Minutes 

Project  SEMMMS A6 to Manchester Airport Relief Road 
Job No   
Date of Meeting  26/11/09 
Meeting No  
Page 1 of 5 
 
 
Location of Meeting 
Hygarth House, SMBC 
Time of Meeting 
10.30 hrs 
Subject of Meeting 
Progress Meeting - SEMMMS A6 to Manchester Airport Relief Road 
Persons present including representation 
 
 
Jim McMahon (JM) 
 
SMBC  
Sue Stevenson (SS)   
SMBC 
Martin Rigby    
 
SMBC 
Tim Baker (TB)  
 
Scott Wilson 
Graham Martin (GM)   
Scott Wilson 
Nasar Malik (NM) 
 
Atkins 
Robin Kimber   
 
Atkins 
 
Distribution of notes to 
 
As above + 
Nick Whelan (NW) 
 
SMBC   
 
 
David Taylor (DT) 
 
SMBC 
Neil Stockley (NSt) 
 
Atkins   
 
 
Naz Huda (NH) 
 
SMBC 
Andrew Thornhill (AT) 
Mouchel 
Tony Mellor (TM) 
 
GMTU 
Nick Benbow (NB) 
 
MVA 
Ian Keyte 
 
 
NPS 
John Smith 
 
 
Corderoy 
John Gray (JG)  
 
Cheshire East Council 
David Bland (DB) 
 
Manchester City Council 
Neil Searle (NS) 
 
Mott MacDonald 
Joseph Roberts (JMR)           Scott Wilson 
 
Date of Notes 
01 December 2009 
s:\projects\semmms major information\15.0 meetings\15.2 progress meetings\progress 
report no 1 091126\semmms progress report minutes 091126.doc 
Form No. Q102 
24.05.00    

 
 
Minutes 

Project  SEMMMS A6 to Manchester Airport Relief Road 
Job No   
Date of Meeting  26/11/09 
Meeting No  
Page 2 of 5 
 
 
 
NOTES 
DATE  
ACTION 
 
Introductions & Apologies 
 
 
 
 
 
1.1 
Nasar Malik and Robin Kimber (Atkins) attending with respect to Atkins 
 
 
 
recent appointment to role of management of SEMMMS 7 Traffic 
 
Modelling.   Robin Kimber will attend further Progress Meetings to report 
 
on progress re traffic modelling matters and liaison with DfT. 
 
 
 
1.2 
Format of Progress Report 1 dated 24/11/09 will form agenda of meeting 
 
 
and cover items of discussion – refer to report (attached). 
 
 
 
 
Project Management 
 
 
1.3 
SW to compile comments to the individual comments raised by Charlie 
30/11/9 
SW 
Sunderland (DfT) on Project Initiation Documents.  
 
 
 
1.4 
SMBC (SS) to approve SW response and issue response re DfT PID 
 
SMBC 
comments. 
 
 
 
1.5 
CE and MCC to respond to SMBC/SW on Governance issues as raised at 
 
 
Project Board.  Confirmed that Joint Committee not acceptable for 
SEMMMS between the 3 no. authorities. 
 
 
 
 
ProjectSpace 
 
 
1.6 
SW (JR) to set-up a brief training session to demonstrate the main 
by Jan 
SW 
functions that ProjectSpace is anticipated to be used for re SEMMMS. 
2010 
 
 
 
1.7 
Agreed that only final versions of documentation; drawings; schedules etc. 
 
Note 
as appropriate will be uploaded onto ProjectSpace. 
 
 
 
 
Programme 
 
 
1.8 
Pre-Planning Consultation start date and duration to be added as key date 
11/12/9 
SW 
for reporting on programme.   
 
 
 
1.9 
RK to assess and review GMTU programme Version 8 with GMTU and 
07/12/9 
Atkins (RK) 
Version 9 to be submitted further to review in line with programme that will 
 
/ GMTU 
be aligned to paper Atkins will submit to DfT.  
 
 
 
 
 
 
1.10 
High level programme to be revised and re-issued by SW further to receipt 
11/12/9 
SW 
and consideration of Traffic Modelling programme (Version 9). 
 
 
 
 
Risk 
 
 
1.11 
SW to update the Risk Register and create a base document that will be 
02/12/9 
SW 
analysed using @risk by Corderoy. 
 
 
 
 
Business Case 
 
 
1.12 
SS and NS Atkins to meet to discuss objectives to resolve queries such 
08/12/9 
SMBC (SS)/ 
that draft Chapters can be progressed for submission to DfT. 
Atkins (NS) 
 
[Proposed that this meeting is convened post Modelling Scenario Definition 
 
meeting] 
Date of Notes 
01 December 2009 
s:\projects\semmms major information\15.0 meetings\15.2 progress meetings\progress 
report no 1 091126\semmms progress report minutes 091126.doc 
Form No. Q102 
24.05.00    

 
 
Minutes 

Project  SEMMMS A6 to Manchester Airport Relief Road 
Job No   
Date of Meeting  26/11/09 
Meeting No  
Page 3 of 5 
 
 
 
NOTES 
DATE  
ACTION 
 
 
 
 
Traffic Modelling 
 
 
1.13 
NM noted that Atkins would be submitting a draft paper with a revised 
 
 
approach to the traffic modelling further to review of the Technical Note 
previously drafted by MVA.  Atkins meeting with GMTU and MVA pm 
26/11/09 to discuss proposed revisions to approach in terms of scope; 
programme; cost and acceptance by DfT. 
 
Post Meeting Note: Transport Modelling Approach – Draft Specification 
submitted by RK to SW/SMBC 29/11/09.
 
 
 
 
1.14 
SMBC to comment on draft paper - Transport Modelling Approach – Draft 
04/12/9 
SMBC/ 
Specification - and Atkins to submit to DfT on receipt of SMBC approval. 
Atkins (RK) 
 
 
 
1.15 
Agreed that all modelling updates and reporting to be issued to SMBC / 
ongoing 
Atkins (RK) 
SW through Atkins, as part of the scope of works agreed within the Traffic 
Modelling role Atkins recently appointed to – confirmed at meeting of 
20/11/09 between SMBC/SW/GMTU/Atkins.  
 
 
 
1.16 
SMBC to issue information in relation to the LDF in terms of incorporation 
 
SMBC 
of related information into the modelling scenario. 
 
 
 
1.17 
Airport has not provided GMTU with data further to requests for information  04/12/9 
Airport / 
(RFI’s) to the Airport.  NM stated that Aecom indicated data relative to 
Aecom 
GMTU’s RFI will be issued by 04/12/09.  
 
 
 
1.18 
Atkins with GMTU will review information issued by Aecom to determine 
 
Atkins (RK) 
that it is sufficient for progressing SEMMMS 7 modelling. 
/ GMTU 
 
 
 
1.19 
RK Atkins to attend the Woodford / SMBC meeting in terms of considering 
t.b.a. 
SMBC / 
incorporation or otherwise into modelling – date t.b.a. by SMBC. 
Atkins 
 
 
 
 
Design 
 
 
1.20 
DF2 currently circulated amongst SEMMMS team to progress work 
Jan ‘10 
SMBC 
activities.  Agreed that DF3 to be issued Jan ’10 will incorporate design 
modifications at Styal Road junction only (not Airport layout revisions). 
 
 
 
1.21 
The revisions to the SEMMMS layout at the Airport will be developed post 
ongoing 
SMBC / 
DF3.  Discussions on current proposals being worked up by SEMMMS 
Airport / 
design team are being progressed with the Airport. 
SW 
 
 
 
1.22 
SEMMMS Design Team to go out to Stats companies in Jan ’10 with DF3 
Jan ‘10 
SMBC 
 
 
 
1.23 
SEMMMS Design Team to re-start meetings with Vulnerable Road User 
Jan ‘10 
SMBC 
groups in Jan ’10 with DF3. 
 
 
 
1.24 
Options Appraisal  reporting to be developed for Styal Road design – 
 
 
consideration of 4 no. options issued by MCC.  Options Appraisal to be 
 
developed by the following parties relative to discipline: 
 
• 
SMBC – Engineering 
SMBC 
Date of Notes 
01 December 2009 
s:\projects\semmms major information\15.0 meetings\15.2 progress meetings\progress 
report no 1 091126\semmms progress report minutes 091126.doc 
Form No. Q102 
24.05.00    

 
 
Minutes 

Project  SEMMMS A6 to Manchester Airport Relief Road 
Job No   
Date of Meeting  26/11/09 
Meeting No  
Page 4 of 5 
 
 
 
NOTES 
DATE  
ACTION 
• 
Mouchel - Environmental   
Mouchel 
• 
NPS – Costings 
NPS 
• 
Atkins – COBA (this will be carried out post review of other 
Atkins 
   
appraisal inputs as above) 
 
 
 
 
1.25 
Structures: Meeting to be arranged with Network Rail with DF3 Jan’10. 
Jan ‘10 
SMBC 
 
 
 
1.26 
Metrolink: SS to make contact with Metrolink Sub-group to ensure that 
ASAP 
SMBC 
JMcM is included as a member of the sub-group to represent SEMMMS. 
 
 
 
1.27 
Stats: C3 estimates to be re-issued Jan ’10 on the basis of DF3. 
Jan ‘10 
SMBC 
 
 
 
1.28 
Design Standards: SEMMMS Design Team to draft standard details 
 
SMBC 
 
 
 
 
Environmental 
 
 
 
1.29 
Mouchel (at meeting of 21/11/09) proposed to meet with SMBC Planning 
ASAP 
Mouchel / 
to discuss draft Scoping Note as passed to Sue Stevenson, so as to assist 
SMBC 
in defining content within the Scoping Report to be submitted pre-Xmas 09. 
 
 
 
1.30 
Mouchel to finalise Scoping Report post Modelling Scenario Definition 
18/12/9 
Mouchel 
meeting and submit to SMBC pre-Xmas 09. 
 
 
 
 
Land & Orders 
 
 
1.31 
Roles and responsibilities to be defined at meeting scheduled for 03/12/09.   
Note 
 
 
 
 
Planning 
 
 
1.32 
Conjoined planning meeting to be arranged between SMBC; CE and MCC 
t.b.a. 
SMBC / 
planning representatives to discuss requirements of SEMMMS in terms of 
SW 
application to be submitted to satisfy the 3 no. authorities. 
 
 
 
1.32 
JMcM, representing SEMMMS project team, to meet with Government 
t.b.a. 
SMBC / 
 
Office North West (GONW) – discuss potential or otherwise for scheme to 
SW 
 
go to Public Inquiry.  
 
 
 
 
Consultation 
 
 
 
1.33 
Log of consultation carried out to date to be passed to NS Atkins for 
 
SMBC 
consideration within appropriate Chapter in BC submission. 
 
 
 
 
Commercial 
 
 
 
1.34 
Noted that the recent review undertaken by Corderoy indicates the £290m 
 
 
Note 
scheme budget considered reasonable estimate with information available. 
 
 
 
1.35 
SMBC meeting with Balfour Beatty Jan’10 with a view to appointing in 
Jan ‘10 
SMBC 
Feb/March ’10 in Contractor advisory role, re buildability and cost. 
 
 
 
1.36 
Spend to be mitigated up to year end 2009/10 where practicable whilst still 
 
Note 
progressing works in line with programme. 
 
 
 
Date of Notes 
01 December 2009 
s:\projects\semmms major information\15.0 meetings\15.2 progress meetings\progress 
report no 1 091126\semmms progress report minutes 091126.doc 
Form No. Q102 
24.05.00    

 
 
Minutes 

Project  SEMMMS A6 to Manchester Airport Relief Road 
Job No   
Date of Meeting  26/11/09 
Meeting No  
Page 5 of 5 
 
 
 
NOTES 
DATE  
ACTION 
1.37 
SW to progress cost monitoring and reporting with information provided to 
Dec ‘09 
SW / 
date by SMBC.  This will include fees paid to date 2009/10 and fees to be 
SMBC 
reconciled on existing Works Orders.  Fee proposals to be submitted by 
SEMMMS project team for works from Dec 09 onwards to be included with 
associated monthly fee scheduling. 
 
 
 
1.38 
 
SMBC to issue reminder to MCC and CE re outstanding monies due to 
Dec ‘09 
SMBC 
 
SMBC on previous cost allocations. 
 
 
 
 
Date of Next Meeting 
 
 
 
1.39 
17th December 2009 at 10.30 hrs, Hygarth House, SMBC. 
 
 
 
 
 
 
Date of Notes 
01 December 2009 
s:\projects\semmms major information\15.0 meetings\15.2 progress meetings\progress 
report no 1 091126\semmms progress report minutes 091126.doc 
Form No. Q102 