This is an HTML version of an attachment to the Freedom of Information request 'SEMMMS meeting minutes'.
 
 
Minutes 

Project  SEMMMS A6 to Airport Relief Road 
Job No   
Date of Meeting  23/10/09 
Meeting No  
Page 1 of 5 
 
 
Location of Meeting 
Hygarth House – Stockport MBC 
Time of Meeting 
1.00 pm 
Subject of Meeting 
Scheme Cost Estimate 
Persons present including representation 
 
 
Martin Rigby  (MR)   
SMBC – Head of Engineering 
David Taylor (DT)                   SMBC – Highway Design Manager 
Naz Huda (NH)                       SMBC – Senior Highway Engineer 
John Smith  (JS)                     Corderoy – Principal Surveyor 
Joseph Roberts (JR)              Scott Wilson – Programme Manager 
 
 
Distribution of notes to 
 
As above and Tim Baker and Graham Martin (Scott Wilson) 
 
S:\Projects\SEMMMS Major Information\15.0 Meetings\15.18 Scheme Cost Estimate 
Date of Notes 
23 October 2009 
Meetings\Scheme Cost Estimate 23 10 09.doc 
Form No. Q102 
24.05.00    

 
 
Minutes 

Project  SEMMMS A6 to Airport Relief Road 
Job No   
Date of Meeting  23/10/09 
Meeting No  
Page 2 of 5 
 
 
 
NOTES 
DATE   ACTION 
1.0 Introduction 
 
 
 
 
 
1.1 The purpose of the meeting was to brief Corderoy on the updated scheme   
 
and  discuss  the  task  of producing  an  updated  scheme  estimate.  Apologies 
from Tim Baker – Scott Wilson. 
 
 
 
2.0 Rates 
 
 
 
 
 
2.1 MR confirmed that all rates to be set at a base date of Q2 2007 as with the   
 
previous estimate. 
2.2  Inflation  would  be  in  accordance  with  latest  (draft)  WebTAG  at  2.7%.  An   
 
allowance  for  fluctuations  in  the  inflation  will  be  made  in  the  project  risk 
register. 
 
 
 
3.0 Preliminaries 
 
 
 
 
 
3.1 The construction contract duration to be 130 weeks in line  with the  current   
 
programme. 
 
 
 
4.0 Safety Fencing 
 
 
 
 
 
4.1  JS to review costs for both steel tension crash barrier and wire rope options.   
 
4.2  MR  requested  that  Scott  Wilson  provide  a  review  of  the  safety  fencing  03/11 
JMR/S
options. 

 
 
 
5.0 Drainage, Service Ducts and Structures 
 
 
 
 
 
5.1 DT to provide JS with a schedule of structures and culverts – DT to review  03/11 
DT 
existing structures schedule against design freeze 2 layout. 
 
 
 
6.0 Earthworks 
 
 
 
 
 
6.1  MR  explained  that  the  earthworks  information  for  the  Manchester  and   
 
Cheshire East section was unavailable at present.  
6.2  In order to allow Corderoy to carry out initial analysis, DT to provide JS with  03/11 
DT 
the original and new vertical alignments of the Stockport section. 
6.3  DT to review the earthworks schedules and inform Corderoy of his findings. 
03/11 
DT 
 
 
 
7.0 Kerbs, Footways and Paved Areas 
 
 
 
 
 
7.1 MR explained that the typical cross section had changed since the previous  23/10 
DT 
estimate with the hardstrips removed and additional kerbs introduced.  DT to 
provide JS with typical cross section dimensions. 
 
 
 
 
 
 
S:\Projects\SEMMMS Major Information\15.0 Meetings\15.18 Scheme Cost Estimate 
Date of Notes 
23 October 2009 
Meetings\Scheme Cost Estimate 23 10 09.doc 
Form No. Q102 
24.05.00    

 
 
Minutes 

Project  SEMMMS A6 to Airport Relief Road 
Job No   
Date of Meeting  23/10/09 
Meeting No  
Page 3 of 5 
 
 
 
NOTES 
DATE   ACTION 
8.0 Lighting 
 
 
 
 
 
8.1 MR confirmed that street lighting would only be provided at the junctions. 
 
 
 
 
 
9.0 Communications 
 
 
 
 
 
9.1  MR  confirmed  that  the  provision  for  communications  would  remain     
 
unchanged since the last estimated cost report. 
 
 
 
10.0 SU Diversions 
 
 
 
 
 
10.1 Corderoy to review the £4.5m stated in the original estimated cost. 
 
JS 
10.2 DT to provide information available on SU diversion costs. 
23/10 
DT 
 
 
 
11.0 Complimentary Measures 
 
 
 
 
 
11.1 MR to review the current allocation for complimentary measures and pass  03/11 
MR 
his information to Corderoy 
 
 
 
12.0 Traffic Signs and Road Markings 
 
 
 
 
 
12.1  DT  to  provide  Corderoy  with  a  schedule  of  junctions  which  will  require  03/11 
DT 
signalisation. 
 
 
 
13.0 Land Values 
 
 
 
 
 
13.1 MR confirmed that SMBC would be looking to Norfolk Property Services to  03/11 
MR 
provide an update on the lands costs for the scheme by mid November for 
the  Stockport  section.  MR  to  confirm  if  Manchester  City  Council  and 
Cheshire  East  council  would  be  providing  an  updated  land  costs  estimate 
for their sections of the scheme. 
 
S:\Projects\SEMMMS Major Information\15.0 Meetings\15.18 Scheme Cost Estimate 
Date of Notes 
23 October 2009 
Meetings\Scheme Cost Estimate 23 10 09.doc 
Form No. Q102 
24.05.00