.  The 
present  Pavilion  is  the  third  structure  and  was  opened  in  1934.  The 
theatre at the Pier Head was destroyed by fire in 1933 and was never 
replaced. 
 
3.3 
From  1968  and  into  the  1970’s  the  buildings  at  the  Promenade  End 
were built as part of a modernisation programme of the Pier by its then 
owner, a subsidiary of Trust House Forte. Finally, the Promenade End 
was widened around 1980 by the subsequent owners. 
 
3.4 
The  Seaward  End  of  the  Pier  was  closed  to  the  public  on  safety 
grounds in 1987 and the whole Pier was closed in 2008. 
 
 
4.0 

Survey work 
 
4.1. 
The survey was carried out on a visual basis only. No sampling, testing 
or uncovering was carried out.  
 
4.2. 
The initial survey was undertaken on 12 November 2009 with members 
of the Council Engineering and Design Department, the Pier owner and 
agent. All areas of the decking were accessed with the exception of the 
worst  affected  Seaward  End  which  was  deemed  unsafe.  The  Pavilion 
building could not be accessed and its inspection was therefore limited 
to  the  external  elevations  only.  The  roof  was  not  inspected.  The 
Entrance Building was accessible for at hand inspection. 
PDF created with pdfFactory Pro trial version www.pdffactory.com

 
4.3. 
The underside of the Pier was viewed from the beach only and at-hand 
inspection of the steel girders and bracing was not therefore possible. 
The  comments  given  below  regarding  the  condition  of  the  steelwork 
that  was  viewed  at  some  distance  is  therefore  necessarily  subjective 
and should be confirmed by closer inspection and evaluation.   
 
 
5.0 

Observations 
 
Promenade End 
 
5.1 
The flat roof of the Entrance Building between grid lines 1 & 2 consists 
of  rockwool  slabs  supported  on  metesec  lattice  beams  spanning  onto 
universal  steel  beams  supported  on  SHS  posts.  The  posts  coincide 
approximately  with  the  positions  of  the  piles of  the  Pier  structure. The 
structure  is  generally  sound  and  would  require  only  minor 
maintenance. The floor structure was not examined. 
 
5.2 
The  building  between  grid  lines  2  and  4  is  again  single  storey  with  a 
nodal space frame roof supported on its edges by SHS posts. The form 
of the roof with its many valleys will lead to maintenance difficulties and 
problems  of  water  ingress.  The  means  of  achieving  lateral  stability  of 
the building was not apparent and may derive from the racking effect of 
the  external  timber  frame  cladding.  The  floor  structure  was  not 
examined.    
 
5.3 
Most  of  the  Pier  steelwork  in  this  area  is  of  a  condition  that  could  be 
refurbished.  Some  relatively  recent  repairs  are  apparent  and  the 
bracing to the piles on grid lines 2 and 3 are significantly different from 
the  remainder  of  the  Pier  structure and  are more  recent.  Some  of  the 
detailing of the new components will however lead to water entrapment 
and  future  maintenance  problems  suggesting  that  their  replacement 
might prove more effective. 
 
5.4 
No particular problems were noted with respect to the piles in this area. 
 
Pavilion Area 
 
5.5 
Access into the Pavilion Building was not possible. From the inspection 
of its perimeter it is of a steel construction clad in rendered expanded 
metal  cladding.  In  many  areas  the  galvanised  cladding  has  corroded 
and  the  render  has  significant  cracks  which  will  allow  water  entry.  In 
areas  the  render  has  become  detached  revealing  both  the  metal 
cladding  and  the  steel  structure.    The  roof  structure  is  hipped  with  a 
pagoda form and its geometry is somewhat complex  which could lead 
to  problems  of  water  ingress.  It  appears  to  be  clad  with  an  asbestos-
cement  sheet  the  condition  of  which  is  doubtful  with  cracked  sheets 
apparent whilst some were missing. 
 
PDF created with pdfFactory Pro trial version www.pdffactory.com

5.6  
The  decking  in  this  area  showed  some  signs  of  decay  and  extensive 
moss growth. It is probable that a significant proportion will need to be 
replaced or at least refixed. The condition of the supporting soft wood 
joists  could  not  be  determined  as  they  were  generally  obscured  from 
view but again extensive replacement will probably be needed. In some 
areas  such  as  the  corner  cantilever  the  timber  structure  is  clearly 
unsafe and is close to collapse.  
 
5.7 
The decorative handrail was found to be in place for most of this area. 
The  detailing  is  poor  however  and  leads  to  water  entrapment  and 
decay  of  the  timber  kerb  to  which  the  standards  are  fixed.  In  most 
areas  the  kerb  showed  decay  and  the  whole  length  will  need  to  be 
refixed or replaced with a suitable new detail. 
 
5.8 
The  Pier  structure  in  this  area  is  in  a  varied  condition.  There  are 
instances of bracing failures near grid lines 12 and 13 whilst the degree 
of  corrosion  of  the  girders  varies  considerably.  Beneath  the  building 
there  are lines  of  deep riveted plate  girders in  place  of  the  usual light 
lattices.  The  steelwork  of  the  plate  girders  appeared  to  be  sound  but 
their  rivets  could  not  be  assessed.  Many  of  the  tie  bars  in  this  area 
would  need  to  be  replaced  and  many  turnbuckles  had  spilt 
longitudinally.  Whilst  much  of  the  lower  steelwork  was  heavily 
encrusted  in  marine  growth  the  horizontal  struts  to  the  piles  and  the 
piles themselves appeared to be sound. 
 
 
Seaward End 
 
5.9 
The  Pier  structure  in  this  area  is  in  the  worst  condition.  Much  of  the 
decking  has  either  been  dislodged  or  is  decayed.  The  steel  girders 
exhibit  general  corrosion  and  elements  of  the  column  head  bracing 
have, in instances, corroded through. Many of the column bracing ties 
have failed. 
 
5.10  A length of approximately 45m of the decorative hand railing had failed 
along the Pier Head and east side. Elsewhere the timber kerb to which 
the standards are fixed was noted to be decayed. 
 
 
 
 
6.0 

Discussion 
 
 
Promenade End 
 
6.1 
Repairs and alterations were carried out in this area in the 1970’s and 
the  structural  components  reflect  the  commercially  available  and 
popular  structural  systems  of  that  period.  The  structural  form  of  the 
buildings between grids 1 and 2 is considered to be appropriate subject 
to  consideration  of  lateral  stability  and  only  localised  repair  and 
maintenance would probably be required. 
 
PDF created with pdfFactory Pro trial version www.pdffactory.com

6.2 
The nodal space frame  whilst popular at the time of its construction is 
now unusual and the ease with which it could be easily maintained for 
a  long  period  is  doubtful.  The  form  of  the  roof  should  be  simplified  to 
minimise  the  risk  of  rain  penetration.  The  means  of  providing  lateral 
stability to this building should be established as it may be dependant 
on  the  racking  resistance  of  the  timber  cladding  whose  condition  will 
deteriorate.   
 
6.3 
The condition of the floor decking in this area should be established in 
any future inspections. 
 
6.4 
The changes to the bracing system on lines 2 and 3 without doubt date 
to  the  time  of  the  erection  of  the  buildings.  The  heavier  and  lower 
sections would provide greater resistance to lateral wind loads imposed 
on the piles by the increased elevation of the buildings. 
 
 
Pavilion Area 
 
6.5 
The  large  number  of  columns  and  the  extensive  bracing  coupled  with 
shelter  offered  by  the  structure  itself  have  resulted  in  the  original 
structure in this area being in relatively good condition.  
 
6.6 
As it was not possible to inspect the superstructure of the Pavilion it is 
not  possible  to  comment  meaningfully  on  its  condition.  However  the 
loss  of  roof  sheets  and  wall  panels  will  inevitably  lead  to  an 
acceleration  of  its  deterioration.  If  it  were  to  be  refurbished  it  is 
probable  that  the  building  would  need  to  be  stripped  back  to  its  steel 
structure which would also in all probability be in need of some degree 
of repair and strengthening as well as general maintenance. 
 
6.7 
A  detailed  inspection  of  each  bay  of  the  Pier  structure  is  required  to 
properly determine the extent of repairs required to the Pier structure in 
this area. The piles generally appeared to be sound however cast iron 
is susceptibly to cracking and testing of the integrity of the piles and a 
check on their embedment should be carried out, initially, on a sample 
basis.  
 
6.8 
The  condition  of  the  column  bracing  systems  varied.  The  horizontal 
struts  appeared  to  be  sound  and  would  probably  only  require 
repainting. Their connection to the columns would need to be checked 
in  detail  and  allowance  should  be  made  for  bolt  replacement.  The  tie 
bars  and  their  turnbuckles in  many  instances  show  signs  of  corrosion 
or have failed. Allowance should be made for their replacement.   
 
6.9 
The  decking  is  far  from  pristine  and  allowance  should  be  made  for 
replacing it in its entirety together with the supporting joists. This would 
then  allow  access  to  the  girders  beneath  to  carry  out  any  necessary 
work. 
 
PDF created with pdfFactory Pro trial version www.pdffactory.com

6.10  The handrails will need to be removed refurbished and refixed to a new 
kerb detail. 
 
Seaward End 
 
6.11  The Pier in this area is in a very poor condition. In areas the columns 
are unbraced and rely on cantilever action to resist any lateral loadings. 
 
6.12  The  Pier  superstructure  in  this  area  will  need  to  be  replaced.  This 
would  probably  entail  the dismantling  of  the columns  and  their  off-site 
refurbishment.  The adequacy  of  the  piles  would  need  to  be  confirmed 
prior to re-erecting the columns followed by the new superstructure.  
 
6.13  The  lost  handrails  would  need  to  be  replaced  with  a  suitable  replica 
pattern.  
 
 
7.0 

Conclusions 
 
7.1 
The  Pier  structure  should  be  inspected  in  detail  and  its  adequacy 
assessed in relation to the loads to which it is subjected arising from its 
intended use and its environment. 
 
7.2 
The  condition  of  the  Pier  superstructure  is  varied  and  is  particularly 
poor at the Seaward End. In this area the superstructure should be re-
built. Elsewhere the superstructure could be repaired and refurbished. 
 
7.3 
The deck timbers and the supporting joists should be replaced. 
 
7.4 
The  handrails  should  be  removed,  refurbished,  supplemented  as 
necessary  and  refixed  to  a  suitable  edge  kerb  detail.  It  may  be 
necessary  to  raise  their  level  to  meet  current  standards  or  to  seek  a 
relaxation under the Building Regulations. 
 
7.5 
The roof and cladding of the Pavilion Building should be removed and 
allowance made for repair of the underlying structure. 
 
7.6 
The feasibility of retaining the nodal roof structure is questionable and 
consideration should be given to its replacement. 
 
7.7 
Areas  of  the  Pier  are  in  a  state  of  near  collapse  and  could  present  a 
danger  to  the  public.  The  public  should  be  excluded  or  at  least 
discouraged from walking beneath these areas.  
 
7.8 
The Seaward End of the Pier is now in a condition whereby it may be 
lost  within  the  next  5  years.  The  Pavilion  Area  with  its  high  degree  of 
redundancy  could  survive  in  an  increasingly  weakened  state  for  a 
period of up to 10 years.  The highly unpredictable nature of significant 
sea  states  should  however  be  borne  in  mind  when  considering  these 
timescales which could be exceeded in a single event. 
PDF created with pdfFactory Pro trial version www.pdffactory.com

 
8.0 

Recommendations 
 
8.1 
An  inspection  and  assessment  of  the  pier  structure  should  be 
undertaken,  if  necessary  on  a  sample  basis,  to  gain  a  more  accurate 
view of its form and condition. 
 
8.2  
A Cost Plan should be prepared from the findings of the Structural 
Assessment.  
 
8.3 
The public should be excluded from beneath or at least warned of the 
dangerous nature of parts of the Pier. The unsafe areas should be 
secured as matter of urgency. 
 
 
 
 
 
 
 

PDF created with pdfFactory Pro trial version www.pdffactory.com

 Costings 
 
The  following  are  intended  as  indicative  costings  only  and  are  based  upon 
unit rates derived from past pier refurbishment work and published unit rates. 
The figures quoted are for the first quarter 2009. 
 
 
Pier Refurbishment at £450/m2    
 
 
£1.8M 
 
Pavilion Refurbishment at £1,500/m2 
 
 
£2.1M 
 
Shops and Entrance Refurbishment at £750/m2 
£0.375M 
 
Contractors overheads at 15% 
 
 
 
£0.64M 
 
Total allowance for Construction 
 
 
£4.915M 
 
The above excludes fees, supervision costs and any contingency. 
 
 
 
In  order  to  a  gather  enough  information  on  the  form  and  condition  of  the 
structure  and  the  extent  of  the  repairs  required  a  Structural  Assessment 
should be carried out. This would include a topographic survey of the columns 
and deck, surveys and inspections of girders and columns on a sample basis. 
The  information  would  allow  a  preliminary  loading  analysis  of  the  Pier  to  be 
carried  out  to  determine  areas  that  could  be  repaired  and  those  that  would 
need  to  be  replaced. The purpose  of  the  Structural  Assessment  would  be  to 
provide  information  for  a  Cost  Plan  to  be  prepared  and  would  need  to  be 
supplemented by further detailed surveys, testing and inspections during later 
stages of the design process.  
 
 
Topographic survey of Pier structure 
 
 
£2,000  
 
Sample survey and inspections of Pier 
(allow 2 engineers 1 week on site) 
 
 
£3,000 
 
Inspection of buildings 
(allow 1 engineer 3 days)   
 
 
 
   £900 
 
Assessment calculations and report 
 
 
£4,500 
 
Hire of access equipment and travel 
 
 
£1,000 
 
Total allowance for Structural Appraisal 
 
£11,400 
 
All the above costing are net of  VAT 
PDF created with pdfFactory Pro trial version www.pdffactory.com

PDF created with pdfFactory Pro trial version www.pdffactory.com

PDF created with pdfFactory Pro trial version www.pdffactory.com

PDF created with pdfFactory Pro trial version www.pdffactory.com