This is an HTML version of an attachment to the Freedom of Information request 'SEMMMS meeting minutes'.
SEMMMS- Airport Options Review 
Minutes of Meeting held 22.12.09 (MR Office - Hygarth House)
Attendees: 
Martin Rigby (SMBC)
Nick Whelan (SMBC)
Naz Huda (SMBC)
Tim Baker (Scott Wilson)
Apologies:
Joseph Roberts (SW), David Taylor (SMBC)
Distribution: As above plus Graham Martin (SW), Steven Payne (SW)
Noted 
Action 
by 
1 Purpose of meeting 
To discuss potential options for the Airport junction for further development. 
1.1 Option 1 - Four signalised roundabouts inc 1 new plus dual carriageway 
links.  
1.1.1 This option was originally titled Airport Option 2 (SMBC) Sheet 3 of 3 (see 
attached).
1.1.2 A larger at-grade roundabout to be built just west of the existing roundabout at 
Aviator Way / Ringway Road West. 
1.1.3 Reconstructed roundabout at Outwood Lane / Outwood Lane West (T1/3). Link 
onto Outwood Lane would be stopped up. 
1.1.4 New signalised roundabout at Thorley Road (serving potential development 
land). 
1.1.5 Modification of Terminal 2 roundabout with new link to Thorley Road 
roundabout. 
1.1.6 Dual carriageway links between T2 r/a and Thorley Rd r/a and Aviator Way r/a. 
1.1.7 Dual carriageway links between Aviator Way r/a and T1/3 r/a. 
1.1.8 Extents of retaining walls to be indicated on dwgs for costing purposes. 
NH/NW
1.1.9 Option 1 is an evolvement of MCC option A of dwg 204420/001 which has 
been rejected at this stage due to insufficient traffic capacities and the 
proposed large gyratory forming an inappropriate layout for future 
development. 
1.2 Option 2 - Compact 3 level entrance into Airport. 
1.2.1 Option 2 attached indicates direct access into T1/T3 and out of T1/T3, both 
east and west. 
1.2.2 Further 2D works required indicating tie in to Aviator Way, impact on Hotel 
SP 
entrance/boundary, proposed metrolink line, pedestrian links to metrolink 
exchange/development site, access to T1 from east. 
1.2.3 Further 3D works require to raise proposed A555 mainline.
SP 
1.3 Option 3 - "Big mac" roundabout 
1.3.1 New option to be developed with grade separated roundabout for T1/T3. 
NW
1.3.2 Balanced option to minimise impact on Hotel to south and minimise land take 
to north (potential) and also direct route through to M56. 
2.0 All options to be drawn up by 20.01.10. 
3.0 Options Evaluation Matrix (elements to be carried out internally / externally on 
completion of drawings (20.01.10)
3.1 Operational Safety
Scheme options for Styal Road to be audited (RSA1) internally by SMBC. 
SMBC
3.2 Environmental 
SW to obtain quote for short Environmental Assessment by Mouchell in the 
SW
order of 3 days work c£1500. 
3.3 Community Effect 
SW to instruct Mouchell as part of 3.2. 
SW
3.4 Construction Issues 
SW and SMBC to assess internally. 
SW/SMBC
3.5 Construction Costs 
SMBC to estimate costs including stats. This is to be carried out in 1st week 
NH
after 20.01.10 then supplied to Atkins 
3.6 Operational and Maintenance Costs
SW to instruct Atkins to assess this following 3.5. Atkins to assess in 2nd week 
SW
after 20.01.10. Header to be changed to Traffic & Economics. 
3.7 Land 
SMBC to instruct NPS to assess. 
SMBC
3.8 3.1-3.7 to be returned / completed by 03.02.10. 
3.9 Meeting to be arranged for w/c 08.02.10 to populate the Option Evaluation 
NH 
Matrix. NH to arrange. 
3.1 Local Authority Column to be added to the matrix. 
NH 
Comments are to be invited from CE and MCC. 
SW
SEMMMS 
Author : Nazrul Huda
Page 1 of 2
Date Produced 23.12.09

SEMMMS 
Author : Nazrul Huda
Page 2 of 2
Date Produced 23.12.09