This is an HTML version of an attachment to the Freedom of Information request 'SEMMMS meeting minutes'.
 
 
Minutes 

Project  SEMMMS A6 to Airport Relief Road 
Job No   
Date of Meeting  02/10/09 
Meeting No   
Page 1 of 5 
 
 
Location of Meeting 
Hygarth House – Stockport MBC 
Time of Meeting 
3.00 pm 
Subject of Meeting 
Progress Meeting 
Persons present including representation 
 
 
Jim McMahon (JMcM) 
SMBC – Service Director 
Sue Stevenson (SS)   
SMBC – Head of Transportation 
Martin Rigby  (MR)   
SMBC – Head of Engineering 
Tim Baker (TJB)  
 
Scott Wilson – Project Manager  
Graham Martin (GM)   
Scott Wilson 
Distribution of notes to 
 
As above 
Joseph Roberts (JR)   
Scott Wilson 
David Taylor (DT) 
 
SMBC 
 
 
Date of Notes 
8 October 2009 
s:\projects\semmms major information\15.0 meetings\15.1 general\progress update to 
smbc 02 10 09.doc 
Form No. Q102 
24.05.00    

 
 
Minutes 

Project  SEMMMS A6 to Airport Relief Road 
Job No   
Date of Meeting  02/10/09 
Meeting No   
Page 2 of 5 
 
 
 
NOTES 
DATE   ACTION 
 
JMcM  stated  that  his  role  as  Project  Director  on  the  Governance   
 
Board and that SEMMMS would be taking priority. 
 
 
 
 
GM  stated  that  Progress  Meetings  have  been  diarised  up  to   
SMBC/
February 2010.  Project Board meetings to be diarised post meeting 
SW 
No.1 scheduled for 16th October 2009. 
 
 
 
1. 
Traffic Modelling 
 
 
 
 
 
1.1 
TJB  confirmed  that  the  traffic  modelling  was  a  significant  issue  in  ASAP 
SW/SS 
terms  of  progress  and  associated  programming.    SW  to  liaise  with 
Motts and GMTU with SS (SMBC) in terms of clarifying matters and 
identifying risk items. 
 
 
 
1.2 
Business  Case  to  be  submitted  in  February  2010  Two  modelling   
 
routes  currently  being  followed,  SEMMMS  6  –  to  be  used  for 
business  case.    Business  Case  to  prove  whether  PFI  is  a  viable 
option.  SEMMMS  7  –  to  be  developed  with  latest  traffic  data  and 
model etc. for planning application. 
 
 
 
 
1.3 
TJB  stated  concern  of  non-fix  of  3  no.  junctions  within  MCC  remit,   
 
being  Styal  Road;  Shadowmoss  Road  and  Terminal1/Airport 
junctions.    Particularly  as  the  fixing  of  the  schemes  are  not  being 
prioritised in line with current programme. 
 
 
 
1.4 
JMcM  to  contact  Chris  Barber  MCC  to  chase-up  progress  and  05/09/9  JMcM 
confirm that design fix required for 16th October 2009. 
 
 
 
1.5 
MR  confirmed  that  SMBC  on  Design  Freeze  1  (although  Drawings   
 
state Freeze 5). 
 
 
 
1.6 
TJB stated that key/fundamental  decisions to  be  made re  above for   
 
modelling  to  progress.    Discussion  with  Motts  indicated  that  Motts 
would be submitting Local Model Validation Report (LMVR) to DfT on 
9th October 2009. 
 
Post Meeting Note: refer to GM email to Motts HF dated 06/09/9 
 
 
 
1.7 
JMcM  to  contact  Charlie  Sutherland  (DfT)  re  response  from  DfT   
JMcM 
ASAP post submission of LMVR to DfT. 
 
 
 
2. 
Highways 
 
 
 
 
 
2.1 
SW received CDs of information from SMBC to initiate design review.  23/10/9  SW 
Date of Notes 
8 October 2009 
s:\projects\semmms major information\15.0 meetings\15.1 general\progress update to 
smbc 02 10 09.doc 
Form No. Q102 
24.05.00    

 
 
Minutes 

Project  SEMMMS A6 to Airport Relief Road 
Job No   
Date of Meeting  02/10/09 
Meeting No   
Page 3 of 5 
 
 
 
NOTES 
DATE   ACTION 
 
 
 
 
 
2.2 
Noted  that  SMBC  have  a  Scheme  Description  on  file  –  D  Taylor   
SMBC 
SMBC to locate documents and revise description accordingly. 
 
 
 
3.  
Environmental  
 
 
 
 
 
3.1 
Scott Wilson to undertake a full and detailed review – SW picked up  08/10/9  SW/ 
report  information  from  Mouchel  01/10/09.    Meeting  arranged  with 
SMBC 
Mouchel for 08/10/09 at SMBC offices. 
 
 
 
3.2 
Establish the extent of winter (bird) surveys to be initiated ASAP with   
SW/ 
Mouchel and SMBC. 
Mouch 
 
Spring  surveys  to  be  identified  ASAP  for  purposes  of  inputting  to 
programme and costs.  Mouchel to fix on delivery dates. 
 
 
 
4.0  
Land & Orders 
 
 
 
 
 
4.1 
Land  and  Orders.  Still  an  area  that  requires  development.  Meeting   
SW/ 
arranged  08.10.09  @  SMBC  offices  to  confirm  status  of  associated 
SMBC 
activities and establish way forward. 
 
 
 
4.2 
Risk associated with additional land being required in terms of MCC  21/09/9  TJB 
design  modifications  that  are  currently  being  progressed  by  MCC  – 
refer to Item 1.3. 
 
 
 
4.3 
JMcM  to  speak  to  Carol  Summers  @  NPC  to  confirm  the  scope  of   
JMcM 
services  that  NPS  can  deliver  to  SMBC  with  regard  to  Land  and 
Orders and actions with Land Registry; ownership etc.  This is with 
view  to  SMBC/SW  appointing  appropriate  parties  to  take  Land  & 
Orders actions forward. 
 
 
 
5.0  
Planning 
 
 
 
 
 
5.1 
Agreement of standard of planning application will need to be agreed   
SW/ 
with  all  3  authorities  –  meeting  with  SMBC  Planning  07.10.09.    SW 
SMBC 
nee dot establish legal requirements for planning submission. 
 
 
 
5.2 
SW  to  make  further  enquiries  and  recommendations  with  regard  to   
SW 
potential  IPC  process.    Seek  to  establish  what  threshold  is  for 
scheme to be considered by IPC.  GM commented that early liaison / 
consultation with IPC would be recommended. 
 
 
 
5.3 
Counsel  to  be  appointed  at  early  stage  to  review  all  issues  of   
 
Planning  Application  and  its  defense.    Traffic  modelling  and 
economic appraisal will be key to this process 
Date of Notes 
8 October 2009 
s:\projects\semmms major information\15.0 meetings\15.1 general\progress update to 
smbc 02 10 09.doc 
Form No. Q102 
24.05.00    

 
 
Minutes 

Project  SEMMMS A6 to Airport Relief Road 
Job No   
Date of Meeting  02/10/09 
Meeting No   
Page 4 of 5 
 
 
 
NOTES 
DATE   ACTION 
 
 
 
6.0  
Scheme Costs 
 
 
 
 
 
6.1 
Commented  that  limited  information  presently  to  justify  290  million   
 
scheme  cost  and  that  this  costing  exercise  required  to  be  revisited 
when there is Scheme FIX; land costs are better established and risk 
items identified/costed post Risk Workshop (16.10.09). 
 
 
 
6.2 
SMBC  will  investigate  appointment  of  Cost  Consultant  for  this   
 
exercise - Corduroy previously did costing exercise. 
 
 
 
6.3 
Separate advice will be required to cost the land values – refer item   
 
4.3. 
 
 
 
7.0  
Risk Workshop 
 
 
 
 
 
4.1 
SW  to  review/comment  on  risk  register  as  provided  by  Motts.    MR   
SW 
passed copy of separate risk register for comparative purposes (also 
developed by Motts).  Revaluation of risk values – this will be further 
developed for and post Risk Workshop 16.10.09. 
 
 
 
4.2 
SW circulating invites for Risk Workshop 16.10.09 and will facilitate. 
16/10/9 
SW 
 
 
 
4.3 
Noted that any risks associated with PFI would be logged separately.   
 
 
 
 
8.0  
Communications 
 
 
 
 
 
4.1 
SW  to  continue  to  update  Project  Directory  and  circulate  –  live   
SW 
documents on ProjectSpace. 
 
 
 
4.2 
SW are  in  process of  setting  up  ProjectSpace,  with filing  system  as   
SW 
will be set-up on S drive (SMBC) for SEMMMS activities from Oct 09 
onwards.    SW  will  provide  log-ons/passwords  to  external  personnel 
for access to ProjectSpace – SW to agree list of personnel provided 
access to ProjectSpace. 
 
 
 
4.3 
Further to meeting with Counter Context, SS confirmed that Counter   
 
Context will address the action re Consultation and SMBC re Media 
relations/communications.    SS  will  coordinate  the  communications 
aspects of the project. 
 
 
 
4.4 
SMBC have historical document on file re Communications Policy –   
SMBC 
to be updated and circulated. 
 
 
 
 
Date of Notes 
8 October 2009 
s:\projects\semmms major information\15.0 meetings\15.1 general\progress update to 
smbc 02 10 09.doc 
Form No. Q102 
24.05.00