This is an HTML version of an attachment to the Freedom of Information request 'SEMMMS meeting minutes'.
 
 
Minutes 

Project  SEMMMS A6 to Manchester Airport Relief Road 
Job No   
Date of Meeting  16/10/09 
Meeting No  
Page 1 of 5 
 
 
Location of Meeting 
Hygarth House – Stockport MBC 
Time of Meeting 
12.00 hrs 
Subject of Meeting 
Project Board Meeting No. 1 
Persons present including representation 
 
 
Jim McMahon (JMcM) 
Stockport MBC 
Chris Barber (CB) 
 
Manchester City Council 
John Gray (JG) 
 
Cheshire East 
Tim Baker (TJB)  
 
Scott Wilson – Project Manager  
Graham Martin (GM)   
Scott Wilson – Deputy Project Manager  
 
Distribution of notes to 
 
As above + 
Andrew Ross (AR) 
 
Cheshire East 
John Twigg (JT) 
 
Manchester Airport 
David Bland   
 
Manchester City Council 
Peter Davies-Colley   
Manchester City Council 
Andrew Buckley 
 
Cheshire East 
Sue Stevenson (SS)   
SMBC – Head of Transportation 
Martin Rigby  (MR)   
SMBC – Head of Engineering 
David Hughes (DH)    
Scott Wilson – Project Director  
Colin Barker (CB)  
 
Scott Wilson – Framework Director 
 
Date of Notes 
19 October 2009 
s:\projects\semmms major information\15.0 meetings\15.3 project board 
meetings\project board no 1\semmms - minutes of mtg project board no 1 16 10 09.doc 
Form No. Q102 
24.05.00    

 
 
Minutes 

Project  SEMMMS A6 to Manchester Airport Relief Road 
Job No   
Date of Meeting  16/10/09 
Meeting No  
Page 2 of 5 
 
 
 
NOTES 
DATE   ACTION 
1. 
Introductions 
 
 
1.1 
Apologies  from  Andrew  Ross  (CE)  and  John  Twigg  (Manchester   
 
Airport). 
 
 
 
2. 
Summary of Current Position 
 
 
 
 
 
2.1 
SEMMMS 6 traffic model is to be utilised for Programme Entry, with   
 
submission  to  DfT  in  February  2010  of  supporting  Business  Case.  
SEMMMS  7  will  be  progressed  in  parallel  as  model  to  support 
planning application and Transport Assessment, late summer 2010 – 
Agreed.  
 
 
 
2.2 
MCC now have agreed layout of junctions at Terminal 1 / Terminal 3   
 
and Styal Road.  These would be forwarded to SMBC/SW 19/10/09 
and would confirm scheme fix for Business Case. 
 
[Post  Meeting  Note:  Peter  Davies-Colley  (MCC)  contacted  TJB 
19/10/09  to  confirm  junction  layouts  will  be  forwarded  to  SMBC/SW 
20/10/09 pm – received 20/10/09] 

 
 
 
2.3 
MCC  advised  that  Metrolink  interface  and  design  issues  remain  w.e. 
MCC 
unresolved  –  MCC  having  meetings  with  the  PTE  w.c.  19th  October  23/10/9 
to resolve.  MCC to feedback to project team SMBC/SW. 
 
 
 
 
 
3.  
Governance 
 
 
 
 
 
 
(i) Project Initiation Documents 
 
 
3.1 
Any comments on documents issued 14/10/9 to be sent to TJB/GM.    
ALL 
However, scope of documents agreed in principle. 
 
 
 
 
(ii) Organisational Structure 
 
 
3.2 
Strategic  Governance  Committee:  JMcM  proposed  that  Joint   
ALL / 
Committee between the 3 no. authorities to be established ASAP for 
JMcM 
prompt  decision  making  –  agreed  in  principle.    JMcM  to  prepare  a 
proposal  for  consideration  and  circulate  details  of  similar  Joint 
Committees that have worked. 
 
 
 
3.3 
MCC,  CE  and  SMBC  to  review  requirements  within  their  LA’s  for   
ALL 
Business Case submission. Executive approval will be required. 
 
 
 
3.4 
It was agreed that design needs to be delivered as a single scheme   
 
by single design teams rather than 3 authorities working separately. 
 
 
 
3.5 
JMcM and CB are represent AGMA on the SEMMMS Project Board. 
 
 
 
 
 
 
Date of Notes 
19 October 2009 
s:\projects\semmms major information\15.0 meetings\15.3 project board 
meetings\project board no 1\semmms - minutes of mtg project board no 1 16 10 09.doc 
Form No. Q102 
24.05.00    

 
 
Minutes 

Project  SEMMMS A6 to Manchester Airport Relief Road 
Job No   
Date of Meeting  16/10/09 
Meeting No  
Page 3 of 5 
 
 
 
NOTES 
DATE   ACTION 
3.6 
Project Management Team: CE and MCC to be represented on Core   
CE 
Management  Team  and  provided  opportunity  to  attend  monthly 
/MCC 
progress meetings.  SW to update organogram and CE and MCC to 
/SW 
confirm/provide  appropriate  names  for  representatives.    CE  and 
MCC will also be invited to Technical Working Group meetings. 
 
 
 
3.7 
SW to correct/update organisational structures within PIDs. 
 
SW 
 
 
 
 
(iii) Organisational Structure 
 
 
3.8 
MCC  and  CE  to  provide  comments  on  Delivery  Teams  paper   
ALL 
(attached)  tabled.    For  certain  teams  it  was  agreed  that  Team 
Leaders  would  coordinate  delivery  of  whole  scheme.  Team  leaders 
with  subsections  of  Delivery  Team  to  communicate  between  the  3 
no. authorities in order to make prompt decisions in moving forward. 
 
 
 
3.9 
SMBC,  CE  and  MCC  to  assess  available  resource  for  the  various   
CE 
delivery  teams  and  report  to  SMBC/SW.    CE  and  MCC  to  consider 
opportunity  for  secondment  into  SEMMMS  design  team  (based  at 
SMBC). 
 
MCC will have no resource available on highway design. 
 
Potential resource for bridges design. 
 
 
 
3.10 
Agreed  that  for  various  Delivery  Teams  Working  Groups  would  be   
ALL 
set-up to establish consistent standards for delivery with appropriate 
representation from each Authority. 
 
 
 
 
(iv) Financial Arrangements between Authorities 
 
 
3.11 
Draft paper tabled documenting Proposed Allocation of Development   
CE/ 
Costs between the Local Authorities (attached).  CE/MCC to provide 
MCC 
comments ASAP to SMBC/SW. 
 
 
 
4.0  
Programme 
 
 
 
 
 
4.1 
Current programme is: 
 
 
• 
Submission to DfT and approval of Business Case  - Feb 2010 
• 
Planning application late summer 2010 
• 
Construction start late 2012 
• 
Opening of scheme 2015 
 
See summary programme (attached). 
 
 
 
4.2 
It  was  agreed  to  review  possibility  of  going  to  pre-planning   
 
consultation in March 2010 with Opening Year 2015 traffic flows only.  
This will require some forecasting work but SEMMMS7 could still be 
used. 
Date of Notes 
19 October 2009 
s:\projects\semmms major information\15.0 meetings\15.3 project board 
meetings\project board no 1\semmms - minutes of mtg project board no 1 16 10 09.doc 
Form No. Q102 
24.05.00    

 
 
Minutes 

Project  SEMMMS A6 to Manchester Airport Relief Road 
Job No   
Date of Meeting  16/10/09 
Meeting No  
Page 4 of 5 
 
 
 
NOTES 
DATE   ACTION 
 
 
 
5.0 
Cost Control 
 
 
 
 
 
5.1 
MR will be issuing all Task Orders to external bodies/consultants for   
 
delivery  of  SEMMMS.    Any  submission  for  works  that  would  be 
considered chargeable to SEMMMS to be submitted / cc’d to MR. 
 
 
 
5.2 
SW  will  be  managing  cost  control  on  behalf  of  SMBC  and  report  to   
 
MR accordingly. 
 
 
 
5.3 
Mitigation  measures  essential  for  the  scheme  to  be  identified  and   
 
costed at earliest opportunity. 
 
 
 
5.4 
Complimentary  measures  to  be  reviewed  and  agreed  with  SMBC,   
ALL 
and other authorities as appropriate, prior to commitment. 
 
 
 
6.0 
Planning and Policy 
 
 
 
 
 
6.1 
Meeting held with SMBC Planners.  MCC and CE also to be met and   
ALL 
associated  Working  Group  to  be  set-up  to  seek  to  establish 
consistent approach across the 3 authorities. 
 
 
 
7.0 
Business Case and Funding 
 
 
 
 
 
7.1 
Business Case is being prepared with information currently available   
 
for  Programme  Entry  and  submission  and  approval  from  DfT 
February 2010. 
 
 
 
7.2 
Separate discussions relating to funding ongoing and will be reported   
 
and considered by the Board as appropriate. 
 
 
 
 
8.0 
Highway Design Standards 
 
 
 
 
 
8.1 
Draft  paper  tabled  by  TJB  and  will  be  circulated  in  due  course.    
SW/ 
Comments  requested  on  receipt  -  Item  2.1  of  the  paper  re  Design 
SMBC 
Speed agreed in principle. 
 
 
 
 
8.2 
Working  Group  to  seek  to  achieve  consistent  standard  details   
SW/ 
(Baseline) across the 3 authorities.  Technical workshop tba. 
SMBC 
 
 
 
9.0 
Environment 
 
 
 
 
 
9.1 
Mouchel to continue in role of delivery of Environmental Statement. 
 
 
 
 
 
 
Date of Notes 
19 October 2009 
s:\projects\semmms major information\15.0 meetings\15.3 project board 
meetings\project board no 1\semmms - minutes of mtg project board no 1 16 10 09.doc 
Form No. Q102 
24.05.00    

 
 
Minutes 

Project  SEMMMS A6 to Manchester Airport Relief Road 
Job No   
Date of Meeting  16/10/09 
Meeting No  
Page 5 of 5 
 
 
 
NOTES 
DATE   ACTION 
10.0 
Public Consultation 
 
 
 
 
 
10.1 
Agreed that all press releases/media for SEMMMS to be issued only   
 
through  Louise  Gresty  SMBC,  with  relevant  approvals  from  the  3 
authorities. 
 
 
 
10.2 
Next major public consultation is pre-planning consultation scheduled   
 
for March 2010 (12 week duration). 
 
 
 
11.0 
AOB 
 
 
 
 
 
11.1 
Noted that joint presentation (from all 3 no. authorities) to appropriate   
ALL 
Members for information purposes. 
 
 
 
11.2 
Title  of  scheme  agreed  as  SEMMMS  A6  to  Manchester  Airport   
 
Relief Road. 
 
 
 
11.3 
SW to circulate SEMMMS design freeze on receipt of MCC junction  w.c. 
SW 
layouts (and on further updates).  This will be Design Freeze 2. 
19/10/9 
 
 
 
12.0 
Date of Next Meeting 
 
 
 
Monday 16th November 2009 @ 10.00 hrs, Hygarth House, SMBC. 
 
ALL 
 
 
 
 
Date of Notes 
19 October 2009 
s:\projects\semmms major information\15.0 meetings\15.3 project board 
meetings\project board no 1\semmms - minutes of mtg project board no 1 16 10 09.doc 
Form No. Q102 
24.05.00