This is an HTML version of an attachment to the Freedom of Information request 'Carnegie Leisure Centre - planned refurbishment information?'.

THE FUTURE OF LEISURE PROVISION IN FIFE

FIFE COUNCIL


0x08 graphic

A

REPORT

BY

PMP

NOVEMBER 2005


CONTENTS

APPENDICES

Appendix A An analysis of the User and Non User Survey (August 2005)

Appendix B Performance analysis of existing facilities

Appendix C Sport and Leisure Potential Report

Appendix D Detailed Business Plans

SECTION 1

INTRODUCTION AND BACKGROUND


Introduction and Background

Context

  1. Leisure in Fife is well developed and already makes a valuable contribution to life in Fife and in particular is critical to achieving many of the aspirations in the Community Plan.

  2. Prior to local government reorganisation in 1996, Fife was divided into three District Councils and a Regional Council, each delivering a range of leisure and recreational services. Since then, Fife Council (the Council) has been operating all of the leisure facilities in-house through Community Services and now, for a number of reasons, is as an opportune time to examine whether the existing provision meets the needs of 21st Century consumers.

Ailing Facilities

  1. The Council is facing many challenges for the future delivery of its sport and leisure services, in particular, an ageing facility stock.

  2. In June 2000, sportscotland published the `Ticking Time Bomb', a report detailing the state of the country's swimming pool provision. The report identified that an investment of around £540m would be required for the maintenance, upgrading and refurbishment of public swimming pools in Scotland by 2020. It highlighted that in Fife alone a £31m investment would be required for swimming pool upgrades and refurbishment. These findings were factored into the report to the Adult Services Committee in June 2004 that highlighted the need for an estimated £60m investment in its wider sport & leisure facility infrastructure within the same timeframe.

  3. The existing sport and leisure portfolio therefore requires a significant level of investment to not only maintain its existing condition, but also enable the Council to offer high quality & appropriate provision for its communities both now and in the future.

The `Future of Leisure' Working Group

  1. In order to begin to address these issues, a cross-party Member and Officer Working Group was established by the Adult Services Committee in June 2004. The Future of Leisure Working Group (FOLWG) was given the remit to examine these issues and challenges and explore the options for future delivery. In addition, the group's work also forms a key part of the `Collective Challenge' currently exercising the Council, the process of budget review for 2005/06 - 2007/08.

  2. The work of this group and the detail of this report is also critical in ensuring that the Council meets `best value' in terms of exploring future delivery and continues the movement to a commitment to modernisation with regards to employment conditions, including Single Status/Modern Employment. The focus of the group has been those sports centres, swimming pools, golf courses & theatres where the investment needs are greatest and that might lend themselves best to alternative forms of management or delivery.

  3. A key task of the FOLWG is to consider the options available to develop a strategy for future investment in Community Services. In order to achieve this, the group has to critically challenge the following:

  1. The initial findings of the FOLWG to date were as follows:

  1. The FOLWG's Interim Report was published in April 2005 and recommended that the Council enlist the help of external consultants to produce an independent & thorough report to advise on facility development options, funding and management, review the key findings to date and set out an objective action plan for the way forward.

Study Objectives

  1. Following on from this recommendation, the Council appointed PMP & Donaldson's in June 2005 to explore options and solutions for the future delivery of leisure in Fife.

  2. The consultants were requested to focus their work on sports centres and swimming pools and in particular the three facilities that require immediate investment:

The Report

  1. This report presents the findings and the key conclusions from the following areas of work undertaken:


SECTION 2

STRATEGIC CONTEXT


Strategic Context

Introduction

  1. This section focuses upon a range of key strategic documents that impact upon the provision and delivery of sport and leisure services in Fife. They range from government strategy aligned with developing a healthier nation and development of a sporting and leisure infrastructure to local policy and agendas for the delivery of sport and leisure services alongside to the Community Planning framework.

  2. We have set out the implications of this strategic context against the future of leisure in Fife, what impact it may have and how it will, in turn, determine future delivery options.

National Context

  1. There are a number of key strategic documents, which set the context for sport within Scotland. A selection of these are summarised below and the implications for sport and leisure provision in Fife are detailed.

Let's Make Scotland More Active: A Strategy for Physical Activity

  1. The Scottish Executive produced the strategy for physical activity in 2003 with a goal to “increase and maintain the proportion of physically active people in Scotland”. Specifically, the strategy looks to ensure that 50% of adults over 16 and 80% of children under 16 are taking part in the recommended levels of physical activity by 2020. To achieve this aim, Scottish Executive pledges to:

  1. The targets and objectives of the strategy are to be reviewed every five years.

What does this mean for Fife?

  1. The implications for Fife as a local authority are the need to deliver a physical activity strategy at a local level in order to contribute towards a more active Fife & Scotland. Community Services clearly has an important role to play in terms of delivering the types of programmes, facilities and opportunities that work towards achieving these objectives.

Sport 21 (2003)

  1. This document - the national sports strategy - was originally produced in 1998, but was revised again in 2003, largely in response to the Physical Activity Strategy, and as a means of reinforcing its contribution to supporting more active lifestyles.

  2. The key objectives of Sport 21 for Scotland are:

  1. The strategy states an ambition to have 60% of adults participating in sport at least once a week by 2020. The following key targets were set to ensure this goal is achieved:

What does this mean for Fife?

  1. A key aim of Sport 21 is to increase participation in sport and leisure activities and the strategy presents a framework for local authorities to deliver its objectives. Whilst the targets are extremely challenging (soon to be reviewed), if Fife is to contribute to these, it is fundamental that the Council has the appropriate facilities, programmes and resources in place to deliver.

National and Regional Sports Facilities Strategy

  1. The National and Regional Sports Facilities Strategy for Scotland, produced by the Scottish Executive in partnership with sportscotland, outlines an ambitious plan to develop the national and regional sporting facilities within Scotland to ensure the future success of sporting generations.

  2. The strategy identifies that current facilities are particularly limiting and are in need of significant refurbishment if the aspirations of Sport 21 are to be realised.

  3. The aim of the strategy is to ensure the delivery of a network of multi-sports facilities across the areas covered by the Area Institutes In Scotland (Central, East of Scotland, Grampian, Highland, Tayside and Fife and the West of Scotland). The strategy identifies the national facility requirements as:

  1. The funding of these facilities will vary between regions, however it is anticipated that 30-40% of the cost of each project will be financed from central resources.

What does this mean Fife?

  1. Whilst Fife expressed an initial interest in an application for a regional centre possibly located at FIPRE, the scale and mix of facilities required and the funding implications for the Council meant that this was taken no further at that particular time. However, there could be some merit in revisiting this project again with sportscotland as it could potentially open up access to funding in the longer term.

0x08 graphic
Local Context

  1. Strategic documents and plans specifically for sport & physical recreation within Fife are reviewed & summarised below. This provides a context for this study and outlines the local sporting agenda.

Fife's Community Plan (2004)

  1. The Fife Community Plan, written in 2000 and revised in 2004, was developed by the Fife Partnership. The plan identifies and reviews the progress that has been made since the previous plan and sets out further challenges and objectives for the future.

  2. The Community Plan highlights the ambition to ensure that Fife is made up of strong, attractive, vibrant and thriving communities, with a high quality of life for its residents. The delivery of high quality leisure and cultural services is identified as crucial to the realisation of this objective.

Investment in Facilities

  1. Although, historically, a significant investment has been made in facilities & services to encourage people to lead more physically active lifestyles, the plan recognises that a substantial effort is still required to address the inequalities in health and well being in Fife. Maintaining the investment in, and maintenance of, Fife's extensive network of community facilities to ensure they reflect changing trends and demands is a key challenge for the Council over the next few years.

  2. In particular, facilities such as sports centres and swimming pools are central to the Council's drive to improve quality of life, secure cultural vitality and enable access to opportunities for Fife residents. The Council will work with a range of partners to make certain that the quality and quantity of these facilities is sufficient to meet the needs and future demands of the communities.

  3. The plan also highlights the importance of having an even balance between public, private and voluntary sector contributions to local leisure provision, and the role of the Council was seen as a pivotal one in ensuring this happens.

Community Services Service Improvement Plan (April 2005)

  1. The Community Services Service Improvement Plan, produced by Fife Council in April 2005, sets out the key targets and objectives for the period 2005-08. The plan is focused around the Community Services' statement of purpose:

“Community Services provides a broad range of cultural, learning, recreational, sporting and social opportunities in communities throughout Fife by opening doors for everyone to engage in learning, leisure and cultural activities. Our approach is positive, enlightened and inclusive. We aim to enhance health and well-being by encouraging communities to use and influence the shape of our services”.

  1. The plan identifies the following service objectives and results for improving health and well being in Fife:

  1. The plan also outlines the financial resources available to Community Services in the year 2005-06. The salient points are as follows:

Fife Sport and Active Recreation Strategy (2005)

  1. The recently revised Fife Sport & Active Recreational Strategy identifies the key aspirations of the Council for the development of sport and active recreation within the region.

  2. The strategy identifies that the key strategic aims of Fife Council are to:

Facilities

  1. The strategy acknowledges that Fife has a large number of existing sports facilities, many of which are in need of significant capital investment for replacement or refurbishment.

  2. With the Council financially unequipped to cope with such a heavy investment, the strategy suggests that the private sector should be encouraged to have a greater involvement in the provision of sport and leisure facilities and services in Fife. This increased involvement could take the form of the development of commercial leisure and also the delivery/operation of more community facilities through Public Private Partnership contracts, etc.

  3. In relation to the provision of sport and leisure facilities in Fife, the strategy identifies the Council's objectives, including:

Services

  1. With regards to the service offered to residents, the Council will ensure that:

  1. Other key targets identified within the strategy which are of particular relevance to this project include to:

A Healthier Future for Fife - Joint Health Improvement Plan

  1. Fife's first Joint Health Improvement Plan (JHIP) forms part of a national strategy to make a step change in Scotland's health, which is laid out in `Improving Health In Scotland - The Challenge 2003'. The plan sets out the targets for the next three years, and is the first step in an on-going process to improve health and wellbeing in Fife.

  2. The long term objectives for improving the health and wellbeing of the people in Fife are laid out in the `Improving Health and Wellbeing' theme of the Community Plan, and are as follows:

  1. The JHIP takes forward the aims of the `Improving Health and Wellbeing' theme of the Community Plan and ensures that improving health receives commitment and impetus amongst all the community-planning partners.

  2. The Plan is divided into the following sections:

User and Non-User Survey (August 2005)

  1. A user and non-user survey was completed by TL Dempster in August 2005. The objective of this survey was to:

  1. A detailed analysis of the results is included in Appendix A, and the key findings in relation to future provision of facilities in Fife are highlighted below:

  1. Updating equipment.

  2. Updating physical facilities.

  3. Fulfilling service promises to users.


Consultation

  1. A series of workshops were held with facility managers, senior management teams and the FOLWG to provide further context regarding both the constraints and opportunities of the facilities in terms of their operation, management, facility mix and condition. The sessions also provided an opportunity to explore the future strategic options for the delivery of leisure in Fife and test a number of pilot scenarios.

  2. Outlined below is a summary of the key findings from these sessions which have helped to establish benchmarks for the facilities alongside options for future delivery:

Facilities

Service

Future Delivery

  1. With regards to the future provision of facilities & services in Fife the following points were raised:

0x08 graphic


SECTION 3

EXISTING PROVISION


Existing Provision

Fife District Council Leisure Provision

  1. Fife Council, through Community Services, currently provide eight sport and leisure centres, three stand-alone swimming pools and one stand-alone sports hall.

  2. Figure 3.1 below illustrates the spread of the population in Fife against the existing facility locations. Those areas identified in red are the most densely populated and include the main urban areas of Dunfermline, Glenrothes, Kirkcaldy and St Andrews. The map also indicates that in terms of geographical spread of facilities across the region, the Council's existing facilities are well distributed across Fife, generally corresponding with the major centres of population.

0x08 graphic
0x08 graphic
0x08 graphic
Figure 3.1 Existing Council facilities and population density

Existing Facilities

  1. A review of the existing facilities was undertaken to develop an understanding of the `where are we now?' in terms of benchmarking the existing service and provision. In terms of addressing this question we have looked at each facility in the context of two key areas:

Fife Institute of Physical and Recreational Education

  1. FIPRE was opened in 1970 and provides a mix of both indoor and outdoor facilities. It is heavily oriented towards education and overcoming health inequalities.

  2. FIPRE has an established regional and national reputation around specific areas of its programme, in particular, it's teaching and coaching of physical activity alongside their utilisation in promoting social inclusion, notably disability sport at all levels.

  3. The facilities provided at the centre include:


Carnegie Leisure Centre

  1. Located in Dunfermline, the Carnegie Leisure Centre opened in 1905 as a Victorian swimming baths/gymnasium. The original building is now B listed and has been expanded and modernised over the last 15 years and provides a comprehensive sport and leisure facility in a town centre location.

  2. However, whilst the expansion of the centre has helped to meet a growing demand, the restrictions of the site and the extensions have somewhat compromised the facility and its functioning. This has in turn led to operational difficulties and high maintenance costs.

  3. The Centre provides a range of facilities including:



  1. The Inspiration Fitness Suite/Cardiozone will undergo a refurbishment in December 2005 which will include the fitting of new carpet tiles, redecoration of walls and skirting, replacement of ceiling tiles and the installation of a new split system air conditioning unit. In addition, essential plant maintenance will also be completed in the swimming pool and health suite during the Christmas period.

Beacon Leisure Centre

  1. Located in Burntisland, the Beacon Leisure Centre is one of Fife's relatively newer facilities having been opened in 1997. The main pool in the centre has recently undergone refurbishment, which was completed earlier in 2005.

  2. The facilities include:

Cowdenbeath Leisure Centre

  1. Located in the centre of Cowdenbeath, the Cowdenbeath Leisure Centre was built in two different phases. The first was completed when the centre opened in 1987 and the second phase was finished eight years later. The centre is due to be closed for minor refurbishment at the end of 2005.

  2. The centre has extensive wet/dry and outdoor provision including:



  1. It is intended that the Fitness Suite will be closed during December 2005, in order to complete some essential refurbishment.

Cupar Leisure Centre

  1. Located in central Fife, Cupar Sports Centre offers a range of wet and dry indoor facilities. The pool was opened in 1978 with the dry-side completed in 1987.

  2. The facilities at provided at Cupar include:

East Sands Leisure Centre

  1. Sitting on the North East coastline of Fife in St. Andrews, East Sands Leisure Centre offers a range of different sporting and leisure facilities. The centre was originally opened in 1988.

  2. East Sands includes the following facilities:



Waterstone Crook Leisure Centre

  1. Situated in the north of Fife in Newport on Tay, the “Crook” as it is known locally is now 30 years old having been opened in 1975. Providing facilities for a wide selection of both indoor and outdoor activities, the centre is still a very popular venue with its users.

  2. Waterstone Crook includes the following facilities:



Dalgety Bay Sport & Leisure Centre

  1. Positioned on the South Coast of Fife in Dalgety Bay, one of Scotland's newest communities, Dalgety Bay is one of Fife's highest profile leisure centres. The Centre was opened in 1994 and was delivered by Tay Homes (Scotland) through a Section 50 Agreement.

  2. The facilities provided at Dalgety Bay include:

Levenmouth Swimming Pool

  1. Opened in 1990 in Leven, Levenmouth Swimming Pool offers a plethora of leisure water facilities as well as capacity for numerous dry-side activities.

  2. The facilities provided include:

Bowhill Pool

  1. Bowhill Pool is a relatively small facility, which opened in 1969 as just a swimming pool. In 1998 the centre was refurbished with funds from sportscotland and Fife Council and now includes a fitness suite and health suite facilities.

  2. The facilities at the pool include:

Kirkcaldy Swimming Pool

  1. Kirkcaldy Pool, positioned on the seafront at Kirkcaldy, was opened in 1971 with swimming and health suite facilities. In 1984 the facility was redeveloped and a fitness suite added.

  2. The centre includes the following facilities:

Bruce Street Sports Centre

  1. Located in Dunfermline, the Bruce Street Sports Centre plays host to a number of major badminton tournaments throughout the year. The centre was opened in 1979.

  2. Facilities include a four badminton court sports hall and a meeting room.

How are the existing facilities performing?

  1. Outlined below is an overview of how the Council's existing facilities are performing with regards to:

  1. This analysis is based on financial information for 2004-05 provided by the Council. This includes an assessment of the performance indicators for operational performance against a number of benchmarks structured to give an indication of how the facilities is performing in comparison with other leisure centres in the UK.

  2. The results of the performance indicator calculations and the financial performance of the existing facilities are included in Appendix B.

Usage

  1. The throughput figures for all facilities are illustrated in Table 3.1 overleaf:

0x08 graphic
Table 3.1 Throughput figures for all existing facilities

  1. Using the Performance Indicator (PI) analysis, contained in Appendix B, based on similar facilities e.g. wet with outdoor or wet only, the scores for `annual visits per square metre' highlights that:

  1. However, account must be taken of the demographics and population base in Fife as well as an allowance for the rural/urban mix and respective population densities. Whilst throughputs for the size of facilities are relatively low, consultation has indicated that levels of participants in a number programme areas are often restricted by the configuration and size of existing facilities.

  2. A more accurate measure of this can be calculated using the total size, in square metres, of the facility. Unfortunately, this was not possible as only the size of the footprint of the building was available for each facility.

Income

  1. In 2004-05, the Council generated an income of c. £4.3 million through their leisure portfolio. The income by facility is broken down in Table 3.2 overleaf.

0x08 graphic
Table 3.2 Total income by facility

* The figure for Beacon Leisure Centre is considered an anomaly due to a large amount of `contributions non-local' (£1.1m) included in their income calculations.

  1. The table above illustrates that five facilities are generating significantly more income than the other facilities. These include Carnegie LC, FIPRE, Cowdenbeath LC Dalgety Bay and Levenmouth swimming pool.

  2. The three worst performing facilities include Bruce Street Hall, Waterstone Crook and Bowhill Pool, all of which generate less than £60,000 income per annum.

  3. An examination of income against key PI's are highlighted in tables 3.3, 3.4 and 3.5. overleaf.

  4. From the tables below, the PI analysis illustrates that:

  1. Comparing the financial performance indicators to earlier commentary from Council staff and Members supports the theory that the existing service is being constrained by the buildings in which it operates.


0x08 graphic
Table 3.3 Total income per visit

0x08 graphic
Table 3.4 Secondary Income per visit

Table 3.5 Income Per Health and Fitness Station

0x08 graphic


Expenditure

  1. In 2004-05, a total of c. £14.3 million was expended on the existing Council leisure facilities. This is an extremely high level of expenditure and when compared against income results in a net operating cost of c. £10m for the Council's existing facilities.

  2. The level of expenditure by facility is broken down in Table 3.6 below.

0x08 graphic
Table 3.6 2004-05 expenditure by facility

  1. The table above illustrates that:

  1. An examination of expenditure against key PI's are highlighted in tables 3.7, 3.8 and 3.9. overleaf.

  2. These tables highlight that:


0x08 graphic
Table 3. 7 Energy costs

0x08 graphic
Table 3. 8 Staff Costs as a % of income

0x08 graphic
Table 3.9 Subsidy per visit


Carnegie, FIPRE and Kirkcaldy

  1. Table 3.10 below summarises the performance of the three key Council facilities. This is based on the performance indicators calculated in Appendix B.

  2. PI

    Performance

    Carnegie LC

    FIPRE

    Kirkcaldy

    Annual visits per m2

    25 - 50%

    50%

    25%

    Subsidy per visit

    25%

    25%

    25%

    Subsidy per opening hour

    25%

    25%

    25%

    Total Income per visit

    50-75%

    25-50%

    25-50%

    Secondary income per visit

    25%

    25%

    25%

    Income per health and fitness station

    Low

    Low

    Low

    Staff costs as % of income

    High

    High

    High

    % of costs on marketing and research

    25%

    25%

    25%

    Energy costs per m2

    25-50%

    25-50%

    25%

    1. This illustrates that overall;

    • these facilities are performing in the lower quartile

    • costs associated with these facilities are extremely high

    • there are high levels of subsidy per visit across the centres, with subsidies in excess of £5 per visit at FIPRE, East Sands, Waterstone Crook, Levenmouth, Bowhill and Kirkcaldy.

    0x08 graphic

    Investment Required

    1. Over the last five years, the Council have completed a number of investigations into the level of investment required to maintain and develop the leisure portfolio in Fife. A range of reports have incorporated condition surveys and feasibility studies at different levels that clearly indicate that a significant level of investment is required in the short term if the Council is to continue maintaining and delivering the existing level of facility provision.

    2. Outlined below are the details of recent reports, which highlight both the extent & magnitude of the challenge facing the Council.

    Previous Condition Reports and Feasibilities

    1. In addition to the `Ticking Time Bomb' report identified in section one, Kit Campbell Associates (2001), Ove Arup (2003) and JQA (2004) reports have all confirmed that major investment in existing facilities is required.

    Kirkcaldy Pool Report (2001)

    1. In November 2001, Kit Campbell Associates was commissioned on behalf of the Council to complete a review of the leisure facilities in the Glenrothes and Kirkcaldy area.

    2. The report indicated that a significant capital investment of between £1.8m and £2.4m would be required to retain Kirkcaldy pool in operation and a total investment of £6m would be required if the facility were to be completely replaced.

    3. The report emphasised the following key points:

    • There is sufficient demand for a pool in Kirkcaldy.

    • Enhanced health and fitness facilities could increase income, relieving revenue pressures.

    • Consideration should be given to a competition pool in central Fife.

    • A possible amalgamation of the FIPRE and Kirkcaldy Pool is an option to be contemplated.

    • A condition survey of FIPRE is required.

    1. The report recommended two scenario's dependant upon the future of the FIPRE:

    • If the Council were minded to keep the Institute in its current form, the replacement of Kirkcaldy Pool with a 25m pool at Kirkcaldy High School with increased heath and fitness provision was the recommended option.

    • If the condition surveys revealed that the Fife FIPRE needed replacing, then it was suggested that a sports complex combining both Kirkcaldy Pool and the FIPRE should be built.

    1. The options were not taken further at the time and the key issues highlighted remain pertinent today.

    Arup (2003)

    1. The survey work specifically focused on the condition of the swimming pool tanks and associated plant at nine of the Council's existing facilities. Arup categorised the works required in relation to immediate repairs required, and the level of expenditure likely to be required within a five and ten year timescale.

    2. Table 3.6 below illustrates the level of investment required (in 2003) in the Council's existing facilities. This estimated that over £11.6m investment in maintenance and upgrading would be required over the next ten years across nine centres to keep the facilities open and maintain acceptable standards of delivery. This figure did not specifically allow for significant levels of capital investment expenditure.

    Table 3.6 The level of investment required in 2003

    Maintenance and/or upgrade

    Carnegie LC

    FIPRE

    Cowden-beath

    Cupar LC

    Beacon LC

    Bowhill SP

    Kirkcaldy SP

    Leven-mouth

    St. Andrews

    5 years

    £4.2m

    £4.7m

    £48k (pool)

    £130k (pool)

    £34k (pool)

    £155k

    £90k

    £77k (pool)

    £11k (pool)

    10 years

    £750k

    £800k

    £77k

    £64k

    -

    £120k

    £380k

    £2k

    £41k

    Total

    £4.95m

    £5.5m

    £125k

    £194k

    £34k

    £275k

    £470k

    £79k

    £52k

    1. The condition surveys included assessment of the pool plant, tanks and ventilation systems. They also identified significant levels of investment (£7.8m) for additional building works required at Carnegie Leisure Centre and FIPRE, most of which would be required in the subsequent five years.

    Future Of Leisure Working Group (2004-05)

    1. The FOLWG updated previous figures to all for inflation and estimated the level of investment required into the Council's sport and leisure portfolio is c. £48m, which includes immediate investment, refurbishment and replacement. The estimated level of investment required is set out in Table 3.7 below:

    Table 3.7 Level of Investment Required

    Facility

    Cost (£m)

    FIPRE (short/medium term)

    6

    Carnegie Leisure Centre (short/medium term)

    5

    Kirkcaldy Swimming Pool

    8

    Swimming Pool Plant (including CUS's)

    6

    Sports Centres and Swimming pools

    20

    Major items of equipment

    3.0

    Total

    48

    1. Replacement costs for FIPRE and Carnegie were also presented in this report estimated at c. £40m. Given their position as flagship facilities for the Council, investment in these centres is considered to be a top priority.

    2. However, the replacement costs identified are based on like-for-like facilities, and are considered to be generous. There is a clear opportunity to provide a more focused facility mix, and reduce the projected costs. For example, a new facility incorporating a 25m pool, learner pool, 4-court sports hall and 50-station fitness suite have been delivered for c. £7m.

    Summary of headline costs & key considerations for Kirkcaldy, Carnegie and FIPRE

    1. Following on from the findings of previous reports, this study focuses primarily upon the immediate investment requirements at the Council's three main leisure assets, Kirkcaldy Swimming Pool, FIPRE and Carnegie Leisure Centre. Table 3.8 overleaf provides a summary of the estimated headline costs based on existing data and key considerations for these three facilities.

    2. The figures provided are based on the Ove Arup condition survey of swimming pools referred to earlier. Whilst the information is somewhat historic it is useful in that it provides a base point for the likely levels of investment that are required in the facilities. We are not aware that these figures have subsequently been updated, although it is recognised that these figures will have increased due to further deterioration of the building fabric and cost inflation. We understand that the Council is seeking to prioritise further survey work in early 2006.

    0x08 graphic


    Table 3.8 Headline costs and key considerations for Kirkcaldy, FIPRE and Carnegie

    Facility

    Immediate repairs

    Upgrade of pool and facilities

    Indicative new build replacement cost*

    Potential issues and options to consider

    Kirkcaldy Swimming Pool

    No figure provided in survey

    Swimming pool

    Within 5 years - £88,000

    Within 10 years - £378,000

    Sub total - £466,000

    Facility upgrade

    No figure provided in Arup survey although Fife Council has estimated that £8.0m may need to be spent in upgrading the facility to a modern standard.

    £4.5-£5.0M

    • Opportunity to release retail value for existing site linked to proposals to extend the Mercat Centre

    • Sequential approach to relocation - availability & deliverability/cost of alternative sites

    • Critical path/phasing issues to potentially provide continuity of operation

    • Potential relationship with other opportunities/Council assets in Kirkcaldy to provide a joined up approach to future provision

    Carnegie Leisure Centre

    Swimming pool - £42,000

    Facilities - £1.5m

    Swimming pool

    Within 5 years - £375,000

    Within 10 years - 1,000

    Subtotal - £376,000

    Facility upgrade

    2-10 years - £3.25M

    Total for building (including immediate repairs) - £5.1m

    Fife Council estimate - £20million

    PMP estimate - £6.0-£7.0M for 25M pool plus learner pool, 70 station health and fitness facility and 6 court sports hall.

    • Relationship with master plan proposals for North City Centre area in medium to long term

    • Potential early value generation from Bruce Street facility disposal

    • Potential residential/mixed use approach to the site if facility was to be relocated in the future but listed building and site constraints severely impact upon value generation

    • Options to address parking constraints with current facility if retained?

    • Potential opportunities for relocation in the medium to long term as part of Dunfermline expansion proposals or potential co-location with other civic/community facilities and use of council owned sites?

    *(PMP estimate, indicative construction cost only)

    Facility

    Immediate repairs

    Upgrade of pool and facilities

    Indicative new build replacement cost
    (PMP estimate, indicative construction cost only)

    Potential issues and options to consider

    FIPRE

    Swimming pool - £1,000

    Facility upgrade - £1.45m

    Swimming pool

    Within 5 years - £580,000

    Within 10 years - £6,000

    Facilities upgrade

    2-15 years - £3.7M

    Total for building (including immediate repairs) - £5.7m

    Fife Council estimate - £20 million

    PMP estimate £10M - £12M

    • Release of surplus land for development driven by review of need/future provision in the area.

    • Significant potential to promote residential development on surplus land identified to help cross subsidise new facility (either on or off site)

    • The principle of using the site for residential development to assist future housing supply is supported from a planning perspective

    • Phasing/critical path issues will require consideration depending on whether an on site or off site solution is proposed

    • If relocated, the deliverability and accessibility of alternative sites requires detailed consideration.


    SECTION 4

    MARKET APRAISAL: SUPPLY AND DEMAND ASSESSMENT


    Evidence of Demand

    Introduction

    1. A key part of the analysis of `where we want to be' is the need to understand the market, particularly in terms of the demand for sport and leisure facilities and activities matched against the existing and future supply. This will help to determine the appropriate levels of sport and recreation provision required to support the needs of the local community and inform any future funding, investment and development strategy. The key elements of the analysis were:

    • A demographic analysis to assess the size and composition of the local leisure markets and the impact they will have upon facility usage

    • A supply and demand analysis exercise to highlight shortfalls and surpluses in sport and recreation provision

    • An analysis of the need for sports halls, swimming pools, health and fitness facilities and STP's within Fife.

    1. The key findings and conclusions drawn from the above areas of work are outlined in the following sections.

    Demographic analysis

    1. In analysing the need and demand for sport and recreation facilities, it is important to assess the size and composition of the local leisure markets and the impact they will have upon facility usage.

    2. We have analysed the 2001 Census data to understand the demographic profile of the area and have also produced a Sport and Leisure Potential report, examining the local population's propensity to take part in a variety of different sports.

    3. The propensity to participate is identified using a representative sample derived from Continental Research's Million Plus Panel. This panel comprises a pool of over 2 million UK residents and holds over 3,000 lifestyle, demographic and purchasing details. This panel is a representative sample of the Experian Ltd (ICD) Lifestyle database, which has in excess of 12 million records.

    4. The research undertaken by Continental Research examined the likelihood of participation in a large number of sports and recreational activities, including minority sports. The study asked what activities people would like to do rather than investigating current levels of activity. Respondents who indicated that they are likely to participate in a particular activity therefore represent those with the propensity to participate, rather than indicating actual participation figures.

    5. A summary of the results of the analysis of Census data and the Sport and Leisure Potential Report is outlined in Table 4.1 and 4.2 overleaf. The full Sport and Leisure Potential Report is shown at Appendix C.

    Table 4.1 Demographic analysis of Fife

    Demographic Indicator

    Impact on facility usage

    The population of Fife is 351,742. This population has increased by 0.1% since the 1991 census, however by 2010 the population is expected to have only increased by 0.06%

    Although there is a large potential user base for leisure facilities within Fife, the size and rural nature of the area results in lower usage than expected.

    The population breakdown is generally consistent with the national average except that there is a low percentage of 20-29 yr olds (0.8% below the national average). There is also a higher than average percentage of 50-59 yr olds (0.7% above the national average)

    Specifically, the Council should ensure that facilities and activities should cater for the 50-59 years age group. The Council should also target the 20-29 years age group to increase participation.

    4.1% of residents are unemployed compared to a national average of 3.6%

    The high level of unemployment within Fife should be reflected by the pricing structure. These figures may indicate a lower propensity to participate due to people with less disposable income. However it should also be noted that unemployed people have more time available for leisure activities

    Fife has a high percentage of retired people, 13.5% compared to the national average of 12.7%

    Retired residents tend to have a large amount of disposable leisure time. Programming and pricing should take into account this high number

    There are substantially less permanently sick/disabled (0.6 % below the national average) or inactive (0.6% below the national average) people in Fife than the rest of Scotland

    The low proportion of permanently sick/disabled and inactive people suggests a high propensity to participate and hence greater usage of facilities

    A high proportion of households are car owners with very few owning no car at all and a large proportion owning two cars

    Mobility is high within the district suggesting less of a dependence on public transport links

    1. The Sport and Leisure Potential report identifies the propensity to participate for different activities within Fife. The results are as summarised in Table 4.2 over the page.

    Table 4.2 Summary of Sport and Leisure Potential in Fife Report

    Sport and Leisure Potential

    Impact on Facility Use

    The Sport and Leisure Potential Report shows that the propensity to participate in swimming in Fife in line with national average, with 23% of the population expressing an interest

    There is steady demand for swimming facilities and it is important to ensure that there are a sufficient number of quality facilities to enable this level of interest and popularity of the sport to continue. Another key factor for consideration is the appropriateness of water space. For example, it is important to provide learner water to cater for swimming lessons for beginners, etc

    The propensity to participate in health and fitness in Fife is lower than the national average with 18.5% expressing an interest compared to the national average of 19.7%

    The low propensity to participate in health and fitness means the level of health and fitness provision in Fife must be considered carefully, to ensure there is no over provision

    The propensity to participate in squash in Fife is lower than the national average with 2.3% expressing an interest compared to the national average of 3.1%

    The demand for squash facilities in Fife is less than in other areas of Scotland. Again careful consideration should be given to the need for squash facilities within Fife

    The propensity to participate in football in Fife is substantially higher than the national average with 23.4% expressing an interest compared to the national average of 19.7%

    The high demand for indoor sports provision in Fife suggests that the current provision should be at the least sustained, if not increased, to accommodate the high numbers wishing to play five-a-side football.

    There will also be increased demand for outdoor synthetic pitch space

    The propensity to go running/jogging in Fife is lower than the national average with 4.5% expressing an interest compared to the national average of 4.9%

    A low interest in jogging and running has implications for the future supply athletics tracks and health and fitness facilities

    The propensity to participate in tennis in Fife is substantially lower than the national average with 2.9% expressing an interest compared to the national average of 5.1%

    On the basis of the Sport and Leisure Potential report, there appears to be little reason or no reason to increase current supply

    Supply & Demand Assessment

    Facilities Planning Model

    1. The Facilities Planning Model (FPM) is a planning tool devised by sportscotland to assess the current provision of sports facilities within areas in Scotland. The FPM determines where future facilities should be developed and potentially where an oversupply of facilities is occurring. The model calculates levels of “unmet demand” based upon the area's population demographics and the capacities and accessibility of the facilities.

    2. Using the FPM, sportscotland have calculated the unmet demand and oversupply of athletics tracks, synthetic turf pitches (STP's), main public swimming pools, 80 m² pools and public and school pools, sports halls (three courts and larger), sport halls (three courts and larger including school halls) and sports halls (two courts and larger, including school halls).

    3. The FPM discovered that within Fife there is an (??????):

    • Oversupply of 0.4 athletics tracks

    • Under supply of 2.1 STP's

    • Oversupply of 2542 m² (circa six 25m pools) of pool space in main public swimming pools

    • Oversupply of 3304 m² (circa 8 pools) of pool space in 80 m² pools and public and school pools

    • Undersupply of 30 four court sports halls (three courts and larger, excluding schools)

    • Undersupply of 14 four court sports halls (three courts and larger, including schools)

    • Undersupply of 13 four court sports halls (two courts and larger, including schools)

    1. In summary, the FPM concluded that broadly, Fife has the right number of facilities in the right places. It did not identify any significant gaps in provision, in terms of the number of facilities but highlights that local access to facilities is important.

    Supply & Demand Assessment

    1. PMP have carried out a comparative analysis to establish the adequacy of current facility provision in meeting identified local demand. This process has involved three stages:

    • Preparation of a full audit of current and planned sports facilities within and closely bordering the District (within a 3km buffer zone) to establish the level of supply.

    • Plotting of all facilities using our in-house geo-demographic mapping package `Active - Bringing Data to Life' to illustrate the geographical spread of facilities across the District.

    • Use of demand modelling techniques, based on national sporting participation parameters, to calculate whether the level of current supply adequately meets demand or whether there is under or overprovision in relation to swimming pools, sports halls and health and fitness facilities.

    Indoor sports hall provision

    Supply

    1. Existing sports halls available for public use are illustrated in Figure 4.1 over the page. Figure 4.1 illustrates that within the Fife District there are:

    • 14 public facilities containing sports halls:

    • 15 dual-use facilities, which offer a reduced number of hours of public access.

    1. In addition, seven public facilities are situated within 3km of the District.

    2. A summary of existing supply is as shown in Table 4.3 below.

    Table 4.3 Sports hall supply

    Type of sports hall

    Number of sports halls

    Number of badminton courts

    Issues raised by map

    Sports halls with full public access

    14

    55

    There is a good spread of public and dual use provision in Fife. Most of the facilities fall within the Dunfermline and Kirkcaldy region, with a potential gap in provision to the North of Glenrothes. The map highlights a lack of public provision in St Andrews.

    Sports halls on school/college sites with dual-use access

    15

    52

    TOTAL

    29

    107

    Adequacy of current provision - shortfall or surplus?

    1. For the purposes of demand modelling, accessibility for public use and size of facility are key factors taken into consideration when assessing the level of current supply provided by the network of existing facilities.

    2. For example, within the model the capacity of dual-use sites is reduced by 25% to reflect the balance of school versus casual public access and, of the 29 sports hall facilities within the catchment area (from Table 4.3 above), Table 4.4 below identifies those that have been excluded from the analysis:

    Table 4.4 Facilities excluded from the demand model

    Sports Hall site

    Reason for exclusion

    Lomand Centre (site no. 17)

    These facilities all have less than 3 badminton courts which exclude them from the demand modelling.

    Beacon Leisure Centre (site no. 1)

    1. On this basis, current supply equates to 104 badminton courts.

    0x08 graphic
    Figure 4.1 Existing sports halls in Fife

    0x08 graphic


    1. Beacon Leisure Centre

    2. Bo'Ness Recreation Centre

    4. Carnegie Sports Centre

    5. Carnoustie Leisure Centre

    6. Cowdenbeath Leisure Centre

    7. Cupar Sports Centre

    8. Dalgety Bay Sports Centre

    9. Dundee International Sports Comp

    10. Dundee University Sports Centre

    11. FIPRE

    12. Grangemouth Sports Complex

    13. Kinghorn Community Centre

    14. Leven Community Centre

    15. Levenmouth Swimming Pool & Leisure Centre

    16. Lochgelly Centre

    17. Lomond Centre

    18. Queens Ferry Recreation Centre

    20. Waid Academy

    21. Waterstone Crook Sports Centre

    22. Balwearie Centre
    23. Beath Community Use
    24. Cosmos Centre

    25. Dunfermline High School

    26. Elmwood College

    27. Kirkcaldy High School

    28. Kirkland Community Use

    29. Lochgelly High School Community Use

    30. Madras College

    31. Strathallan School

    32. Woodmill High Street

    33. Bell Baxter High Street

    34. Glenwood High School

    35. Inverkeithing High School

    36. Queen Anne High School

    37. University of St Andrews


    Demand

    1. The level of demand for sports hall facilities can be determined by applying accepted sports participation rate standards and peak usage parameters to the population within a chosen catchment.

    2. Use of this demand modelling technique for the District calculates a level of current demand equivalent to 74 badminton courts.

    Therefore a current over supply equivalent to 30 badminton courts

    1. If however, dual use facilities provided by schools are excluded from the modelling, the level of supply with Fife is 52 badminton courts. Based on a level of demand equivalent to 74 badminton courts

    Therefore a current under supply excluding dual use facilities is equivalent to 22 badminton courts

    Conclusions and recommendations

    1. The findings indicate that there is an over supply of badminton courts. Excluding the provision of sports halls in schools, the findings indicate there is an under supply of badminton courts, which is comparable to the findings of the FPM. The critical factor is the availability and access to dual use facilities for members of the public.

    2. This provides some justification for the rationalisation of the existing facilities, however it would not be recommended that the number of courts available be significantly reduced in any re-provision of facilities.

    Swimming Pools

    1. Figure 4.2 over the page identifies the current level of supply within the District. As evident from the map, current supply within the District includes:

    • 10 public swimming facilities

    • 9 dual use facilities

    1. Existing supply of swimming pools is summarised in Table 4.5 below:

    Table 4.5 Swimming pool supply

    Type of swimming pool

    Number of swimming pools

    Issues raised by map

    Pools with full public access

    10

    The map illustrates that there is an excellent spread of public swimming pools - with no significant gaps in provision identified.

    Pools on school/college sites with dual use access

    9

    TOTAL

    19

    Figure 4.2 Existing swimming pools in Fife

    0x08 graphic

    0x08 graphic

    0x08 graphic



    Adequacy of current provision - shortfall or surplus?

    1. Once again the capacity of dual use sites and/or those offering limited public access has been reduced by 25% within the demand modelling to reflect the balance of school versus casual public access.

    2. On this basis, current supply equates to 4491m2 of water space.

    3. If however, dual use facilities are excluded, current supply equates to 3612m2 of water space.

    Demand

    1. The potential demand for swimming can be determined by applying accepted sports participation rate standards (by age and gender) to the population profile within a chosen catchment. It should also be noted that propensity to participate in swimming in the District is in line with the national average, with 23% of the population expressing an interest (see Sport and Leisure Potential report at Appendix C).

    2. The `at one time capacity' (the capacity in any peak session) can then be used to establish the level of supply needed to cater for identified demand, based on accepted parameters including peak hours, proportion of visits during peak times, average visit duration and pool area. This approach ensures that supply is sufficient in size to cater for the maximum demand at any point in time.

    3. Use of this demand modelling technique calculates a level of current demand equivalent to 1248m2 of water space.

    Therefore there is a current level of over supply equivalent to 3243m2

    1. Excluding dual use facilities;

    There will be an over supply of 2364m2 equivalent to 11 25m (4 lane) swimming pools

    Swimming - Conclusions and recommendations

    1. The findings indicate that, currently there is an oversupply of water in the District. However there are a number of factors which need to be noted in the context of considering future facility developments:

    • the condition of existing facilities is extremely poor and require significant capital investment

    • potential future increases in swimming participation due to the targets for increasing participation in sport and physical activity

    • these findings support the findings of the FPM

    1. We would therefore suggest that a degree of rationalisation of existing facilities is feasible.

    Health and fitness

    1. Existing health and fitness facilities are illustrated in Figure 4.3.

    0x08 graphic
    0x08 graphic
    0x08 graphic
    0x08 graphic
    0x08 graphic
    0x08 graphic
    0x08 graphic
    0x08 graphic
    0x08 graphic
    0x08 graphic
    Figure 4.3 Existing health and fitness facilities

    0x08 graphic


    1. Alpha Leisure

    2. Beacon Leisure Centre

    3. Body Zone

    4. Bowhill Swimming Pool

    6. Carnegie Leisure Centre

    7. Carnoustie Leisure Centre

    8. Cowdenbeath LC

    9. Cupar Sports Centre

    10. Curves For Women

    11. Dalgety Bay Sport & LC

    12. Dundee International

    13. East Sands Leisure Centre

    14. Fife Institute of Physical and Recreational Education

    15. Figure World

    16. Inch Blitz

    17. Kirkcaldy Swimming Pool

    18. Levenmouth Swimming Pool and Leisure Centre

    19. Loch Leven Leisure Centre

    20. Olympia Leisure Centre

    21. Priory Park Health Club

    22. Queens Ferry Recreation Centre

    25. Waid Academy

    26. Waterstone Crook Sports
    Centre

    27. Balbirnie Gym

    28. Bannatynes Health Club

    29. Bannatynes Health Club

    30. Bell Baxter High School

    31. Club One Fitness Ltd

    32. Curves

    33. Dundee JJB Fitness Gym

    34. Energy Zone

    35. Fitness First

    36. Jax Health Club

    37. Living Well Health Clubs

    38. Lomond Centre

    39. Millenium Fitness Centre

    40. Next Generations Clubs

    41. Picture of Health Clubs

    42. Sea Health Clubs

    43. The Tone Zone Health and Fitness Club

    44. Unique Physique Gym

    45. Inverkeithing High School

    46. Queen Anne High School

    47. Balwearie Centre

    48. Elmwood College

    49. Kirkcaldy High School

    50. Kirkland Community Use

    51. Lochgelly High School Community Use

    53. Woodmill High School

    54. Beath Community Use

    55. University of St Andrews


    1. As illustrated in Figure 4.3 above, within Fife there are:

    • 20 public health and fitness facilities

    • 12 private facilities

    1. Table 4.6 below summarises the current provision of health and fitness facilities within the catchment area.

    Table 4.6 Health and fitness supply

    Type of facility

    Number of facilities

    Number of stations*

    Issues raised by map

    Public health and fitness facility

    20

    473

    There is a good mix of public and private facilities. There is a good geographical spread of facilities across most areas of the borough, although a potential gap in the East quadrant.

    Private health and fitness facility

    12

    371

    TOTAL

    32

    844

    * One station = one piece of cardio vascular equipment or one
    fixed weight machine

    Adequacy of current provision - shortfall or surplus?

    1. The audit findings illustrate that current supply in the identified catchment area equals 844 stations.

    2. The potential demand for health and fitness can be determined by applying accepted sports participation rate standards (by age and gender) to the population profile within a chosen catchment. It should also be noted that propensity of residents in the catchment area to participate in health and fitness is lower than the national average - 18.5% in comparison to 19.7% nationally.

    3. The current demand equates to 1202 stations. This demonstrates an under unmet demand of 358 stations.

    Conclusions

    1. The demand modelling analysis has highlighted the need for further health and fitness facilities in the District to cater for unmet demand. The results indicate that the level of market demand within the identified catchment area is sufficient to support additional health and fitness provision.

    2. In considering any further provision, regard must be given to the performance of the existing facilities, as detailed previously in section 3.

    Synthetic Turf Pitches

    1. Figure 4.4 below identifies the current level of supply within the catchment area.

    Figure 4.4 Existing STP's

    0x08 graphic

    0x08 graphic

    0x08 graphic

    0x08 graphic

    0x08 graphic


    1. Cowdenbeath Leisure Centre

    2. Dalgety Bay High School

    4. Fife Institute of Physical and Recreational Education

    5. HMS Caledonia

    7. Townhill Sport Complex

    8. University of St Andrews

    9. Waid Academy

    10. Woodmill High School

    12. Inverkeithing High School

    13. Queen Anne High School

    14. Balwearie Centre

    15. Beath Community Use

    17. Dunfermline High School

    18. Kirkcaldy High School

    19. Kirkland Community Use

    20. Lochgelly High School

    21. Madras College


    1. As illustrated in the figure 4.4 above there are:

    • 8 public facilities

    • 9 dual use facilities

    1. A summary of the supply is shown in Table 4.11 below.

    Table 4.11 STP Supply

    Type of facility

    Number of facilities

    Issues raised by map

    Public STP

    8

    There are a large number of STP facilities, however the majority are within the Dunfermline and Kirkcaldy area. There is a lack of facilities within Northern Fife.

    Dual use STP

    9

    TOTAL

    17


    Adequacy of current provision - shortfall or surplus?

    1. The audit findings illustrate that current supply in the identified catchment area equals 17 STP facilities.

    2. The most comprehensive parameter to assess the level of demand for STP's is the following:

    "One STP for every 60,000 people within a 20 minute off-peak drivetime"

    1. Use of this parameter indicates that for Fife the level of current demand is equivalent to 6 STP's.

    Therefore a current oversupply of 11 STP's.

    1. However, a large proportion of these are dual use facilities. If these are excluded;

    The level of over supply is equivalent to 2 STP's.

    Conclusions and Recommendations

    1. The demand modelling analysis indicates that the level of supply within the identified catchment area is sufficient to meet the demand. In fact there is an oversupply of 11 STP's however the inclusion of school facilities results in a small oversupply (2 STP's). We do not believe that further provision is required.

    0x08 graphic


    SECTION 5

    INTERIM FINDINGS


    Interim Findings

    Introduction

    1. Given the historical and political rationale for current levels of provision and the scale of investment required in maintaining and upgrading existing facilities, plus any restructuring in terms of management and operation in Fife, it will be difficult to achieve a solution that in the short term can solve all problems simultaneously.

    2. Instead, a pragmatic approach will be required, which phases the redevelopment and upgrading works required according to the level of capital / revenue available to the Council, the priorities in terms of delivering sustainable provision and considers the wider corporate priorities of the Council.

    3. We have therefore considered both the priorities alongside options that offer a deliverable solution to the Council in the short to medium term, and how finance can be released to promote a long-term sustainable service. The key considerations include:

    • Political Acceptability

    • Financial Affordability

    • Management Change/Stability.

    1. We believe that in order to `sell' a long-term strategy to the residents of Fife, the Council need to demonstrate a number of `quick wins', highlighting development and improvement in service delivery, whilst not launching into schemes that are unsustainable in the long-term.

    2. Collating all of the information presented in sections 1-4, has resulted in formulation of the following hypothesis, which will be tested in the next few sections:

    • A Phase I, focused on resolving issues and challenges faced at FIPRE and Kirkcaldy Swimming Pool:

    • the replacement/re-provision/renovation of FIPRE / Kirkcaldy Swimming Pool

    • short term essential maintenance and upgrade of Carnegie LC

    • manage maintenance priorities for other Centres

    • A Phase II, based on solving the problems for Carnegie LC:

    • medium to long term refurbishment of Carnegie LC. The option of an alternative site/facility should also be explored by way of comparison to a refurbishment, possibly linked to the western expansion if a site is achievable and appropriate

    • A Phase III, which reviews the management and asset provision for the remaining facilities, utilising savings accessed from rationalisation of existing stock, Kirkcaldy Pool, FIPRE and Carnegie LC to pay for capital investment.

    [Phases II and III could potentially be run parallel to each other within a longer term development timeframe]

    1. The 3-phase approach is based on tackling the immediate problems highlighted at Kirkcaldy Pool, FIPRE and Carnegie LC, and the need to strategically consider the location of facilities in rural areas in more detail.

    2. Within Phase I, there are two sub-options, as outlined below:

    • Option 1: separate replacement of Kirkcaldy Pool and FIPRE,

    • Option 2: a combined facility replacing Kirkcaldy Pool and FIPRE

    1. In both options there will be a need to fund short term maintenance and some upgrade works at Carnegie LC, which will allow provision to continue until Phase II can be implemented.

    2. The current position, in terms of provision `fit for purpose' and the ongoing revenue support, particularly at these three sites, but essentially across the portfolio is not sustainable. Key implications of maintaining a status quo are the continued levels of revenue support, operational functionality and continued delivery of services and programmes.

    3. Given the proximity of FIPRE and Kirkcaldy pool there is geographical justification for combining the facilities to achieve alongside the management/usage/financial synergies of a single site solution. However, cognisant of the wider considerations (political/social etc.) we have not focused simply on a single site solution, rather we have investigated three options.

    Funding and Management

    1. In the next two sections, we will focus on the management and funding opportunities for these pilot projects, outlining the key considerations and decisions required from the Council in order to progress.

    2. It is important to note that, whilst the following sections will focus on delivery of the pilot projects, the management and funding commentaries are relevant for Phases II and III, when the Council is in a position to implement them.

    0x08 graphic


    SECTION 6

    MANAGEMENT OPTIONS


    Management Options

    Introduction

    1. The Council's sport & leisure facilities are currently operated in-house by Community Services.

    2. However, in considering the future form of the service, it is necessary to revisit whether this management arrangement is best placed to deliver the service in the future. We will start by giving a description of the different management options available to the Council and the advantages and disadvantages of each. The three main management options available are:

    • Not for Profit Distributing Organisation (NPDO) or Trust Management.

    • Private Sector Operation

    • Continued In-House Management

    1. It is interesting to note that the FOLWG have specifically identified the NPDO as an option requiring further investigation, as this is a route already in operation in many local authorities across Scotland and the rest of the UK.

    2. We have deliberately not focused on in-house management within this section, as this is the current management route, with which the Council will be familiar.

    NPDO Management

    1. An NPDO is a “not for profit” organisation; meaning that, while profits or surpluses can be made in the general operation, they must be re-invested in the service and not distributed to shareholders or other outside bodies. NPDO or Trust management has become a very popular vehicle for leisure management since the late 1980's. One of the main reasons for this is the savings that the Council generates from the reduction in National Non-Domestic Rates (NNDR) and VAT. NPDO's usually have charitable status as this ensures that NNDR and VAT reduction is maximised.

    2. There are typically three types of NPDO:

    • Company Limited by Guarantee (CLG)

    • Industrial and Provident Society (IPS)

    • Unincorporated Association

    1. The key differences between these Trust structures are outlined in Table 6.1 overleaf:

    Table 6.1. Key differences between different trust structures

    Charitable company limited by guarantee

    Industrial and Provident Society

    Unincorporated Charitable NPDO

    • limited liability for Directors and NPDO's

    • familiar corporate structure

    • one individual can register

    • Charity Commission registration

    • more flexible regime

    • most commonly used for new local authority ventures.

    • model rules adopted for various classes of organisation

    • shareholding entities with employee or community involvement

    • limited liability for Board Members

    • employees as shareholders and Board Members in non-charitable NPDO

    • “exempt” charities if adopting charitable rules.

    • created by the authority, philanthropic donor or a group of individuals

    • Charity Commission registration and regulation

    • duty of care imposed on a NPDO

    • difficulties amending rules

    • unlimited personal liability for a NPDO.

    1. The Council also has further options with the transfer of management to an NPDO. These include:

    • Creating a new NPDO.

    • Transferring the management of leisure services and facilities to an existing NPDO.

    • Transferring the management of leisure services and facilities to a “hybrid NPDO” (some private leisure operators have managed to create an NPDO vehicle and claim discretionary rate relief).

    1. With all of these options, the NPDO will employ staff, incur all expenditure and retain all income. The Council will typically have a management contract or funding agreement in place with the NPDO and thus will pay a fixed sum each year for the operation of the facilities.

    2. If the Council decides to transfer to an existing NPDO, there may be lower central costs because the Board will already be in place, it will not be necessary to search for Board members who are willing and capable of performing the job and there will be none of the teething problems which might be encountered in the initial days of a new NPDO. However, an existing NPDO is unlikely to be based in the district and therefore there may be a lack of focus on the facilities and residents in Fife.

    3. If there is a new NPDO set up to manage Fife's leisure services, the NPDO will be able to concentrate its efforts entirely on the Council's facilities and maximise benefits to the local community. However, the set up costs will be more expensive due to all the legal documents that will need to be drawn up, the central costs will be more expensive than for an existing NPDO due to the need for more staff (e.g. Chief Executive, Finance Director etc) and it will be necessary to find people capable and willing to be Board Members, although it is not normally a problem to find people willing to be Board Members for a leisure NPDO.

    4. In terms of Council control, there will be little difference between a new NPDO and an existing NPDO as the Council will be able to control pricing, programming etc through the grant agreement.

    5. The Transfer of Undertakings (Protection of Employment) Act 1981 would apply to staff transferring to the NPDO from the Council.

    Key Advantages of NPDO Management

    1. There are a number of key benefits to using NPDO's compared to other management options. These include:

    • National Non Domestic Rate (NNDR) relief

    • VAT savings

    • External funding accessibility (certain grant funding organizations will only fund charitable bodies)

    • Sharper focus

    • More rapid response to change.

    Rate Relief

    1. A NPDO can gain either mandatory or discretionary rate relief, depending upon whether the NPDO is a registered exempt charity or not and the Council's policy relating to discretionary relief. The government meets the cost of the relief provided through mandatory relief and the Council and government share the cost of discretionary relief on a ratio of 75:25 respectively.

    2. Registered charitable organisations can currently claim 80% mandatory relief on NNDR and the remaining 20% may be discretionary. The cost to the Council is 75% of the discretionary element only. Thus there is the opportunity for an NPDO to gain between 80-85% relief from business rates.

    VAT

    1. Potential financial savings from VAT are much more complex. The basic principle is that VAT paid on expenditure can only be recovered in the same proportion as the VAT charged on services provided. Where, for example, an NPDO charges VAT on only 10% of their activities, they can only recover 10% of the VAT they have incurred on delivery those activities.

    2. Only certain aspects of income when the service is run in house are VAT exempt, including educational classes, use by schools and clubs etc, whereas for an NPDO, all general admissions are VAT exempt, but that has an impact on their VAT recovery.

    3. In effect, this means that circa 90% of a leisure NPDO's sports activities are exempt from VAT. This price advantage of NPDO's compared to in house or private sector management can offer significant benefits, which the NPDO can use either to raise additional income or keep prices down.

    Increased Income

    1. For any organisation to be largely dependent on annual funding is a risk, although many sports, arts and community organisations have become reconciled to this fact. NPDO's engaged in leisure provision, however, have demonstrated that it is certainly possible to increase income generation and reduce the dependency on annual revenue grants.

    2. Typically, this has been through investment in the facilities to improve the service, which generates increased income and enables investment in community-focused activities.

    External Funding

    1. An NPDO is able to access the same external funding sources as the Council, including Lottery and the New Opportunities Fund etc. NPDO's are also able to access funds designated for charities as long as they are registered. Joint projects with educational institutions, local health authorities and with regeneration partnerships are sometimes much more attractive to potential partners if the approach comes from an NPDO rather than from a Council.

    2. This is generally because the other institutions see the NPDO as being focused on delivering community services, particularly if it is a charitable organisation. However, this is not always the case and it does depend on the Council's previous track record.

    Sharper Business Focus

    1. Trustees provide a significant resource to the NPDO. Unpaid Trustees can offer a plethora of specialist knowledge and expertise, business acumen and local community contacts.

    2. Experience from existing NPDO's demonstrates that people of quality and calibre are attracted by the opportunity to contribute to the management of leisure NPDO's. For example, most leisure NPDO's will have accountants and lawyers as well as community representatives as members of the Board.

    3. A well-managed recruitment process can secure these benefits for the new NPDO. In addition, Trustees usually have their own networks and these are likely to offer an invaluable source of business development opportunities and collaborative partnerships for joint working. It should however be recognised that it is not always easy to attract trustee's and it is critical that personal liabilities are limited.

    4. The business focus that a leisure NPDO brings, however, is likely to be the most important benefit. Any senior leisure officer is likely to be required to contribute a significant amount of time to corporate affairs and consider the wider Council benefits when making decisions. Whilst the Council, as a whole, benefits from this support, the quality of direct leisure management may suffer from lack of focus and of time. An NPDO will work exclusively for the benefit of the leisure facilities, which can improve the service significantly.

    Rapid Response to Change

    1. Flexibility of response is another clear benefit of NPDO management. Leisure trends in particular change rapidly and Councils can be very slow to react. An NPDO, however, upon deciding that a new gym or extension is needed, for example, can plan for and make that investment.

    2. There will be a time in the early stages during which the NPDO needs to build up its reserves, and borrowing may be a problem, particularly if the Council only grants a short term lease, but this can usually be addressed successfully. With the opportunities of prudential borrowing, this may reduce the funding concerns.

    3. It is critical that within the establishment of the NPDO, the Council considers the level of initial and future capital investment and who is going to make the investment. If the Council invests the capital, then the lease can be short term. But if the NPDO is expected to make this investment, then the lease should be long term. In the initial stages it is likely that the Council will be able to invest the capital more cheaply than the NPDO, in which case an initial short-term lease is appropriate.

    Key Disadvantages of NPDO Management

    1. As well as significant advantages, there are also a number of disadvantages with an NPDO transfer, including:

    • Reduced influence or control

    • Possible lack of capital investment

    • Set up costs

    • Lack of risk transfer

    • Long term solution

    • Continuity of management team.

    Reduced Influence or Control

    1. The factor that is often considered to represent a significant disadvantage of an NPDO transfer is a reduced level of influence, often seen by elected Members as loss of control. This relates to the Local Government and Housing Act 1989 and subsequent regulations, which prevents local authorities from retaining control of NPDOs that provide services or facilities.

    2. There is a 20% rule within the Act that states that elected representatives or employees of the Council should be less than 20% of an NPDO Board. If these limits are exceeded, the NPDO is considered to be a local authority influenced or controlled company and its expenditure is counted as local authority expenditure in central government calculations. The NPDO will not therefore be authorised as a body independent of local authority capital control.

    3. NPDOs are considered to be independent from their local authority if they adhere to the 20% rule, although some NPDOs retain places for members within the 20% rule and the vast majority are still dependent on Council grant aid. Council control is exercised and retained through the mechanism of grant aid and monitoring procedures, rather than by direct representation.

    Possible Lack of investment

    1. An NPDO will not usually have immediate access to significant funds for capital investment. In the early years, it will need to build a business case to access investment funds, which may be difficult as the NPDO will have no significant track record and the only security will be the lease. During this period, the Council will probably pay for any investment in non-revenue generating schemes, through an increased grant.

    2. Given the current situation with the Council in need of significant capital investment, this is a particularly important point and the Council will need to consider other means of capital investment - for example, prudential borrowing or use of capital receipts.

    Set Up Costs

    1. Prior to commencing operation and in its early days, there will be costs associated with setting up the NPDO. Generally the one-off costs associated with the development of a new NPDO can be in the region of £100,000 - £150,000, which covers external legal advice, any new staff required prior to commencement of the new arrangement, financial advice (VAT) etc. Obviously this will not be an annual cost. In addition, there is the potential for redundancy costs in relation to central support services where a reduced service is required from the Council.

    2. However, in the majority of transfers to date the central services staff can either be redeployed or the remaining work is initially spread over too many people. Savings will then be realised by not filling posts that become vacant, through natural turnover of staff, avoiding redundancy costs.

    Long Term Solution

    1. Another disadvantage of setting up a NPDO is that although they are not legally irreversible, in practice it is very difficult to do so. Therefore, if the Council does take the option of transferring the facilities to a new NPDO, it should not be seen as a short-term solution for management and operation whilst other options are considered. We are not aware of any NPDO operation being reversed, however as the number of transfers increases then the likelihood of this happening increases.

    Continuity of Management Team

    1. If the Council opted to set up a new NPDO, usually the in house management team would be carried across. In some situations, therefore, the NPDO simply operates like a DSO and if it was performing poorly before, then it is likely to perform poorly after the transfer.

    2. In summary, therefore, outsourcing to an NPDO does mean a reduced level of direct Council control. Influence of the NPDO is exercised through leases of the property and other contractual arrangements, the most significant of which is likely to be a revenue grant agreement or contract.

    3. An NPDO can be an attractive option. Financial savings can be made, the community can become involved in the running of facilities and there may be a more direct focus on the leisure and cultural facilities and services, resulting in improved quality of service delivery.

    Private Operator Management

    1. A partnership with the private sector could be created by transfer of the management of facilities to a private company for a specified period of time, with an agreed refurbishment and development programme, and incorporating a fixed or performance linked fee. In short, a private company operating in partnership with the Council under the terms of whatever operational agreements are put in place.

    2. Contracting services to the private sector means that control is through the contract rather than through direct control of services. The Council defines the scope of the project and services needed. There are a number of different types of private sector management, usually dependent upon the level of capital investment the private sector will be making. These include:

    • Management Contract (with little or no investment)

    • Design, Build, Finance and Operate (DBFO)

    • Design, Build, Operate and Maintain (DBOM)

    • Hybrid NPDO structure.

    1. With each of these types of management arrangements, the Council would set out a specification and contract to which a Leisure Management Operator or a consortium of operator, builder and funder would work and the Council would pay a management fee for these services

    2. The private sector would employ staff, incur all expenditure and retain all income. Thus the Council is transferring the operating risk of the service to the private sector. There may also be the opportunity for the Council to enter into a profit share arrangement.

    3. Private sector contracts are a rare occurrence in Scotland as the market for leisure has traditionally focused on either in-house provision or NPDO management. However, as private operator contracts are one of the most effective ways of generating capital, an appraisal of the different contract types has been included below.

    Design, Build, Finance and Operate (DBFO)

    1. The DBFO Contract provides for the Council to enter into a contractual arrangement with the private sector to design, build, finance and operate new or existing facilities and take on the risks of these in return for a management fee, known as a Unitary Charge.

    2. The main drivers for these solutions are:

    • A strong commercial leisure sector and facility management market seeking sites and opportunities

    • Increasing public participation in core market sectors

    • A greater acceptance by local authorities of public leisure facilities being managed by the private sector and a recognition of the public sector's enabling role

    • The opportunity to maximise income.

    1. The Council's ability to provide revenue support is critical, but with new or enhanced facilities resulting in improved income streams and lower operating costs, any `reductions' in the subsidy created as a result of the new facility can then help to pay for the costs of the private sector finance.

    2. In addition, the private sector offers the benefit of wide commercial knowledge and experience, which should lead to financial savings, through greater efficiency of operation and higher income generation. Their culture is highly customer focused and market driven.

    3. It is worth noting that there may be difficulties in developing an appropriate contract that protects any current emphasis on community developments as a private company is ultimately answerable to shareholders, and may have few social objectives or little community involvement. However, the Council should be assured that it can control policy such as pricing, programming and participation targets via the Output Specification, which forms a key part of the documentation to be signed by the selected private sector operator or consortia.

    Design, Build Operate and Maintain (DBOM)

    1. This is a variation of the DBFO contract, where the Council enter into a long-term service contract with the private sector consortium for the design, build, operation and maintenance of a facility, but the Council provide the finance to meet the initial capital costs of the arrangement.

    2. A particular benefit that the private sector has traditionally brought to schemes is the ability to access significant capital investment. However, the advent of prudential borrowing and the removal of borrowing restrictions on local authorities has created the opportunity for a new form of contract, referred to as a Design, Build, Operate and Maintain (DBOM) contract.

    3. The funding of the initial capital costs of these schemes may be from capital receipts, capital grants, land sales or swaps, revenue contributions or from the new prudential borrowing system introduced by the Local Government Act 2003. The financing of these types of contract using public sector resources is likely to be more cost effective than the use of private sector finance.

    Hybrid NPDO Structure

    1. This contractual arrangement involves the use of the DBFO or a DBOM Contract, but with the use of a commercial NPDO provided by the leading private sector operators, for example, DC Leisure, Leisure Connection or SLM.

    2. It is therefore possible that the Council could enter into a DBFO or DBOM arrangement whereby the Contractor subcontracts the management of the facilities and/ or services to a NPDO. Under such circumstances, the Council could benefit from revenue savings through the allocation of discretionary NNDR relief whilst also being able to attract significant capital investment.

    3. These structures are not able to attract the mandatory relief as they are not deemed to have charitable status. As a result, where the Council agree to discretionary NNDR relief, the Council are obliged to finance 25% of this relief to the NNDR Pool. As a result, these types of arrangements can only lead to a 75% saving in NNDR costs.

    4. In conclusion, the outsourcing of leisure facilities to a private operator can secure significant amounts of capital and ensure efficiency in the operation of the leisure services. The Council can also enjoy a reduction of associated risk and retain an element of control through operational specifications. The financial cost of these benefits can however be high, as the Council could have to pay a significant management fee.

    5. The strengths and weaknesses of the options are summarised in Table 6.2.

    Table 6.2 Summary of the possible management options

    Option

    Strengths

    Weaknesses

    Implications for Fife

    Trust/ Not for Profit Distributing Organisation (NPDO)

    Many authorities have or are proposing to set up NPDOs to manage their leisure facilities and services. Benefits include:

    • focus on leisure business

    • surpluses reinvested in the service and local community

    • community involvement

    • TUPE satisfied

    • VAT and NNDR savings

    NPDOs without a track record of successful and viable delivery are unlikely to be able to raise finance for any new capital investment.

    Changes to NNDR or VAT regulations may reduce financial savings.

    There may be a perceived loss of `control'.

    The Council could make significant savings through the reduced NNDR and VAT associated with Trust management.

    This could ease the revenue pressure and potentially free up some revenue for funding investment via Prudential Borrowing.

    Private contractor - Voluntary Competitive Tendering

    Some councils are continuing to tender the management of their leisure facilities to private sector operators in return for a management contract, with or without capital investment.

    The longer the contract, the greater the potential for capital investment.

    Significant risk transfer.

    Contractors alone are normally unable or unwilling to contribute more than circa £2-3 million in return for contracts (often circa 10-15 years).

    The cost of this finance can be very expensive and is reflected in the revenue costs/management fees.

    Historically, little interest from private operators in managing Scottish leisure facilities.

    This would solve the issue of the required capital investment however this is an expensive form of financing.

    In addition, it is unlikely that private operators would consider the market strong enough to engage in a contract, without payment of a significant management fee.

    In house

    Council control of service quality, pricing etc

    Maintains current quality of the in house team.

    Good local knowledge.

    Limited access to capital for refurbishment / investment.

    Senior staff have corporate responsibilities, not a singular leisure focus.

    Existing problems with decision-making processes, staffing levels etc. will continue.

    The absence of capital and current poor performance of the facilities suggests that this is not a realistic long-term option, if the service is to be developed and improved in line with aspirations.

    It is worth noting that the concerns relate to the systems and structures associated with in-house management, not necessarily the staff themselves, who will be primarily the same under an NPDO structure.

    1. Having considered each of the management options in general terms, Table 6.3 compares the routes to some of the key drivers for Fife, as identified in previous sections of the report.

    Table 6.3 Management options compared

    In-house

    NPDO

    Private Partner

    Community Focus (Public service ethos)

    Service enhancement (ability to make revenue savings, for investment into capital borrowing)

    X

    Integration of services (community focus, linking with other community services - libraries / community centres etc.)

    X

    X

    Security over funding levels (how sustainable is the revenue position?)

    X

    Protection of staff (TUPE transfer and protection of Pensions)

    Transfer of risk (demand and operating risks)

    X

    Accountability to the Council (clear terms and conditions of operation and deliverables)

    1. Table 6.3 indicates that the NPDO route is best placed to deliver the integrated community service ethos that the Council is focused on delivering, whilst delivering financial benefits to allow investment in the assets of the service.

    2. We are concerned that, given the size of change required within the service, continuation of in-house management, with existing practices and customs, will hinder this process and continue to provide financial uncertainty to the Council.

    3. However, transfer of 12 leisure facilities will be a major task, and not something implemented easily. It is therefore suggested that the Council consider phased transfer, in line with the phased works on facilities. Phase I transfer would involve the management of FIPRE, Carnegie and Kirkcaldy being transferred to an NPDO, with the financial benefits being used to fund the required capital investments.

    4. Following this first stage transfer, the Council will be in a position to evaluate the success of NPDO management, before rolling-out the vehicle to the other 8 facilities in the District. Longer-term, the Council could then consider including other community assets within the NPDO, such as community centres and libraries. An NPDO covering this range of community services would be in a position to deliver a truly integrated service to the people of Fife.


    SECTION 7

    FINANCING


    Financing

    Introduction

    1. Having considered the Phase I schemes in outline, and the associated management routes, we will now investigate the financial implications for the Council.

    2. The capital and revenue positions are inter-related, and changes to one will impact on the other, however, for ease of presentation, we will consider each in turn.

    Capital Expenditure Requirement

    1. The estimated capital expenditure [construction costs] required for elements of the Phase I programme are projected to be:

    • Kirkcaldy Replacement Pool c.£5m

    • FIPRE Replacement (community facility) c.£10m

    • Combined Facility (inc. ice rink) c.£16m

    • Carnegie LC essential maintenance/Upgrade c.£3m

    1. The capital estimates are based on the previous work undertaken by the Council, and on the costs of recently provided leisure facilities.

    2. The Kirkcaldy replacement pool is considered to be a 25m 6-lane pool, with learner pool and health & fitness provision. Using a SWIM25 model, a capital cost of £5m is considered to be realistic, and includes an allowance for inflation to a late 2006 start on site.

    3. FIPRE replacement has been modelled as a comprehensive wet & dry leisure centre, incorporating 25m 6-lane pool, learner pool, six court sports hall, health & fitness and ancillary provision, plus external provision if required (STP and pitches). A capital cost of £10m is based on recent estimates seen by PMP on other leisure projects, plus an allowance for inflation.

    4. A combined facility, that provide a single facility replacement for FIPRE and Kirkcaldy Pool, would include all of the elements in the FIPRE replacement, but incorporate an enlarged 8-lane competition pool, larger sports hall (8 court), enlarged health & fitness suite (c. 80 stations) and ice rink to replace the existing facility in the town, which we understand to be in a poor state of repair. The capital cost of £16m is based on estimates received on a recent scheme in the North of England with a very similar facility mix, plus an allowance for inflation.

    5. The combined facility would represent a more regional type facility serving the wider area of Glenrothes and Kirkcaldy, as opposed to the two smaller `local' centres in Kirkcaldy and Glenrothes.

    6. The essential maintenance works and upgrade to Carnegie LC is an estimate based upon previous Council commissioned survey work.

    7. The estimated combined capital cost of the different options will therefore be circa £18-£20m, irrespective of whether a one or two centre solution is chosen. Of critical importance therefore will be the revenue positions associated with each option. However, a combined solution would offer a wider facility mix and deliver a solution that offers greater flexibility/accessibility as well as a wider strategic functionality.

    Revenue position

    1. Assuming the facility mixes outlined earlier in this section, the revenue positions for each facility have been business planned, using the following assumptions:

    Prices

    • The prices of the activities available are broadly based on comparable prices at the existing leisure facilities within the District

    • The most significant of these prices are as follows:

      • Badminton court - peak £6.30 per hour

      • Adult swim £2.60

      • Junior Swim £1.40

      • Fitness membership - full £30.00 per month

      • Fitness suite - casual £4.00 per session

      • Fitness suite - casual (concession) £2.50 per session

      • Exercise class - peak £4.00 per class

    Opening times

    • The opening hours of the dry side facilities are assumed as follows:

      • Monday to Friday 9am - 11pm

      • Saturday / Sunday 9am - 9pm

    • The opening hours of the fitness suite and swimming pool are assumed as follows:

      • Monday to Friday 7am - 11pm

      • Saturday / Sunday 7am - 9pm

    • The opening hours of the outdoor facilities are assumed as follows:

      • Monday to Friday 10am - 10pm

      • Saturday / Sunday 9am - 9pm

    • The opening hours of the café are assumed as follows:

      • Monday to Friday 10am - 9pm

      • Saturday / Sunday 10am - 7pm.

    Usage levels

    • The business plan assumes total annual throughputs of:

    • Kirkcaldy Pool Replacement 144,000

    • FIPRE Replacement 253,000

    • Combined Facility 407,000

    Secondary spend

    • The business plans assume that the catering facilities will be managed as part of the Centre as a whole

    • It is assumed that an average of £0.20 will be spent on catering and other secondary spend offers per visit to the facility.

    Other costs

    • Lifecycle costs have been included for each facility at a rate of 1.5% of construction cost.

    • Utilities costs are assumed at a rate of £18-20.00 per m² of facility, depending on type of building.

    • General maintenance costs are assumed at a rate of £15.50 per m².

    • Marketing costs are assumed at 3% of projected income levels, with additional launch costs incorporated in year 1.

    • Administration costs are assumed at approximately 5% of total staffing costs.

    • The plans include a contingency of 5% of total income levels, to cover unforeseen events.

    1. The income and expenditure for each facility is detailed in table 7.1:

    Table 7.1. Income and expenditure projections

    Kirkcaldy Replacement Pool

    £000

    FIPRE

    £000

    Combined Facility

    £000

    Income

    463

    586

    990

    Expenditure

    (881)

    (1,319)

    (1,944)

    Net position

    (418)

    (733)

    (954)

    1. Appendix D contains the detailed business plans, with sensitivity analysis of the key income and expenditure items. Reviewing the sensitivity analysis for each facility suggest that the operating deficit ranges are likely to be:

    • Kirkcaldy Pool Replacement £350-500k pa

    • FIPRE Replacement £650-900k pa

    • Combined Facility £850-1,200k pa

    1. It is important for budgeting purposes to ensure that sufficient revenue is available to cover the ranges identified above, particularly in the early years of operation whilst the facility programmes are being developed and income streams reviewed.

    2. In comparison, the current deficits for the facilities in question are:

    • Kirkcaldy Pool £1m pa

    • FIPRE £2.1m pa

    1. The combined revenue funding currently expended on these facilities is therefore circa £3.4m pa. Comparing this the higher end of the new facility revenue ranges indicates that savings of circa £2m pa may be achievable on current revenue budgets.

    Potential Release of Value from Existing Assets

    1. We understand that the Council is currently in the process of preparing its Asset Management Plan. This will provide a formal document setting out the Council's wider strategy and approach to management of its assets in accordance with the principles of Best Value. It is important that the Council's existing leisure assets are strongly considered not only in relation to outstanding cost issues through updated survey work, but also in relation to the potential to release value to cross-subsidise new facilities where appropriate.

    2. Within any disposal of assets, the Council has an obligation to achieve Best Consideration and it is important that any future marketing/disposal strategy enables this to be achieved. This also needs to be within the wider context of the strategy for future facilities provision in the area and the opportunity to ring fence capital receipts to contribute to future leisure provision where appropriate.

    3. A detailed assessment of the asset value of the Council's leisure portfolio is therefore required, particularly in respect of Kirkcaldy Swimming Pool, FIPRE at Glenrothes and Carnegie Leisure Centre in Dunfermline. As part of our options appraisal we have undertaken an assessment of alternative use/disposal value of these assets, and highlight key principles that will be important in releasing value from these facilities.

    Kirkcaldy Swimming Pool

    1. The existing condition and level of investment required for Kirkcaldy Pool reinforces that represents a priority for action in the short term. The existing pool occupies a prominent, although physically constrained, site fronting onto The Esplanade and adjacent to the Thistle Mill and Esplanade Multi Storey car parks. The pool currently occupies as site of circa 0.7 acres. It also sits to the rear of the Mercat Shopping Centre, the main covered retail centre in the town, linking back to the High Street, which has undergone a series of environmental improvements.

    2. Although the Mercat Centre is trading relatively well with limited voids and rising footfall, it is remains constrained in terms of the critical mass of retail floorspace provided and the potential to accommodate additional retailers/anchor stores capable of increasing throughput and spend is currently limited. It is considered therefore that there is opportunity to progress the potential relocation/re-provision of pool in parallel with negotiations with City Site Estates, the owners of the Mercat Centre, to release the retail potential of the existing site.

    3. This would release value from the existing pool site and help deliver an important qualitative and quantitative improvement to the retail offer in the town centre, which would bring wider regenerative benefits. We understand that Debenhams have a potential requirement for Kirkcaldy which could provide an important additional retail anchor to the Mercat Centre and Kirkcaldy's retail offer as a whole.

    4. A detailed assessment of the value of the Swimming Pool site will be required within the context of a development appraisal. This will establish the viability of the extension to the centre (together with any marriage value created through potential uplift in value of the existing centre) and the respective returns to the Council in negotiation with City Site Estates. The Council should however be aware that whilst in general terms retail use will tend to drive the highest values for the site, its physical constraints and the nature of the extension will have a significant impact on the level of value that can be generated. In particular, small-scale retail developments as extensions to an existing centre tend to have relatively high costs compared to the level of value generated.

    5. In addition, anchor tenants and in particular department stores, pay relatively low rental levels and generally require significant reverse premiums and/or fit out contributions to come to a scheme. At this stage we have therefore adopted a conservative approach to the estimated level of capital receipt that maybe released from this site.

    6. Furthermore an important consideration from a property perspective relates to the necessity for continuity of provision and the critical path for the release of asset value and the co-ordination of a potential solution with the Mercat Centre. Whilst a period of closure may not be prohibitive from an operational/business planning perspective, this may not be acceptable politically. It will be important to consider other facilities (e.g. within community use schools) that could provide a local interim solution and reinforces the need for relatively rapid resolution of the funding strategy for a new facility and timescales for delivery of a site if required for a new facility in the area.

    7. From the perspective of creating certainty, it is likely to be preferable for the alternative site to be within Fife council ownership, within the context of a positive planning framework to bring the site forward for development. Opportunities for securing enabling development (e.g. residential) in and around the preferred location should also be examined, together with the potential to lever in Section 75 contributions from nearby developments where appropriate.

    8. Further work is required in relation to the timescales for bringing forward an alternative site, together with the preferred strategy on the wider location and facility mix. Initial consultations with officers have suggested that Kirkcaldy Eastern Expansion area could be an appropriate location, with individual sites promoted through the forthcoming Local Plan review process. This potential promotes an opportunity for the combined facility location.

    Fife Institute of Sport, Glenrothes

    1. The Fife Institute of Sport occupies a circa 35 acre site in Glenrothes, to the South of the town centre and adjacent to Glenrothes College. In addition to the main building, there are a number outdoor facilities, which represent a significant land take in total. Whilst the ability to vacate the site partially or in its entirety will be driven by the options for future delivery of provision, it is considered that there exists potential to release some residential value from areas of the site that are currently surplus to requirements. If a leisure facility was to remain on the site, any redevelopment could take place on a phased basis to enable continuity of provision on part of the site or main building, particularly if a new facility was developed elsewhere.

    2. It is anticipated that residential will be the highest value generating use for the site, given its out of town location and proximity to existing residential uses. Initial discussions with Planning Officers at the Council have indicated that the principle of residential development on the site would be supported in view of the need to identify future housing land supply in the Glenrothes area, particularly if it is demonstrated that the land is surplus to requirement for sporting/community use. Issues of residential densities and affordable housing provision will require further discussion to inform a detailed assessment of potential residential values generated from the site.

    Carnegie Leisure Centre, Dunfermline

    1. The listed status of Carnegie Leisure Centre, combined with its strategic town centre location and existing range of facilities, make this the most challenging of the three centres in terms of releasing additional value and redevelopment potential.

    2. The centre is located in the north of Dunfermline Town Centre occupying a site of circa 1.4 acres, adjacent to the NHS clinic and associated surface parking. The site restricted by Carnegie Drive, Pilmuir Street, Campbell Street and Inglis Street. Despite its close proximity to the existing retail park, the potential to release substantial development value is significantly constrained by the existing buildings on the site and surrounding uses.

    3. The Council is currently progressing a Development Strategy for this part of the town centre building on the findings of the Yellow Book Report (2004) on Dunfermline town centre. We understand that this provides a framework for the potential medium to long term redevelopment of the retail park, fire station and area to the north of Carnegie Drive. The framework may help to provide future opportunities for enhancing value released from the existing leisure centre site, if a relocation option was pursued, including the potential for residential conversion.

    4. However, the Yellow Book Strategy currently retains the existing leisure facility given its contribution to the range of facilities currently provided in the town centre.

    5. If an alternative location for a modern leisure facility in Dunfermline were required it would necessitate the release of the existing site and the location of an alternative option, which will be more challenging than in other areas. Initial consultations have suggested that this could perhaps be accommodated as part of the Western Expansion area proposals for Dunfermline post 2010 or potentially within Pittencreave Park, subject to a sensitive scheme design (in discussion with Historic Scotland) and linked to longer-term plans for the park as a whole.

    Prudential Borrowing

    1. Under the prudential borrowing system, authorities can borrow as much money as they want, without prior government consent, provided that they can demonstrate that their planned borrowing is affordable in that the Authority has sufficient resources to meet the revenue costs associated with the borrowing - for example, from savings made against existing budgets via improvements in the revenue position.

    2. Based upon the business planning models and revenue positions alongside the potential release of asset value consideration is now given to how the revenue savings and capital receipts can be used to fund the required capital investment.

    The Prudential Code

    1. The code sets out a number of prudential indicators that should be calculated by authorities in order to demonstrate that their borrowing plans are affordable.

    2. The following prudential indicators are key indicators of affordability:

    • Ratio of financing costs to net revenue stream.

    • Level of the Council Tax.

    1. Other prudential indicators include:

    • Capital expenditure.

    • Adoption of the treasury management codes.

    • Levels of external debt.

    • Prudence.

    1. The code sets out the minimum prudential indicators required and authorities are encouraged to set their own additional indicators.

    2. It is worth noting that Central Government has retained reserve powers, which it could use to restrict local authority borrowing in the event that this is deemed necessary. The circumstances in which these powers might be used are:

    • where an individual authority's borrowing was not shown to be affordable through the prudential indicators

    • where borrowing by all authorities was so high that the overall national limit determined by the government would be breached unless borrowing of individual authorities was restricted.

    Risk exposure

    1. Under a standard PPP project, the funder (bank) will ensure that all the project risks are allocated and managed, using insurances, financial provisions and risk pricing. The funder will also ensure that they have rights over the Special Purpose Vehicle (SPV) and the LA to step into the project and make changes that protects their annual debt servicing costs and the project's cash flows.

    2. As such the funder will ensure, through a comprehensive due diligence exercise, that the operators and developers cost and income projections are valid, that the SPV can meet its contractual obligations and that risks are identified and managed.

    3. With the Local Authority providing the role of the funder, their forward risk profile will change and the Authority will need to be comfortable that the design and construction warranties are robust, and the operational business plans are sustainable.

    Costs of borrowing

    1. Following discussions with CIPFA and the Public Works Loan Board (PWLB) we have developed a prudential indicator model to assess the net revenue cost associated with the Council borrowing the required capital via their powers under the Prudential Code.

    2. The borrowing costs have been outlined in Table 7.2 for each option, based on the following assumptions:

    • 25 year operational and 18 month development period

    • RPI (operational costs and incomes) inflation at 2.5% per annum

    • Revenue budget inflation of 1.5% per annum (1% pa below RPI), reflecting the pressure on leisure budgets

    • Council borrowing costs

    • MRP rate of 4%

    • method of borrowing - maturity approach and equal installment payments

    • average cost of External Debt Rate of 4.60%

    • Council's average investment rate of 3.60%.

    Table 7.2 - Base Financing Costs

    Kirkcaldy Replacement Pool

    FIPRE Replacement

    Combined facility

    Capital cost

    £5m

    £10m

    £16m

    Carnegie investment

    £0m

    £3m

    £3m

    Capital receipts (estimated)

    (£0.5m)

    (£4.5m)

    (£5m)

    Capital borrowing required

    £4.5m

    £8.5m

    £14m

    Annual borrowing cost

    £249k pa

    £470k pa

    £775k pa

    Life-Cycle Annual Costs

    1. As noted in the business plans at Appendix D, life-cycle costs represent a significant additional revenue cost per annum, and are intended to be invested in a sinking fund to pay for future repair and refurbishment of the facilities. The inclusion of this sinking fund presents a new approach for the Council in relation to future maintenance responsibilities and costs and prevents the build up of major maintenance issues through the use of whole life costing.

    2. However, given that the lifecycle fund is unlikely to be required in the first few years of operating a new building, there is an opportunity to profile the lifecycle sinking fund investment in order to ensure that early year cashflow implications are managed. For example, to cover redundancy costs/set-up costs for an NPDO, etc. The business plans include at least £225k pa of lifecycle funding, so there is sufficient monies available to be flexible in the early years.

    Combined cost to the Council

    1. Taking the operational costs and borrowing repayment costs together, Table 7.3 shows the annual cost to the Council of each facility.

    Table 7.3. Annual cost to the Council

    Kirkcaldy Replacement Pool

    FIPRE Replacement

    Combined Facility

    Annual revenue cost

    £667k

    £1,203k

    £1,729k

    1. These represent average costs, rather than year 1 costs, and further consideration of the cash flows will be required to match budgets with costs. However, it is clear that the options are comfortably affordable within present budgets.

    2. Comparing the combined facility cost to the existing budget, indicates a potential saving of c.£1.37m pa. This saving could then be used to implement phases II and III of the future plan, which are less likely to deliver the sort of savings available in phase I.

    3. Having demonstrated that the project is affordable, Section 8 will now consider how to deliver the new facilities.


    SECTION 8

    PROCUREMENT


    Procurement

    1. The key issues that will determined the preferred procurement option include:

    • Level of design input

    • Transfer of risk (design, construction and maintenance)

    • Value for money (vfm)

    • Use of a not for profit vehicle/trust for operation or continued in-house management.

    1. The above issues have been considered against a range of procurement options, including:

    • Separate design, construction and operating contracts

    • Design and Build Contract with separate operating contract

    • Design, Build, Operate and Maintain Contract.

    1. A summary of each option is outlined below with an appraisal of design, risk, treatment of long term maintenance and vfm considered against the key objectives. The project is being reviewed on a whole-life basis, meaning that the Council should be looking to optimise the long-term provision of services from a new facility and not necessarily simply select the best route for initial construction of the facility. The comments against each option should therefore be viewed in this `whole-life' context.

    JCT Build Contract

    Fig 8.1 - JCT Build Contract Structure

    0x08 graphic

    1. The traditional JCT route separates the design, construction and operation of a facility. The procuring body (in this case, the Council) would need to have separate arrangements in place with each company appointed to undertake specific aspects of the scheme.

    2. The key benefit of this approach is the level of control and input afforded to the procuring body. The procuring body has ultimate flexibility to influence each stage of the process separately, and have different arrangements in place for different aspects of the work. However, there are a number of issues with this route, particularly when considered on a whole-life costing basis:

    • Design - the design of the facility would be undertaken separately, and then a build contract let to construct the new facility as per the stated design.

    • Risks - appointing and taking on the Professional Team to complete the design will involve the Council incurring costs prior to the procurement of the build contract, without a guarantee that the design will work or that the project will be signed up to by a suitable building contractor. This removes their negotiating advantage with the building contractor. The cost of procuring the design team is a risk that could result in the Council incurring a significant level of abortive fees as initial outlay. The Council will also effectively take the risk on design and be reliant upon the Professional Team warranties, which may be difficult to enforce. This procurement route also involves potential risks of delay and increased costs arising from disputes between the builder and the professional team.

    • Maintenance - this procurement route does not provide any requirement to account for the transfer of risk associated with long-term maintenance of the facility, particularly early failure of plant and equipment and cost variations in maintenance/ replacement. However, there will be a series of warranties in place from the professional team and construction company against which the Council could claim if there was an obvious failure in quality of workmanship.

    • VFM - in terms of VFM, a whole life approach to capital investment and asset maintenance cannot easily be achieved through a JCT type building contract only and the Council will need to include within the operating contract, an obligation to find a suitable solution that optimises the cost of the asset over the life of the project.

    Design and Build Contract

    Fig 8.2 - Design and Build Contract Structure

    0x08 graphic

    1. The design and build route links the design of the facility with the construction process. This is beneficial in that construction issues are taken into account in the design process, and often offers more cost control than a JCT route. In addition, the procuring body will be running a competition to chose the most effective route of achieving the new facility, which can help to add innovation and cost reduction initiatives to the scheme. Disputes between separate design teams and construction teams are removed, as the procuring body is entering into a single contract.

    2. However, this approach still focuses solely on the initial provision of a new building, without linking to the long-term operation or maintenance of the building. Assessing this against the whole-life approach:

    • Design -The Council will have adequate influence over the design of the facilities using a detailed output specification and clarification meetings.

    • Risks - with a Professional Team working in partnership with the Contractor, the risks that relate to design issues during the construction period are contained within the consortia and not borne by the Council. Any delays relating to this will therefore be for the contractor and professional team to resolve at no cost to the Council.

    • Maintenance - as with the JCT Build Contract, no provision is made for the transfer of risks associated with long term maintenance of the facilities and it will be for the Council to deal and pay for any cost variations or unbudgeted replacement of assets.

    • VFM - As above.

    Design, Build, Operate and Maintain Contract

    Fig 8.3 - DBOM Contract Structure

    0x08 graphic

    1. This type of contract allows the procuring body to enter into a single contract with a consortium who will design, build, operate and maintain the new facility. This type of structure looks at the whole-life costs of a project, and links the original construction methods with the long-term maintenance of the building.

    2. However, the procuring body has less direct input into the design and operation, therefore detailed consideration of the output specification for the facilities is essential if the procuring body is to receive the type of building and service it expects.

    • Design - the design will be carried out by a professional team working with the building contractor and operator. The Council will determine their requirements using an output specification and use clarification meetings with consortia to determine design issues that do not conform to their specification.

    • Risks - Most of the key risks are retained by the Bidding Consortia. Most issues will need to be resolved by the Consortia and not the Council. Any delays or additional costs will normally be for the account of the Consortia and will therefore provide certainty over the price. Within this type of contract it is possible for the Council to include long term maintenance within their procurement approach and transfer the risk to the private sector, who are likely to be in a position to best manage this risk. Under a traditional DBOM route the operating risks would also be transferred. However, the consortium will clearly include a risk premium in their price for taking most of the risk, and therefore the value for money assessment is key.

    However, the preferred management option, as outlined earlier, is that the operation of the facility will be undertaken by a new Leisure Trust. The operational risk under this structure will therefore be borne by the Trust, which ultimately means that the operating risk sits with the Council.

    • Maintenance - this route provides for long term maintenance to be taken into account alongside the initial capital cost of the new facilities and transfers the hard FM risks to the private sector - subject to disputes between the operator and maintenance provider, as noted above.

    • VFM - the integrated approach can drive improved value for money and provides more cost certainty. Although risks are included in their price, in a competitive environment, these should be mitigated or reduced. However, a premium for the transfer of risk will ultimately be paid and it is an assessment for the Council whether that risk transfer at a set cost offers a solution, which provides value for money.

    Summary

    1. Given the preference for NPDO management, and the Council's stated preference for maintaining the facilities in-house rather than contract with the private sector, the preferred procurement route is likely to be a design and build type contract with the Trust in place to operate the facilities.

    2. However, the benefits of an integrated DBOM-type structure need to be considered further before confirming the management route.


    SECTION 9

    CONCLUSIONS AND RECOMMENDATIONS


    Conclusions and Recommendations

    1. The Council has a number of significant decisions to make regarding the future strategy and delivery of the future of leisure in Fife. The joint work undertaken by FOWLG and this study concludes that the delivery of spot and leisure service provision in its current form is not sustainable long term both operationally and financially.

    2. A significant amount of the existing facility stock is in need of major investment to simply maintain the facilities and prevent significant downtime or closure. In light of the Council's collective challenge and pressure on revenue budgets the authority needs to progress future options for delivery that can provide sustainable, affordable and appropriate provision for delivering leisure in Fife.

    3. Many of the existing facilities are in need of significant capital investment for either refurbishment or replacement to ensure they reflect changing trends and demands. There needs to be a balance in the type of provision available, between the public, private and voluntary sector and partnership working will be crucial to optimising facilities and services.

    4. Given the scale of the challenges ahead it is prudent that solutions are delivered on phased basis. Initial consultations with the working group identified that the key priorities for the sport and leisure centres and swimming pools were Kirkcaldy, Fife Institute and Carnegie LC. This represents a significant part of the leisure portfolio and are facilities serving key population areas within Fife.

    5. Our options appraisal and consultation led to development of a pilot model solution as a first phase of a three phased development programme for sport and leisure across Fife, including its management and operation.

    6. A national strategic focus relating to increased physical activity and participation provides a headline framework for authorities across Scotland to deliver at a local level and it is recognised that a higher standard and availability of facilities across all areas of the community will be a key ingredient to delivering these objectives.

    7. The authority recognises health improvement as a key target for Fife and increasing the levels of participation is critical. Key objectives include better access to facilities for all, in particularly young and older people, with high quality leisure and cultural services identified as critical to ensuring that Fife has strong, attractive, vibrant and thriving communities.

    8. The Council has a significant number of existing facilities across the sport and leisure portfolio generally corresponding with the major centres of population. However, generally their performance is weak. Usage levels are low and whilst income per visit is reasonable, there are specific areas of revenue that are very low (health and fitness, food & beverage). The facilities suffer from high utilities costs per sq.m. (gas, electricity, water), high staffing costs when compared with income and high levels of subsidy.

    9. An analysis of the market together with the supply and demand for leisure across Fife indicates that there is over provision for swimming, sports halls, STPs and a demand for health and fitness. Whilst the current facility provision is adequate a significant amount is not fit for purpose and carries a large maintenance burden, coupled with some location issues. A solution that mixes refurbishment, upgrade and a degree of rationalisation is supported by the market analysis.

    10. A number of reports clearly also indicate that a significant level of investment is required if the Council is to continue maintaining and delivering the existing level of leisure facility provision.

    11. A range of investment requirements has been highlighted both in terms of basic maintenance priorities and significant upgrades or replacement. The FOLWG estimated c.£48m would be required for investment/refurbishment over the next 5-10years. At the three main Council facilities, FIPRE, Carnegie and Kirkcaldy the level of investment to maintain the existing facilities, provide minimal upgrades and deliver an acceptable standard of service over the next 5 -10 years is estimated at a minimum of c.£19m.

    12. Our recommendations therefore conclude that:

    1. The investment requirements are too significant to adopt a single phase solution, therefore works need to be phased in order to match capital works with funding

    2. A three phase solution should be agreed, focusing on solving problems with Kirkcaldy and the Fife Institute in the first instance as part Phase I, then Carnegie LC in Phase II

    3. As part of the delivery process, the Council should also continue to review how all their facilities are to be managed in the future. It is recommended a pilot NPDO type model be developed as part of the phase one options.

    Way Forward

    1. It is recommended that further work on the detail of Phase I is undertaken to move forward the planned approach to development and delivery of leisure in Fife.

    2. This should be initiated by developing a programme to deliver a combined facility solution for Kirkcaldy and the Fife Institute. This solution offers the most benefit in terms of service and financial delivery. It fits with the supply and demand analysis for provision in Fife and provides an opportunity to explore the management and operation of key centres under an NPDO type structure to provide both financial and service delivery benefits.

    3. The next phase of this work and immediate way forward includes seeking approvals form Committee/Council for the following:

    • approval to develop and move forward Phase I of the programme

    • approval `in principle' to use Prudential Borrowing and release capital receipts to fund the phased leisure development programme

    • approval to undertake detailed financial modelling and business planning for the development of phase I and examine the transfer of `part' operations to an NPDO-type vehicle

    • approval to take forward a detailed assessment of value release and planning and development brief for existing sites linked to the provision of new facilities

    • approval to work up design and capital costs for a combined new facility (Kirkcaldy/Glenrothes) and the minimum refurbishment of Carnegie LC, particular areas for revenue development

    • approval to undertake further analysis for the medium and long term development and operation of the leisure portfolio.

    SECTION 1 - INTRODUCTION

    Future Leisure Provision in Fife Page 1

    SECTION 2 - STRATEGIC CONTEXT

    Future Leisure Provision in Fife Page 13

    SECTION 3 - EXISTING PROVISION

    Future Leisure Provision in Fife Page 21

    Future Leisure Provision in Fife Page 22

    Future Leisure Provision in Fife Page 24

    Future Leisure Provision in Fife Page 30

    SECTION 4 - MARKET APPRAISAL: SUPPLY & DEMAND ASSESSMENT

    Future Leisure Provision in Fife Page 42

    SECTION 5 - INTERIM FINDINGS

    Page 44

    Future Leisure Provision in Fife

    SECTION 6 - MANAGEMENT OPTIONS

    Page 54

    Future Leisure Provision in Fife

    SECTION 7 - FINANCING

    Future Leisure Provision in Fife Page 63

    SECTION 8 - PROCUREMENT

    Future Leisure Provision in Fife Page 68

    SECTION 9 - CONCLUSIONS & RECOMMENDATIONS

    Future Leisure Provision in Fife Page 71

    0x01 graphic

    0x01 graphic

    0x01 graphic

    45

    0x01 graphic

    0x01 graphic

    0x01 graphic

    0x01 graphic

    0x01 graphic

    Key priorities arising from the local context include:

    • Health improvement is a key target for Fife.

    • Increasing the levels of participation of Fife residents is critical. To assist this better access to facilities for all, especially young people and old people is essential.

    • High quality leisure and cultural services is identified as crucial to ensure that Fife is full of strong, attractive, vibrant and thriving communities.

    • A large number of facilities, most of which are ageing and in need of refurbishment, places a serious financial strain on the Council.

    • Many of the existing facilities are in need of a significant capital investment for replacement or refurbishment to ensure they reflect changing trends and demands.

    • There must be a balance in the type of provision available, between the public, private and voluntary sector.

    • Partnership working is crucial to optimising facilities and services.

    Key issues arising from the national context include:

    • To increase the levels of physical activity

    • An increase in participation levels is expected

    • Improving performance levels is a key objective. To assist this it is recognised that a higher standard of facilities is required

    • There must be an improvement in access to facilities for all areas of the community

    0x01 graphic

    Summary and Implications

    Key findings from this section include:

    • lower than expected usage levels.

    • lower than average propensity to participate in health and fitness, squash, tennis and jogging and a high propensity to participate in football and swimming.

    • the FPM concluded that broadly, Fife has the right number of facilities in the right places. It did not identify any significant gaps in provision, in terms of the number of facilities but highlights that local access to facilities is important.

    • for sports halls there is some justification for the rationalisation of the existing facilities, however it would not be recommended that the number of courts available be significantly reduced in any re-provision of facilities.

    • there is an oversupply of water area in Fife, however when considering a number of factors in the context of future facility developments, it is suggested a degree of rationalisation of existing facilities is feasible.

    • there is an under supply of 358 health and fitness stations the results indicate that the level of market demand within the identified catchment area is sufficient to support additional health and fitness provision.

    • there is a small over supply of STP's.

    Summary and Implications

    1. Investment requirements are too significant to allow a single phase solution, therefore works need to be phased in order to match capital works with funding.

    2. A three phase solution should be adopted, focusing on solving problems with Kirkcaldy Pool and the Fife Institute in Phase I, then Carnegie LC in Phase II.

    3. As part of the delivery process, the Council should review how their facilities are to be managed in the future.

    11

    6

    15

    46

    38

    3

    16

    13

    12

    2

    Council

    Building Contract

    Maintenance Contracts

    Council Funding

    Professional Team

    Operating Contract

    Council

    Building Contract

    Operating Contract

    Council Funding

    Employers Agent

    Maintenance Contract

    Council

    Maintenance Contractor

    Operator

    Council Funding

    SPV Consortia

    Building Contractor

    Key findings - existing provision:

    • Fife Council currently provide 12 leisure facilities including eight sport and leisure centres, three stand-alone swimming pools and one stand-alone sports hall.

    • the Council's existing facilities are well distributed across Fife, generally corresponding with the major centres of population.

    • usage levels of existing facilities are low, however consultation has indicated that levels of participants are often restricted by the rural nature of the population and the configuration and size of existing facilities.

    • income per visit is reasonable at most centres although secondary income (e.g. food & beverage) is very low

    • income per health & fitness station is low.

    • the facilities suffer from high utilities costs per sq.m. (gas, electricity, water).

    • the staffing costs are high compared to income generation levels.

    • there are high levels of subsidy per visit across the centres, with subsidies in excess of £5 per visit at Fife Institute, East Sands, Waterstone Crook, Levenmouth, Bowhill and Kirkcaldy.

    Key findings - Investment required:

    • Previous reports indicate that a significant level of investment is required if the Council is to continue maintaining and delivering the existing level of leisure facility provision.

    • At the 3 main Council facilities; FIPRE, Carnegie and Kirkcaldy the estimated level of investment required over the next 5-10 years is in the order of:

        1. £5.1m at Carnegie Leisure Centre

        2. £5.7m at FIPRE

        3. £8m at Kirkcaldy

0x01 graphic