Minutes
Project SEMMMS A6 to Airport Relief Road
Job No
Date of Meeting 23/10/09
Meeting No 1
Page 1
of 5
Location of Meeting
Hygarth House – Stockport MBC
Time of Meeting
1.00 pm
Subject of Meeting
Scheme Cost Estimate
Persons present including representation
Martin Rigby (MR)
SMBC – Head of Engineering
David Taylor (DT) SMBC – Highway Design Manager
Naz Huda (NH) SMBC – Senior Highway Engineer
John Smith (JS) Corderoy – Principal Surveyor
Joseph Roberts (JR) Scott Wilson – Programme Manager
Distribution of notes to As above and Tim Baker and Graham Martin (Scott Wilson)
S:\Projects\SEMMMS Major Information\15.0 Meetings\15.18 Scheme Cost Estimate
Date of Notes
23 October 2009
Meetings\Scheme Cost Estimate 23 10 09.doc
Form No. Q102
24.05.00
Minutes
Project SEMMMS A6 to Airport Relief Road
Job No
Date of Meeting 23/10/09
Meeting No 1
Page 2
of 5
NOTES
DATE ACTION
1.0 Introduction
1.1 The purpose of the meeting was to brief Corderoy on the updated scheme
and discuss the task of producing an updated scheme estimate. Apologies
from Tim Baker – Scott Wilson.
2.0 Rates
2.1 MR confirmed that all rates to be set at a base date of Q2 2007 as with the
previous estimate.
2.2 Inflation would be in accordance with latest (draft) WebTAG at 2.7%. An
allowance for fluctuations in the inflation will be made in the project risk
register.
3.0 Preliminaries
3.1 The construction contract duration to be 130 weeks in line with the current
programme.
4.0 Safety Fencing
4.1 JS to review costs for both steel tension crash barrier and wire rope options.
4.2 MR requested that Scott Wilson provide a review of the safety fencing 03/11
JMR/S
options.
W
5.0 Drainage, Service Ducts and Structures
5.1 DT to provide JS with a schedule of structures and culverts – DT to review 03/11
DT
existing structures schedule against design freeze 2 layout.
6.0 Earthworks
6.1 MR explained that the earthworks information for the Manchester and
Cheshire East section was unavailable at present.
6.2 In order to allow Corderoy to carry out initial analysis, DT to provide JS with 03/11
DT
the original and new vertical alignments of the Stockport section.
6.3 DT to review the earthworks schedules and inform Corderoy of his findings.
03/11
DT
7.0 Kerbs, Footways and Paved Areas
7.1 MR explained that the typical cross section had changed since the previous 23/10
DT
estimate with the hardstrips removed and additional kerbs introduced. DT to
provide JS with typical cross section dimensions.
S:\Projects\SEMMMS Major Information\15.0 Meetings\15.18 Scheme Cost Estimate
Date of Notes
23 October 2009
Meetings\Scheme Cost Estimate 23 10 09.doc
Form No. Q102
24.05.00
Minutes
Project SEMMMS A6 to Airport Relief Road
Job No
Date of Meeting 23/10/09
Meeting No 1
Page 3
of 5
NOTES
DATE ACTION
8.0 Lighting
8.1 MR confirmed that street lighting would only be provided at the junctions.
9.0 Communications
9.1 MR confirmed that the provision for communications would remain
unchanged since the last estimated cost report.
10.0 SU Diversions
10.1 Corderoy to review the £4.5m stated in the original estimated cost.
JS
10.2 DT to provide information available on SU diversion costs.
23/10
DT
11.0 Complimentary Measures
11.1 MR to review the current allocation for complimentary measures and pass 03/11
MR
his information to Corderoy
12.0 Traffic Signs and Road Markings
12.1 DT to provide Corderoy with a schedule of junctions which will require 03/11
DT
signalisation.
13.0 Land Values
13.1 MR confirmed that SMBC would be looking to Norfolk Property Services to 03/11
MR
provide an update on the lands costs for the scheme by mid November for
the Stockport section. MR to confirm if Manchester City Council and
Cheshire East council would be providing an updated land costs estimate
for their sections of the scheme.
S:\Projects\SEMMMS Major Information\15.0 Meetings\15.18 Scheme Cost Estimate
Date of Notes
23 October 2009
Meetings\Scheme Cost Estimate 23 10 09.doc
Form No. Q102
24.05.00