This is an HTML version of an attachment to the Freedom of Information request 'internal audit reports'.
  
 
 
 
 
 
 
 
 
 
Risk & Audit Department 
 
 
Ol ympic Delivery Authority 
Report on General IT Controls 
Reference Number – WP20 
Overall Report Rating – 
NEEDS IMPROVEMENT 
 
May 2007 
 
 

O L Y M P I C   D E L I V E R Y   A U T H O R I T Y   –   G E N E R A L   I T   C O N T R O L S  
 
Contents 
 
 
EXECUTIVE SUMMARY ..................................................................................................................................................................................................................................... 3 
OVERALL REPORT RATING ................................................................................................................................................................................................................................. 3 
KEY FINDINGS ...................................................................................................................................................................................................................................................... 3 
KEY ACTION ITEMS ............................................................................................................................................................................................................................................. 6 
BACKGROUND...................................................................................................................................................................................................................................................... 8 
CONTEXT .............................................................................................................................................................................................................................................................. 8 
OBJECTIVES AND SCOPE ...................................................................................................................................................................................................................................... 8 
APPROACH............................................................................................................................................................................................................................................................ 9 
A. GOVERNANCE ............................................................................................................................................................................................................................................... 10 
B. IT CONTROL ENVIRONMENT ................................................................................................................................................................................................................... 16 
C. THIRD PARTY MANAGEMENT ................................................................................................................................................................................................................. 21 
APPENDIX A:  OVERALL REPORT RATING DEFINITION ...................................................................................................................................................................... 25 
APPENDIX B:  RISK MATRIX CRITERIA ..................................................................................................................................................................................................... 26 
APPENDIX C:  PRIORITISATION OF FINDINGS AND ACTION ITEMS ................................................................................................................................................ 28 
 
 
 
 
 
 
 

 

O L Y M P I C   D E L I V E R Y   A U T H O R I T Y   –   G E N E R A L   I T   C O N T R O L S  
 
Executive Summary  
The  objective  of  this  audit  was  to  examine  the  general  IT  control  environment  and  assess  whether  it  provides  a  reliable,  secure  and  effective 
control framework for the processing of key information needed by the organisation and other stakeholders. 
Overall Report Rating 
This  report  has  been  given  an  overall  report  rating  of  “Needs  Improvement”  in  accordance  with  the  Risk  &  Audit  report  definition  criteria  as 
outlined in Appendix A.  The “Needs Improvement” rating was assigned because of the number of major issues identified, particularly in relation 
to: 
• 
consultation and communication between the business and IT department on programme decisions which have an IT impact 
• 
the contractual arrangements with, and management of, third party contractors 
Management were aware of these control weaknesses which may have resulted from the rapidly evolving operating environment and, prior to the 
audit,  management  had  commenced  some  mitigation  activities.    However,  we  noted  that  whilst  the  overall  assessment  of  the  IT  control 
environment relating to user access and change management was satisfactory, some minor process improvements were identified in this area.   
Key Findings 
There  is  insufficient  communication  between  senior  management  and  the  IT  department  in  relation  to  programme  issues  and  decisions  which 
may have an IT impact.  As a result the IT department may not be fully aware of the impact on IT of decisions made at a high level, in a timely 
manner.    Within  the  procurement  and  contract  negotiation  process  there  has  been,  and  continues  to  be,  limited  involvement  of  IT  specialists.  
Typically  IT  specialists  have  been  consulted  at  a  late  stage  or  have  not  been  fully  integrated  into  the  process.    This  has  resulted  in  a  lack  of 
effective means by which the ODA  can manage  and monitor the  third  party contractors  going  forwards.   We noted that there are a number of 
existing contracts which have inadequate clauses relating to IT governance, such that the ODA may encounter problems in the future with regard 
to enforcement of policies and procedures, and rights of access to gain assurance that adequate IT controls are in place. 
In addition, the ODA has not yet put in place a framework of policies and procedures relating to the management and monitoring of third parties, 
from an IT perspective.  Going forwards, this may result in inconsistencies and informality in the processes for managing third parties, increasing 
the likelihood of non-compliance with ODA IT polices and procedures. 
 
 
 
 
 
 
 

 

O L Y M P I C   D E L I V E R Y   A U T H O R I T Y   –   G E N E R A L   I T   C O N T R O L S  
 
Governance of IT, in particular the IT strategy and budgeting process, is not robust.  The IT Governance arrangements are in the process of being 
negotiated with CLM, the Delivery Partner.  The roles and responsibilities of the ODA and CLM IT departments are still to be agreed, with initial 
indications of ODA IT retaining responsibility for internal IT and provision of advice to the programme at a project sponsor level.  We noted that 
the IT budget is developed without full consideration of the detailed costs and alignment with a formal IT strategy.  A draft IT strategy (ODA IT 
Vision) document was developed in 2006 however, this was not approved.  This strategy has a number of deficiencies and has not been updated 
to reflect recent and significant organisation developments within the ODA.  
 
Key Risks 
The key risks identified during the course of the project are illustrated in the matrix below.  ODA’s Risk Management Framework was used to 
rate the identified risks, and is outlined in Appendix B.  The below matrix plots all the risks associated with findings described throughout the 
body of this report.  The risks with an overall severity rating of major are summarised in the table below for your reference.   
 
Risk Matrix 
                                                                         Likelihood 
Rare 
Unlikely 
Possible 
Likely 
Almost 
Consequence 
Overall Risk Severity  
Certain 
 
Fundamental 
Fundamental 
 
 
 
 
 
 
Major 
Major 
 
 
C1, C2 
A2, C3 
 
 
Moderate 
 
Minor 
A3, A5,  
Moderate 
 
A1, A4 
 
 
B1, B2 
 
Insignificant 
 
Minor 
 
B3 
 
 
 
Insignificant 
 
 
 
 
 
 
 
 
 
 
 
 
 

 

O L Y M P I C   D E L I V E R Y   A U T H O R I T Y   –   G E N E R A L   I T   C O N T R O L S  
 
 Major Risks 
Ref 
Summary Finding 
Summary Risk 
Report Page 
Ref 
A2 
Lack of timely communication with IT. 
There is a risk that business decisions may be made without full 
P12 
understanding of the associated IT related risks.  Lack of timely 
communication may mean that IT is not fully aware of projects with an IT 
impact, or of potential issues which may impact the overall programme.  
This may result in the need to handle IT requests at short notice, potentially 
impacting IT work on other parts of the programme and potential unplanned 
and more expensive IT expenditure.  In extreme cases, due to the lack of 
notice, it may not be possible to address the issues and provide adequate IT 
services and solutions to meet the organisational requirements.   
C1/C2  Limited IT contractual requirements in 
ODA and its contractors may not comply with government legislation e.g., 
P21, 22 
existing contracts and limited IT 
Freedom of Information Act (FOIA), Data Protection Act (DPA), as well as 
engagement in the procurement and 
National Archive (TNA) requirements resulting in reputational impact and 
contract negotiation process 
financial penalties.  In addition, the third parties may not comply with ODA 

policies, procedures and standards.  
ODA may have limited remit to enforce IT polices and procedures on third 
party contractors, potentially resulting in IT control weaknesses and 
reputational impact, as well as increased costs and inefficiencies.  
C3 
Lack of processes and procedures for 
ODA may be unable to adequately manage and monitor third party 
P24 
monitoring third parties 
contractors; potentially resulting in non-compliance with ODA policies and 
 
procedures, potentially resulting in security breaches and reputational 
impact. 
 
 
 
 
 
 
 
 

 

O L Y M P I C   D E L I V E R Y   A U T H O R I T Y   –   G E N E R A L   I T   C O N T R O L S  
 
Key Action Items 
Detailed action items are included throughout the body of this report.  ODA’s Risk Management Framework was used to rate identified risks, and 
the criteria used to prioritise findings and action items is outlined in Appendix C.  In addition, the below table provides a summary of the high 
priority action items.   
Ref 
High Action Items 
Agreed Implementation Date 
Primary 
Secondary 
Report Page Ref 
Responsibility for 
Responsibility for 
Action Item 
Action Item 
A2 
Whilst the IT department is making significant efforts to 
June 2007 
Dennis Hone, 
Simon Pitt, Head of  P12 
align its function to the business environment by assigning 
Director of Finance 
IT 
project managers to specific areas of the business, this 
and Corporate 
approach should be formalised within the IT strategy 
Services 
document and communicated to stakeholders.  The IT 
strategy document should include the IT department’s 
approach to communication, including its IT spend 
decision making process, to make this transparent to the 
wider organisation and to facilitate more timely 
consultation with IT. 
A2 
The IT department and wider ODA need to take joint 
June 2007 
Dennis Hone, 
N/A 
P12 
responsibility to work together to communicate and 
Director of Finance 
consult on IT topics on a timely basis.  This responsibility 
and Corporate 
can be championed by the Director of Finance and 
Services 
Corporate Services, to raise awareness and promote the 
two way communication and engagement between the IT 
department and wider ODA, to facilitate the IT planning, 
procurement and budgeting process. 
C1 
ODA should finalise relevant IT policies and procedures 
July 2007 
Dennis Hone, 
Simon Pitt, Head of  P21 
and formally issue these to third party contractors as soon 
Director of Finance 
IT 
as possible. 
and Corporate 
Services 
C1 
The IT requirements within existing contracts (other than 
July 2007 
Dennis Hone, 
Simon Pitt, Head of  P21 
the Remediation Demolition contract) and projects should 
Director of Finance 
IT 
be identified and, where considered relevant based on a 
and Corporate 
formal risk assessment, arrangements should be put in 
Services 
place for monitoring the provision of these IT services by 
the third parties. 
 
 
 
 
 
 
 

 

O L Y M P I C   D E L I V E R Y   A U T H O R I T Y   –   G E N E R A L   I T   C O N T R O L S  
 
Ref 
High Action Items 
Agreed Implementation Date 
Primary 
Secondary 
Report Page Ref 
Responsibility for 
Responsibility for 
Action Item 
Action Item 
C2 
Procurement should engage IT within the procurement and  May 2007 and onging  
Morag Stuart, Head 
Simon Pitt, Head of  P22 
contract negotiation process.   
of Procurement 
IT 
C2 
The ODA IT department should continue liaising with the 
May 2007 
Simon Pitt, Head of 
Celia Carlisle, 
P22 
legal teams to identify and agree standard terms and 
IT 
Head of Legal 
contracts to enable adequate clauses in relation to IT to be 
included within contracts going forwards.  The use of such 
clauses should be determined based on a review of the 
associated risks and benefits to the ODA so that a 
balanced and cost effective approach can be taken.   
C3 
Whilst contractors are contractually responsible for 
July 2007 
Dennis Hone, 
Simon Pitt, Head of  P24 
management of the IT services and solutions required to 
Director of Finance 
IT 
support the provision of procured services, IT 
and Corporate 
management should assess the risks associated with the 
Services 
loss of data, or security breaches of contractor IT systems, 
and the level of oversight they should retain over the 
contractors’ IT environments.   
C3 
IT should develop third party management and monitoring 
July 2007 
Dennis Hone, 
Simon Pitt, Head of  P24 
policies and procedures as soon as possible and implement 
Director of Finance 
IT 
these for key third parties.  This should include the 
and Corporate 
development of a third party audit plan, based on an 
Services 
assessment of associated risk. 
 
 
 
 
 
 
 

 

O L Y M P I C   D E L I V E R Y   A U T H O R I T Y   –   G E N E R A L   I T   C O N T R O L S  
 
Background 
Context 
The Olympic Delivery Authority (ODA) has been set up to deliver new venues and infrastructure in time for the 2012 Olympic and Paralympic 
Games  (“London  2012”).    The  ODA  works  alongside  the  London  Organising  Committee  for  the  Olympic  Games  and  Paralympic  Games 
(LOCOG) which will organise, publicise and stage the London 2012 Games.  LOCOG and the ODA operate as discrete organisations, however 
they work closely together and share offices and Information Technology (IT) infrastructure. 
The current IT environment at the ODA is under development.  During the last 12 months IT related projects have been undertaken to assess and 
develop  the  IT  infrastructure  at  the  ODA.    The  IT  environment  is  complicated  as  it  must  dovetail  with  CLM  who  are  engaged  to  provide 
programme and project management experience and to implement a suite of supporting IT function s to achieve joint ODA/CLM objectives.  
In  April  2006,  an  Initial  IT  Security  Situation  Assessment  was  performed  by  Ernst  &  Young  to  understand  the  ODA’s  current  IT  security 
requirements.  This identified “quick wins” that the ODA should implement to improve its current IT security controls and “next steps” that the 
ODA should perform in order to further enhance and maintain its IT security controls as it evolves and develops over the coming year. 
During  the  summer  of  2006  a  project  was  undertaken  to  identify  the  requirements  and  procure  the  ODA  Back  Office  Systems  and  Services 
(BoSS).  Following from this, Fujitsu have been selected to implement and manage the identified BoSS, with an expected delivery date of June 
2007.   
Objectives and Scope 
This review examined the general IT control environment and assessed if it provides a reliable, secure and effective framework for the processing 
of key information needed by the organisation and other stakeholders. 
The review examined the existence and operation of key controls since 1 April 2006 in the areas listed below.   
The scope of this review was reduced to the extent that we were able to rely on ODA relevant controls assessed as part of the LOCOG external 
financial audit.  The scope included the following areas: 
• 
Overview of the IT function 
• 
IT Governance 
• 
Programme governance and management  
 
 
 
 
 
 
 

 

O L Y M P I C   D E L I V E R Y   A U T H O R I T Y   –   G E N E R A L   I T   C O N T R O L S  
 
• 
Third party management 
• 
Access Controls 
• 
Software / Systems Development 
• 
System and Network Security Controls 
• 
Problem and incident management 
• 
Physical and Environmental Controls 
• 
Back Ups, Contingency Planning and Disaster Recovery 
Out of scope of this review were any controls or systems that have been implemented for LOCOG.  Specifically, we did not perform a review of 
the Information Management systems which are being implemented for LOCOG, which are to be used by the ODA. 
Approach 
This project was conducted in accordance with the Risk & Audit Department’s audit methodology.  The approach included: 
  Interviews  with  IT  and  business  personnel  responsible  for  applications  within  the  user  departments  (as  agreed  with  Simon  Pitt,  the 
nominated key contact within the ODA IT department).   
  Review of external audit documentation of the IT control environment prepared as part of the LOCOG external audit, and confirmation of 
controls for the ODA through inquiry. 
  Review of relevant, available documentation. 
  Process or control walkthroughs were performed to help validate information gained through management discussions. 
 
 
 
 
 
 
 
 

 

O L Y M P I C   D E L I V E R Y   A U T H O R I T Y   –   G E N E R A L   I T   C O N T R O L S  
 
A. Governance 
IT  Governance  helps  provide  stakeholders  and  IT  management  with  comfort  that  IT  is  aligned  to  short  and  long  term  business  goals  and 
priorities.    Effective  IT  Governance  requires  the  support  of  senior  management  within  an  organisation,  particularly  when  making  business 
decisions  that  potentially  have  an  IT  impact.    In  making  business  decisions,  IT  related  risks  should  be  considered  and  decisions  should  be 
communicated  to  IT  in  a  timely  manner  to  enable  IT  management  to  adequately  plan  and  budget  for  support  and  resource  requirements.  
Underpinning effective IT governance is an up to date IT strategy.  The IT strategy should be aligned to the organisation’s business strategy and 
should include areas such as the definition of IT principles that guide IT decision making, the current and future IT state and competencies, and 
the IT operating model and governance structure.  In addition, the IT strategy should define the organisation’s transformation plan for achieving 
the desired future state of IT.  
The ODA IT governance processes and operating environment is currently in a state of significant change.  The ODA is currently working with 
CLM, their Delivery Partner, to negotiate and clarify the IT related roles and responsibilities of the ODA and CLM, IT Governance arrangements 
and  an  overall  IT  strategy.    For  the  ODA,  the  time  critical  nature  of  the  programme  is  a  significant  factor  to  consider  in  the  IT  Governance 
arrangements and decision making processes.   
It  is  understood  that  the  ODA  IT  department  is  to  be  responsible  for  the  provision  of  the  internal  IT  at  the  ODA  and  to  provide  advice,  at  a 
project sponsor level, regarding IT services and solutions within other areas of the programme.  CLM will project manage IT implementation for 
Programme related IT.  Management represented that an Integration Manager is being appointed to oversee the IT services and solutions to be 
provided for contractors on the Olympic Park.   
 
 
Finding 
Action Items 
Management Response 
A1  IT Budgeting and Lack of IT Strategy 
1.  The IT Strategy should be modified to 
Primary Action Item Owner: Dennis Hone, Director 
IT budgeting and forecasting of IT spend is not 
accommodate recent developments (eg, 
of Finance and Corporate Services 
currently aligned with an overall IT strategy.  In 2006, 
appointment of CLM and Fujitsu) and specifically 
Secondary Action Item Owner: Simon Pitt, Head of 
the ODA developed an IT Strategy (ODA “IT Vision, 
extended to include the following: 
IT 
Aim, Objectives and Key Principles Guidance for Third 
• 
Governance of IT  
 
Party Contractors”), which remains in draft and has not 
• 
Decision making processes, specifically in 
been approved.  Since this strategy was drafted, there 
Implementation Date: June 2007 
respect of investment 
have been significant developments (eg. appointment of 
 
CLM, appointment of Fujitsu to deliver back office 
• 
Alignment of ODA, CLM, Fujitsu and others 
Comments:  
systems).  It is understood that this draft strategy 
in delivering IT projects and services. 
document will now form the basis of a new ODA IT 
In addition, the revised IT Strategy document 
The ODA deferred the finalization of the IT strategy 
strategy which is being developed in conjunction with 
should be approved by the EMB.  
until certain strategies in many business areas were 
the Delivery Partner, CLM. 
developed; and CLM had agreed and justified the 
This strategy should then be used to drive the IT 
business and IT programme in place.  The current IT 
 
 
 
 
 
 
 
10 
 

O L Y M P I C   D E L I V E R Y   A U T H O R I T Y   –   G E N E R A L   I T   C O N T R O L S  
 
Finding 
Action Items 
Management Response 
Discussions about the approval of IT spend indicated 
budget and guide the IT project prioritisation and 
strategy and CLM/ODA programme of IT work will be 
that this is typically performed on a project by project 
IT spend decision making process. 
updated and approved by the EMB. 
basis.  While scheduled projects may appear on the 
2.  Refer to recommendations from the Business 
 
annual budget with an allocation, there are a large 
Planning Review, relating to process improvements 
The IT Budget is an amalgamation of CLM and ODA 
number of unscheduled projects for which IT spend is 
in the budget process and re-forecasting process.  
activity with the Head of IT acting as Project Sponsor 
required to be approved and this is made via the 
Such improvements can assist in obtaining clear 
and CLM taking on the Project Manager role for 
Executive Management Board.  It is understood that 
oversight of the annual IT budget and monitoring 
programme support IT.  For 2006/07 (start up) budget 
there is limited provision made within the IT budget for 
performance against this.   
processes were by necessity based on broad estimates 
such unscheduled projects and that these are reviewed 
3.  Going forwards, a sufficient discretionary project 
and affordability criteria, however the agreed 
and approved on a case by case basis.  This situation is 
budget should be allocated out of the agreed IT 
programme of work between CLM and ODA now 
understood to be common across the ODA as a result of 
budget to fund unplanned IT projects and 
provides a factual basis for further budgeting.   
the ODA being within the start up phases in 2006-07 
requirements.   
and in the initial stages of working with CLM.  
See responses to A2. 
4.  To gain a clearer view of the cost of IT, the IT 
In addition, IT spend is frequently subsumed within 
department should: 
wider third party contracts and the ODA IT department 
may be unaware of the full cost of IT to the 
• 
Actively engage in the Procurement process 
organisation.  A clearer view of the cost of IT could be 
(refer to Finding B1) to gain oversight of 
determined by reviewing the budgets in these contracts. 
proposed IT spend in contracts.   
 
• 
Review IT spend within existing third party 
contracts and projects and, where considered 
Risks:   
relevant based on risk assessment and 
Without adequate controls around the IT budget process 
resource prioritisation, arrangements should 
and allocation, and lack of alignment with an overall IT 
be put in place for the ODA to maintain 
strategy, there is an increased risk that IT demands on 
oversight of the third party IT spend.   
the overall budget may be higher than stakeholder 
 
expectations or else may result in reduced budget 
allocation to scheduled projects due to the uncertainty 
Action Item Priority: Medium 
around unplanned projects and the need to retain a 
contingency budget.  This is particularly of concern due 
to the number of IT projects identified within the work 
streams.  Business cases for these IT projects may be 
developed and spend approved without a strategic view 
of the provision of IT services.  This may lead to a 
fragmented and inefficient IT environment.  Further 
complexity within the IT environment may arise due to 
the lack of visibility over IT spend within contracts. 
 
Risk Severity Rating: Moderate 
 
 
 
 
 
 
 
 
 
11 
 

O L Y M P I C   D E L I V E R Y   A U T H O R I T Y   –   G E N E R A L   I T   C O N T R O L S  
 
Finding 
Action Items 
Management Response 
A2  Lack of Timely Communication with IT 
1.  Whilst the IT department is making significant 
Primary Action Item Owner: Dennis Hone, Director 
Based on our discussions with IT management, we 
efforts to align its function to the business 
of Finance and Corporate Services 
understand that there have been occasions when there 
environment by assigning project managers to 
Secondary Action Item Owner: Simon Pitt, Head of 
has been a lack of timely communication with IT.  This 
specific areas of the business, this approach should 
IT 
has resulted in IT being informed, at short notice, of the 
be formalised within the IT strategy document and 
 
requirement for the provision of IT services.  For 
communicated to stakeholders (Refer to Finding 
example, the provision of IT services to CLM staff who 
A1).  The IT strategy document should include the 
Implementation Date: June 2007 
were relocated to Lee Valley sports centre and to the 
IT department’s approach to communication, 
 
Galliford-Try Site Office. 
including its IT spend decision making process, to 
make this transparent to the wider organisation and 
Comments:  
 
to facilitate more timely consultation with IT. 
CLM and ODA IT have agreed a governance structure 
Risks:   
2.  The IT department and wider ODA need to take 
for IT and are in the process of finalising an “IT 
Without IT consultation at early stages in an initiative, 
joint responsibility to work together to 
Strategy and Work Programme” for presentation to the 
there is a risk that business decisions may be made 
communicate and consult on IT topics on a timely 
ODA EMB on 16 May 2007. 
without full understanding of the IT related risks.  
basis.  This responsibility can be championed by 
The Director of Finance and Corporate Services  has 
Additionally, without timely communication and 
the Director of Finance and Corporate Services, to 
already taken action to set up a working group to 
consultation of IT, there is a risk that the IT department 
raise awareness and promote the two way 
effectively embed IT and other corporate functions into 
may not be fully aware of and informed at an early 
communication and engagement between the IT 
appropriate decision making processes. 
stage of projects where there may be IT impact, or of 
department and wider ODA, to facilitate the IT 
  
potential issues which may impact the overall 
planning, procurement and budgeting process. 
programme.  The lack of IT involvement at early stages 
 
may also result in the need to handle IT requests at short 
notice, potentially resulting in resource being redirected 
Action Item Priority: High 
from other tasks, impacting and delaying other parts of 
the programme and increasing the likelihood that IT 
services and equipment need to be procured at short 
notice.  This may result in unplanned and potentially 
more expensive IT expenditure due to the short time 
scales.  In extreme cases, due to the lack of notice, it 
may not be possible to address the issues and provide 
adequate IT services and solutions to meet the 
organisational requirements.   
 
Risk Severity Rating: Major 
 
 
 
 
 
 
 
12 
 

O L Y M P I C   D E L I V E R Y   A U T H O R I T Y   –   G E N E R A L   I T   C O N T R O L S  
 
Finding 
Action Items 
Management Response 
A3  Existence of Draft IT Policies and Procedures 
1.  The policy and procedure documents should be 
Primary Action Item Owner: Simon Pitt, Head of IT  
A number of the ODA policies and procedures eg, the 
finalised and approved at the earliest opportunity 
Secondary Action Item Owner: N/A 
Information Systems Acceptable Use Policy - Code of 
and should be issued to third party contractors.     
 
Practice, Dormant Account Policy, and Disaster 
2.  IT induction and awareness training should be 
Recovery policy, have been drafted but not finalised 
performed for staff and contractors.  The 
Implementation Date: May 2007 
and approved.  At the time of the audit, the ODA were 
Information Systems Acceptable Use Policy - Code 
 
in the process of reviewing the ODA policies and 
of Practice should also be issued to ODA staff and 
Comments:   
procedures to make them more applicable to the ODA 
contractors and they should be required to sign up 
situation with regard to reliance on third party 
to agree that they will comply with this. 
Policies will continue to be revised in line with the 
contractors.  The IT department has recently recruited 
changing business environment. 
 
an IT security manager who is revising these to reflect 
An updated Information Security Policy is now in place. 
the ODA’s role and that of the third party contractors. 
Action Item Priority: Medium 
This policy was approved by the Information Security 
We also noted that staff and contractors do not currently 
Working Group on the 13/4/07. As from April 2007, all 
receive IT induction and awareness training. 
induction packs contain an Information Security 
Awareness Booklet.  
 
All new inductees (both permanent and contractors) will 
Risks:   
be shown an Information Security presentation as part 
If these documents are not finalised and approved, ODA 
of their roles. In addition, an Information Security 
staff and contractors may not comply with the policies 
Awareness Programme is being developed to educate 
and procedures.  This may result in, for example, 
all staff permanent and contractors. 
weaknesses in IT security arrangements, inappropriate 
use of the IT systems by staff and contractors and 
inadequate provision of disaster recovery services. 
 
Risk Severity Rating: Moderate 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
13 
 

O L Y M P I C   D E L I V E R Y   A U T H O R I T Y   –   G E N E R A L   I T   C O N T R O L S  
 
Finding 
Action Items 
Management Response 
A4 Regulatory Compliance Policies and Procedures 
1.  Regular training and education sessions should be 
Primary Action Item Owner: Celia Carlisle, Head of 
The ODA policies and procedures in relation to 
held to increase staff awareness of the FOIA and 
Legal  
compliance to the Freedom of Information Act (FOIA) 
DPA and their responsibilities in relation to the 
Secondary Action Item Owner: Pieter De Waal, 
were approved by the ODA Board at the Board Meeting 
acts.  
Project Manager - Legal  
on 25 January 2007.  Although key staff handing FOIA 
2.  Policies and procedures relating to the acts should 
 
requests were aware of the approved FOIA policies and 
be finalised, where applicable, and circulated to 
procedures, there was limited circulation of these 
staff, as appropriate.  
Implementation Date:  July 2007 
policies and procedures to staff generally. In addition, 
Action Item Priority: Medium 
 
the ODA policies and procedures for compliance with 
Comments:   
the Data Protection Act (DPA) had not yet been 
finalised and approved.  Whilst training and awareness 
The ODA are updating the intranet procedures and are 
had been provided to ODA employees and contractors 
also adding an easy to use step-by-step handling 
in 2006, some staff eg, new joiners, may be unaware of 
procedure.  There is a Freedom Of Information (FOI) 
the procedures to follow in relation to the FOIA and 
help page for staff on the intranet which is to be more 
DPA. 
visible and easier to read when the Intranet is 
redesigned. There is an FOI page on the external 
Risks:   
website and requests are routed to the Communications 
There is a risk that employees and contractors of the 
department to be assessed and managed. This is to be 
ODA may receive requests for information but may be 
made more prominent when the website is redesigned. 
unaware of their significance and hence appropriate 
As a result of a change of personnel handling the FOI 
action may not be taken within the timescales required.  
requests in the Communications team, processes were 
This may result in breaches of the FOIA and the DPA, 
formalised and improved with assistance from the Legal 
potentially resulting in legal action against the ODA. 
team. A dedicated FOI resource is to be appointed 
 
within the legal team who will take over the 
Risk Severity Rating: Moderate 
responsibility for FOI administration and processing.  
The processes may then need some minor adjustment. 
Further FOI staff training is planned. This will be 
performed by the Legal and Communications teams.  
The presentations have already been prepared. There 
are also plans to raise FOIA awareness via input into 
the HR "arrivals manual" for new joiners. 
The ODA has recently appointed a Records Manager 
and they will take on responsibility for Data Protection 
Act (DPA) compliance, including the development of 
policies and procedures.  It is expected that DPA 
awareness will be incorporated into the awareness 
programme for FOI. 
The implementation date of July 2007 is dependent on 
website re-launch and how quickly the legal department 
is able to acquire the additional resource. 
 
 
 
 
 
 
 
14 
 

O L Y M P I C   D E L I V E R Y   A U T H O R I T Y   –   G E N E R A L   I T   C O N T R O L S  
 
Finding 
Action Items 
Management Response 
A5  Scope for Improving  IT Project Management 
1.  We support IT management in formalising their 
Primary Action Item Owner: Simon Pitt, Head of IT  
Processes 
approach to managing IT projects consistently.  
 
The approach to managing IT projects is an area that 
There is scope for improvements in the tracking 
Implementation Date: May 2007 
has been under development over the last twelve 
and documentation of IT projects.  IT management 
months.  Scheduled projects appear in the approved 
should formalise the IT project process (including 
 
budget and a spreadsheet is maintained of smaller 
EMB approval) to clarify the documentation 
Comments:   
projects. The documentation of the projects is an area 
requirements for individual projects, and should 
The comments are taken positively.  Historic projects 
that is being improved, with the Project Manager now 
review compliance with this process on a periodic 
may not have had all formal documentation in place – a 
requiring scoping documents, approved budgets and 
basis.  
conscious decision was taken to not “back date” this 
Project Closure reports, requiring sign off from key 
2.  For budget review and audit purposes (Refer to 
documentation as many of the “projects” were small 
stakeholders.  At the time of the audit, the process had 
Finding A1), IT management should consider 
internal “packets of work” with no external costs or low 
not been formally documented and approved, and was 
retaining a log of those scheduled and unscheduled 
impact.   
not being consistently applied. 
projects that have been completed and formally 
All new Projects should comply with a formal PID and 
 
closed. 
PCR. The definition of an IT “project” needs 
clarification.  It is agreed that an “IT Project Process” 
 
 
summary document be drawn up to help clarify the 
Risks:   
Action Item Priority: Medium 
processes, definitions, reporting requirements and 
Without clear tracking and documentation of project 
project initiation, tracking and closure. 
scope and closure, there is a risk that the scope, risks 
and interdependencies of IT projects may not be clear 
and may not meet the project sponsor’s requirements, 
with potential financial and time implications.   
 
Risk Severity Rating: Moderate 
 
 
 
 
 
 
 
 
 
15 
 

O L Y M P I C   D E L I V E R Y   A U T H O R I T Y   –   G E N E R A L   I T   C O N T R O L S  
 
B. IT Control Environment 
The ODA IT environment is currently undergoing significant change, with CLM, the Delivery Partner, expected to take on a significant role in 
the  delivery  of  IT  services  to  the  ODA  going  forwards.    The  IT  solutions  currently  in  use  at  the  ODA  are  interim  arrangements,  involving 
significant use of spreadsheets, which are expected to be replaced during the next twelve months.  
The ODA is currently in the process of implementing a Back Office System and Service, in conjunction with the third party, Fujitsu.  As such the 
OpenAccounts finance application is to be replaced by Oracle Financials.  This system is also to replace the existing IT solutions supporting the 
HR and procurement processes.   CLM is also planning to implement Active Risk Manager to replace the existing spreadsheets that support the 
Risk Management process.  Other planned system implementations include the Electronic Document and Records Management (EDRM) system 
and Enterprise Content Management system which are expected to be implemented in 2007. 
 
Finding 
Action Items 
Management Response 
B1  Weak User Access Controls 
1.  We understand that the OpenAccounts system is to 
1. Primary Action Item Owner: SianWilliams, Head 
Within OpenAccounts, a number of weaknesses in user 
be replaced by Oracle Financials and that through 
of Finance 
access controls were identified.  It is understood that 
this implementation the issues identified in relation 
Secondary Action Item Owner: N/A 
issues were also identified in the “Banking, Receipt and 
to OpenAccounts, in both this review and the 
 
Payment review”.  Whilst remediation was put in place 
“Banking, Receipt and Payment review” are to be 
following that review, these new processes need to be 
addressed.  However, Finance should: 
Implementation Date: May 2007 
embedded and incorporated into day to day joiner, 
•  Confirm interim controls are consistently 
 
leaver and mover processes: 
implemented until Oracle controls are 
Comments:  
operating. 
• 
There are no formalised procedures for 
The Financial Systems Accountant is to train another 
authorising new users, amending their access 
•  Segregate the roles of user administration and 
member of the team, the Financial Controller, to run the 
levels or deleting user profiles when an employee 
review of user access. 
reports for the review of user access.  Having two 
changes role or leaves the organisation.   
•  On a periodic basis, review user access to 
people skilled to run the necessary reports will facilitate 
• 
There are weaknesses in the password controls, 
validate that the access rights to the IT systems 
consistent and ongoing control implementation.   The 
such that users are not required to change their 
and network remain in line with users’ job roles 
Financial Controller will also review the reports on a 
password on first login and there is no minimum 
and to identify redundant accounts. 
monthly basis and pass to the Head of Finance for 
length or password complexity enforced due to 
•  Review the user accounts and profiles present 
formal sign off.  
limitation in the application. 
within the system and disable/remove those 
Management have reviewed the identified redundant 
• 
There is no segregation of duties between the 
which are not necessary for the operation of the 
accounts, and identified the following: 
roles for user administration and the review of 
application and are not used by the business.  
user access. 
This is particularly important due to the 
• 
Demo: (Demonstration User):  This is used for the 
TEST environment, and Open Accounts help desk 
implementation of the new Oracle system to 
• 
A number of generic profiles and accounts (i.e. 
use when helping sort any problems (proxy in). 
reduce the likelihood that, during the 
 
 
 
 
 
 
 
16 
 

O L Y M P I C   D E L I V E R Y   A U T H O R I T Y   –   G E N E R A L   I T   C O N T R O L S  
 
Finding 
Action Items 
Management Response 
accounts not owned by a single person) are 
implementation process, additional user 
Password on Demo will only be known to systems 
present within the application. 
accounts are not set up.   
accountant.  
We also noted that there are no formal processes around 
2.  IT should formally establish and communicate 
• 
NAO1: set up for NAO.   Management discussed 
the removal of users at the network level.  This includes 
procedures for terminating a former employee’s 
this account with NAO but as the account cannot 
the access controls for the private directories for the 
access to the organisation’s systems and network. 
be used to edit anything they felt it is ok. 
individual departments.  In addition, the access to the 
The IT team and system administrators should be 
• 
POP1, POP2: These accounts have now been 
Private directories is not reviewed on a periodic basis. 
promptly informed when an employee leaves the 
deleted 
We noted that, at the time of the audit, there were three 
organization. This procedure should be 
The Financial Systems Accountant will put in place a 
users on the access control list for the Procurement 
accompanied by the appropriate supporting 
process for new user requests, a form will be completed 
department, who had left the organisation over 25 days 
documentation. 
and then signed by Head of Finance before user is set 
previously, one of whom was a user unknown to the 
3.  With the implementation of Oracle, IT should take 
up. 
Head of Procurement and the Procurement Manager.  In 
the opportunity to introduce formal access control 
mitigation, a dormant account policy is enforced, which 
procedures and enforce password controls in line 
 
requires accounts that have not been used for 21 days to 
with the ODA IT Security policy for the Oracle 
2 & 3. Primary Action Item Owner: Simon Pitt, Head 
be disabled. 
system.  We understand that due to the current size 
of IT 
Risks:   
of the finance function of the ODA, it has been 
Secondary Action Item Owner: N/A 
possible to communicate user administration 
The risks arising from weak user access controls: 
changes for OpenAccounts by word of mouth.  
 
• 
It may be possible for someone to request a user 
However, as the organisation grows, these 
Implementation Date: August 2007 
account to be set up in relation to a different job 
procedures become more unmanageable.  The new 
 
role or function to their own, thus resulting in 
Oracle system is to support business processes 
users being granted an inappropriate level of 
within multiple departments, including HR, 
Comments:  
access to the system, or leading to circumvention 
procurement, as well as finance.  Therefore, the 
Oracle Finance will go live in June 2007, single sign on 
of segregation of duties controls.   
user base for Oracle will be larger and more 
to Oracle via active directory will be implemented by 
complex, increasing importance of implementing 
• 
Without user termination and regular user access 
August 2007.  This will centralise the administration of 
strong user access controls around the new system.  
review processes, there is a risk that redundant 
access controls within the IT Team. The processes 
User access requests can take the form of emails or 
profiles may be left on the system for a period 
which are applied to all other user access to ODA 
be made on a standard form, authorised by 
after an employee has left the organisation or 
systems will then apply.  
specified individuals within individual departments 
users may have excessive access rights to data 
and should be retained by the appropriate systems 
The leavers process has been in place for some time and 
held on the systems, thus creating an exposure to 
administrator as an audit trail. 
has operated centrally for all systems other than Cedar 
unauthorised access attempts and data 
Open Accounts.  However processes will be formalised 
modification.  This leads to an increased risk of 
 
across ODA.   
fraud, loss of service of IT systems, and financial 
Action Item Priority: Medium 
 
loss.   This is particularly of concern due to the 
large number of contractors within the ODA. 
  
• 
Weaknesses in password controls can compound 
the risks associated with deficiencies in the user 
access removal processes. 
• 
The lack of segregation of duties between the user 
administration and access review processes 
 
 
 
 
 
 
 
17 
 

O L Y M P I C   D E L I V E R Y   A U T H O R I T Y   –   G E N E R A L   I T   C O N T R O L S  
 
Finding 
Action Items 
Management Response 
permits the user administrator to grant themselves 
or other users’ unauthorised privileges within the 
system and then remove the corresponding entries 
from the access/activity report.  Such access, and 
potential associated malicious activity, may then 
go unnoticed by management.  This may lead to 
the confidentiality and integrity of business 
information being compromised and loss of 
system availability.  This increases the risk of 
sabotage, damage to reputation and potentially 
financial loss and fraud. 
• 
If someone is able to directly log into a generic 
account, as this is not assigned to an individual, 
there is reduced user accountability for activities 
performed.  This may encourage unauthorised and 
malicious activity and the lack of accountability 
means that it is difficult to identify and stop those 
causing errors or irregularities. 
 
Risk Severity Rating: Moderate 
 
 
 
 
 
 
 
18 
 

O L Y M P I C   D E L I V E R Y   A U T H O R I T Y   –   G E N E R A L   I T   C O N T R O L S  
 
Finding 
Action Items 
Management Response 
B2  Lack of Logging and Monitoring of Log Files on 
1.  IT should enable the ‘Audit Object Access’ 
Primary Action Item Owner: Simon Pitt, Head of IT 
OpenAccounts Server 
function to facilitate monitoring of critical files and 
Secondary Action Item Owner: N/A 
We noted that on the CPAP01 server hosting the 
directories. 
 
OpenAccounts application that the ‘Audit Object 
2.  IT should implement procedures for the regular 
Access’ function is not enabled.  Security logs are 
review of security and audit logs for the critical 
Implementation Date: June 2007 
cleared too frequently and there is no regular review of 
application servers. 
 
the security logs.  In addition, system audit logs are not 
3.  Log retention policies should be adjusted to assist 
Comments:   
reviewed on a regular basis. 
with such reviewing.  Logs should be backed up 
1. We have reviewed the auditing and log capture on the 
 
and archived on a regular basis depending on the 
Open Account system, taking into account the 
Risks:   
business requirements and size of log files. 
recommendations below and raised an RFC to address 
If comprehensive audit logs are not maintained and 
 
this. The action was completed on 9 April 2007.   
reviewed, there is an increased risk that unauthorised 
Action Item Priority: Medium 
2. There is a current project to centralise the correlation 
activity may not be detected and addressed in a timely 
and monitoring of all logs. In the meantime, we have 
manner. 
created a Log Review spreadsheet for log reviews on 
Failure to retain log files for an adequate period of time 
Open Accounts and, other critical and mission critical 
increases the risk that unauthorised activity may not be 
systems. 
traced at a later date or may result in system failures 
3. Audit Logs recording user activities, exceptions, and 
being untraceable, preventing the identification and 
information security events have now been 
correction of problems or security incidents in an 
implemented as appropriate and kept for an agreed 
accurate or timely fashion.  The lack of evidence may 
period to assist in future investigations and access 
also negatively impact upon the success of disciplinary 
control monitoring. Logs will be kept securely and 
action or criminal prosecution of an individual 
access to logs managed and monitored. Log retention is 
undertaking unauthorised activity. 
covered in our Information Security Policy (Section 
Failure to review audit logs in a timely manner 
10.10). 
increases the risk of unauthorised access to server 
resources being undetected for an extended period of 
time.  Lack of monitoring gives a potential intruder 
sufficient time to find a weakness in security and 
potentially obtain access to sensitive data and programs. 
 
Risk Severity Rating: Moderate 
 
 
 
 
 
 
 
19 
 

O L Y M P I C   D E L I V E R Y   A U T H O R I T Y   –   G E N E R A L   I T   C O N T R O L S  
 
Finding 
Action Items 
Management Response 
B3  Non-compliance of Account Lockout Settings 
1.  IT should change the Default Domain Policy 
Primary Action Item Owner: Simon Pitt, Head of IT 
with Security Policy 
configuration to be in line with the ODA Security 
Secondary Action Item Owner: N/A 
We noted that account lockout is set to 4 invalid logon 
Policy. 
 
attempts, which is not compliant with the ODA IT 
 
Implementation Date: April 2007 
Security Policy which details that account lockout 
Action Item Priority: Low 
  
should be set to 3 invalid logon attempts. 
Comments:   
Industry good practice is to set network accounts to 
Completed.  A Change was raised in order to rectify this 
lockout or delay further logon attempt after three 
situation as soon as the issue was raised. We are 
invalid logon attempts.  We understand that the ODA IT 
grateful to internal audit for identifying this issue, 
Security Policy also stipulates that this value.   
which was immediately rectified. 
Risks:   
Failure to implement the defined account lockout 
increases the risk of an unauthorised individual being 
able to compromise the system by executing a brute 
force “dictionary” attack against user accounts.  Such 
attacks are used to attempt to guess user passwords and 
gain unauthorised access to the IT systems, potentially 
resulting in disclosure of sensitive information or 
violating the integrity of the data. 
 
Risk Severity Rating: Minor 
 
 
 
 
 
 
 
 
20 
 

O L Y M P I C   D E L I V E R Y   A U T H O R I T Y   –   G E N E R A L   I T   C O N T R O L S  
 
C. Third Party Management 
Ineffective control and management of third party contracts in relation to IT may have both financial and security implications.  The ODA is in 
the process of negotiating many contracts that may have IT implications.  As such, it is expected that there would be consideration of IT, and 
consultation of IT specialists, during the procurement and contract negotiation process.  It is understood that some of the contracts, that have 
already been agreed and signed, do not include full consideration the IT related contractual requirements e.g., for rights of audit over the third 
party, enforcement of compliance with ODA policies and procedures and government regulatory requirements.  Other contracts are currently in 
negotiation, or are to be negotiated in the immediate future. 
 
Finding 
Action Items 
Management Response 
C1 IT Contractual Requirements in Existing 
1.  As noted in Finding A3, the ODA should finalise, 
Primary Action Item Owner:  Dennis Hone, Director 
Contracts 
where necessary, relevant IT policies and 
of Finance and Corporate Services 
Following our review of the LDA Legacy Remediation-
procedures and formally issue these to the 
Secondary Action Item Owner: Simon Pitt, Head of 
Demolition contract, we noted that there are no 
contractor as soon as possible. 
IT  
contractual clauses relating specifically to IT.  For this 
2.  The IT requirements within other existing contracts 
 
contract, we are aware that there is a significant budget 
and projects should be identified and, where 
allocation for IT, worth £1 million, for the provision of 
considered relevant based on a formal risk 
Implementation Date:  July 2007 
onsite IT services for a site office.  The ODA has little 
assessment, arrangements should be put in place for   
control either over this IT spend or the subcontractor 
monitoring the provision of these IT services by the 
Comments:  
who has been appointed to provide the IT services.  We 
third parties. 
understand that there was no due diligence performed in 
Following receipt of advice from ODA Legal the 
 
relation to the appointment of the IT subcontractor and 
following policies and procedures were issued to the 
that it is understood that they do not have experience 
Action Item Priority:  High 
LDE legacy Remediation-Demolition contractors: 
within the government sector and are not aware of the 
 
• 
Third Party Security Policy - draft 
specific requirements in relation to this.  It was noted 
during our review that IT service performance issues 
• 
Third Party Security Assessment - final draft 
arising from power cuts have already been experienced 
• 
Network Connection Agreement and Code of 
at the site office. 
Connection - final draft 
Furthermore, we understand that there is no disaster 
• 
Information Security Policy - ODA final draft 
recovery provision for the IT services that are being 
• 
Procedures - email access 
provided to the site office under this contract. 
• 
Policy deviation - Risk acceptance form 
We understand that the ODA IT department is 
discussing the IT service provision and the need to 
• 
Security Awareness handbook 
comply with the ODA standards and this is currently 
• 
Intranet Security model 
taking place out of good will on the part of the 
• 
Policy and Operating Procedure for London 2012 
 
 
 
 
 
 
 
21 
 

O L Y M P I C   D E L I V E R Y   A U T H O R I T Y   –   G E N E R A L   I T   C O N T R O L S  
 
Finding 
Action Items 
Management Response 
contractor and subcontractor, as the contractual 
IT Equipment Rooms v1_1 
arrangements are such that the contractor has agreed to 
• 
Policy and Op Proc Access to Mailboxes v1_0 
undertake responsibility for the providing the IT 
services required to fulfill their contract.   
• 
Data Access Security Model v1_0 
It is understood that the ODA legal team has advised 
• 
Backup and Recovery Policy FINAL v1_0 
that there is a clause in the contract that requires the 
• 
London2012 Dormant account policy Draft 
contractor to comply with policies and procedures that 
Version1.3 
are issued to them.   
 
 
A review of all other contracts is underway and will be 
Risks:   
completed by July 2007. 
The ODA has little contractual control over the IT 
 
services being implemented at the site office as part of 
See response to C3 for monitoring.   
this contract.  There is a risk that the contractor may not 
be willing to comply with the ODA policies, procedures 
 
and standards and it will be difficult for the ODA to 
 
enforce such compliance. 
 
The inability of the ODA to easily enforce the relevant 
policies, procedures and standards, particularly in 
relation to the need to demonstrate value for money 
from IT, may mean that the ODA aims are not met and 
may also mean that government legislation e.g. 
Freedom of Information Act (FOIA), Data Protection 
Act (DPA) and the National Archives (TNA) is not met.  
Without adequate rights of audit and agreement of 
SLAs and KPIs, the ODA may find it difficult to gain 
visibility of and monitor the quality of service and 
compliance with policies and procedures.  This may 
result in additional cost and reputation implications. 
 
Risk Severity Rating: Major 
C2 IT Engagement in the Procurement and Contract  1.  Procurement should engage IT within the 
1.  Primary Action Item Owner:  Morag Stuart, Head 
Negotiation Process 
procurement and contract negotiation process.   
of Procurement  
There is limited or no engagement of IT specialists 
2.  The ODA IT department should continue liaising 
Secondary Action Item Owner: Simon Pitt, Head of 
during the procurement and contract negotiation 
with the legal teams to identify and agree standard 
IT 
processes.  We noted that the ODA IT department has 
terms and contracts to enable adequate clauses in 
 
limited visibility over the procurement and contract 
relation to IT to be included within contracts going 
negotiation process, and has had limited input to the 
forwards.  The use of such clauses should be 
Implementation Date: May 2007 and ongoing 
contract drafting process to help bring consistency into 
determined based on a review of the associated 
 
 
 
 
 
 
 
 
22 
 

O L Y M P I C   D E L I V E R Y   A U T H O R I T Y   –   G E N E R A L   I T   C O N T R O L S  
 
Finding 
Action Items 
Management Response 
contracts and include relevant IT contract clauses to 
risks and benefits to the ODA so that a balanced 
Comments:   
enable effective control and visibility of third party 
and cost effective approach can be taken.  
The ODA has now developed standard contract terms 
contractors in relation to IT e.g. agreement of SLAs, 
 
relating to IT and has embedded relevant work 
KPIs, appointment of IT subcontractors, compliance 
instructions relating to IT in all contracts.  The 
with IT policies and procedures covering areas such as 
Action Item Priority:  High 
Procurement department is continuing to work with IT 
security, Freedom of Information Act (FOIA), Data 
 
and other functions within the organisation to ensure 
Protection Act (DPA) and the National Archives (TNA) 
consistency of process and true embedding of policies 
and value for money. 
throughout all contracts. 
We understand that multiple procurement and legal 
 
teams are working on various contracts and there is 
limited sharing of information and awareness of the 
2.  Primary Action Item Owner:  Simon Pitt, Head of 
importance of inclusion of IT consideration during the 
IT 
contract negotiation process. 
Secondary Action Item Owner: Celia Carlisle, Head 
The IT department is currently working with the ODA 
of Legal  
and CLM legal teams to identify standard IT clauses 
 
that should be included in contracts going forwards. 
Implementation Date: May 2007 
 
 
Risks:   
Comments:   
As evidenced in Finding C1, without the engagement of 
ODA IT specialists in the procurement and contract 
The ODA has now developed a set of documented 
negotiation processes, there is a risk that the ODA has 
procedures in relation to IT to be performed prior to 
limited remit to enforce policies and procedures on the 
entering into contracts with any third party services. 
third party contractors, and appointed subcontractors.  
Information security requirements are integrated into all 
This may weaken the ability of the ODA to act in the 
third party contracts. 
role of the “intelligent client” and gain oversight of and 
 
effectively manage the contracts.  As the number and 
complexity of contracts increases within the ODA, so 
does the ODA's exposure to risks associated with those 
contracts.  There is the potential that deficiencies within 
the contracts may result in increased costs and 
inefficiencies in relation to IT as well as risks to 
reputation and national security arising from breaches 
of security through non-compliance with ODA policies 
and procedures. 
 
Risk Severity Rating: Major 
 
 
 
 
 
 
 
23 
 

O L Y M P I C   D E L I V E R Y   A U T H O R I T Y   –   G E N E R A L   I T   C O N T R O L S  
 
Finding 
Action Items 
Management Response 
C3 Lack of Processes and Procedures for 
1.  Whilst contractors are contractually responsible for 
Primary Action Item Owner: Dennis Hone, Director 
Monitoring Third Parties 
management of the IT services and solutions 
of Finance and Corporate Services  
There are currently no IT related policies and 
required to support the provision of procured 
Secondary Action Item Owner: Simon Pitt, Head of 
procedures in place to manage and monitor third party 
services, IT management should assess the risks 
IT 
contractor compliance with the contract and ODA 
associated with the loss of data, or security 
 
policies and procedures. 
breaches of contractor IT systems, and determine 
the level of oversight the ODA should retain over 
Implementation Date:  July 2007 
 
the contractors’ IT environments.   
 
Risks:   
2.  IT should develop third party management and 
Comments:   
Without defined IT related policies and procedures for 
monitoring policies and procedures as soon as 
Outsourced areas are integrated into the internal control 
management and monitoring of third party contractors, 
possible and implement these for key third parties.  
there is a risk that, going forwards, informality and 
This should include the development of a third 
system and there is a method of monitoring and 
inconsistencies may be taken in the approach to monitor 
party audit plan, based on an assessment of 
controlling the third party service provider on an 
and manage third party contractors.  This increases the 
associated risk, incorporating aspects such as: 
ongoing basis with regular reporting from the service 
likelihood of future non-compliance with contractual 
provider. In addition, the ODA will regularly review 
• 
Third party contractor risk assessments 
arrangements and ODA policies and procedures, 
and monitor the security practices and processes of the 
potentially resulting in security breaches and 
• 
Regular third parties self assessments of 
service provider, including performing periodic audits 
reputational impact. 
compliance with ODA policies and 
on the security adequacy and compliance of the service 
procedures 
provider.  Third party contracts include explicit security 
 
• 
ODA compliance verification audits 
requirements, including incident response requirements. 
Risk Severity Rating: Major 
 
• 
Reporting on service quality and performance 
 
against SLAs and KPIs. 
A third party contractor audit plan is under development 
and will be in place in July 2007.  
 
Action Item Priority: High 
 
 
 
 
 
 
 
 
24 
 

O L Y M P I C   D E L I V E R Y   A U T H O R I T Y   –   G E N E R A L   I T   C O N T R O L S  
 
Appendix A:  Overal  Report Rating Definition 
Overall report ratings are provided for each audit deliverable to indicate a general level of internal control, risk mitigation and performance.  It 
is used by management to provide an overall indicator of report contents and severity of findings, which have been identified and require action.     
Report Category 
Report Category Summary 
Report Category Definition 
Excellent 
Overall internal controls 
Only a small number of minor or insignificant risks or control weaknesses were identified.   
 
were in place, operating 
Line management will address the low priority action items as, and when, required.   
effectively and adequately 
mitigated key risks 
Good  
With limited exceptions, 
A number of minor or insignificant risks and control weaknesses were identified, and, if taken together, 
 
overall internal controls 
may indicate a general weakness in the control environment to be addressed as a low priority.   
were in place, operating 
Line management will undertake actions to strengthen the control environment.   
effectively and adequately 
mitigated key risks 
Satisfactory 
Overall internal control 
A number of moderate and minor risks or control weaknesses were identified.  Or, recognising the first 
 
and risk mitigation 
year of operation of the ODA, some major risks with mitigation strategies were identified. These 
activities were satisfactory  weaknesses may result in inefficient or ineffective resources, and a decrease in management control.   
 
Line Management will address identified action items within the agreed timeframes.  Risk & Audit will 
apprise the Audit Committee of the status of agreed actions, and in particular when agreed 
implementation dates have not been met.     
Needs 
Overall internal controls 
A number of major or moderate risks were identified.  There were weaknesses in controls which could 
Improvement  
and risk mitigation 
compromise or undermine management control, there were largely inefficient or ineffective use of 
 
activities require 
resources, or there were risks which were not effectively mitigated.   
improvement 
A number of high and medium priority action items were identified and will be addressed by Line 
 
Management within the agreed timeframes.  Risk & Audit will apprise the Audit Committee of the 
status of agreed actions, and in particular when agreed implementation dates have not been met.     
Unacceptable  
Overall controls were not 
A number of fundamental or major risks were identified.  Either the design of controls did not 
 
in place, operating 
appropriately mitigate identified risks, there were numerous indicators that controls were not 
effectively or mitigating 
functioning as designed, or there were largely inefficient or ineffective use of resources.   
key risks 
A number of immediate and high priority action items were identified and will be addressed by Line 
 
Management as a matter of priority.  Risk & Audit will apprise the Audit Committee of the status of 
agreed actions and in particular when agreed implementation dates have not been met.     
 
 
 
 
 
 
 
25 
 

O L Y M P I C   D E L I V E R Y   A U T H O R I T Y   –   G E N E R A L   I T   C O N T R O L S  
 
Appendix B:  Risk Matrix Criteria 
The ODA Risk Management Framework requires risk severity to be determined using a five by five risk matrix.  The tables below outline the 
likelihood and consequence assessment definitions used to facilitate categorising the risk severity of audit findings and risks.   
 
 Likelihood Risk Assessment Criteria  
Likelihood Category 
Likelihood Category Definition 
Almost Certain 
Expected to occur in most circumstances 
Likely 
Will probably occur in most circumstances 
Possible 
Could occur at some time 
Unlikely 
Not expected to occur 
Rare 
May occur only in exceptional circumstances 
 
 
 
 
 
 
 
 
26 
 

O L Y M P I C   D E L I V E R Y   A U T H O R I T Y   –   G E N E R A L   I T   C O N T R O L S  
 
Consequence Risk Assessment Criteria  
 
CONSEQUENCE DEFINITION 
Risk Group 
Fundamental 
Major 
Moderate 
Minor 
Insignificant 
Strategic  
Inability to deliver 
Severe impact on ability 
Significant impact on 
Material impact on 
Little impact on ability to 
programme, project or 
to deliver programme, 
ability to deliver projects 
ability to deliver project 
deliver project or 
business objective 
project or business 
or business objectives  
or business objectives  
business objectives  
objective  
Operations 
Inaccurate or delayed 
Inaccurate or delayed 
Delays in obtaining 
Delays in obtaining ad 
Delays in obtaining ad 
information used in key 
information used for 
accurate management 
hoc information 
hoc information in 
decision making  
internal reporting  
information  
 
isolated instances 
 
 
 
 
 
Inefficient or ineffective 
Inefficient or ineffective 
Inefficient or ineffective 
Inefficient or ineffective 
Inefficient or ineffective 
controls in a critical 
controls in a significant 
controls in a material 
controls in some 
controls in a very minor 
component of the control 
component of the control 
component of the control 
components of the 
component of the control 
environment arising 
environment arising 
environment arising 
control environment 
environment arising 
from, inter alia: resource 
from, inter alia: resource 
from, inter alia: resource 
arising from, inter alia: 
from, inter alia: resource 
management; 
management; information  management; information  resource management; 
management; information 
information technology 
technology; management;  technology management; 
information technology 
technology management; 
management; or asset 
or asset and property 
or asset and property 
management; or asset and  or asset and property 
and property 
management.   
management.   
property management.   
management.   
management.   
Compliance 
Failure to comply with 
Failure to comply with 
Failure to comply with a 
Failure to comply with 
Failure to comply with a  
critical mandatory legal 
mandatory legal or 
mandatory legal or 
recommended legal or 
recommended legal or 
or regulatory 
regulation requirements  
regulation requirement in 
regulatory requirements  
regulatory requirement in 
requirements 
an isolated instance 
an isolated instance 
Financial 
Adverse impact on actual  Adverse impact on actual  Adverse impact on actual  Adverse impact on actual  Adverse impact on actual 
revenue or actual costs > 
revenue or actual costs 
revenue or actual costs 
revenue or actual costs 
revenue or actual costs 
£20 million 
between £10 - £20 
between £5 - £10 million 
between £1 and £5 
less than £1 million 
NAO audit qualification 
million 
NAO raises isolated 
million 
NAO raises some low 
on the reports or accounts   NAO raises significant 
control weaknesses or 
NAO raises process 
priority process 
control weaknesses or 
management issues 
improvement suggestions  improvement issues 
management issues 
 
 
 
 
 
 
 
27 
 

O L Y M P I C   D E L I V E R Y   A U T H O R I T Y   –   G E N E R A L   I T   C O N T R O L S  
 
Appendix C:  Prioritisation of Findings and Action Items 
The following criteria has been used to prioritise findings and action items.  The Risk Severity Rating has been derived from ODA’s Risk 
Management Framework 
which uses a five by five risk matrix to define risk severity.   
Risk Severity 
Finding &  Action 
Priority Definition 
Rating 
Item Priority 
Fundamental 
Immediate 
  weakness which could negate management control and the ability to direct and manage ODA’s  business 
affairs 
  weaknesses may result in largely inefficient or ineffective use of resources 
  issues categorised as immediate could have the potential to severely impact the operation of the ODA  
Major 
High 
  weakness which could compromise management control and the ability to adequately direct and manage 
ODA’s business affairs 
  weaknesses may result in significantly inefficient or ineffective use of resources 
  issues categorised as high could have the potential to significantly impact the operation of the ODA  
Moderate 
Medium 
  weakness which could undermine the system of management control, and the ability to demonstrate proper 
accountability, probity and openness in business operations 
  weaknesses may result in inefficient or ineffective use of resources 
  issues categorised as medium could have the potential to materially impact the operations of ODA  
Minor or 
Low 
  weaknesses which could have a minor impact on the system of management control 
Insignificant 
  weaknesses may have a minor impact on the efficiency or effectiveness of processes or use of resources at 
present 
 
 
 
 
 
 
 
 
28