Minutes
Project SEMMMS A6 to Manchester Airport Relief Road
Job No
Date of Meeting 24/11/09
Meeting No 2
Page 1
of 5
Location of Meeting
Hygarth House – Stockport MBC
Time of Meeting
14.30 hrs
Subject of Meeting
Environmental Update re SEMMMS A6 to Airport relief Road
Persons present including representation
Sue Stevenson (SS)
SMBC
Andy Thornhill (AH)
Mouchel
Jamie Gleave (JG)
Mouchel
Tim Baker (TJB)
Scott Wilson
Graham Martin (CB)
Scott Wilson
Distribution of notes to As above +
Jim McMahon (JMcM)
SMBC
Martin Rigby (MR)
SMBC
Robin Kimber (RK)
Atkins
Neil Stockley (NS)
Atkins
Joseph Roberts (JR)
Scott Wilson
Gordon Davidson (GD)
Scott Wilson
Diane Corfe (DC)
Scott Wilson – EIA
Date of Notes
27 November 2009
s:\projects\semmms major information\15.0 meetings\15.7 environmental team
meetings\semmms envtl update mtg 091124.doc
Form No. Q102
24.05.00
Minutes
Project SEMMMS A6 to Manchester Airport Relief Road
Job No
Date of Meeting 24/11/09
Meeting No 2
Page 2
of 5
NOTES
DATE ACTION
Introductions & Apologies
2.1
Apologies from Jim McMahon SMBC.
2.2
Agreed that as a result of changes on overall SEMMMS approach,
since previous Environmental Update meeting dated 08/10/09, the
previous Notes of Meeting would be covered and new actions noted.
Proposed Scheme Programme
2.3
Business Case to be developed with SEMMMS 7 as per high level
programme that is to be developed with SEMMMS project team. SW 11/12/9 SW
aim to issue revised programme early/mid-December (relative to
SEMMMS 7 programme from Atkins/GMTU).
Change in Legal Requirements
2.4
SMBC to confirm whether SEMMMS will go through the IPC process. ongoing
SMBC
Planning Strategy
2.5
ES still to be developed for submission on basis of breakpoints with
the 3 no. local authority boundaries.
2.6
Mouchel to submit list of required contacts within SMBC for 27/11/9 Mouch
information required.
SMBC to create list of contacts within SMBC; CE and MCC to
SMBC
develop responses and SMBC would coordinate these responses
back to Mouchel.
Responsibilities (e.g. Public Consultation)
2.7
SW issued Executive Summary as prepared by SMBC to Mouchel.
[Post Meeting Note: issued by SW]
2.8
Mouchel to update historic information with that undertaken by
Mouch/
SMBC/Counter Context post writing up of previous information.
SMBC
Agreed Assessment Methodologies
2.9
Mouchel tabled a Scoping Memo based on revised guidance from
Mouch
DMRB Volume 11. Mouchel to upload to ProjectSpace.
2.10
Agreed that Scoping Report cannot be finalised until conclusions of 18/12/9 Mouch
Modelling Scenario Definition meeting – scheduled for w.c. 07/12/09.
Date of Notes
27 November 2009
s:\projects\semmms major information\15.0 meetings\15.7 environmental team
meetings\semmms envtl update mtg 091124.doc
Form No. Q102
24.05.00
Minutes
Project SEMMMS A6 to Manchester Airport Relief Road
Job No
Date of Meeting 24/11/09
Meeting No 2
Page 3
of 5
NOTES
DATE ACTION
2.11
Any changes in scope from that to be submitted mid-Nov as a result
of design modifications etc. would be documented and justified in
ES.
Environmental Assessment Review
2.12
SW Environmental issued review report to Mouchel 28/10/09.
2.13
Mouchel to complete review of the Assessment report – to date no 06/12/9 Mouch
queries on that noted by SW other than Cultural Heritage comments.
Mouchel to complete review and confirm any further queries/issues.
2.14
SW (Annie Bingham) has contacted Rachel Morse (Mouchel) 06/12/9 Mouch
26/09/09 – RM to respond to AB to resolve queries on SW
comments.
Environmental Master Plan
2.15
Mouchel to utilise Design Freeze 2 (DF2) for master plan for
Mouch
progressing Scoping.
2.16
Mouchel to be provided with latest design freeze (DF3 – Jan ’10) to Jan ‘10
SW
incorporate into EIA as soon as available from SMBC.
2.17
Environmental review of options as part of decision process in
SMBC/
moving towards DF3 and beyond – Mouch input required to inform.
Mouch
Target Cost Documents
2.18
Mouchel to review mitigation costs in terms of that previously advised
Mouch
and based on latest Design.
Environmental Statement
2.19
Robin Kimber, Atkins (Modelling Strategic role) to be informed of 19/10/9 Mouch/
information that is required from Modelling to inform EA and timing of
Atkins
issue from Modelling process – Mouch / Atkins meeting re timing of
Mouchel input to Business Case.
2.20
Detailed discussion on priority to resolve cumulative (environmental)
SW/
impacts for further development of SEMMMS (full scheme) and other
SMBC/
‘pipeline’ developments. Modelling Scenario Definition meeting to be
Mouch/
scheduled by SW for w.c. 07/12/09.
Atkins
Date of Notes
27 November 2009
s:\projects\semmms major information\15.0 meetings\15.7 environmental team
meetings\semmms envtl update mtg 091124.doc
Form No. Q102
24.05.00
Minutes
Project SEMMMS A6 to Manchester Airport Relief Road
Job No
Date of Meeting 24/11/09
Meeting No 2
Page 4
of 5
NOTES
DATE ACTION
2.21
Mouchel to progress environmental screening re Habitats
Mouch
Regulations to establish appropriate assessments.
2.22
Mouchel to progress with outline frameworks for Waste Management
Mouch
Plan; Construction and Environmental Plan and taking account of
WebTag updates. Requires Contractor input.
2.23
Mouchel to engage with SMBC public health officer re development
Mouch
of Health Impact Assessment.
2.24
SMBC would be appointing a Contractor for early involvement/advice
SMBC
on construction and buildability issues – anticipated March 2009
appointment by SMBC.
2.25
Mouchel to consult with SMBC (Vanessa Brooks) re Landscape
Mouch
design element of the EIA for resource (Mouchel would manage any
SMBC design input). Mouchel to include in fee proposal.
2.26
SS confirmed that SMBC will require to declare the carbon footprint
Mouch/
for delivery of the scheme. Mouchel to contact Hannah Matthews
SMBC
SMBC to agree a methodology and develop this across the 3 no.
LA’s. To be included in the Scoping Report.
2.27
Listed Building consents – decision to be made on responsibility and
SMBC
timing of associated actions on this matter. Will inform ES re
impacts.
Scoping Report
2.28
Mouchel to update and re-scope previous Scoping Report and issue 18/12/9 Mouch
for comment to SMBC. Scoping Report to be issued post Modelling
Scenario Definition meeting – scheduled for w.c. 07/12/09.
2.29
Mouchel passed copy of responses and addressees to SS for
information – no major issues raised through responses.
2.30
Mouchel to advise SMBC on focused list of consultees for Scoping
Mouch/
Report. Mouchel proposed to meet with SMBC Planning to discuss
SMBC
Scoping Memo and proposed submission for Scoping Report.
2.31
SS stated that scoping report be posted on SMBC website and
Mouch
SEMMMS ProjectSpace.
Date of Notes
27 November 2009
s:\projects\semmms major information\15.0 meetings\15.7 environmental team
meetings\semmms envtl update mtg 091124.doc
Form No. Q102
24.05.00
Minutes
Project SEMMMS A6 to Manchester Airport Relief Road
Job No
Date of Meeting 24/11/09
Meeting No 2
Page 5
of 5
NOTES
DATE ACTION
Task Order
2.32
Mouchel to reconcile with SMBC on value of Task Orders agreed to 04/12/9 SMBC
date with SMBC (circa £43K).
2.33
Mouchel to submit a revised estimate for scope of works. This is to tba
Mouch
include breakdown of costs and programming against deliverables, pre-
Xmas 09
including surveys; scoping Nov 2009; consultations; EIA; monthly
progress reporting.
Baseline Data
2.34
Mouchel to assess baseline data for all elements of EIA in terms of
that done previously and would be required for proposed
submissions with new scheme – A6 to Manchester Airport. SW
Environmental review will input to this.
Ecological Survey
2.35
Mouchel to organise for seasonal ecology surveys and assess
resourcing for completion within timescales.
2.36
Mouchel to submit fee proposal and programme for Surveys.
04/12/9
Mouch
2.37
Mouchel submitted revised buffer zone to SMBC (27/11/09). SMBC
SMBC
to review and respond as appropriate. Revised buffer zone was to
increase areas west of A555 as a result of design not being fixed.
2.38
Mandy Clarke, Cheshire East, confirmed as contact to liaise re
consents for access to land.
Health Impact Assessment
2.39
Mouch to liaise with SMBC public health officer on production of HIA.
Mouch
Any Other Business
2.40
Options report to be developed in support of design – issue re
SMBC/
severance of golf course issue to this regard.
SW
Date of Next Meeting
2.41
To be arranged.
SW
Date of Notes
27 November 2009
s:\projects\semmms major information\15.0 meetings\15.7 environmental team
meetings\semmms envtl update mtg 091124.doc
Form No. Q102
24.05.00