Crossrail
Project Delivery Partner
OJEU Notice 2008/S 65-088136 Lot 2
Invitation to Tender
Part 1 - Instructions for Tendering


 
 
Confidential 
        __________________________________________________________ 
 
 
 
CROSS LONDON RAIL LINKS 
 
 
PROJECT DELIVERY PARTNER 
OJEU Notice 2008/S 65-088136 Lot 2 
(Contract No. 2072 – Lot 2) 
 
 
Invitation to Tender 
 
Part 1 - Instructions for Tendering 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
This document contains proprietary information.  No part of this document 
may be reproduced without prior written consent from the Executive 
Chairman of Cross London Rail Links Ltd. 
 
 
1

 
 
Confidential 
        __________________________________________________________ 
 
Contents 
 
1. General 
1.1 Introduction 
1.2 Document 
Structure 
1.3 Disclaimer 
1.4 Confidentiality 
Agreement 
1.5  
Change in Circumstances 
1.6 
Publicity and Marketing 
 
2. 
The Tendering Process 
2.1 General 
2.2 Tender 
Process 
2.3 Data 
Room 
2.4 Tender 
Programme 
2.5 Tender 
Communications 
2.6 
Tender Queries and Tender Amendments 
 
3. Tender 
Returns 
3.1 General 
Requirements 
3.2 Tender 
Qualifications 
3.3 Pricing 
Errors 
3.4 Submission 
Structure 
3.5 Alternative 
Tenders 
 
4. 
Stage 1 Tender Submission 
4.1 Submission 
Requirements 
4.2 Technical 
Submission 
4.3 Commercial 
Submission 
4.4 
Form of Tender 
 
5. 
Stage 2 Tender Submission 
5.1 Submission 
Requirements 
5.2 Technical 
Submission 
5.3 Commercial 
Submission 
5.4 
Form of Tender 
 
2

 
 
Confidential 
        __________________________________________________________ 
 
 
6. 
Tender Evaluation and Contract Award 
6.1 Compliance 
6.2 
Assessment Criteria and Evaluation 
6.3 Tender 
Presentations 
6.4 
Stage 1 Evaluation and Short-listing 
6.5 
Stage 2 Evaluation 
6.6 Contract 
Award 
 
Appendices 
Appendix A 
Glossary 
Appendix B 
Form of Tender 
Appendix C 
Crossrail eSourcing Portal Guidance 
Appendix D 
Data Room Protocol 
Appendix E 
Commercial Information 
Appendix F 
Award Criteria, Sub-Criteria, Questions and Weightings 
Appendix G 
Staff Rates Schedule 
Appendix H 
Contract Duration Resource Estimate 
Appendix I 
Interim Incentive Schedule Pro forma 
Appendix J 
Final Incentive Schedule Pro forma 
Appendix K 
Incentives Flow Chart 
Appendix L 
First Service Delivery Plan 
Appendix M 
ITT Compliance Checklist 
Appendix N 
Resource Schedule 
Appendix O 
Resource Estimate 
 
3

 
 
Confidential 
        __________________________________________________________ 
1. General 
 
1.1. Introduction 
 
1.1.1  These Instructions for Tendering (IFT) are issued by Cross London Rail Links 
Limited (CLRL). 
 
1.1.2  Tenders are being invited from contracting entities who were selected by 
CLRL following the evaluation of Expressions of Interest submitted in 
response to a Contract Notice (2008/S 65-088136 Lot 2) published in the 
Official Journal of the European Union. 
 
1.1.3  The procurement process for this Contract will be in accordance with EU 
Utilities Directive 2004/17/EC and the Utilities Contracts Regulations 2006 
using the Negotiated Procedure. 
 
1.1.4  Defined terms used in this IFT are as defined in Appendix A. 
 
1.2 Document 
Structure 
 
1.2.1  The Invitation to Tender (ITT) documents are structured in two parts: 
 
Part 1 - The Instructions for Tendering (IFT) provides details of the 
competition being conducted by CLRL to select a Project Delivery Partner to 
enter into the Contract . 
 
Part 2 - The Contract sets out the terms and conditions for the appointment of 
the Project Delivery Partner and defines the scope of the services that the 
Project Delivery Partner is required to provide. 
 
1.2.2  In addition to the ITT a briefing material document has been provided to 
Tenderers.  This provides background information on the Programme, Project 
and the delivery organisation.  This briefing material must be read in 
conjunction with the ITT and all of the information provided in the data room. 
  
1.3 Disclaimer 
 
1.3.1  Any disclaimers or limitations in this ITT (whether appearing under the 
heading of Disclaimer or otherwise) shall apply to and be for the benefit of 
CLRL, its advisers and/or representatives acting on behalf of CLRL and shall 
continue to apply to and be enforceable by CLRL. 
 
1.3.2  This ITT and all other information, statements, opinions, conclusions, data 
and communications, whether written or oral and however transmitted or 
otherwise made available to Tenderers, which is made available to Tenderers 
during the procurement process (together, the 'Information') is being provided 
to Tenderers for information only and for the sole purpose of assisting them 
to submit Tenders relating to the Crossrail Project Delivery Partner. 
 
1.3.3  The Information does not purport to be comprehensive or to contain all of the 
information that a Tenderer may require to submit a Tender.  Any Tenderer 
considering submitting a Tender in response to this ITT shall conduct its own 
due diligence and seek its own professional, financial, legal and other advice 
as appropriate. 
 
4

 
 
Confidential 
        __________________________________________________________ 
 
1.3.4  The Information made available by CLRL does not include any Legislation 
which is applicable in relation to this ITT and/or the Contract.  In producing 
their Tenders, Tenderers shall satisfy themselves as to the requirements of 
Legislation. 
 
1.3.5  Words such as “anticipates”, “expects”, “projects”, “intends”, “plans”, 
“believes”, “will” and terms with similar meaning indicate the present 
expectation held by CLRL of future events, which are subject to a number of 
factors and uncertainties that could cause CLRL’s requirements to differ from 
those described in this ITT.  If CLRL’s requirements change at any time 
during this procurement process, Tenderers will be notified as soon as is 
reasonably practicable. 
 
1.3.6  Neither CLRL nor any of its advisers, representatives or agents acting on 
CLRL’s behalf: 
 
i) 
accept any liability arising out of or in connection with the Information 
including without limitation for any error or misstatement in, or 
omission from, the Information and, so far as permitted by law, in 
respect of any negligence or misrepresentation; and/or 
 
ii) 
give any representation, warranty or undertaking, express or implied, 
with respect to the Information, including, without limitation, with 
respect to the fairness, accuracy, adequacy or completeness of any of 
the Information; and/or 
 
iii) 
shall be liable for any loss or damage (other than in respect of 
fraudulent misrepresentation) arising out of or in connection with any 
reliance on the Information. 
 
1.3.7  None of the Information shall constitute a contract or part of a contract in any 
way, and none of the Information is or should be relied on as a promise or 
representation as to CLRL's ultimate decisions in relation to the Crossrail 
Programme or that CLRL will enter into a contract with any Tenderer. 
 
1.3.8  CLRL does not bind itself to enter into any contract or contracts arising out of 
the procedures envisaged by this ITT and no contractual rights, express or 
implied, arise out of this ITT or the procedures set out in it. 
 
1.3.9  A response to this ITT does not guarantee that a Tenderer will be awarded a 
contract. 
 
1.3.10  CLRL reserves the right, at any time and without cost to CLRL, to the extent 
permitted by law: 
 
i) 
to terminate or suspend any part of or the whole of this procurement 
process and/or to withdraw this ITT at any time or to re-invite 
responses on the same or any alternative basis; and/or 
 
ii) 
to waive any requirements of this procurement process; and/or 
 
iii) 
to vary any requirements and/or procedures relating to the 
procurement process; and/or 
 
 
5

 
 
Confidential 
        __________________________________________________________ 
iv) 
not to award the whole or part of the Contract as a result of this 
procurement process. 
 
1.3.11  CLRL reserves the right to reject or disqualify any Tenderer who: 
 
i) 
provides information or confirmations which later prove to be untrue or 
incorrect; and/or 
 
ii) 
does not submit a Tender in accordance with the requirements of this 
ITT or as directed by CLRL during the procurement process; and/or 
 
iii) 
fulfils any one or more of the criteria detailed in Regulation 26 of the 
Utilities Contracts Regulations 2006; and/or 
 
iv) 
undergoes a change in identity, control, financial standing or other 
materially adverse change affecting the Tenderer which in the 
reasonable opinion of CLRL would have an adverse impact on the 
procurement process or the ability of the Tenderer to perform the 
Contract; and/or 
 
v) 
fails to put forward proposals to manage any actual or potential conflict 
of interest arising, including any conflict between the interests of CLRL 
and the Tenderer, any subcontractor of the Tenderer or any of their 
respective professional advisers; and/or 
 
vi) 
fails to put forward proposals to manage any actual or potential conflict 
of interest arising as a result of being appointed to both the 
Programme Partner and Project Delivery Partner roles. 
  
1.3.12 CLRL reserves the right to require the submission by a Tenderer of any 
additional or supplemental information or clarification as it may, in its absolute 
discretion, consider appropriate. 
 
1.3.13  All Tenderers are solely responsible for all their costs and expenses incurred 
in connection with this procurement process at all stages.  Under no 
circumstances will CLRL be liable for any costs or expenses borne by or on 
behalf of the Tenderer or any party associated with this procurement process. 
 
1.3.14 CLRL will be subject to the Freedom of Information Act 2000 and the 
Environmental Information Regulations 2004, together with all codes of 
practice, guidance and directions issued pursuant to the same from time to 
time.  CLRL may at its sole discretion be required to disclose any information 
submitted by Tenderers as part of their response to this ITT. 
 
1.3.15  The submission of a Tender in response to this ITT shall be deemed to imply 
the Tenderer’s acceptance of terms and conditions in this ITT without 
qualification. 
 
1.4 Confidentiality 
Agreement 
  
1.4.1  This ITT has been issued to Tenderers who have entered into or agreed to 
enter into a confidentiality agreement with CLRL (the "Confidentiality 
Agreement").  All Information contained within this ITT constitutes 
"Information" pursuant to the terms of the Confidentiality Agreement and 
shall, as such, be treated by Tenderers in accordance with the terms of the 
 
6

 
 
Confidential 
        __________________________________________________________ 
Confidentiality Agreement.  Any Tenderer who has not yet entered into a 
Confidentiality Agreement acknowledges and agrees that this ITT has been 
issued to it on the basis that it will enter into a Confidentiality Agreement and 
agrees to comply with the terms set out therein as from the date of issue of 
this ITT.    
 
1.4.2  All Tenderers must have signed a Confidentiality Agreement before they can 
gain access to the Data Room.  Only individuals whose names have been 
provided by the Tenderer to CLRL in advance will be allowed access to the 
Data Room. 
 
1.5 
Change in Circumstances 
 
1.5.1  Tenderers must notify CLRL immediately if there is a change in 
circumstances from the Tenderer’s Expression of Interest including any 
change to the identity, control, financial standing or composition of the 
contracting entity comprising the Tenderer.   Details of any changes must 
also be set out in the Tender.  
 
1.6 
Publicity and Marketing 
 
1.6.1  Tenderers are not permitted to: 
 
i) 
Make a public statement or communicate in any form with the media in 
connection with this procurement process without first obtaining the 
prior written consent of CLRL; and/or 
 
ii) 
Use any trade marks, logos or any other intellectual property rights 
associated with CLRL or the Crossrail Programme; and/or 
 
iii) 
Represent that the Tenderer is directly or indirectly associated in any 
way with CLRL or the Crossrail Programme; and/or 
 
iv) 
Engage in any form of ambush marketing or marketing which creates, 
implies or refers to an association between the Tenderer and CLRL 
and/or the Crossrail Programme; and/or 
 
v) 
Do anything or refrain from doing anything which would have an 
adverse effect on or embarrass CLRL or the Crossrail Programme. 
 
1.6.2  Tenderers should direct the media to the CLRL Helpdesk on 0845 602 3813 
or [email address].  If required, Tenderers should seek further 
guidance from CLRL through the Crossrail eSourcing Portal. 
 
 
 
7

 
 
Confidential 
        __________________________________________________________ 
2. 
The Tendering Process 
 
2.1. General 
 
2.1.1 The tendering process seeks to determine the most economically 
advantageous offer from the point of view of CLRL.  CLRL will evaluate the 
Tenders using the criteria and weightings listed in Appendix F. 
 
2.1.2  Tenders must be submitted in accordance with the instructions in this IFT.  
Tenders not complying with these instructions may be rejected by CLRL 
whose decision on the matter will be final.   
 
2.1.3  CLRL is conducting this tendering process via the Crossrail eSourcing Portal 
(www.crossrail.bravosolution.com).  Further guidance on the use of this portal 
can be found in Appendix C. 
 
2.1.4  Should the Tenderer find discrepancies in, or omissions from, the ITT 
documents, should the intent or meaning appear unclear, or should any 
question arise relating to the documents or the tender process, the Tenderer 
should request clarification from CLRL. 
 
2.1.5  All communications with regard to this tendering process must be via the 
Crossrail eSourcing Portal only.  Except where otherwise directed in this IFT, 
Tenderers must not contact any person within CLRL, or connected with 
Crossrail. 
 
2.1.6  Any information issued to Tenderers in connection with this ITT remains the 
property of CLRL.  All such information may only be used for the purpose of 
tendering and must be returned to CLRL on completion of the tendering 
process. 
 
2.2 Tendering 
Process 
 
2.2.1  The tendering process is divided into four broad stages: 
 
i) 
Stage 1 Tender period 
 
ii) 
Stage 1 evaluation and short-listing 
 
iii) 
Stage 2 Tender period and negotiation  
 
iv) 
Stage 2 evaluation and Contract award 
 
The activities that will take place within these broad stages are outlined 
below. 
 
2.2.2  During the Stage 1 Tender period all Tenderers will jointly receive a briefing 
from the CLRL Executive Team on the role of the Project Delivery Partner 
and the tendering process.  Tenderers will have an opportunity to ask 
questions at this briefing.  Any questions raised will be treated as tender 
queries. 
 
2.2.3  During Stage 1 tendering all Tenderers must prepare a Stage 1 Tender in 
accordance with this IFT. 
 
8

 
 
Confidential 
        __________________________________________________________ 
 
2.2.4  During Stage 1 evaluation and short-listing CLRL will evaluate the Stage 1 
Tenders against the award criteria shown in Appendix F. 
 
2.2.5  As part of the evaluation of the Stage 1 Tenders, Tenderers will be required 
to provide a presentation of no more than 1 hour duration. 
 
2.2.6  Following the Stage 1 evaluation CLRL will shortlist one or more Tenderers.  
The short-listed Tenderer(s) will enter a period of negotiations with CLRL and 
develop their Stage 1 Tender into a Stage 2 Tender. 
 
2.2.7  CLRL will arrange meetings with each short-listed Tenderer during Stage 2 of 
the Tender period.  Short-listed Tenderers will be invited to discuss their 
proposals, but nothing said or intimated by CLRL at these meetings will be 
deemed to constitute an approval of any proposal or an acceptance of its 
adequacy in meeting CLRL’s requirements. 
 
2.2.8  During Stage 2, Tenderers may request meetings with CLRL in addition to 
those initiated by CLRL.  If a Tenderer wishes to request such a meeting, 
they should use the Crossrail eSourcing Portal messaging service to request 
a meeting.  When requesting a meeting, Tenderers should provide an agenda 
and supporting information indicating the subject matter to be discussed so 
that CLRL can arrange for the appropriate people to attend.  CLRL will not be 
obliged to agree to such requests. 
 
2.2.9  During Stage 2, CLRL will issue guidance to all short-listed Tenderers on 
proposals made or issues raised in meetings with a Tenderer where it 
believes that is required by the duties of transparency and of equal and non-
discriminatory treatment. 
 
2.2.10  CLRL will evaluate Stage 2 Tenders against the criteria listed in Appendix F 
to establish the most economically advantageous offer from the point of view 
of CLRL. 
 
2.2.11 CLRL will notify all Tenderers of its intended Contract award decision 
following the Stage 2 Tender evaluation. 
 
2.2.12  Following a 10 day standstill period the Contract will be awarded. 
 
2.3 Data 
Room 
 
2.3.1  Information relevant to this Tender will be made available to Tenderers within 
a data room.  The data room is both electronic and hard copy within the 
CLRL offices.  Further information on the data room is included in Appendix 
D. 
 
 
2.4 Tender 
Programme 
 
2.4.1  The Tender programme is given in Table 1 below.  If these dates change 
then new dates will be confirmed via the Crossrail eSourcing Portal 
messaging service. 
 
 
 
 
 
9

 
 
Confidential 
        __________________________________________________________ 
 
Table 1 – Tender Programme 
Key Stage 
Event 
Week 
Date/Time
Stage 1 
Issue ITT 

25/09/08 
Tendering 
Stage 1 Tenders returned 
10 
05/12/08 
12 noon 
Stage 1 
Stage 1 presentations 
11 
15/12/08 
Evaluation 
16/12/08 
and Short-
listing 
Time t.b.c 
Stage 1 evaluation and short-listing 
14 09/01/09 
completed 
Stage 2 
Stage 2 Tenders returned 
19 
13/02/09 
Tendering 
12 noon 
Stage 2 
Stage 2 Presentations 
20 
23/02/09 
Evaluation 
Time t.b.c 
and 
Contract 
Stage 2 Evaluation completed and 
23 01/04/09 
Award 
Notify Tenderers 
Award Contract 
25 
15/04/09 
 
 
2.5 Tender 
Communications 
 
2.5.1  All communications between Tenderers and CLRL must be in English. 
 
2.5.2  All written submissions, questions, queries, communications and the like from 
Tenderers and CLRL, at all stages of the Tender and negotiation process, 
shall be undertaken via the Crossrail eSourcing Portal messaging service. 
 
2.5.3  Tenderers will be expected to make their own record of meetings.  CLRL 
does not intend to issue or agree minutes or other records of meetings.  
Tenderers will not be allowed to use voice or other recording equipment to 
record the meetings. 
 
2.6 
Tender Queries and Tender Amendments 
 
2.6.1  CLRL intends to circulate the answers to all Tender queries to all Tenderers 
for information.  Tenderers should clearly identify any queries they wish to 
have treated as confidential.  It shall be at the discretion of CLRL, acting in 
accordance with the requirements of the Regulations, whether any such 
query can be responded to on a confidential basis.   
 
 
10

 
 
Confidential 
        __________________________________________________________ 
2.6.2  All Tender queries will be responded to via the Crossrail eSourcing Portal 
messaging service. 
 
2.6.3  CLRL will answer Tenderers’ queries provided they are received at least 
seven days prior to the relevant stage Tender return date.  Queries raised in 
the seven day period prior to the Tender return date may not be answered. 
 
2.6.4  If any query results in a change to the ITT documents then a tender 
amendment will be issued.  Tender amendments will be communicated via 
the Crossrail eSourcing Portal messaging service. 
 
2.6.5  If a statement is made at any meeting by any CLRL representative that the 
Tenderer considers is not in accordance with the ITT documents then the 
Tenderer must raise a query via the Crossrail eSourcing Portal messaging 
service. 
 
 
 
11

 
 
Confidential 
        __________________________________________________________ 
3 Tender 
Returns 
 
3.1 General 

Requirements 
 
3.1.1  Tenders must be submitted in accordance with the IFT including any tender 
amendments. Please refer to Appendix M – ITT Compliance Checklist 
 
3.1.2  CLRL’s decision as to whether or not a Tender complies with this IFT will be 
final. 
 
3.1.3  Tenders not received by CLRL by the relevant Tender return date and time 
will be excluded from further consideration.  Stage 2 Tenders must remain 
open for acceptance for 120 calendar days from the Stage 2 Tender return 
date as notified by CLRL. 
 
3.1.4  If a Tenderer is successful in being awarded the Contract, proposals for 
undertaking the requirements of the Contract contained within its Tender shall 
carry forward into the operation and delivery of the Contract.  Tenderers must 
therefore ensure that their commercial submissions within their Tenders 
reflect the commitments given in the remainder of their submission. 
 
3.1.5  All Tender prices, rates and the like must be completed in pounds sterling (£).  
Only the Commercial Submission is to contain pricing information.   No 
reference should be made within any other sections of the Tender to prices, 
lump sums, costs, unit rates, hourly rates, or other information of a 
commercial nature unless specifically requested by CLRL. 
 
3.1.6  Tenders shall be self contained documents and should not rely on cross 
references to documents which are not required to be submitted as part of 
the Tender. 
 
3.1.7  Tenders must include the question (See Appendix F) followed by its 
response. When stating the question it is essential that it is preceded by the 
relevant reference number including the square brackets e.g. [B3]. 
Supporting information must be referenced to the relevant question otherwise 
CLRL may not be able to evaluate information. 
 
3.1.8  When producing the Commercial Submission assume the following dates: 
 
•  Contract Start Date 
 
20 April 2009 
 
•  Contract Completion Date 
31 December 2017 
 
3.2 Tender 
Qualifications 
 
3.2.1  Tender qualifications are strongly discouraged and should only be made in 
relation to Contract terms and conditions that the Tenderer cannot comply 
with under any circumstances, or at any price.  If the Tenderer wishes to 
make any qualifications then this must be done with the Stage 1 Tender and 
they must be contained within, and in accordance with, Part 4 of the Form of 
Tender in Appendix B.  Qualifications are not permitted with Stage 2 Tenders. 
 
3.2.2  CLRL reserves the right to disregard a Tender which contains tender 
qualifications. 
 
12

 
 
Confidential 
        __________________________________________________________ 
3.3 Pricing 
Errors 
 
3.3.1  Should a genuine error be discovered in the Tenderer’s pricing during the 
evaluation period the Tenderer will be given an opportunity of confirming the 
Tender or of amending it to correct the error. 
 
3.4 Submission 
Structure 
 
3.4.1  The Tender submission must have the file structure and file name convention 
as detailed within Table 2. Sections 1–8 (Technical Submission) should be 
submitted as a single file. Sections 9-12 (Commercial Submission) should be 
submitted as a single file. Sections 13-17 should be submitted as individual 
files. 
 
3.4.2  Documents must be submitted in both a Microsoft Word format and a text 
readable pdf file format. The commercial file must be submitted in an Excel 
format. 
 
3.4.3  Tenders must only attach documents that have been requested. 
 
Note: The columns entitled Stage 1 and Stage 2 indicate what is required to 
be submitted at each stage. 
 
Table 2 
Submission Structure 
Stage 1 
Stage 2 
File No. / Name 
Section 
 
 
1. General Approach to 
* * 
01_Technical Submission. – 
delivering an effective and 
General 
efficient service 
Approach_[Tenderers Name] 
* * 
01_Technical Submission. – 
2. Delivering the 
Programme 
Programme to Budget 
Budget_[Tenderers Name] 
* * 
01_Technical Submission. – 
3. Delivering the 
Programme 
Programme on Time 
Time_[Tenderers Name] 
* * 
01_Technical Submission – 
4. Safe Delivery of the 
Safe Delivery of the 
Programme 
Programme_[Tenderers 
Name] 
* * 
01_Technical Submission – 
5. Sustainable and 
Sustainable & Responsible 
Responsible Delivery of the 
Delivery of the 
Programme 
Programme_[Tenderers 
Name] 
* * 
01_Technical Submission – 
6. Delivering a World Class 
Delivering a World Class 
Railway 
Railway_[Tenderers Name] 
 
13

 
 
Confidential 
        __________________________________________________________ 

NA 01_Technical 
Submission 
– 
7. Design Package 
Design Package 
Comments 
Comments_[Tenderers 
Name] 
* * 
01_Technical Submission – 
8. Previous Projects 
Previous Projects 
Schedule 
Schedule_[Tenderers Name] 
* * 
02 Commercial Submission 
9. Staff Rates Schedule – 
–Staff Rates 
(Appendix G) 
Schedule_[Tenderers Name] 

NA 
02 Commercial Submission 
10. Contract Duration 
–Resource Estimate 
Resource Estimate – 
Appendix H_[Tenderers 
(Appendix H) 
Name] 
NA * 
02 Commercial Submission 
11. Resource Schedule          
– Resource 
(Appendix N) 
Schedule_[Tenderers Name] 
NA * 
02 Commercial Submission 
12. Resource Estimate          
– Resource Estimate 
(Appendix O) 
Appendix O_[Tenderers 
Name] 
13. Interim Incentive 
* 
* 
03 Commercial Submission 
Schedule (Appendix I) 
–IIS_[Tenderers Name] 
14. Final Incentive 
* 
NA 
04 Commercial Submission 
Schedule (Appendix J) 
–FIS_[Tenderers Name] 
15. First Service Delivery 
* 

05 Commercial Submission 
Plan (Appendix L) 
–FSDP_[Tenderers Name] 
16. Change in 
* 
* 
06_CIS_[Tenderers Name] 
Circumstances 
17. Form of Tender 
* 

07_FOT_[Tenderers Name] 
(Appendix B) 
 
3.5 Alternative 
Tenders 
 
3.5.1  Tenderers may provide alternative Tenders, but these will only be considered 
if the Tenderer has also submitted a compliant Tender.  If providing an 
alternative Tender this should be within an entirely self-contained and 
separate document clearly indicating that it is an alternative Tender 
submission. 
 
 
14

 
 
Confidential 
        __________________________________________________________ 
4. 
Submission of Stage 1 Tenders 
 
4.1 Submission 
Requirements 
 
4.1.1  The following must be submitted with the Stage 1 Tender: 
 
Signed Confidentiality Agreement (if not already provided). 
 
The Stage 1 Tender must include the following information contained within 
the electronic and hard copy documents: 
 
i) 
Technical Submission as explained below; 
 
ii) 
Commercial Submission as explained below; 
 
iii) 
Change in circumstances; and 
 
iv) 
Form of Tender in the form contained in Appendix B. 
 
4.1.2  Tenderers must publish their Stage 1 Tender in the Crossrail e-Sourcing 
Portal in accordance with the Tender programme in Table 1. 
 
4.1.3  Within 1 working day of publishing their Stage 1 Tender, Tenderers must also 
submit one bound hard copy of the proposal to the following address. 
 
Alistair Booth – Procurement Manager 
Cross London Rail Links Ltd 
Procurement Department 
Portland House 
Bressenden Place 
London 
SW1E 5BH 
 
4.1.4  The hard copy should be submitted in a sealed unmarked package with the 
Commercial Submission contained within a separate envelope within that 
package and marked ‘Commercial Submission’.  The hard copy and the 
electronic copy of the Stage 1 Tender must have identical content. 
 
4.2 Technical 
Submission 
 
4.2.1  The Technical Submission must clearly articulate the Tenderer’s proposed 
approach to delivery of the Contract. 
 
4.2.2  The award criteria, sub-criteria and questions are linked to the subject matter 
of the Project Delivery Partner Contract. The Technical Submission must be 
structured to answer the questions as detailed within Appendix F. 
 
4.2.3  The Technical Submission must include, as requested, evidence from 
previous projects undertaken by the Tenderer to demonstrate that the 
proposed approach is likely to be successfully delivered. 
 
 
 
 
15

 
 
Confidential 
        __________________________________________________________ 
4.2.4  The organisational proposals should in particular take account of the 
following key information: 
 
i) 
The scope of works as set out in this ITT defining the role of the 
Programme Partners; 
 
ii) 
Background to the organisation contained in the briefing material 
issued with the ITT; 
 
iii) 
Organisation charts in the data room; 
 
iv) 
The existing CLRL staff schedule in the data room; 
 
4.2.5  The Technical Submission should explain how, if awarded the Contract, the 
Tenderer will deliver the services, manage or help to mitigate the key risks, 
and help to deliver a successful Project outcome.  In particular, the questions 
require Tenderers to consider: 
 
i) 
Delivering the Project to budget 
ii) 
Delivering the Project to time 
iii) 
Safe delivery of the Project 
iv) 
Sustainable and responsible delivery of the Project 
v) 
Delivering a world-class railway 
 
CLRL’s obligations and aspirations in these areas are contained in the ITT, 
briefing material issued with the ITT, and the data room. 
 
4.2.4  Tenderers should note that the briefing material represents the position in 
July 2008 and the scope sets out the current position.  It is possible that there 
are discrepancies between these documents and, if this occurs, Tenderers 
must base their proposals on the ITT. 
 
4.2.6  In total, the Technical Submission must not exceed the page limit, which is 50 
sheets of A4 paper (100 sides).  Text must be presented in the Tenderer’s 
‘house style’ with a font no smaller than Arial 11 point, single-spaced with the 
margins set at 2.5cm.  A minimum of Arial 8 point font can be used for 
diagrams, drawings and flow charts. 
 
4.2.7  The hard copy of the Technical Submission should be printed on both sides 
of each sheet.  The contents page and covers of the hard copy are not 
included in the page limit.  Tenderers may use A3 paper in lieu of A4, but 
each A3 sheet will be counted as two A4 sheets.  The pages of the hard copy 
of the Technical Submission must be numbered.  Page numbers and other 
header or footer information may be included in the margin space. 
 
4.2.8  The Technical Submission must include a ‘previous projects’ schedule listing 
all of the previous projects referred to in your Tender.  The schedule must 
contain the following information: 
 
i) 
Client, contact name and contact details 
ii) 
Overall value of the project 
iii) 
The value of your services 
iv) 
The dates between which your services were provided 
 
The previous projects schedule does not form part of the page limit. 
 
16

 
 
Confidential 
        __________________________________________________________ 
4.2.9  The Technical Submission must include a proposed Interim Incentive 
Schedule for the first Contract Year using the pro forma given in Appendix I.  
The proposed Interim Incentive Schedule must not include Interim Actual 
Amounts (or other commercial information) but must clearly show: 
 
i) 
The proposed Interim KPIs, which must be supported by definitions 
and methods of measurement; and 
 
ii) 
Proposed Performance Bands that cover the full range of possible 
performance levels for each Interim KPI. 
 
The Interim Incentive Schedule submission is to be provided by Tenderers 
for information purposes only and will not be evaluated.  It does not form 
part of the page limit. 
 
4.2.10  The Technical Submission must include a proposed Final Incentive Schedule 
using the pro forma given in Appendix J.  The proposed Final Incentive 
Schedule must not include any percentages relating to Programme KPIs and 
Performance Bands (or other commercial information) but must clearly show: 
 
i) 
The proposed Programme KPIs, in line with the aims identified in the 
pro forma, which must be supported by definitions and methods of 
measurement; and 
 
ii) 
Proposed Performance Bands that cover the full range of possible 
performance levels Programme KPI. 
 
The Final Incentive Schedule submission is to be provided by Tenderers for 
information purposes only and will not be evaluated.  It does not form part of 
the page limit. 
 
4.2.11 The Technical Submission must include the Tenderers comments on the 
proposed design packages that are anticipated to be awarded under the 
design framework contract. This is to be provided for information purposes 
only and will not be evaluated. It does not form part of the page limit. 

4.2.12 The Technical Submission must include a proposed First Service Delivery 
Plan Schedule of Deliverables and Target Dates for the first Contract Year 
using the table format given in Appendix L.  This schedule is to be provided 
by Tenderers for information purposes only and will not be evaluated.  It does 
not form part of the page limit. 
 
4.2.13  If the Technical Submission exceeds the page limit then the Tender may be 
rejected. 
 
4.2.14 If a Tenderer considers that the page limit is insufficient to provide the 
information required by this IFT then a Tender query should be raised.  No 
guarantee can be given that the page limit will be increased. 
 
 
 
 
 
 
 
 
17

 
 
Confidential 
        __________________________________________________________ 
4.3 Commercial 
Submission 
 
4.3.1  Background to the Commercial Submission is provided in Appendix E. 
 
4.3.2 Tenderers 
must: 
 
i) 
Provide a completed staff rates schedule using the template 
spreadsheet provided in Appendix G.  
 
ii) 
Provide a Project Delivery Partner Contract Duration Resource 
Estimate for the entire duration of the Contract using the template 
spreadsheet provided in Appendix H. 
 
4.4 
Form of Tender 
 
4.4.1  Tenderers must complete and include the Stage 1 Form of Tender provided 
in Appendix B. 
 
4.4.2  The Form of Tender must be completed and signed by an officer (or officers) 
empowered to make such commitments on behalf of the Tenderer. 
 
 
 
18

 
 
Confidential 
        __________________________________________________________ 

Submission of Stage 2 Tenders 
 
5.1 Submission 
Requirements 
 
5.1.1  Each short-listed Tenderer must submit a compliant Stage 2 Tender.   This 
must adopt and develop the proposals submitted in the Tenderer's Stage 1 
Tender. 
 
5.1.2  The Tender must be a stand alone document and must not cross-refer to the 
Stage 1 Tender. 
 
5.1.3  The Tender must include the following information contained within the 
electronic and hard copy documents: 
 
i) 
Expanded Technical Submission as explained below; 
 
ii) 
Updated Commercial Submission as explained below; 
 
iii) 
Change in circumstances; and 
 
iv) 
Form of Tender in the form contained in Appendix B. 
 
5.1.4  Tenderers must publish their Stage 2 Tender in the Crossrail e-Sourcing 
Portal in accordance with the Tender programme in Table 1. 
 
5.1.5  Within 1 working day of publishing their Stage 2 Tender, Tenderers must also 
submit one bound hard copy of the proposal to the following address. 
 
Alistair Booth – Procurement Manager 
Cross London Rail Links Ltd 
Procurement Department 
Portland House 
Bressenden Place 
London 
SW1E 5BH 
 
5.1.6  The hard copy should be submitted in a sealed unmarked package with the 
Commercial Submission contained within a separate envelope within that 
package and marked ‘Commercial Submission’.  The hard copy and the 
electronic copy of the Stage 2 Tender must have identical content. 
 
5.2 Technical 
Submission 
 
5.2.1  The Technical Submission must clearly articulate the Tenderer’s proposed 
approach to delivery of the Contract. 
 
5.2.2  The award criteria, sub-criteria and questions are linked to the subject matter 
of the Contract. The Technical Submission must be structured to answer the 
questions as detailed within Appendix F. 
 
5.2.3  Tenderers must submit a proposed First Service Delivery Plan.  The First 
Service Delivery Plan must be consistent with the remainder of the Technical 
Submission.  The First Service Delivery Plan is not independently evaluated 
but parts of it may be taken into account in the evaluation where the 
 
19

 
 
Confidential 
        __________________________________________________________ 
Technical Submission expressly cross-refers to it in responses to the 
questions contained in Appendix F. 
 
5.2.4  The First Service Delivery Plan must include the Schedule of Deliverables 
and Key Dates as supplied by CLRL following the Stage 1 evaluation.  
 
5.2.5  In total, the Technical Submission (excluding the First Service Delivery Plan) 
must not exceed the page limit, which is 75 sheets of A4 paper (150 sides).  
Text must be presented in the Tenderer’s ‘house style’ with a font no smaller 
than Arial 11 point, single-spaced with the margins set at 2.5cm. 
 
5.2.6  The hard copies of the Technical Submission should be printed on both sides 
of each sheet.  The contents page and covers of the hard copy are not 
included in the page limit.  Tenderers may use A3 paper in lieu of A4, but 
each A3 sheet will be counted as two A4 sheets.  The pages of the hard copy 
of the Technical Submission must be numbered.  Page numbers and other 
header or footer information may be included in the margin space. 
 
5.2.7  If the Technical Submission exceeds the page limit then the Tender may be 
rejected. 
 
5.2.8  If a Tenderer considers that the page limit is insufficient to provide the 
information required by this IFT then a Tender query should be raised.  No 
guarantee can be given that the page limit will be increased. 
 
5.2.9  The Technical Submission must include a ‘previous projects’ schedule listing 
all of the previous projects referred to in your Tender.  The schedule must 
contain the following information: 
 
v) 
Client, contact name and contact details 
vi) 
Overall value of the project 
vii)  The value of your services 
viii)  The dates between which your services were provided 
 
The previous projects schedule does not form part of the page limit. 
 
5.3 Commercial 
Submission 
 
5.3.1  In advance of submission of Stage 2 Tenders, Tenderers will be provided 
with the completed Final Incentive Schedule, which will be included in 
Appendix 4 of the Contract. 
 
5.3.2   Tenderers must: 
 
i) 
Provide a completed staff rates schedule using the template 
spreadsheet provided in Appendix G.  These staff rates must not 
exceed the rates submitted in the Stage 1 Tender. 
 
ii) 
Provide a Resource Schedule for the first Contract Year using the 
template spreadsheet provided in Appendix N. 
 
iii) 
Provide a Resource Estimate from the end of the first Contract Year to 
the assumed Contract Completion Date (see 3.1.8) using the template 
spreadsheet provided in Appendix O. 
 
 
20

 
 
Confidential 
        __________________________________________________________ 
iv) 
Complete the Interim Incentive Schedule containing the Interim KPIs 
as supplied by CLRL following the Stage 1 evaluation.  The completed 
Interim Incentive Schedule must clearly show: 
 
a.  The Interim Maximum Amount; and 
 
b.  The Interim Actual Amounts, in pounds, that would be allocated to 
the achievement of the particular Performance Bands for the 
Interim KPIs. 
 
5.4 
Form of Tender 
 
5.4.1  Complete and include the attached Stage 2 Form of Tender (see Appendix 
B). 
 
5.4.2  The Form of Tender must be completed and signed by an officer (or officers) 
empowered to make such commitments on behalf of the Tenderer. 
 
 
 
 
 
21

 
 
Confidential 
        __________________________________________________________ 

Tender Evaluation and Contract Award 
 
6.1 Compliance 
 
6.1.1  Each Tender will be checked initially for compliance with this IFT.  CLRL may 
seek clarification from a Tenderer to help determine if a Tender submitted by 
that Tenderer is compliant. 
 
6.2 
Assessment Criteria and Evaluation 
 
6.2.1  All Tenders that are compliant will be assessed using the same methodology.  
CLRL will carry out its evaluation according to the criteria, sub-criteria and 
weightings given in Appendix F. 
 
6.2.2  The Evaluation Panel will evaluate the Tenders based wholly on the contents 
of the written Tender submissions, which must therefore contain all the 
information which Tenderers wish to be considered, and the Tender 
presentations. 
 
6.3 Tender 
Presentations 
 
6.3.1  Presentations must be given by the key persons who will be responsible for 
the day-to-day delivery of the Contract services.  The presentations are not 
an opportunity to add new information and modify the Tender but to explain 
the Tender.  Presentations should be used to explain the proposals and the 
rationale underpinning their development, including the input of experience 
gained from the delivery of similar work. 
 
6.3.2  Presentations will be assessed in accordance with the criteria in Appendix F. 
 
6.4 
Stage 1 Evaluation and Short-listing 
 
6.4.1  As part of the evaluation of the Stage 1 Tenders, Tenderers will be required 
to provide a presentation of no more than 1 hour duration covering the key 
aspects of their proposal. 
 
6.4.2  Up to eight of the Tenderers’ key persons should attend the presentation.  
CLRL may ask questions during and/or after the presentation.  Overall the 
presentation and question/answer session will last no more than 2½ hours. 
 
6.4.3  Tenderers may be required to answer written queries and provide further 
information to clarify their Stage 1 Tender. 
 
6.4.4  Tenderers may be required to attend further clarification interviews or provide 
further presentations on specific aspects of their Stage 1 Tender. 
 
6.4.5  Following the Stage 1 evaluation CLRL will shortlist one or more Tenderers.  
The short-listed Tenderer(s) will enter a period of negotiations and develop 
their Stage 1 Tender into a Stage 2 Tender. 
 
 
 
 
 
 
22

 
 
Confidential 
        __________________________________________________________ 
6.5 
Stage 2 Evaluation 
 
6.5.1  As part of the evaluation of the Stage 2 Tenders, Tenderers will be required 
to provide a presentation of no more than 2 hours duration covering the key 
aspects of their proposal. 
 
6.5.2  Up to eight of the Tenderers’ key management staff (who would comprise the 
key persons under the Contract) should attend the presentation.  CLRL may 
ask questions during and/or after the presentation.  Overall the presentation 
and question/answer session will last no more than 4 hours. 
 
6.5.3  Tenderers may be required to answer written queries and provide further 
information to clarify their Stage 2 Tender. 
 
6.5.4  Tenderers may be required to attend further clarification interviews or provide 
further presentations on specific aspects of their Stage 2 Tender. 
 
6.6 Contract 
Award 
 
6.6.1  Following the Stage 2 Tender evaluation and before Contract award, CLRL 
will require confirmation that the key people are available to commence 
delivery of the services. 
 
6.6.2  CLRL will notify all Tenderers of its Contract award decision. 
 
6.6.3  Following the 10 day standstill period the Contract will be awarded. 
 
6.6.4  CLRL will award the Contract to the Tenderer submitting the most 
economically advantageous offer from the point of view of CLRL. 
 
 
 
 
 
 
 
 
 
23

 
 
Confidential 
        __________________________________________________________ 
Appendix A 
Glossary 
 
 
In this Part 1, the following defined terms have the following meanings. 
 
CLRL 
Cross London Rail Links Limited of Portland House, 
 
Bressenden Place, London SW1E 5BH. 
 
Contract 
The Project Delivery Partner contract to be entered into 
 
between CLRL and the successful Tenderer in the form 
contained in Part 2 of this ITT. 
 
Contract Year 
A twelve month period, commencing 1 April, save that the first 
Contract Year shall be the period from the Contract Date to and 
including the 31 March 2010. 
Design 
The design consultants to be appointed by CLRL under 
Framework 
framework agreements relating to the detailed design of the 
Consultants 
Crossrail Programme pursuant to OJEU Notice 2008/S 65-
 
088136. 
 
DfT 
The Department for Transport. 
 
Expression of 
An expression of interest submitted in response to a Contract 
Interest 
Notice (2008/S 65-088136 Lot 1) published in the Official 
 
Journal of the European Union. 
 
incentive schedule  The “Incentive Schedule” as defined in the Contract. 
 
IFT 
The Instructions for Tendering in this Part 1 
 
ITT 
This Invitation to Tender (Parts 1 and 2). 
 
key people / 
“key persons” as defined in the Contract in Part 2. 
persons / staff 
 
Legislation 
As defined in the Contract in Part 2. 
 
PDA 
The project development agreement to be entered into between 
 
CLRL and the Sponsors appointing CLRL to deliver and 
implement the Crossrail Project. 
 
Pre-qualification 
The pre-qualification pack for the Project Delivery Partner(s) 
Pack 
contract 2072 pursuant to OJEU Notice 2008/S 65-088136. 
 
Programme or 
The “Programme” as defined in the Contract in Part 2. 
Crossrail 
Programme  
 
Programme 
The partner to be appointed by CLRL pursuant to OJEU Notice 
Partner 
2008/S 65-088136 in relation to the Crossrail Programme. 
 
 
Regulations 
The Utilities Contracts Regulations 2006. 
 
Resource 
As defined in the Contract in Part 2. 
 
24

 
 
Confidential 
        __________________________________________________________ 
Schedule 
 
 
Scope 
The Scope at Appendix 1 to the Contract in Part 2. 
 
Service Delivery 
As defined in the Contract in Part 2. 
Plan 
 
services 
“services” as set out in the Contract in Part 2. 
 
Sponsors  
TfL and DfT. 
 
 
staff rates 
“staff rates” as defined in the Contract in Part 2.  
 
Subconsultant  
As defined in the Contract in Part 2. 
 
Tender 
A submission by a Tenderer in response to this ITT. 
 
 
Tenderer 
A party selected by CLRL following the evaluation of 
 
Expressions of Interest submitted in response to a Contract 
Notice (2008/S 65-088136 Lot 1) published in the Official 
Journal of the European Union. 
 
TfL 
Transport for London. 
 
Time Charge 
As defined in the Contract in Part 2 
 
 
 
 
25

 
 
Confidential 
        __________________________________________________________ 
Appendix B 
Form of Tender 
 
PART 1 - OFFER 
INVITATION TO TENDER FOR CONTRACT NO. 2072 – LOT 2 
[STAGE 1] / [STAGE 2]1 TENDER 
Crossrail Project Delivery Partner Contract  
Having examined the Invitation to Tender documents (ITT) for the above named 
contract, we hereby submit our Tender and confirm that: 
1. 
our completed Tender constitutes a bona fide offer, in full conformity with the 
ITT documents, to carry out the services in accordance with the Contract terms 
and conditions contained in Part 2 of the ITT for the rates and prices as set 
forth in the Commercial Submission forming part of our Tender;  
2. 
[we will submit a Stage 2 Tender in accordance with the ITT if invited to do so 
by CLRL; and]2 
[this offer shall be valid for one hundred and twenty (120) days from the Tender 
return date; and]3 
3. 
Parts 2 - 4 of this Form of Tender are an integral part of our Tender. 
 
Signed:4 
 
 
For and on behalf   
of: 
Name:  
 
Date:  
 
Position:  
 
 
Notes: 
 
1.  Delete as appropriate 
2.  Include in Stage 1 Tender only 
3.  Include in Stage 2 Tender only 
4.  This form should be completed and signed by an officer empowered to make 
such commitments on behalf of the Tenderer. 
 
26

 
 
Confidential 
        __________________________________________________________ 
Appendix B (cont.) 
Form of Tender 
 
PART 2 - CERTIFICATE OF BONA FIDE TENDER 
INVITATION TO TENDER FOR CONTRACT NO. 2072 – LOT 2 
Crossrail Project Delivery Partner Contract 
We, the undersigned, certify that: 
1. 
this is a bona fide Tender intended to be competitive and the amount has not 
been fixed or adjusted by any agreement or arrangement with any other person 
or persons; 
2. 
we have not and shall not undertake any of the following acts prior to the award 
of a formal contract: 
a.  Communicate to a person or persons other than CLRL, the amount or 
approximate amount of the Tender or any part thereof except where 
necessary, in confidence, to obtain quotations required for the preparation 
of this Tender; 
b.  Obtain or attempt to obtain, directly or indirectly, from any person or 
persons information concerning any other Tenderer or Tender submitted by 
another Tenderer in relation to this procurement process; 
c.  Enter into any agreement or arrangement with any other person or persons: 
i. 
to fix or adjust any Tender price; 
ii. 
such that said person or persons shall refrain from submitting a 
Tender or as to the amount of Tender or any part thereof to be 
submitted by such person(s); 
d.  Offer, pay, give or agree to pay or give any sum of money or valuable 
consideration directly or indirectly to any person or persons for doing, 
agreeing to do or having done or causing, agreeing to cause or having 
caused to be done to any tender for these services any act or thing of the 
sort described above; 
e.  Commit an offence under the Prevention of Corruption Acts 1889 to 1916 or 
give any fee or reward the receipt of which is an offence under sub-section 
2 of Section 117 of the Local Government Act 1972. 
In this certificate "any person or persons" refers to any body or association, 
incorporated or unincorporated, and any "agreement or arrangement" including any 
such transaction, formal or informal and, whether legally binding or not. 
 
 
 
 
27

 
 
Confidential 
        __________________________________________________________ 
 
Signed: 
 
 
For and on behalf   
of: 
Name: 
 
 
Date: 
 
 
Position: 
 
 
 
 
28

 
 
Confidential 
        __________________________________________________________ 
Appendix B (cont.) 
Form of Tender 
 
PART 3 - ITT AMENDMENTS 
INVITATION TO TENDER FOR CONTRACT NO. 2072 – LOT 2 
Crossrail Project Delivery Partner Contract 
We acknowledge acceptance of the following modifications of the ITT documents: 
Date Number 
Method 
of 
Title 
transmission
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Note: 
Either in response to requests for additional information or clarification in respect of 
this ITT, or in its own right, CLRL may modify the ITT in any respect, by way of 
clarification, addition, deletion or otherwise, prior to the closing date.  The Tenderer 
shall incorporate such modification(s), confirmation of which shall be made in this 
Part of the Form of Tender. 
 
29

 
 
Confidential 
        __________________________________________________________ 
Appendix B (cont.) 
Form of Tender 
 
PART 4 - QUALIFICATIONS TO ENQUIRY 
INVITATION TO TENDER FOR CONTRACT NO. 2072 
Crossrail Project Delivery Partner Contract 
Tenderers must provide a statement confirming acceptance of the Contract terms 
and conditions contained in Part 2 of the Invitation To Tender documents.  In the 
event that the Tenderer cannot comply with any of the Contract terms and conditions 
under any circumstances or at any price and therefore wishes to make any 
qualification, then the precise alternative wording, together with the commercial 
benefit to Cross London Rail Links Limited should any qualification be accepted, 
should be clearly stated using this form with the Stage 1 Tender.  No qualifications 
may be submitted with the Stage 2 Tender.  Only those qualifications so stated 
below shall be considered by Cross London Rail Links Limited, and any qualifications 
raised or submitted at a later date will not be considered.   
Provide details below: 
 
 
30

 
 
Confidential 
        __________________________________________________________ 
Appendix C 
Crossrail eSourcing Portal - Guidance 
 
Overall Process 
This Tender will be conducted under an eTendering procedure. eTendering is a suite 
of collaborative, web based tools that enable procurement professionals and 
suppliers to conduct the strategic activities of the procurement lifecycle over the 
internet. It provides a simple, secure and efficient means of managing tendering 
activities, reducing the time and effort for both buyers and suppliers. 
CLRL intends to conduct this procurement via the Crossrail eSourcing Portal 
(www.crossrail.bravosolution.com).  
Tenderers will have already registered on the Crossrail eSourcing Portal and 
downloaded the ITT documents. 
Responding to the Invitation to Tender 
Tenderers should use the “Messages” function to communicate with Crossrail. 
Tenderers must click the “Reply” button to activate the “Publish” button. 
Tenderers should upload the Tender Submission and click “Publish” and then 
“Confirm” when they wish to submit their final completed Tender. 
Please note that the deadline for completion is a precise time and the eSourcing 
portal will reject Tender submissions published after this time. 
Please note that there is detailed online help. For further assistance contact the 
BravoSolution help desk which is available Monday to Friday ( 8am to 6pm BST) on: 
email: [email address]; or 
telephone: 0800 011 2470 / Fax: 020 7080 0480; Outside UK +(44)2070600490 
General Guidance 
All communications from CLRL will be notified by email to the main contact who has 
registered.  If Tenderers want the communications to go to other users then this can 
be achieved by accessing the User Rights area in the portal and enabling the other 
users to receive messages. 
If CLRL make changes to a ‘Live’ tender, Tenderers MUST “re-publish” their 
response. Tenderers will receive a message prompt from CLRL notifying the 
Tenderer that changes have been made. 
The Crossrail eSourcing portal is a secure site and you will be logged out if you are 
inactive for more than 15 minutes. 
 
Tenderers should note that all files uploaded cannot be amended by anyone once 
published and that original files published by Tenderers will be maintained in an un-
altered state on the system right through the procurement process.
 
31

 
 
Confidential 
        __________________________________________________________ 
Appendix D 
Data Room Protocol 
 
Overview 
Crossrail’s Data Room has been established as a resource that will provide the 
opportunity for Tenderers to access information that may be required to effectively 
develop a Tender. Data Room documents will be available to view as follows: 
i) 
Highly Confidential documents will only be available in hardcopy 
format within the CLRL Data Room at Portland House; 
ii) 
Confidential documents will be available in hardcopy format and 
electronic format within the CLRL Data Room at Portland House; and 
iii) 
Low level security categorised documents will be available in hardcopy 
format and electronic format within the CLRL Data Room at Portland 
House. 
Rules to regulate the access and use of the Data Room are identified below. 
All Tenderers must have signed a Confidentiality Agreement before they can gain 
access to the Data Room.  Tenderers will be provided with specific access 
dates/times to the Data Room. Only individuals whose names have been provided by 
the Tenderer to CLRL in advance will be allowed access to the Data Room. 
Low level security information will also be made available via a ‘data stick’.  
Tenderers should request this from the Data Room Manager once the Confidentiality 
Agreement has been returned and the ITT downloaded from the Crossrail eSourcing 
Portal 
The Data Room Manager will provide controlled access to ‘Highly Confidential’ and 
‘Confidential’ documents. 
All the documents within the Data Room are recorded on a Data Room Register. 
Portland House Data Room 
To arrange access Tenderers should contact the Data Room Manager at 
[email address] referring to the time slots previously provided. 
This email address must only be used for arranging access to the Portland House 
Data Room.  Any other queries or questions on any other matter regarding the Data 
Room must be directed via the Crossrail eSourcing Portal messaging service. 
Tenderers may not use mobile phones or cameras within the Data Room.      
Tenderers may not photocopy any information.  
All visitors must sign in at Portland House reception and will be issued with a visitor’s 
pass.  All visitors will be directed to Crossrail reception on the 6th Floor where the 
Data Room Manager will collect them.  A Health and Safety Welcome pack will also 
be issued on arrival.   
Any visitors with special requirements need to contact the Data Room Manager 
before their visit.  
 
32

 
 
Confidential 
        __________________________________________________________ 
Electronic Data Room - Access Within the Portland House Data Room 
The Data Room Manager will provide access to the electronic data room, providing 
access to two terminals in Portland House.  Tenderers should ensure that they log 
out when leaving the Data Room. 
Documents on the electronic system are in PDF form. 
Tenderers may not use any removable storage and media including memory stick or 
disks.  
Tenderers should only use the PC Workstations for viewing data or for searching for 
information.   
Tenderers may not print out any data. 
 
 
 
 
 
33

 
 
Confidential 
        __________________________________________________________ 
Appendix E 
Commercial Information 
 
 
This section provides an overview and explanation of CLRL’s commercial approach 
to the Project Delivery Partner Contract.  Given that the Project Delivery Partner 
Contract is complex, of a long duration, requires flexibility and close working with the 
Employer, the following reimbursement and incentivisation framework has been 
developed: 
 
i) 
Payment based on staff rates; 
 
ii) 
Alignment of CLRL and Project Delivery Partner objectives through 
incentive schemes linked to annual performance and overall delivery 
of the Crossrail Project outcomes. 
 
iii)  Pre-agreed periodic Service Delivery Plans (with Resource 
Schedules); 
 
iv)  CLRL controlled Project Delivery Partner staff selection and staffing 
levels; and 
 
v) 
Key staff retention measures. 
 
Agreement of Resources 
 
During the course of the Contract, and as part of the agreement of Service Delivery 
Plans, CLRL will agree with the Project Delivery Partner Resource Schedules for a 
defined period of time (usually one year commencing 1 April with a two-year look 
ahead for planning purposes). 
 
Resource Schedules should include details of all staff required by the Project 
Delivery Partner showing the names of individual staff (where known), grades (as per 
the staff rates schedule), numbers of staff, function, position within the organisation, 
whether designated a key person, days to be worked per period, applicable staff 
rates,
 and maximum Time Charge for each period. 
 
Staff Rates 
 
The schedule of staff rates provided by the Tenderer as part of the Tender will form 
Appendix 3 of the Contract.  This schedule should include all types and grades of 
staff required by the Project Delivery Partner and shall include staff rates for all 
personnel whether services are provided directly by the Project Delivery Partner’s 
staff or by Subconsultants.  Tenderers should ensure that a complete schedule is 
provided.  
 
Notwithstanding the agreement and/or instruction of any Resource Schedule or 
Service Delivery Plan, before the Project Delivery Partner allows any key persons or 
any other persons to commence providing the services, it shall propose to CLRL an 
appropriate staff rate that is consistent with the staff rates shown in Appendix 3 of the 
Contract and shall obtain CLRL’s acceptance of that person and their applicable staff 
rate.  Requests for the acceptance of staff rates shall include detailed curriculum 
vitae of each person together with details of the proposed role and responsibilities, 
position within the Project Delivery Partner’s team and reporting lines, anticipated 
duration of appointment and any other information requested by CLRL. 
 
34

 
 
Confidential 
        __________________________________________________________ 
 
Staff rates
 are amended for inflation in line with the change in the index as set out in 
the Contract. 
 
Amendment of an agreed Resource Schedule 
 
As part of the implementation of a compensation event or otherwise by agreement 
with CLRL, a revised Resource Schedule may be agreed. 
 
Payment for Resources 
 
Payment will be made, each period, for the staff time properly spent on work under 
the Contract at the staff rates.  However, for each period this shall not exceed the 
maximum time commitment for each staff member set out in the Resource Schedule 
nor the Time Charge for the corresponding assessment interval shown within the 
Resource Schedule.  Payment shall not be made for staff time incurred by staff not 
included in the Resource Schedule. 
 
Incentivisation 
 
The Project Delivery Partner will have a highly influential role and will have a major 
impact on the delivery of Crossrail.  Performance incentives will be included within 
the Project Delivery Partner’s Contract. 
 
Incentives will be based on performance against Key Performance Indicators (KPIs) 
that reflect the key aims and priorities of CLRL.  These will be determined by CLRL 
following feedback from Tenderers provided at Stage 1 of the tender process.  The 
Contract will include two incentive schemes: 
 
i) 
Interim Incentive Scheme (IIS) 
 
ii) 
Final Incentive Scheme (FIS) 
 
These schemes are described below and have been developed to operate together 
to incentivise performance against the overall Crossrail outcomes and ongoing aims 
and priorities. 
 
Capitalised terms used in the following sections of this ITT have the meanings 
ascribed to them in the Contract.  Tenderers should refer to the Contract for full 
details of the Interim and Final Incentive Schemes. 
  
Interim Incentive Scheme (IIS) 
 
The Interim Maximum Amount that can be earned per annum under the IIS will be 
determined prior to the start of each Contract Year.  The Interim Maximum Amount 
will be the product of the anticipated Price for Services Provided to Date for the next 
Contract Year (staff time multiplied by staff rates) and the Performance Incentive 
Percentage, which shall be 15%. 
 
The Interim Maximum Amount is allocated within the Interim Incentive Schedule to 
the achievement of particular Performance Bands for each Interim KPI.  Such 
allocated amounts are the Interim Actual Amounts. 
 
 
 
35

 
 
Confidential 
        __________________________________________________________ 
The Interim Earned Amount is the Interim Actual Amount which has been earned 
under the IIS per Contract Year based upon the Project Delivery Partner’s actual 
performance against the Interim KPIs.  The Interim Earned Amount may be a 
positive or negative amount, where it is a negative amount the aggregate deductions 
in any contract year shall not exceed 10% of the anticipated Price for Services 
Provided to Date (PSPD) for the Contract Year.  
 
The Interim KPIs, Performance Bands and Interim Actual Amounts will be fixed prior 
to the start of each Contract Year, which will run from 1 April to 31 March.  The 
Interim Actual Amounts, in pounds, must be allocated within the Interim Incentive 
Schedule in accordance with the following rules: 
 
i) 
The Interim Maximum Amount shall be earned only in the event of 
‘Excellent’ performance against all of the Interim KPIs in the IIS. 
 
ii) 
The maximum deduction will only apply the event of ‘Very Poor’ 
performance against all of the Interim KPIs in the IIS. 
 
iii) 
In the case of ‘Poor’ or ‘Very Poor’ performance the Interim Earned 
Amount may be a debt due from or deducted from the sums otherwise 
payable to the Project Delivery Partner. 
 
iv)  There should be a clear differential between the Interim Actual 
Amounts allocated to the performance bands. 
 
Improvement plans will be required if actual performance falls below the “Excellent” 
Performance Band. 
 
The first Contract Year Interim KPIs, Performance Bands and Interim Actual 
Amounts will be determined as part of the Tender process and included in Appendix 
4 to the Contract when awarded.  It is expected that the first Contract Year will run 
from the Contract Date to 31 March 2010. 
 
A pro-forma for the Interim Incentive Schedule is given in Appendix I.   
 
Interim KPIs, Performance Bands and Interim Actual Amounts (agreed and shown in 
the Interim Incentive Schedule) will allow alignment of incentives with short-term 
aims and a reasonable degree of flexibility during the course of the Contract.   
 
The Interim Maximum Amount may only be adjusted during the course of the 
Contract Year when there has been a significant omission of services due to any 
failure by the Project Delivery Partner. 
 
There will be an expectation that performance will continually improve during the 
course of the Contract, which will be taken into account when agreeing Interim KPIs, 
Performance Bands and Interim Actual Amounts . 
 
Where the Interim Earned Amount for a Contract Year is a positive number it will be 
treated as follows: 
 
i) 
25% will be paid to the Project Delivery Partner; and 
 
ii) 
75% will be added to the Final Maximum Amount that can be earned 
under the Final Incentive Scheme (the “Reserved Amount”). 
 
 
36

 
 
Confidential 
        __________________________________________________________ 
Where the Interim Earned Amount for a Contract Year is a negative number that 
Interim Earned Amount is deducted from sums otherwise payable or is a debt due to 
CLRL.  There is no change to the Final Maximum Amount. 
 
Final Incentive Scheme (FIS) 
 
The Final Maximum Amount that can be earned under the FOIS will be the sum of 
the Reserved Amounts earned from the IIS during the Contract period. It is 
anticipated that the Employer will determine a minimum Final Maximum Amount to 
ensure that an incentive to deliver the Crossrail outcomes remains effective in any 
event.  The minimum Final Maximum Amount will be notified to Tenderers in 
advance of submission of their Stage 2 Tenders. 
 
The Final Earned Amount earned under the FIS will be determined based on 
performance against the Programme KPIs given in the incentive schedule.  The Final 
Earned Amount will be paid to the Project Delivery Partner as the FIS payment.  If 
the Final Earned Amount is a negative amount, this amount will be repaid by the 
Project Delivery Partner to CLRL. 
 
Programme KPIs and Performance Bands are aimed at ensuring that a focus is 
maintained on the ultimate Project outcomes.  Illustrative Programme KPIs and 
Performance Bands are given in the pro forma schedule in Appendix J to this ITT.  
This schedule will be determined by CLRL following feedback from Tenderers 
provided at Stage 1 of the tender process and will be included in Appendix 4 to the 
Contract.  This will be provided to Tenderers in advance of submission of their Stage 
2 Tenders. 
 
A flow chart illustrating the incentivisation mechanism is given in Appendix K. 
 
Proposing Interim KPIs and Targets 
 
As part of the Stage 1 Tender, Tenderers must propose Interim and Programme 
KPIs and Performance Bands in accordance with this IFT.  The pro-formas given in 
Appendix I and Appendix J must be used for this purpose. 
 
Tenderers should note that the Interim and Programme KPIs and Performance 
Bands entered into the Interim Incentive Schedule and Final Incentive Schedule 
must comply with the following principles: 
 
i) 
The KPIs must be simple to understand and administer. 
 
ii) 
The KPIs must be open to objective assessment to support efficient 
Contract management and help to ensure that the incentive scheme 
operates as intended, i.e., to promote behaviour which is aligned with 
the delivery of the key aims of the Project. 
 
iii)  All KPIs should be designed to support an open approach to their 
measurement.  It should be noted that if CLRL uncovers misreporting 
of performance then payments will not be made against the affected 
KPIs. 
 
iv)  There is an absolute expectation that there will be no fatalities or 
serious injuries during the delivery of Crossrail and full compliance with 
the law (including with the Undertakings and Assurances given during 
the passage of the Bill). 
 
37

 
 
Confidential 
        __________________________________________________________ 
 
v) 
All of the KPIs must be clearly linked to one of the key aims of the 
Crossrail Project, i.e., 
 
a.  Delivery within Budget 
b. Delivery 
on 
Time 
c. Safe 
Delivery 
d.  Sustainable and Responsible Delivery 
e.  Delivery of a World Class Railway 
f.  Excellence of approach (enabling activities) 
 
The Interim KPIs should provide three types of incentive as follows: 
 
i) 
Efficiency of Project Delivery Partner services, i.e., an incentive to 
minimise Project Delivery Partner Time Charge; 
 
ii) 
Effectiveness of Project Delivery Partner services in achieving the 
Crossrail Project aims; and 
 
iii) 
Excellence in the approach to delivery of the service, i.e, incentives 
relating to key enablers such as staff retention, management of 
relationships, etc. 
 
The incentivised Interim KPIs should be balanced to help ensure that there is not 
excessive focus on one particular type of incentive, e.g., focussing too much on 
efficiency may achieve lower Project Delivery Partner Time Charges in the first 
instance but this may be at the expense of effectiveness. 
 
  
 
38

 
 
Confidential 
        __________________________________________________________ 
Appendix F 
Award  Criteria,  Sub-Criteria, Questions and 
Weightings 
 
Award Criteria 
Award Sub-criteria 
Questions 
Description 
Wt 
Description 
Wt
Description 
Wt



Technical Submission – Criteria 1 to 6inclusive 
1.  General 
28 
Leadership - Appropriate 

[A1.1] Explain how the leadership 

approach to 
leadership for the Project 
role directly accountable for the 
delivering an 
Delivery Partner role 
Project Delivery Partner organisation 
effective and 
will operate. 
efficient 
service 

  
Organisation 

Appropriate 

[A1.2] Provide organisation charts 

and complete organisation 
including key roles, their functions 
structures for the provision 
and their relationship to CLRL: 
 
of the services aligned with 
 
the requirements of the role 
a.  For the first Contract Year. 
and CLRL. 
b.  At peak resource level 
 
 
 
 
People – Appropriate 
18 
[A1.3] Provide a list of eight key 
16 
qualifications, skills and 
persons with a statement of their 
experience of the key 
qualifications, skills and experience 
 
persons and the ability to 
that demonstrates their suitability for 
 
retain and motivate these 
the role that they will fulfil.  The 
and other staff. 
minimum period of availability is to 
 
be given for each key person

[A1.4] Describe how you will retain 
and incentivise key persons and 
other staff and ensure succession 
planning during the course of 
delivering the services. 
 
 
 
Relationships - Suitability of 

[A1.5] Describe the values and 

the approach proposed to 
behaviours you will promote and how 
working with CLRL and 
these will be implemented and 
 
other key stakeholders. 
maintained throughout delivery of the 
 
services. 
 
[A1.6] Describe how effective 
relationships with CLRL and other 

key Project stakeholders will be 
developed and managed. 
 
 
 
Incentives - The quality and 

[A1.7]  Provide details of the people, 

effectiveness of the 
processes and systems that will be 
proposed arrangements for 
used to monitor and manage the 
managing KPIs. 
Interim and Programme KPIs   
 
 
39

 
 
Confidential 
        __________________________________________________________ 
 
Award Criteria 
Award Sub-criteria 
Questions 
Description 
Wt 
Description 
Wt
Description 
Wt



2.  Delivering 

Understanding of the key 

[B2.1] Describe the key risks to 

the Project to 
risks to delivering the 
delivering the Project to budget that 
budget 
Project to budget 
the Project Delivery Partner can 
control or influence
 
 
Management of the key 

[B2.2] Explain how you will manage 

risks to delivering the 
or help to mitigate each of the key 
Project to budget  
risks to delivery to budget. Describe 
where you have previously applied 
the proposed approach. 
3.  Delivering 

Understanding of the key 

[C3.1] Describe the key risks to 

the Project on 
risks to delivering the 
delivering the Project on time that 
time 
Project on time 
the Project Delivery Partner can 
control or influence
 
 
Management of the key 

[C3.2] Explain how you will manage 

risks to delivering the 
or help to mitigate each of the key 
Project on time 
risks to delivery on time. Describe 
where you have previously applied 
the proposed approach. 
4.  Safe  

Understanding of the key 

[D4.1] Describe the key risks to 

delivery of the 
risks to the safe delivery of 
Project health and safety that the 
Project 
the Project 
Project Delivery Partner can control 
or influence
 
 
Management of the key 

[D4.2] Explain how you will manage 

risks to the safe delivery of 
or help to mitigate the key risks to 
the Project 
health and safety. Describe where 
you have previously applied the 
proposed approach. 
5.  

Understanding of the key 

[E5.1] Describe the key risks to the 

Sustainable 
risks to the sustainable and 
sustainable and responsible delivery 
and 
responsible delivery the 
of the Project that the Project 
responsible 
Project 
Delivery Partner can control or 
delivery of the 
influence. 
Project 
 
 
Management of the key 

[E5.2] Explain how you will manage 

risks to the sustainable and 
or help to mitigate the key risks to 
responsible delivery of the 
sustainable and responsible delivery. 
Project 
Describe where you have previously 
applied the proposed approach. 
6.  Delivering 

Understanding of the key 

[F6.1] Describe the key risks to the 

a world-class 
risks to delivering a world-
delivery of a world-class railway that 
railway 
class railway 
the Project Delivery Partner can 
control or influence
 
 
Management of the key 

[F6.2] Explain how you will manage 

risks to delivering a world-
the key risks to the delivery of a 
class railway 
world-class railway. Describe where 
 
you have previously applied the 
proposed approach. 
 
40

 
 
Confidential 
        __________________________________________________________ 
 
Award Criteria 
Award Sub-criteria 
Questions 
Description 
Wt 
Description 
Wt
Description 
Wt



Commercial Submission 
7. Price for 
30 
The CLRL assessed cost of 
30 
[G7.1] Using the template .xls 
30 
the Services 
the services using CLRL’s 
spreadsheet, provide a completed 
own resource model. 
staff rates schedule and incentive 
schedules as directed. 
 
Presentations 
8. Confidence 
12 
Confidence in the key staff 
12 
Demonstrate drive, professionalism, 
12 
in the team 
and delivery proposals 
experience, competence and 
gained from the Tender 
personal capability in the 
presentations. 
presentations.  
 
 
41

 
 
Confidential 
        __________________________________________________________ 
 
Appendix G 
Staff Rates Schedule 
 
Note: See separate excel file. 
 
 
Appendix H 
 
Contract Duration Resource Estimate 
 
Note: See separate excel file. 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
42

 
 
Confidential 
        __________________________________________________________ 
Appendix I  
Interim Incentive Schedule Pro forma 
 
Interim Incentive Schedule 
Aim 
Interim KPI Description and Definition 
A = Performance Band 
B = Interim Actual Amount (£) 
Excellent 
Very Good 
Acceptable 
Poor 
Very Poor 
1. Delivery 
Example themes for KPIs: 

[Performance] [Performance] [Performance] [Performance] [Performance] 
within budget 
• Delivery to Project spend profile 

[£] [£] [£] Charge 
[-£] 
Charge 
[-£] 
• Delivery within Project Delivery Partner forecast spend (efficiency) 
 
2. Delivery on 
Example themes for KPIs: 

[Performance] [Performance] [Performance] [Performance] [Performance] 
time 
• Delivery of key Project milestones 

[£] [£] [£] Charge 
[-£] 
Charge 
[-£] 
 
 
3. Safe 
Example themes for KPIs: 

[Performance] [Performance] [Performance] [Performance] [Performance] 
delivery 
• Approach to behavioural safety and accident prevention 

[£] [£] [£] Charge 
[-£] 
Charge 
[-£] 
 
Note: All safety KPIs should be designed to support an open approach to 
accident and incident reporting.  Any examples of misreported by the 
Delivery Partner will result in no payment against safety KPIs. 
 
 
 
 
 
 
 
 
43

 
 
Confidential 
        __________________________________________________________ 
Interim Incentive Schedule 
Aim 
Interim KPI Description and Definition 
A = Performance Band 
B = Interim Actual Amount (£) 
Excellent 
Very Good 
Acceptable 
Poor 
Very Poor 
4. Sustainable 
Example themes for KPIs: 

[Performance] [Performance] [Performance] [Performance] [Performance] 
and 
• Encouraging a diverse base of suppliers 
responsible 

[£] [£] [£] Charge 
[-£] 
Charge 
[-£] 
delivery 
• Promoting fair employment practices 
• Promoting workforce welfare 
• Meeting strategic labour needs and enabling training opportunities     
• Community benefits 
• Ethical sourcing practices 
• Promoting greater environmental sustainability 
 
5. Delivery of 
Example themes for KPIs: 

[Performance] [Performance] [Performance] [Performance] [Performance] 
a world-class 
• Accurate reporting of Project defects and approach to re-work 
railway 

[£] [£] [£] Charge 
[-£] 
Charge 
[-£] 
 
 
6. Excellent 
Example themes for KPIs: 

[Performance] [Performance] [Performance] [Performance] [Performance] 
delivery of 
• Retention of key staff 
enabling 

[£] [£] [£] Charge 
[-£] 
Charge 
[-£] 
activities 
• Key stakeholder relationships 
• Risk management 
 
 
44

 
 
Confidential 
        __________________________________________________________ 
Appendix J 
Crossrail Final Incentive Schedule Pro forma 
 
Final Incentive Schedule 
Aim 

KPI Description and Definition 
A = Performance Band 
B = Final Earned Amount (% of Final Maximum Amount) 
Excellent 
Very Good 
Acceptable 
Poor 
Very Poor 
1. Delivery 
Example KPI: Cost 

[Performance] [Performance] [Performance] [Performance] [Performance] 
within budget 
Actual cost of the Project at Final Completion less the anticipated cost of  B  [+%] [+%] [+%] [-%]  [-%] 
the Project in the PDA, expressed as a percentage of the anticipated cost 
of the Crossrail Project in the PDA. 
2. Delivery on 
Example KPI: Time 

[Performance] [Performance] [Performance] [Performance] [Performance] 
time 
Actual date of Final Completion of the Project compared to the anticipated  B  [+%] [+%] [+%] [-%]  [-%] 
date of Final Completion. 
3. Safe 
Example KPI: Accident Incidence Rate (AIR) 

[Performance] [Performance] [Performance] [Performance] [Performance] 
delivery 
Reportable accidents per 100,000 employed on the Project per year. 

[+%] [+%] [+%] [-%]  [-%] 
Reportable accidents are as defined by HSE 
4. Sustainable 
Example KPI: Impact on the Environment 

[Performance] [Performance] [Performance] [Performance] [Performance] 
and 
How satisfied CLRL was that the impact on the environment (such as 
responsible 

[+%] [+%] [+%] [-%]  [-%] 
pollution, noise and dust) was controlled during the Project construction 
delivery 
process, using a 1 to 10 scale where: 10 = Very effective control; 8 = 
Good control; 5/6 = Fair control; 3 = Little control; 1 = No effective control 
5. Delivery of 
Example KPI: Defects 

[Performance] [Performance] [Performance] [Performance] [Performance] 
a world-class 
The condition of the Project with respect to defects at the time of 
railway 

[+%] [+%] [+%] [-%]  [-%] 
handover, using a 1 to 10 scale where:  10 = Defect Free; 8 = Some 
defects with no significant impact on the Employer; 5/6 = Some defects 
with some impact on the Employer; 3 = Major defects with major impact 
on the Employer; 1 = Totally defective 
A defect is a fault which adversely affects the appearance or full intended 
performance and function of the product. 
 
45

 
 
Confidential 
        __________________________________________________________ 
Appendix K 
Incentives Flow Chart 
 
 
Final 
Interim Ince
rim Incentive Sch
 Scheme (Annual)
Incentive Scheme
Final
incentive
Inter
Inte i
rim
payment or
Agree
Maximum
charge (£) =
Interim KPIs
Amount =
Reserved
Amount =
and
Interim
15% of
Amount (£) = 
15% of
Final
Performance
Earned
75% Interim
anticipated
Maximum
Bands
Amount (£) =
PSPD for the
Earned Amount
PSPD for the
Amount x
Contract Year
% for
Service
ice
Calcula
lculate
performa
rformance
Delivery
using Inter
using Interim
Maximum
achieved
Plan
Plan
Incentive
char
charge =
ge =
Schedule
Interim
10% of
incentive
Agree
based on
sed on
incent
anticipated
payment (
Resource
Performa
rformance
payment £) =
PSPD for the
25% Interim
Schedule
Achieved
25% Inte
Contract Year
Earned Amount
Allocate
values (£) to
Performance
mance
Net negative
Bands
Bands
amounts
deducted from 
deducted from 
sums
sums otherwise
payable
 
46

 
 
Confidential 
        __________________________________________________________ 
Appendix L 
First Service Delivery Plan 
 
 
The requirements of the First Service Delivery Plan (FSDP) are set out below: 
 
i) 
Further definition of services; 
ii) 
Schedule of Deliverables, Key Dates and conditions; 
iii) 
Programme for services (conditions of contract clause 31.1); 
iv) Resource 
Schedule; 
v) 
Key Dates and conditions; 
vi) 
Key persons and other employees, identifying responsibilities; 
vii)  Incentive schedule (Interim Incentive Schedule); and 
viii)  Any further information required by the Employer or proposed by the 
Project Delivery Partner and agreed by the Employer. 
 
 
First Service Delivery Plan 
Schedule of Deliverables and Key Dates 
 
Deliverable 
Key Dates and 
Condition (see Note) 

Ref  Deliverable 
Draft (B) 
Final (A) 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Note - Condition of the deliverable at the Key Date: 
 
Condition A: The Project Delivery Partner's deliverable is acceptable without 
comments. 
 
Condition B: The Project Delivery Partner's deliverable is acceptable subject to 
changes or clarification requested by the Employer and the deliverable to be 
resubmitted. 
 
 
 
47

 
 
Confidential 
        __________________________________________________________ 
Appendix M  Submission Schedule Checklist 
 
The following schedule outlines the documents, schedules and other material 
Tenderers are required to submit as part of their Tender. CLRL does not warrant its 
completeness and / or accuracy and Tenderers must satisfy themselves as to the 
completeness of the tender submission. 
 
SUBMISSION SCHEDULE CHECKLIST 
Doc. Ref. 
STAGE 1 
 
Notification of actual or potential conflict of interest 
1.3 
arising 
Confidentiality Agreement 
1.4 / 4.1 
Change in circumstances 
1.5 / Table 2 / 4.1 
Notification of discrepancies and requests for 
2.1 
clarification 
Notification of confidential queries 
2.6 
Publish Stage 1 Tender 
3.1 / 4.2 / Appendix C 
Submit Hard Copy of Stage 1 Tender 
4.1 
Technical Submission 
4.1 / 4.2 / Table 2 
Previous Projects Schedule 
4.2 / 5.2 / Table 2 
Alternative Tenders 
3.5 
Response to Appendix F questions 
3.1 / Appendix F 
Proposed Interim Incentive Schedule 
4.2 / Appendix E & I 
Proposed Final Incentive Schedule 
4.2 / Appendix E & J 
Proposed Schedule of Deliverables and Target Dates 
4.2 / Appendix L 
Commercial Submission 
4.1 / 4.3 / Table 2 
Completed Staff Rates Schedule 
4.3 / Appendix E & G 
Contract Duration Resource Estimate 
4.3 / Appendix H 
Form of Tender 
4.1 / 4.4 / Table 2 / 
Appendix B 
Certificate of Bona Fide Tender 
Appendix B 
 
48

 
 
Confidential 
        __________________________________________________________ 
ITT Amendments 
Appendix B 
Qualifications to Enquiry 
3.2 / Appendix B 
Stage 1 Presentation 
2.2 / 6.3 / 6.4 
SUBMISSION SCHEDULE CHECKLIST 
Doc. Ref. 
STAGE 2 
 
Stage 2 Meeting requests and Agenda 
2.2 
Publish Stage 2 Tender 
5.1 / Appendix C 
Submit hardcopy of Stage 2 Tender 
5.1 
Expanded Technical Submission 
5.1 / 5.2 
Previous Projects Schedule 
4.2 / 5.2 / Table 2 
Alternative Tenders 
3.5 
Response to Appendix F questions  
5.2 / Appendix F 
Proposed First Service Delivery Plan 
5.2 / Appendix L 
Schedule of Deliverables and Key Dates 
5.2 / Appendix L 
Updated Commercial Submission 
5.1 / 5.3 
Completed Staff Rates Schedule 
5.3 / Appendix E & G 
Resource Estimate 
5.3 / Appendix O 
Resource Schedule 
5.3 / Appendix N 
Completed Interim Incentive Schedule 
5.3 / Appendix I 
Form of Tender 
5.1 / 5.4 / Appendix B 
Certificate of Bona Fide Tender 
Appendix B 
ITT Amendments 
Appendix B 
Qualifications to Enquiry 
Appendix B 
Stage 2 Presentation 
6.5 
POST TENDER 
Doc. Ref. 
Return of ITT 
2.1 
 
 
 
 
49

 
 
Confidential 
        __________________________________________________________ 
Appendix N  Resource Schedule 
 
Note: See separate excel file. 
 
 
Appendix O  Resource Estimate 
 
Note: See separate excel file. 
 
 
50

Crossrail