This is an HTML version of an attachment to the Freedom of Information request 'Tyne and Wear Metro in Washington'.
PROJECT ORPHEUS PHASE 1B   
SIFT RECOMMENDATIONS 

Report  
 
 
Final 6th March 2003 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Prepared for: 
Prepared by: 
 
 
Nexus Steer 
Davies 
Gleave 
Jacobs Gibb 
Ernst & Young 
 
 

 
 
CONTENTS 
 
1. 
INTRODUCTION 3 
Context 3 
Summary of Approach and Recommendations 

2. 
ISSUES TO CONSIDER IN APPRAISAL OF PHASE 1A ROUTES 
5 
Phase 1A Pre-feasibility NATA Assessment 

Demand and Benefit Estimate Risks and Opportunities 

Cost Estimate Risks and Opportunities 

Practicality / Implementability Risks and Opportunities 

Future Potential Changes in Appraisal Guidance 
11 
Potential Synergy between Orpheus Extensions and Other Policy Measures 
Under Consideration in Achieving Local Transport Plan Objectives 
11 
Potential Impacts 
11 
Appraisal Issues 
12 
Metro Financial Performance 
13 
Indicative Timescales for Implementation of Wider Policy Measures 
13 
3. 
RECOMMENDATIONS 15 
Summary 15 
Asset Renewal Issues 
19 
Recommended Short-term Phase 1B Actions 
19 
\\Douglas\Work\Projects\4800s\4884\Outputs\Working Notes\Phase 1B Sift Recommendations _ Final Report.doc 
 


 
 
1. INTRODUCTION 
Context 
1.1 
The purpose of this working note is to present to Nexus and their study partners the 
recommendations of the Orpheus study team arising from the review process 
undertaken during the initial stage of the Phase 1B study. The note summarises the 
potential risks and opportunities in the route-based analysis of the ten shortlisted 
Orpheus extensions that were identified as being likely to generate significant benefits 
during Phase 1A, and draws conclusions regarding the case for their continued 
inclusion in Orpheus. In the final section, two potential approaches to the remainder of 
the Phase 1B process are set out for discussion, and a number of short-term action 
recommendations are listed. 
1.2 
This review process is aimed at ensuring that the Phase 1B study is appropriately 
focused, so that the achievement of the objectives of the Outline Business Case, in 
delivering renewal and extension of the Metro system, is strengthened by the inclusion 
of fundable extension proposals. Whilst this note focuses primarily on the potential 
extensions to Metro, the importance of developing the renewal options for the existing 
system to the overall Orpheus project is also highlighted. 
1.3 
It is worth noting that whilst the DfT will consider a package of extensions where the 
economic and financial advantages of doing this are clear, they will still expect each 
extension to pass the fundability and economic viability thresholds individually. It 
should be anticipated the DfT will pay close attention to the financial impact of any 
renewal proposals and when considering extensions the DfT will wish to have 
confidence in a positive financial case for the extension and the Metro extensions as a 
whole. 
1.4 
The note builds on the information provided in Working Note 31. It is also informed 
by a draft report provided by JacobsGibb into potential cost variances within the Phase 
1A scheme cost estimates2, and further work undertaken by the study team as a whole. 
Summary of Approach and Recommendations 
1.5 
The approach taken in making the recommendations has been informed both by the 
NATA assessment and also by an assessment of the potential risks to the Outline 
Business Case both for the Orpheus project as a whole, and for each of the 10 
potential extensions individually.  
1.6 
Inevitably, the assessment of risk is largely a matter of the informed judgement of the 
consortium: however this process has identified some clear differences in levels of risk 
between the potential extensions, some of these risks being largely outwith the control 
of the study partners.  
                                                      
1  
Steer Davies Gleave, 4th February 2003. Working Note 3, 1st Draft: Potential Impact of Supportive 
Planning Policy Measures on Economic Appraisal of Orpheus Extensions 
2  
JacobsGibb, February 2003. A Consideration of Potential Cost Variances on Shortlisted 1B Routes 
\\Douglas\Work\Projects\4800s\4884\Outputs\Working Notes\Phase 1B Sift Recommendations _ Final Report.doc 
 


 
 
1.7 
The note makes recommendations that a phased approach to the assessment be 
considered in order, prior to submission of a bid for funding from the DfT, to: 
i) 
ensure that resources are appropriately targeted; 
ii) 
allow time to explore the implications and attitudes of local authority partners 
to the nature and detail of potential complementary policy measures and to 
ensure a satisfactory level of commitment;  
iii) 
understand the potential impacts of these complementary policy measures on 
the case for central Government funding, where appropriate, once the likely 
impact of these measures is better understood and tested within a overall 
Local Transport Plan strategy for the study area; and to 
iv) 
allow time to fully explore any significant interface or implementation risks 
with third parties (such as the SRA and Network Rail) so that an 
understanding can be arrived at with these third parties. 
 
 
\\Douglas\Work\Projects\4800s\4884\Outputs\Working Notes\Phase 1B Sift Recommendations _ Final Report.doc 
 


 
 
2. 
ISSUES TO CONSIDER IN APPRAISAL OF PHASE 1A ROUTES 
Phase 1A Pre-feasibility NATA Assessment 
2.1 
The initial economic assessment of the ten shortlisted Orpheus routes was set out in 
Working Note 3, incorporating recent changes to Government guidance regarding 
discount rates and treatment of costs (Table 1).  
2.2 
This Working Note indicated that the Phase 1A route sifting and assessment process 
has identified a number of Metro extensions that clearly merit further examination 
during the Orpheus study. It should be noted, however, that although all the Phase 1A 
shortlisted routes are likely to generate important levels of economic benefits, none of 
the routes clearly demonstrates, at this stage, a Cost:Benefit case which would meet all 
the criteria set by the DfT for major scheme funding. It should be noted that all ten 
shortlisted proposals have been selected from a long list of 29 using the NATA 
appraisal framework as a sifting tool, and thus all ten routes should perform well 
under the other NATA appraisal headings, although this is not sufficient in itself to 
achieve central Government funding. 
2.3 
Inevitably in a pre-feasibility study of this nature, the analysis of costs and benefits 
has been based on illustrative or specimen routes within the corridors identified as 
being worthy of detailed analysis, and this has guided the interpretation of the 
economic indicators developed for each potential extension. 
2.4 
In making recommendations regarding the extensions options to be taken forward 
within Phase 1B, it is prudent to take into account the areas of potential risk and 
opportunity inherent in the estimation of project costs and forecasts of benefits at this 
stage in the development process of any such project. These risks and opportunities 
may have implications for the timing of further development of some of the shortlisted 
routes. An outline assessment of the extent of potential up-side and down-side factors 
is set out in this section under the following headings: 
i) 
Demand and benefit levels; 
ii) 
Cost estimates; and 
iii) 
Practicality / implementability issues. 
2.5 
Where there are differences in the level of risks and opportunities between the ten 
shortlisted extensions this is noted: others may apply uniformly to all extensions. The 
assessment presented here is inevitably subjective, but is based on the combined 
judgement and experience of the Orpheus project team. 
Demand and Benefit Estimate Risks and Opportunities 
2.6 
The key areas of risk and opportunity in the demand and benefit estimates relate to the 
following issues: 
•  Base year demand levels and patterns. The economic assessment assumes that the 
travel and land use patterns forecast by the TAMMS study provide an adequate 
indication of travel volumes and patterns throughout the Tyne & Wear area. This 
\\Douglas\Work\Projects\4800s\4884\Outputs\Working Notes\Phase 1B Sift Recommendations _ Final Report.doc 
 


 
 
is likely to be the case for routes centred on the area central to that study, namely 
Newcastle & Gateshead. Further away from this focus (and particularly for routes 
in Sunderland, Durham and Northumberland) it is likely to be a less reliable 
information source. Further work in this area, particularly the collection of new 
bus trip origin-destination data, will significantly improve confidence in this 
element of the assessment in the remainder of Phase 1B (and this is a key lesson 
learnt from the Sunderland Direct development process). The effects, however 
may equally be upside or downside. 
•  Future demand levels and patterns. The assessment uses the TAMMS projections 
of changes in demand and travel patterns to 2011. Following 2011 it has been 
assumed that public transport growth will occur at a rate of 1% per annum over 
the project life. While the approach is consistent with other studies, this has not 
been the recent experience in Tyne & Wear and therefore an assessment using a 
different level of outturn growth may be required. 
•  Mode choice and potential competitive position of Orpheus routes. The Phase 1A 
appraisal has assumed that bus services will not change following introduction of 
Orpheus. This is seen as a central position, which could be down-side (if new 
competing services are introduced) or up-side (if the network is redrawn to 
reduce parallel services). There are, however, some route-specific issues relating 
to level of segregation (and thus ability to maintain service attractiveness – as 
implicit in the mode constant and other mode choice parameters - with increasing 
congestion levels) and to proposals for other services. Further assessment of the 
potential synergy of Orpheus extensions with other policy measures is set out in 
the next section. It should also me noted that other initiatives to improve bus 
services are contained within the Local Transport Plan, and these improvements 
will need to be taken into account in any future more detailed assessment. 
•  Potential for additional travel markets not currently included in case. The 
provision of Park and Ride facilities has been excluded from the analysis 
undertaken to date in view of the lack of detailed knowledge of site availability 
and size, but a qualitative assessment (see Working Note 3) indicates that Routes 
9, 19 and 21 show potential for park and ride provision. 
2.7 
A summary of the potential demand and benefit risks as they relate to individual 
extension is set out in Table 2.1. 
TABLE 2.1 
POTENTIAL LEVEL OF RISK TO ECONOMIC CASE ARISING FROM 
DEMAND AND BENEFIT ESTIMATION 

Base 
Future 
Segregation 
Changes to 
Additional 
Route 
Year 
year 
Level 
Other Services 
Markets 
Demand  Demand 
Route 1 – Seaham to 

Sunderland 
+/- - 
0  (Inc. in rail freqs. 

on Durham Coast) 
Route 2 – Sunderland to 
+/- -  +/- 
 

Doxford/Ryhope  
Routes 5/6– Sunderland 
 
 
 
 
 
to Washington 
via S Hylton 
+/- - 

 

via Southwick 
+/- 

+/- 
 

Route 8 – Washington to 
+/- -  +++/--- 
- (Leamside Line 

Gateshead/Heworth 
reopening) 
Route 9 – Team Valley 
+/- - 

 
+++ 
to Gateshead 
\\Douglas\Work\Projects\4800s\4884\Outputs\Working Notes\Phase 1B Sift Recommendations _ Final Report.doc 
 


 
 
Base 
Future 
Segregation 
Changes to 
Additional 
Route 
Year 
year 
Level 
Other Services 
Markets 
Demand  Demand 
Route 12 – West Harton 
+/- - 

 

to Biddick Hal  
Route 19 - Gateshead to 
+/- - 
0 Centrelink service 
++ 
MetroCentre 
development 
Route 21 – West End 
 
 
 
 
 
St James to Walbottle  
+/- 

+++/--- 
 
+++ 
St James to MetroCentre 
+/- 

++/-- 
 
++ 
Route 23  
 
 
 
 
 
K’worth to 4 Lane Ends 
+/- 

++/-- 
 

C’lington to 4 Lane Ends 
+ (ECML-driven 
+/- -  ++/-- 
reductions in local 

rail services) 
Route 28 – Byker to 
Walkergate 
+/- -  +/- 
 

Note:  Scale runs between  --- (risk of significant negative impact) through 0 (neutral) to +++ (risk of 
significant positive impact) 
Cost Estimate Risks and Opportunities 
2.8 
JacobsGibb has assessed the potential level of cost risk associated with the extensions 
under the following headings: 
•  Alignment (and particularly dependence on parallel Masterplanning work) 
•  Isolation from existing system (a standalone system likely to be higher cost) 
•  Rolling stock (need for bespoke vehicles) 
•  Heavy rail interface (where use of Network Rail alignments may be required) 
•  Structures (need for, and extent of, structures) 
•  Utilities (level of cost relating to diversion of Statutory Undertaker’s utilities) 
•  Integration with Metro (if means of access to the existing Metro system is not yet 
fully established) 
2.9 
The conclusions of this exercise are set out in the Table overleaf. All risks to the costs 
have currently been identified as having a down-side effect. Some specific exclusions 
from the cost estimates have been identified, and (with the general exception of land 
costs and – potentially - the use of 20% for utility diversions rather than 10% 
employed here). These are largely route-specific. Examples include amendments to 
heavy rail signalling and power supply on Network Rail routes, bespoke LRVs for the 
gradients on Route 21, and additional allowances for difficult structures. 
2.10 
It should be noted that the application of the Green Book recommendations (and in 
particular the uplift applied to capital costs to reflect optimism bias3) are intended to 
                                                      

The Green Book provides a range of outturn cost overruns for non-standard civil engineering 
projects. It is not possible at this stage to assess the applicability of a specific value with confidence 
– however for the purposes of this exercise a factor of 1.66 has been used, representing the top end 
of the quoted range. As the project definition becomes sharper in scope, and as risk management 
processes are identified and adopted, it should be possible in later stages of the appraisal to agree a 
lower figure with the DfT. 
\\Douglas\Work\Projects\4800s\4884\Outputs\Working Notes\Phase 1B Sift Recommendations _ Final Report.doc 
 


 
 
account for many of these down-side risks which can be difficult to quantify at this 
stage of project development. Note therefore that the costs or impacts shown in the 
Table overleaf are merely for information to show differences by routes – the costs 
should only be added in addition to the Green Book uplift where there may be 
omissions from the cost headings.  
2.11 
Any reduction in the level of optimism bias uplift would require evidence of the 
outcome of quantified risk assessments or particular consideration of key risks or 
elements of the proposed design which have not been undertaken (or would 
necessarily be expected to have been undertaken) at this stage of the development of 
the Orpheus project.  
TABLE 2.2 
POTENTIAL LEVEL OF RISK TO ECONOMIC CASE ARISING FROM 
DEMAND AND BENEFIT ESTIMATION 

 

i
l
 
a

es 
tro 
e

t
 

Route 
t
ainty 

f
ace 

ctur
cer
u
Cos
Rolling 
Stock 
eavy R
Utilities 
Impact 
Alignment 
n
Isolatio
Inter
Potential 
U
H
Str
Integration
with M
Route 1 – Seaham to 
     - 
-      +10 
to 
15% 
Sunderland 
Route 2 – Sunderland to 
+10-15% 
Doxford/Ryhope  
   

-4   -  - plus £0.6 - 
£0.8m 
Routes 5/6– Sunderland to 
 
 
 
 
 
 
 
 
Washington 
via S Hylton 
 
 
 
- - 
- - 
 
 
+£3-£4m 
via Southwick 
 
 
 
- - 4 - 
-   
  +£5-£7m 
Route 8 – Washington to 
 - -  - 


-  +£5-6m + 
Gateshead/Heworth 
10-20% utils 
Route 9 – Team Valley to 
   - 

-   
+£9-£11m 
Gateshead 
Route 12 – West Harton to 
   

-4      
N/a 
Biddick Hall 
Route 19 - Gateshead to 
    - 
-   
+£9-£11m 
MetroCentre 
 
 
 
 
 
 
 
 
 
Route 21 – West End 
St James to Walbottle 
 
 
- - 
 
- - 

 
+£10-£15m 
St James to MetroCentre 
 
 
- - 
 
- - 

 
+£10-£15m 
Route 23  
 
 
 
 
 
 
 
 
K’worth to 4 Lane Ends 
+ / - 
 
 
 
- - 
 
 
N/a 
C’lington to 4 Lane Ends 
+ / - 
 
 
 
- - 
 
 
N/a 
Route 28 – Byker to 
Walkergate 
-      - - -  N/a 
Note: 
Scale runs between  --- (significant negative impact) through 0 (neutral) to +++ (significant positive impact) 
 
                                                      

If service extended beyond Sunderland 
\\Douglas\Work\Projects\4800s\4884\Outputs\Working Notes\Phase 1B Sift Recommendations _ Final Report.doc 
 


 
 
Practicality / Implementability Risks and Opportunities 
2.12 
An internal workshop was held by Nexus and the study team on the 27th January 2003 
to assist in the process of understanding: 
•  The potential risks in integrating LRT, Metro and Heavy Rail technologies, and  
•  Risks relating to asset life and replacement strategy. 
2.13 
Notes of this meeting were issued on the 13th February to Nexus, and JacobsGibb is 
currently preparing a report. The main issues as they relate to the Phase 1B sift relate 
to costs (considered above) and to implementation risk (often driven by the nature and 
extent of the interfaces between the Promoter and other interested bodies.) 
2.14 
In the absence of the report, it is possible to make some general points that may affect 
the Phase 1B sift. In particular, these relate to  
•  The potential for low floor LRV operation on the existing system; and 
•  Whether the project may impact on the capacity (and therefore the performance) 
of the heavy rail network. 
2.15 
The workshop identified that the potential for operation of low floor LRV through the 
central area Metro tunnels may involve a considerable risk that the station boxes may 
need to be extended, and that it is possible that these changes may result in the need to 
apply the standards of safety applicable to underground stations since the Kings Cross 
fire. This could result in a significant level of additional cost to the project through, for 
example, the provision of additional exits from central stations, specialist fire fighting 
equipment and may require modified working practices. No conclusion on this area of 
risk has yet been made by the study team, and it is not yet clear whether this may have 
implications on route selection. 
2.16 
Regarding Orpheus extensions onto heavy rail alignments, the SRA has made two 
relevant statements recently regarding spending priorities. First, they have indicated 
that the SRA is interested in assessing options for replacing heavy rail local services 
with light rail where they are likely to achieve a robust economic case. Although it is 
understood that Nexus is intending to discuss this further with the SRA, it is thought 
that at this stage the focus of this interest is likely to be Birmingham and Manchester 
where there are major rail capacity and/or subsidy issues which light rail could 
address. In the North East, the options are less obvious, with no lines providing only 
local rail services and most having significant volumes of freight and/or intercity 
traffic. Indeed, as part of the Capacity Utilisation Strategy process, local services on 
the ECML north of Newcastle are believed to be under examination in an attempt to 
increase capacity for longer-distance services, and there are few opportunities to divert 
freight services from the Durham Coast and ECML north of Newcastle. 
2.17 
Secondly, the SRA has clearly set out, in the Second Strategic Plan and in the 
announcement regarding steps to improving rail network performance of 16th January 
2003, that in the next few years it is unlikely to fund schemes which may add to 
congestion on the network. In this context, the main conclusions that can be drawn is 
that the routes involving use of Network Rail infrastructure are likely to involve a 
considerable level of implementation and institutional risk, and that this risk is likely 
\\Douglas\Work\Projects\4800s\4884\Outputs\Working Notes\Phase 1B Sift Recommendations _ Final Report.doc 
 


 
 
to continue through 2003/4 and beyond. Moreover, the de-scoping of ECML upgrade 
proposals is, in the short to medium term, likely to limit opportunities for enhancing 
local rail capacity (for shared or sole use) as well as limiting the potential for new 
local rail services. On the Durham Coast and Hexham lines, however, it may be that 
potential changes to the level of service in response to the capacity utilisation review 
could have a positive effect on the case for Orpheus extensions. 
2.18 
The main implication of this for the Phase 1B study is in relation to the timing of any 
funding submission to Government for routes involving heavy rail alignments 
(although there may be a cost impact as well), specifically routes 1, 2, 9, 12 and 19 
and potentially 5 & 6 (if through-running beyond Park Lane is envisaged). In the case 
of the Sunderland to Pelaw line, for example, it has been indicated that an additional 
six paths per hour would be operable were the Durham Coast services to terminate at 
Sunderland from the south. It may be sensible in this case to establish a dialogue 
during Phase 1B with the study partners regarding the optimal use of the capacity of 
this line prior to further work on the transportation case for Orpheus extensions, as the 
final outcome may affect not only scheme costs but service characteristics (tram type, 
speeds, frequencies, reliability and so on) and therefore passenger preferences. 
TABLE 
2.3 
POTENTIAL LEVEL OF RISK RELATING TO INTERFACES WITH 
NETWORK RAIL 

Route 
Network Rail Interface Risk 
 
Route 1 – Seaham to 
- - 
Capacity on Sunderland – Pelaw 
Sunderland 
– Seaham 
Route 2 – Sunderland to 
- - 
Capacity on Sunderland – Pelaw 
Doxford/Ryhope  
(if through running) 
Routes 5/6– Sunderland to 
 
 
Washington 
via S Hylton 
- - 
Capacity on Sunderland – Pelaw 
(if through running) 
via Southwick 
- - 
Capacity on Sunderland – Pelaw 
(if through running) 
Route 8 – Washington to 
N/a  
Gateshead/Heworth 
Route 9 – Team Valley to 
- - 
Current alignment utilises 
Gateshead 
Hexham - Newcastle line 
Route 12 – West Harton to 
Capacity on Sunderland – Pelaw 
Biddick Hall 
- - - 
(if through running). Introduces 
new conflicts at the south end of 
the alignment 
Route 19 - Gateshead to 
- - 
Current alignment utilises 
MetroCentre 
Hexham - Newcastle line 
Route 21 – West End 
 
 
St James to Walbottle 
N/a 
 
St James to MetroCentre 
N/a 
 
Route 23  
 
 
K’worth to 4 Lane Ends 
N/a 
 
C’lington to 4 Lane Ends 
Reduction of services to 

Cramlington could improve case 
for Orpheus extension 
Route 28 – Byker to 
Walkergate 
N/a  
Note: 
Scale runs between  --- (significant negative impact) through 0 (neutral) to +++ (significant positive impact) 
\\Douglas\Work\Projects\4800s\4884\Outputs\Working Notes\Phase 1B Sift Recommendations _ Final Report.doc 
 
10 

 
 
Future Potential Changes in Appraisal Guidance 
2.19 
Although the appraisal guidance changes announced with the publication of the 
Treasury Green Book have already been incorporated into the assessment presented in 
Working Note 3, further changes are likely.  
2.20 
Further possible changes are set out in the table overleaf. The inclusion of an 
assessment of distributional impacts may, if translated into guidance, go some way to 
countering the effects of the optimism bias factors – however the DfT’s position on 
this is not clear at the present time. 
TABLE 2.4 
CHANGES IN APPRAISAL GUIDANCE 
 Change 
Effect 
Source 
Status 
 
Negative for all 
Confirmed and 
Accounting for 
schemes at initial 
Treasury Green 
included in 
optimism bias 
stages of 
Book 
assessment 
development 
Confirmed and 
Discount rate 
Positive for all 
Treasury Green 
included in 
reduced 6% to 3.5% 
schemes5 
Book 
assessment 
Appraisal period 
Slight Positive for all 
Department for 
Not confirmed - but 
increased beyond 30 
schemes6 
Transport 
likely 
years 
Effect varying 
Precise application 
between schemes 
Equity considerations 
Treasury Green 
to transport projects 
and areas, could be 
in appraisal 
Book 
under consideration 
positive in North 
but not confirmed 
East 
Effect varying 
Economic Impact 
Promoter will still 
between schemes 
report (Establishes 
need to pass 
and areas, could be 
DfT 
regeneration 
established financial 
positive in North 
impacts) 
and economic tests 
East 
 
Potential Synergy between Orpheus Extensions and Other Policy Measures 
Under Consideration in Achieving Local Transport Plan Objectives 

Potential Impacts 
2.21 
Fiscal measures of road user charging have been assessed (reported in Working Note 
3) as having a very broad range of potential effects, with the magnitude of the impact 
likely to be dependent on the extent to which car travel is currently faster and cheaper 
than public transport travel (and thus more generally on the levels of traffic congestion 
in the area). 
                                                      
5  
Unless on-going revenue support is significant 
6  
But note that this may have negative implications in terms of the need to incorporate renewal costs 
\\Douglas\Work\Projects\4800s\4884\Outputs\Working Notes\Phase 1B Sift Recommendations _ Final Report.doc 
 
11 

 
 
2.22 
In areas of limited congestion, the effects of fiscal restraint could be less than a 10% 
increase in demand for a new public transport scheme. In areas of significant 
congestion, the effects could be greater, with levels of increase of up to around 50% 
being forecast in Edinburgh and in the south-east outside London. 
2.23 
It should be noted that with the exception of Route 21, an increase of 20% in the 
forecast level of benefits for all Orpheus routes does not significantly change the 
economic Cost:Benefit case for the routes, which remain poor. Furthermore, it is 
likely that the magnitude of change would be significantly lower for schemes outside 
Newcastle/Gateshead, given the significantly lower levels of traffic congestion that 
occur there and the forecast future year network conditions. 
Appraisal Issues 
2.24 
There is undoubted potential for synergy between Orpheus extensions and other 
potential Local Transport Plan policies. It is difficult to estimate with any certainty the 
magnitude of this effect at this stage, however. This is due principally to two reasons: 
i) 
The variety of potential policy measures, particularly those which aim to 
change the relative balance between the costs of car travel and that of public 
transport, their differing effects on the market for Orpheus (and on travel 
generally), and the currently-uncertain implementation routes which some 
measures may require; and 
ii) 
The importance of treating the policy measures within a holistic transport 
strategy package (and the lack at this stage of a firm plan by the Local 
Transport Plan partners to implement such measures in a committed do-
minimum scenario against which Orpheus extensions could be compared, 
compounded by the absence of a tool by which the potentially-supportive 
measures could be assessed in terms of an overall transport strategy for the 
Local Transport Plan area.) 
2.25 
Steer Davies Gleave has undertaken further work in attempting to examine the DfT’s 
potential viewpoint on this issue, as it relates particularly to recent evidence in other 
light rapid transit scheme submissions. The conclusions of this work indicate that: 
•  The submission of Annex E documentation in which the case depends upon a do-
minimum situation that is not yet committed in the LTP strategy (and that are in 
line with stated LTP objectives) is unprecedented to date. It is therefore crucial 
that this issue is explored with the DfT to establish their specific view on this 
relative to the Orpheus project; 
•  Another option would be where a do-something scenario is created that includes 
certain complementary measures as well as the Orpheus extensions. This 
approach has been accepted by the DfT in the past, although experience suggests 
that this is only acceptable if the measure is directly related to construction of the 
scheme itself (such as physically reducing roadspace along the corridors to be 
served by Light Rail, rather than any form of fiscal restraint). This would also be 
worthy of further exploration with the DfT. 
•  Regarding integration, the DfT have in the past accepted the reorganisation of the 
bus network as part of the appraisal of bus transit schemes, but this is not yet been 
done for a light rail scheme. There are examples, however, of LRT scheme 
\\Douglas\Work\Projects\4800s\4884\Outputs\Working Notes\Phase 1B Sift Recommendations _ Final Report.doc 
 
12 

 
 
appraisals where it has been an accepted assumption that there would be a 
reduction in frequency of competing bus services in the do-something case on the 
basis of an agreed view on what would constitute a reasonable competitive 
response. It is worth noting that for a scheme to qualify for funding it should not 
be reliant on bus operating cost savings to achieve the necessary economic 
performance, however. 
2.26 
Overall, it is suggested that it will be necessary to demonstrate commitment to the 
adopted measures, and to be able to demonstrate an understanding of the broader 
impacts of the approach. This will enable a coherent holistic package to be presented 
to the DfT in parallel with the Orpheus funding submissions. 
Metro Financial Performance 
2.27 
Confidence in the case for extensions to Metro would be enhanced by a more robust 
financial performance of the existing Metro system. Any programme of renewal is 
unlikely to be supported by DfT if it results in an increased operating subvention for 
Metro. Moreover, an enhanced operating performance (with increased revenue and/or 
reduced operating costs) prior to any enhancement/extension programme would be 
more than likely to make the case more robust. 
Indicative Timescales for Implementation of Wider Policy Measures 
2.28 
To inform development of a way forward for Phase 1B, depending on the response 
from DfT on the above issues, an assessment of the time period that might be required 
to develop the case for certain complementary measures has been undertaken. This 
assessment is based on an understanding of the statutory requirements of a promoter 
of such measures, and any evidence from schemes in preparation or implemented to 
date (notably London’s Congestion Charging scheme). 
Road User Charging options 
2.29 
The practicalities and timescales for implementing road user charging are uncertain 
given the lack of examples. However, our first assessment is as follows: 
•  Road user charging: this is likely to involve a period of three to five years from 
conception to implementation. 
•  Workplace charging: about three to four years. 
2.30 
It is worth noting that the net revenues from both types of charge of must go directly 
or indirectly to fund local authority transport policies. The likelihood of road user 
charging in particular being implemented in the near future in the UK will very much 
depend upon the perceived success of London's scheme, and this is too early to judge. 
Statutory Bus Quality Contracts 
2.31 
Quality contracts: exclusive rights to serve a corridor or area are granted to one 
operator. Quality of service is specified in terms of frequency, vehicles type and 
reliability. The Transport Act establishes what has to be done to implement a Quality 
Contract and the associated timetable: the timescales for implementation are likely to 
be at least three years, but as there are no quality contracts in operation in the UK at 
\\Douglas\Work\Projects\4800s\4884\Outputs\Working Notes\Phase 1B Sift Recommendations _ Final Report.doc 
 
13 

 
 
present, it remains unproven. Coventry is currently awaiting a decision from Secretary 
of State, due in September. If permission is granted then it is likely that there will be a 
delay to see how this works before any other contracts are approved. Nexus 
understood that Sunderland, as a designated Centre of Excellence, is currently 
exploring the possibility of using powers contained under a “Freedoms and 
Flexibilities" clause in the Local Govt Act 2000. It is possible that further 
developments in this area may occur in the future: however a funding submission to 
the DfT that was reliant on efficiency gains through this quality contracts, however, 
would need to demonstrate local partner commitment and the deliverability of this 
mechanism. 
\\Douglas\Work\Projects\4800s\4884\Outputs\Working Notes\Phase 1B Sift Recommendations _ Final Report.doc 
 
14 

 
 
3. RECOMMENDATIONS 
Summary 
3.1 
Overall, the analysis undertaken during Phase 1A and in the Phase 1B sifting process 
indicates that all routes will bring important benefits. However there are a number of 
very significant risks and opportunities in the development and submission of a 
funding application (Annex E) for the great majority the shortlisted 10 routes. At 
present, of the illustrative routes examined within the 10 corridors identified as being 
worth further analysis, one route (Route 21) appears to have the potential to present a 
positive economic case under the current appraisal guidelines and within the existing 
policy framework. It should also be noted that the development of the case for renewal 
of the Metro, a key part of the Orpheus concept, will in itself deliver significant 
benefits to all project stakeholders. 
3.2 
Overall, the levels of forecasting, appraisal and implementation risks and opportunities 
vary considerably between routes. Whilst all routes would perform better in 
conjunction with other complementary policy measures (albeit some better than 
others), many of these take time to implement and have high levels of risk, and the 
DfT will look for clarity from promoters as to means/timescales of implementation. 
These risks are summarised in the table overleaf. 
3.3 
This table also re-presents the estimated economic benefit to cost ratios for each 
extension option individually. This is done both with and without the additional 
allowance on costs required by DfT to allow for potential optimism bias. In the case 
where no optimism bias adjustment has been applied, the cost estimates represent the 
latest position set out in JacobsGibb, February 2003 report “A Consideration of 
Potential Cost Variances on Shortlisted 1B Routes”. 
3.4 
An alternative case for Route 6 is also presented here, assuming that the structures 
cost for the new Wear crossing that is required for this route can be reduced through 
advance passive provision within a new structure currently planned by Sunderland 
City Council independently of the Orpheus scheme. It should be noted that 
JacobsGibb originally estimated a cost for this structure at £3m. 
 
\\Douglas\Work\Projects\4800s\4884\Outputs\Working Notes\Phase 1B Sift Recommendations _ Final Report.doc 
 
15 

 
 
TABLE 3.1 
POTENTIAL LEVEL OF RISK AND OPPORTUNITY RELATING TO INTERFACES WITH THIRD PARTIES 
Change 
Change 
Level of Risk and Opportunity through 
to 
to 
Demand/ 
Route BCR 
Benefits 
BCR 
Benefits 
benefit 
Supporting 
Cost 
Implement
Network 
at which 
at which 
Charging 
Overall 
Estimate 
Estimates 
-ability 
Integration 
NPV = 0 
NPV = 0 
Policies 
Inputs 
 
No adjustment to costs to 
Costs adjusted in line with 
reflect Green Book 
 
 
 
 
 
 
Green Book guidelines 
guidelines 
Route 1 – Seaham to Sunderland 
1.0:1 
1% 
0.7:1 
37% 
0 / -- 
- - 
- - 


- - 
Route 2 – Sunderland to 
0.8:1 
19% 
0.6:1 
60% 
+ / -- 
- - 
- - 


- - 
Doxford/Ryhope  
Routes 5/6– Sunderland to 
 
 
 
 
 
 
 
 
 
 
Washington 
via S Hylton 
0.5:1 112% 0.3:1 208% + 

-  - 
-  - 





via 
Southwick 
0.3:1 208% 0.2:1 352% + 

-  - 
-  - 





via Southwick (excluding cost of Wear 
0.4:1 190% 0.2:1 342% + 

-  - 
-  - 





Bridge) 
Route 8 – Washington to 
0.5:1 105% 0.3:1 210% ++ 

-  - 

0  ++  + 

Gateshead/Heworth 
Route 9 – Team Valley to Gateshead 
0.5:1 106% 0.4:1 170% + 

-  - 
-  - 
-  ++  + 

Route 12 – West Harton to Biddick 
0.6:1 
59% 
0.5:1 
105% 
0 / - 
- - 
- - - 


- - 
Hall 
Route 19 - Gateshead to MetroCentre 
0.6:1 59% 0.5:1 113% + 

-  - 
-  ++  +  0 
Route 21 – West End 
     


    
St James to Walbottle 
1.3:1 
N/a 
0.9:1 
9% 
++ / -- 
- - 

++ 


St James to MetroCentre 
1.2:1 
N/a 
0.9:1 
12% 
++ / -- 
- - 

++ 


Route 23  
 
 
 
 
 
 
 
 
 
 
K’worth to 4 Lane Ends 
0.8:1 
28% 
0.5:1 
92% 
+ / - 


++ 


C’lington to 4 Lane Ends 
0.7:1 
51% 
0.4:1 
123% 
+ / - 


++ 


Route 28 – Byker to Walkergate 
0.7:1 
41% 
0.5:1 
116% 
+ / - 
- - 

++ 


Note: 
Scale runs between  --- (significant negative impact) through 0 (neutral) to +++ (significant positive impact) 
\\Douglas\Work\Projects\4800s\4884\Outputs\Working Notes\Phase 1B Sift Recommendations _ Final Report.doc 
 
16 

 
 
3.5 
In view of these conclusions, it is suggested that there are two main options for Phase 
1B of Project Orpheus, as follows: 
i) 
Submission of funding applications during Phase 1B should be staged, with 
routes that appear to have the potential to be justified without complementary 
policy change, and which are unlikely to face serious unresolved 
interface/implementation risks, are developed first. Funding applications in 
Autumn 2003 would then constitute the first phase of a longer-term 
implementation plan. These areas of risk would be assessed in more detail in 
parallel with this exercise and the development of the funding case for 
remaining routes being progressed later during 2003 and into 2004 as parallel 
workstream timescales dictate; or 
ii) 
The overall Phase 1B stage is extended considerably to encompass the 
development of a holistic transport and demand management strategy, to be 
enshrined within the forthcoming Local Transport Plan 2006-11 and 
containing a wider assessment of the potential contribution of Orpheus 
extensions within the overall local and regional plans for transport in the 
region. 
3.6 
The second approach would have the advantage of considering the Orpheus project in 
parallel with other LTP schemes, but would introduce a major delay in project 
development that may be unacceptable. 
3.7 
On the basis of the first option, therefore, it is suggested here that Route 21 should be 
taken forward to an Annex E submission during 2003 (with both the two identified 
western variants and with Route 28 as an eastern variant), as originally envisaged, 
subject to a valid case being developed during the remainder of 2003. The case for 
route 23 appears the most likely to be assisted by complementary planning measures, 
and there may therefore be some merit in considering these within a more holistic 
assessment when the precise nature of these measures is understood and has local and 
regional acceptance. However further work on investigation of alternative alignments 
for this route may also improve the position of this route and it is recommended that 
work on this route therefore continues in parallel with that for Route 21, with a 
decision being taken on whether to proceed with an Annex E submission in 2003 as 
the case develops. For both of these options, the work programme will include the 
development of a lower cost alternative as a comparator. 
3.8 
Amongst the other routes, Routes 1, 2 & 12 in Sunderland/South Tyneside/Durham 
show the potential to generate useful levels of benefits, but these routes are subject to 
considerable implementation risks, largely dependent on an interface with Network 
Rail that in the current policy framework may not be feasible in the short term, and 
also are likely to benefit less than routes in more congested areas from parallel policy 
measures to increase the relative costs of car travel. Routes 9 & 19 could also merit 
further examination, but are also considered to be at risk from the interface with 
Network Rail (and potentially also from serious cost risks, especially the tunnel 
section).  
3.9 
It is therefore proposed that in view of the high level of risk to Nexus and partners in 
further developing the case for these extensions at this stage routes 1, 2, 9, 12 and 19 
\\Douglas\Work\Projects\4800s\4884\Outputs\Working Notes\Phase 1B Sift Recommendations _ Final Report.doc 
 
17 

 
 
should form part of a later stage of the Orpheus project. This phase would also 
encompass the process of choosing and developing complementary measures by the 
Local Transport Plan partners, on the basis of their contribution to the objectives of 
the 2006 – 11 Tyne & Wear Local Transport Plan.  
3.10 
It does not appear likely that a satisfactory case for routes 5, 6 & 8 is foreseeable 
within the current timescales, even with supportive policy measures, and it is therefore 
recommended that alternative solutions are sought to the transport problems for areas 
served by these routes. A final view on Route 8 if treated as an extension of Route 9 
through Team Valley as requested by Gateshead, would then form part of the 
development of the case for Route 9 if the first assessment of this option appears 
favourable. 
3.11 
An indicative programme for the two-stage approach is set out in the table. 
TABLE 3.2 
INDICATIVE PHASING FOR STAGED ORPHEUS ROUTE DEVELOPMENT 
OPTION 

Year 2003 
2004 
2005 
2006 
Quarter 
Q2 Q3  Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4  Q1  Q2 Q3  Q4 
Original Orpheus 
Phase 1B 
Phase 2 
Phase 3 
Phasing 
Orpheus Stage 1 
Development case for 
Routes 21, 23 and 
Develop Annex E 
OBC 
Potential Procurement 
TWA Process 
potential variants 
Submission 
Submission
Start 
(including lower cost 
alternatives) 
 
 
Explore policy 
 
Implement  
Development of Local 
framework 
 
Strategies 
Transport Plan Strategy 
changes, 
 
Complementary 
Summer  
Define  
Measures 
2003 APR 
Strategies 
 
Assessment of 
Explore capacity 
Implementation risks 
utilisation and Third 
and capacity issues on 
Party Interface Risks 
Network rail routes 
and Opportunities 
 
 
 
Orpheus Stage 2 – 
 
Preparatory works on 
Develop  
Potential development 
Funding Case for  
Annex E 
of Funding Case for 
Routes 1, 2, 9 & 19 
Submission(s) 
TWA Process commences 
Routes 1, 2, 9, & 19  
and OBC 
 
\\Douglas\Work\Projects\4800s\4884\Outputs\Working Notes\Phase 1B Sift Recommendations _ Final Report.doc 
 
18 

 
 
Asset Renewal Issues 
3.12 
During the early development of routes in the first stage of Phase 1B during 2003, it 
will be crucial that the technical development of the asset replacement strategy for 
Metro considers impacts on the potential second stage routes in order that the impacts 
of any technology decisions on future extensions are fully understood and accepted. 
Recommended Short-term Phase 1B Actions 
3.13 
Some early recommended actions for the Orpheus Team arising have been identified 
as follows: 
•  Continued development of potential do-minimum scenarios for the existing Metro 
system including consideration of a range of renewal options; 
•  Early discussions with DfT regarding the do-minimum scenarios and local 
stakeholders’ proposals for the development of supporting policy measures and 
potential interaction with the eventual Local Transport Plan strategy and the case 
for Orpheus extensions (including feeder options which may improve the 
financial performance of the existing Metro system); 
•  Travel demand data collection to be carried out in corridors serving routes 9, 19, 
21, 23 and 28 and in March 2003 (according to timescale and resource 
constraints), to be followed by additional data collection for 1 & 2 in late 
April/May; 
•  Establishment of a forum for considering the options for future utilisation of 
capacity on the Sunderland – Pelaw and Newcastle – MetroCentre heavy rail 
routes, and potential levels of interface risks; 
•  Establishment of a working group to establish guidelines and principles for the 
detailed development of route alignments and specifications, urban design prior 
to further detailed technical or transport planning feasibility work on individual 
corridors – this should include conclusions on the potential costs and benefits of 
low-floor LRV operation in the central Newcastle tunnels and in Sunderland; 
•  Finally, establishment of route-specific working groups to develop the alignment 
and service proposals in conjunction with study partners. 
 
\\Douglas\Work\Projects\4800s\4884\Outputs\Working Notes\Phase 1B Sift Recommendations _ Final Report.doc 
 
19 

 
 
 
CONTROL SHEET 
 
 
Project/Proposal Name: 
Project Orpheus 
 
 
Document Title: 
PROJECT ORPHEUS PHASE 1B SIFT 
RECOMMENDATIONS 
 
 
Client Contract/Project Number: 
 
 
 
 
 
 
 
Document Number: 
See footer 
 
 
Originator: Luke 
Miller 
 
 
Other Contributors: 
Nick Joyce / Peter Gross / Jim Woffenden / Neil Chadwick 
 
 
 
Review By: 
Print: 
Tim Ryder 
 
 
 
 Sign: 
Approved 
remotely 
 
ISSUE HISTORY 
 
Issue No. 
Date 
Details 
1  
19 / 02 / 03 
First Preliminary Draft 

27 / 02 / 03 
Second Internal Draft 

06 / 03 / 03 
Final 
 
DISTRIBUTION 
 
Clients: 
Nexus internal 
 
 
Study Team 
Ernst & Young, Steer Davies Gleave, 
JacobsGibb 
 
\\Douglas\Work\Projects\4800s\4884\Outputs\Working Notes\Phase 1B Sift Recommendations _ Final Report.doc 
 
Control Sheet