Cambridge East Delivery Board
2.45-4pm – Thursday, 12th June 2008
The Ramparts (Bailey Rooms), Cambridgeshire County Council
A G E N D A
Introduced by:
1.
14.45
Welcome and Apologies
AP
2.
14.50
Membership of Delivery Board
AP
3.
15.05
Delivery Plan and Action Plan for Cambridge East
JO / PM
(outline Delivery Plan and 4th March Workshop Write-up)
4.
15.30
Masterplanning
SS
5.
15.55
Agenda Plan and Any Other Business
All
6.
16.00
Date of next meeting:
All
Board Members:
Alex Plant
Cambridgeshire Horizons
Graham Hughes
Cambridgeshire County Council
Peter Studdert
Director for Joint Planning
Gareth Jones
South Cambridgeshire District Council
John Williamson
GO-East
Steve Sillery
Marshall Aerospace
Jonathan Barker
Marshall Aerospace
Paul Mumford
Cambridgeshire Horizons
Michelle Hawker
Cambridgeshire Horizons
Also in attendance
John Onslow
Cambridgeshire Horizons
Laura Halstead
Cambridgeshire Horizons
Geoff Bruce
Cambridgeshire Horizons
Substitutes:
1
David Roberts
Cambridge City Council
Apologies:
Steve Hampson
South Cambridgeshire County Council
Liz Bisset
Cambridge City Council
Simon Payne
Cambridge City Council
2
Cambridgeshire Horizons
Cambridge East Delivery Board
12th June 2008
Final
Cambridge East Delivery Board
Minutes from Thursday 12th June 2008
The Ramparts (Bailey Room)
Cambridgeshire County Council
Board Members Present:
Alex Plant (Chair)
Cambridgeshire Horizons
Paul Mumford
Cambridgeshire Horizons
Peter Studdert
Director of Joint Planning
Graham Hughes
South Cambridgeshire District Council
John Williamson
Go East
Steve Sillery
Marshall Aerospace
Jonathan Barker
Marshall Aerospace
Also in attendance:
John Onslow
Cambridgeshire Horizons
Suzanne McBride (Sub)
South Cambridgeshire District Council
Ken Hay (Sub)
Cambridge City Council
David Roberts (Sub)
Cambridge City Council
Michelle Hawker (Minutes)
Cambridgeshire Horizons
Apologies:
Steve Hampson
South Cambridgeshire District Council
Liz Bissett
Cambridge City Council
Simon Payne
Cambridge City Council
1
Cambridgeshire Horizons
Cambridge East Delivery Board
12th June 2008
Final
Actions
1.
Welcome/ Apologies and Introductions
As
above
2.
Membership of Delivery Board
Members were asked to review above attendees list and
All
confirm that the most appropriate representatives were invited
to the Board.
Key points:
• AP as Chair and PM as Project Manager.
• Gareth Jones will not be attending this Board.
• The new Communities directorate representative from
SCDC may replace Steve Hampson.
• Representative from health will feed into the Cambridge
East Delivery Board when necessary.
• The Cambridge East Delivery Board structure will mirror
that of the Northstowe Delivery Board.
• A need for Stakeholder involvement at an early stage,
especially health, is useful during the design process.
Actions:
•
Membership and structure report needed to summarise
PM
above.
•
Public Health representative, Doctor Lincoln Sargeant
MH
to be invited to joint the Delivery Board.
3.
Delivery Plan and Action Plan for Cambridge East (Outline Delivery Plan and 4th March Workshop Write-up)
presented by John Onslow.
Key Points:
• The Delivery plan helps the Programme Management
Process.
• Identify Key risks, issues and objectives keeping the
focus.
• Delivery Managers are Sheryl French & Geoff Bruce
• (JB) Page 2 of the Delivery Plan (referring to
organisations owning the Plan) needs to include
landowners and developers.
• The Cambridge East Delivery Board will link to the
Senior Officer Board.
Actions:
• Terms of Reference are to be worked on for the next
meeting.
PM
A discussion ensued, issues raised include:
•
Consideration to early viability study as an objective
due to current market situation and reaffirm the need for
PM
2
Cambridgeshire Horizons
Cambridge East Delivery Board
12th June 2008
Final
funding studies.
• AP had presented a paper on a Tariff approach to the
Horizons Board; this could be pertinent to Cambridge
AP
East.
• Phasing frameworks are also being considered, with a
workshop planned for July, which can identify and then
AP
hopefully resolve viability gaps, to increase flexibility, for
example affordable housing allocation for very large
projects.
JO briefed the Board on the successful workshop 4th March.
The following action plan was agreed:
1. Ensure partnership working on existing
Marshall
communities specifically Barnwell.
2. Put in place stronger partnership working and
identify projects and capture in the Delivery Plan.
Horizons
3. Set out clear structures for programme
management (Delivery Board Terms of
Horizons
Reference and sub structures)
4. Develop an investment plan for Cambridge East
Horizons
to address infrastructure cost and viability.
Horizons
5. Prepare a Communications Strategy
6. Transport – agree approach to transport and
County
funding.
Council/
Horizons
4. Master
Planning
Key Issues:
• JB asked about the boundary change process. AP
explained the lengthy process and probable timelines
for completion.
• Relocation is a major issue. The target for Marshall’s
relocation is the 1st January 2016. Moving the site
before 2016 is reliant on constraints associated with
any relocation site. Recognition that Horizons and LA
engagement would be helpful to move relocation
negotiations forward.
• Consideration for phasing the Cambridge East
development in line with the Area Action Plan (Phasing
options on Newmarket Rd and Cherry Hinton as first
elements of the total project)
• Communications strategy needs to be sensitive to the
2000 employees currently at Marshall offices.
• Discussions around linkages between TIF and
Cambridge East concluded that it would be difficult to
proceed with Cambridge East without TIF.
• Master Plan to be commented on by stakeholders,
aiming to reach a consensus by February 2009
3
Cambridgeshire Horizons
Cambridge East Delivery Board
12th June 2008
Final
Action:
• Outline Communications Strategy for Cambridge East
LH
to presented to the Delivery Board late autumn 2008.
• A list of Marshall businesses, which need relocating to
MH
be circulated to the Cambridge East Delivery Board.
SS
• Marshall Master Plan to be presented to the next JSGIC
• Horizons to send a letter regarding the Master Plan to
AP
Marshall’s.
5
Agenda Plan and Any Other Business
Horizons to provide output from Conference/ Arts facility study
PM
when complete.
6
Date of next meeting
TBC - September 2008
4
Cambridgeshire Horizons
Cambridge East Delivery board
June 2008
CAMBRIDGE EAST PROGRAMME AND RISK MANAGEMENT WORKSHOP
TUESDAY 4TH MARCH 2008, 09.30 – 12.30
CAMBRIDGE AIRPORT
Attendees
Kathy Baldwin
Cambridgeshire County Council
Joseph Whelan
Cambridgeshire County Council
Barry Louth
Cambridge City Council
Sharon Brown
Cambridge City Council
David Roberts
Cambridge City Council
Brian Human
Cambridge City Council
Sara Cass
Cambridge City Council
Caroline Hunt
South Cambridgeshire District Council
Wayne Campbell
South Cambridgeshire District Council
John Watkins
Marshall Group
Jonathan Barker
Marshall Group
Steve Sillery
Marshall Group
Richard Atkinson
Cheffins
John Onslow
Cambridgeshire Horizons (Facilitator)
Geoff Bruce
Cambridgeshire Horizons
Paul Mumford
Cambridgeshire Horizons
Anna Keyes
Cambridgeshire Horizons
Background and Objectives
The workshop gave an opportunity for stakeholders to come together and discuss the
programme for development and capture key risks to progress. The session on the
programme for development of Cambridge East gave confirmation of key milestones
and the sequence of events up to the granting of outline planning permissions for all
of Cambridge East.
The session on risk management also concentrated on stages of development up to
granting of outline planning permissions. The session allowed stakeholders to identify
and capture key risks to development progress.
The workshop divided into three groups to brainstorm risks. Each group took one of
the following:
• Community and Economy
• Sustainable Infrastructure
• Planning / Political / Legal matters
Groups were encouraged to apply lessons learned from work on other major
development sites. The “Top Ten” risks are shown below and all risks identified at the
workshop have been transferred to the first draft Risk Log for Cambridge East, to be
included in the Delivery Plan for Cambridge East. Group members are shown below:
Community & Economy
Sustainable Infrastructure
Planning / Political / Legal
Paul Mumford
Geoff Bruce
Sara Cass
Joseph Whelan
Wayne Campbell
Kathy Baldwin
Sharon Brown
Steve Sillery
Caroline Hunt
Jonathan Barker
Richard Atkinson
John Watkins
Anna Keyes
Brian Human
Dave Roberts
Barry
Louth
1
Cambridgeshire Horizons
Cambridge East Delivery board
June 2008
Top ten risks to the progress of Cambridge East
1. Lack of progress with Transport Innovation Fund bid and decisions lead to
funding shortage for key schemes
2. Inadequate transport infrastructure is in place to support communities
3. Lack of leadership undermines progress
4. Inadequate resources (people and early funding) to progress project
5. Development is not viable, with insufficient funds to bridge viability gap
6. Failure to agree the masterplan
7. Failure to agree with MOD on relocation of operations, leading to site availability
being delayed
8. Concerns over capacity of A14
9. Ineffective governance and participation in place to progress development
10. Failure to ensure high quality early phases of development results in loss of
confidence in overall masterplan
Key themes
The findings from the session were then considered by the whole group. The
following key themes were identified:
• Tackling the transport strategy and funding;
• Ensuring effective leadership throughout delivery of Cambridge East;
• Implementing strong decision-making and project management structures to
maximise progress and tackle key issues/blockages.
Action Plan for Cambridge East over next six months
The workshop spent some time addressing how to make Cambridge East a success
and what progress should be made in the short-term. Four opportunities were
identified, which form the ‘Action Plan’ for Cambridge East over the next six months.
1. Prepare a communications strategy and promote Cambridge East as part of the
growth of Cambridge;
2. Show benefits to existing communities by working with them and early delivery of
infrastructure (e.g. community, transport);
3. Put in place stronger partnership working using new structures (including Section
29 Committee); Set up Delivery Board (public and private sector membership);
prepare of Cambridge East Delivery Plan and oversee implementation;
4. Develop an investment plan of infrastructure requirements and costs for the
development and its related strategic infrastructure.
The Delivery Board is already being put in place. The Delivery Board will oversee the
implementation of the actions set out above.
2
Cambridge East
Programme Management
and Delivery Plan
Cambridge East Delivery Board, 12th June 2008
Programme Management – Why?
•
Joint Working
– Multi-agency inputs required
– Full engagement between public sector and
landowners/developers
– No single lead authority
– Effective partnership is rewarded by Government
– Aim for
win-win not
win-lose
•
Co-ordination
– Large complex development with multiple stakeholders
– Need to manage risk and address issues on a cross-cutting
basis
•
Delivery
– Need to identify roles and responsibilities and monitor
progress
1
Stakeholders
Businesses
CLG
GO
Parishes
Environment
Housing Corp
Agency
Residents
Housing
Highways
County
Assoc
LDV
Agency
EEDA
Council
PCT
City Council
District Council
Energy
Telcos
Companies
EERA
Landowners /
DfT
Developers
Water
Companies
DEFRA
Bus
Companies
Cambridgeshire Horizons
• Business Plan 2008-2011
• Key objectives:
- Coordinate development and infrastructure
implementation
- Overcome barriers to sustainable
development
- Secure and manage funding for
infrastructure
- Ensure development employ high quality
urban design
- Communicate the benefits of the planned
development to the wider community
• Core team
2
Joint Working
Development Delivery
Policy and Development Control
Cambridgeshire
County
City
SCDC
Horizons Board
Council
Council
Joint Strategic
Member
Growth
Reference
Implementation
Groups
Committee
Northstowe
Fringe Sites
Section 29 Joint
Development Control
Development
Planning
Committee
Control
Committee
Senior Officer
Committee
Board
Northstowe
Cambridge East
Fringe Sites
Director for
Delivery Board
Delivery Board
Delivery Board
Joint Planning
PROJECT RESOURCE
Cambridge City, S Cambs DC, County Council, Horizons
Structure – Delivery Boards
•
Three Delivery Boards; Northstowe, Cambridge Fringes and
Cambridge East
•
Representation from key organisations involved (chaired by
Horizons)
•
Management of Major Projects through shared understanding
– Delivery Plans
– Develop Masterplan
– Reduce risks and address issues
•
Meet on regular basis, but critical to work as a team in between
3
Delivery Plans
•
Managed by Delivery Manager on a site by site
basis using input from partners
•
Comprehensive tool for successful delivery
•
Components are:
– Summary
Cambridge Southern Fringe Delivery Plan 2008 – 2011
– Programme / Milestones / Targets
Summary of risk management
Number of risks identified
22
Overall statement of progress by Cambridgeshire Horizons Delivery Manager - April 2008
Number of separate mitigations
26
Trumpington Meadows outline application granted approved, subject to Section106, at Joint DC
– Resources required
Committee 20 Feb 2008. Triggers and phasing agreed with developer 21st April. Closing negotiations
on Section106 continue.
Status of mitigations
Clay Farm outline application to be considered by Joint DC Committee 14 May 2008. Section 106 deal
agreed in principle 11th April 2008. Letter sent from Countryside 28th April (i hand at time of compiling
– Risks and Issues
t
his report).
pie chart
Community Facility specification for proposed joint facility sent to Countryside for agreement 28 April.
Summary of issues
General Note:
Number of issues identified
9
– Communications Plan
This is the first version of the new format of the delivery plan, revised and updated for easy accessibility
t
o information in one document. The tabs at the bottom of the screen give access to the various
sections.
Status of remediations
To print the whole file, press Control+P, then select "entire workbook" and the whole file will print (the
– Projects
pages have been sized to suit).
pie chart
Completed risks/issues
•
Updated frequently – an ‘organic’ document
Cambridge East Delivery Plan
Cambridge East Delivery Plan 2008 – 2011
Summary of risk management
Number of risks identified
11
Overall statement of progress by Cambridgeshire Horizons Delivery Manager - 23 May 2008
Number of separate mitigations
11
This is the first version of the Cambridge East Delivery Plan. The tabs at the bottom of the screen give access
to the various sections.
Status of mitigations
To print the whole file, press Control+P, then select "entire workbook" and the whole file wil print (the pages
have been sized to suit).
This version has been produced for the inaugural Cambridge East Delivery Board on 12 June 2008 and
pie chart
includes the top ten risks identified at the risk management workshop on 4 March 2008 (plus an additional risk
around completing pre-application work) and a few schematic dates in the programme to demonstrate how the
Summary of issues
Programme section works and looks. Most of the remainder of the document is "work in progress" and shown
only for illustration purposes. No issues have been added to the schedule.
Number of issues identified
3
Status of remediations
pie chart
Completed risks/issues
4
Cambridge East Delivery Plan - Programme
8
8
8
8
8
8
8
9
9
9
9
9
9
9
0
0
s
8
8
8
9
9
9
9
0
0
-
0
8
-
0
-
0
-
0
-
0
-
0
9
-
0
-
0
-
0
-
0
t
e
-
0
r
-
0
-
0
-
1
r
-
0
y
-
0
g
p
t
-
0
v
c
-
0
r
-
0
r
-
0
y
-
0
g
p
t
-
0
v
c
-
1
r
-
1
r
-
1
a
b
b
b
e
a
p
a
n
l
-
0
n
n
l
-
0
n
u
u
u
e
c
o
e
a
e
a
p
a
u
u
u
e
c
o
e
a
e
a
p
D
F
M
A
M
J
J
A
S
O
N
D
J
F
M
A
M
J
J
A
S
O
N
D
J
F
M
A
Relocation of Airport
Decision to relocate airport
New airfield negotiation
Negotiations with Defence Estates and USAF
New airfield implementation
Area Action Plan
First Review
Masterplan
Draft Spatial Masterplan preparation
Development of North Works site
Temporary Vehicle Park planning application
Submission
Swavesey planning application
Preparation
Submission
(dependent upon A14 final announcement)
Car Centre Relocation?
Residential Planning Application
Preparation
Submission
Development of Land North of Cherry Hinton
Residential Planning Application
Preparation
Submission
Development of Airfield
Planning Application
Transport
TIF Announcement
A14 route & junctions final announcement
A14 construction
Newmarket Road
Guided Busway Extension
Waste
Local Recyling Centre
Cambridge East Delivery Plan - Risks
No
Topic
Risk
P
I
Mitigation
Date to
Status
Owner
Owner
Owner
Authority
Director
Officer
Complete
(RAG)
ER1
Transport
Lack of progress with Transport Innovation Fund
bid and decisions lead to funding shortage for
County
A
key schemes
ER2
Transport
Inadequate transport infrastructure is in place to
support communities
County
A
ER3
Resources
Lack of leadership undermines progress
Horizons
A
ER4
Resources
Inadequate resources (people and early funding)
to progress project
All
A
ER5
Funding
Development is not viable, with insufficient funds
to bridge viability gap
Horizons
A
ER6
Planning
Failure to agree the masterplan
All
A
ER7
Planning
Failure to agree with MOD on relocation of
operations, leading to site availability being
Marshall
A
delayed
ER8
Transport
Concerns over capacity of A14
County
A
ER9
Resources
Ineffective governance and participation in place
to progress development
Horizons
A
ER10
Planning
Failure to ensure high quality early phases of
development results in loss of confidence in
City and
A
overall masterplan
District
ER11
Planning
Failure to complete necessary pre-application
work delays planning applications
City and
A
District
5
Programme and Risk Management
Workshop 4th March 2008
• Representatives from each authority, Marshall
Aerospace and Horizons
• Key risks and programme discussed
• Identified 3 key themes:
Tackling transport strategy & funding
Ensuring effective leadership throughout delivery of
Cambridge East
Implementing strong decision-making and project
management structures to maximise progress and tackle key
issues/blockages
Action Plan for Cambridge East
Making Cambridge East a success – four opportunities
Prepare a communications strategy and promote Cambridge East
as part of the growth of Cambridge
Show benefits to existing communities by working with them and
ensuring early delivery of infrastructure (e.g. community, transport)
Put in place stronger partnership working using new structures
(Delivery Board, Delivery Plan, Section29 Committee)
Develop an investment plan of infrastructure requiremetns and
costs for Cambridge East and related strategic infrastructure
Additional actions
Continue to develop Masterplan
Pre-application work (Project Planning Team)
6
Cambridge East Delivery Plan 2008 – 2011
Summary of risk management
Number of risks identified
11
Overall statement of progress by Cambridgeshire Horizons Delivery Manager - 23 May 2008
Number of separate mitigations
11
This is the first version of the Cambridge East Delivery Plan. The tabs at the bottom of the screen give
access to the various sections.
Status of mitigations
To print the whole file, press Control+P, then select "entire workbook" and the whole file will print (the
pages have been sized to suit).
This version has been produced for the inaugural Cambridge East Delivery Board on 12 June 2008 and
pie chart
includes the top ten risks identified at the risk management workshop on 4 March 2008 (plus an additional
risk around completing pre-application work) and a few schematic dates in the programme to demonstrate
Summary of issues
how the Programme section works and looks. Most of the remainder of the document is "work in progress"
and shown only for illustration purposes. No issues have been added to the schedule.
Number of issues identified
3
Status of remediations
pie chart
Completed risks/issues
Cambridge Southern Fringe Delivery Plan 2008-2011 - Background
Background
Contents of the Delivery Plan
Other commentary
The Delivery Plan for Cambridge East is reviewed for
The Delivery Plan comprises the following sections:
each Delivery Board meeting by the Fringe Sites Delivery
Manager in collaboration with partner organisations. The
1. Cover Page - a high level overview of the status of
Plan sets out the programme for implementing the
risks and issues and update from the Delivery Manager.
development, the allocation of responsibilities and
activities, together with the mechanisms for identifying
2. Introduction - Background, contents of the plan
risks, resolving issues and reviewing / reporting on
progress.
3. Programme - high level chart setting out key dates
for delivery of development in this area, with progress
The Delivery Plan will be “owned” by the key
reporting as available
organisations involved in the project; these will include at
minimum Cambridgeshire Horizons and the relevant
4. Resources - a schedule of resources available to
Local Authorities. However, it is also essential that other
ensure delivery of the developments in the Southern
key organisations add influence to the plan, such as the
Fringe, including personnel and finances.
PCT and other Government agencies.
5. Risk Log - a schedule of the risks identified, together
All the above organisations are represented on the
with proposed mitigations and a RAG score for each.
Cambridge East Delivery Board and this Plan will be their
key management tool for delivery. The Cambridge East
6. Issues Log - a schedule of issues arising during the
Delivery Board will approve any revisions to the Plan, and
development, including a RAG score for each.
compare progress with the Plan.
Completed issues are removed from the table for the next
version of the delivery plan.
The Delivery Plan is a comprehensive management tool
for the project, it sets out the agreed scope and
7. Communications Plan - schedule of proposed
objectives outlined in an set of milestones which have
communications and any other matters relating to
been compiled by the wider ‘delivery team’ drawn from
communications and media contacts.
across the partner organisations. Against this, a number
of risks have been identified which are recorded against
8. Projects associated with the Southern Fringe -
the programme and contained within a risk register. The
schedule of growth-related projects associated with
programme and Risk Register form the backbone to the
Southern Fringe, including any funded by Housing
Delivery Plan.
Growth Funds.
9. Version Control - schedule of changes made to the
Delivery Plan since the last issue.
Cambridge Southern Fringe Delivery Plan 2008-2011 - Master Programme of Developments
8
8
8
8
9
9
9
9
0
0
0
0
1
1
1
1
2
2
2
2
3
3
3
3
4
4
s
08
8
0
8
9
9
0
0
1
1
2
2
3
3
4
08
8
08
08
-
0
-
0
09
09
0
09
9
09
09
-
0
-
0
10
10
1
10
0
10
10
-
1
-
1
11
11
1
11
1
11
11
-
1
-
1
12
12
1
12
2
12
12
-
1
-
1
13
13
1
13
3
13
13
-
1
-
1
14
14
1
14
4
14
14
t
e
r-0
r-0
y-
t
-
0
v
c
r-0
r-0
y-
t
-
0
v
c
r-1
r-1
y-
t
-
1
v
c
r-1
r-1
y-
t
-
1
v
c
r-1
r-1
y-
t
-
1
v
c
r-1
r-1
y-
t
-
1
v
c
r-1
r-1
y-
eb-
a
l
-
0
l
-
0
l
-
1
l
-
1
l
-
1
l
-
1
l
-
1
un-
ug-
ep-
an-
eb-
a
un-
ug-
ep-
an-
eb-
a
un-
ug-
ep-
an-
eb-
a
un-
ug-
ep-
an-
eb-
a
un-
ug-
ep-
an-
eb-
a
un-
ug-
ep-
an-
eb-
a
un-
ug-
ep-
Da
F
M
Ap
Ma
J
Ju
A
S
Oc
No
De
J
F
M
Ap
Ma
J
Ju
A
S
Oc
No
De
J
F
M
Ap
Ma
J
Ju
A
S
Oc
No
De
J
F
M
Ap
Ma
J
Ju
A
S
Oc
No
De
J
F
M
Ap
Ma
J
Ju
A
S
Oc
No
De
J
F
M
Ap
Ma
J
Ju
A
S
Oc
No
De
J
F
M
Ap
Ma
J
Ju
A
S
Relocation of Airport
Decision to relocate airport
Decision date to be confirmed
New airfield negotiation
Negotiations with Defence Estates and USAF
New airfield implementation
Area Action Plan
First Review
Masterplan
Draft Spatial Masterplan preparation
Development of North Works site
Temporary Vehicle Park planning application
Submission
Swavesey planning application
Preparation
Submission
(dependent upon A14 final announcement)
Car Centre Relocation?
Residential Planning Application
Preparation
Submission
Development of Land North of Cherry Hinton
Residential Planning Application
Preparation
Submission
Development of Airfield
Planning Application
Transport
TIF Announcement
A14 route & junctions final announcement
A14 construction
Newmarket Road
Guided Busway Extension
Waste
Local Recyling Centre
Utilities
Gas
Water supply
Electric Mains
Storm Drainage/SUDS
Sewerage
Telecomms
Education
Primary School 1
Primary School 2
Primary School 3
Primary School 4
Primary School 5
Primary School 6
Primary School 7
Primary School 8
Secondary School 1
Sixth Form provision
Community Facilities
Housing Trajectory
Other to be added:
Marshall Centenary year
Olympics
Cambridge Southern Fringe Delivery Plan 2008-2011 - Master Programme of Developments
4
4
5
5
5
5
6
6
6
6
7
7
7
7
s
4
5
5
6
6
7
7
-
1
-
1
15
15
1
15
5
15
15
-
1
-
1
16
16
1
16
6
16
16
-
1
-
1
17
17
1
17
7
17
17
-
1
-
1
18
t
e
t
-
1
v
c
r-1
r-1
y-
l
-
1
t
-
1
v
c
r-1
r-1
y-
l
-
1
t
-
1
v
c
r-1
r-1
y-
l
-
1
t
-
1
v
c
an-
eb-
a
un-
ug-
ep-
an-
eb-
a
un-
ug-
ep-
an-
eb-
a
un-
ug-
ep-
an-
Da
Oc
No
De
J
F
M
Ap
Ma
J
Ju
A
S
Oc
No
De
J
F
M
Ap
Ma
J
Ju
A
S
Oc
No
De
J
F
M
Ap
Ma
J
Ju
A
S
Oc
No
De
J
Relocation of Airport
Decision to relocate airport
New airfield negotiation
New airfield implementation
Area Action Plan
First Review
Masterplan
Development of North Works site
Temporary Vehicle Park planning application
Swavesey planning application
Car Centre Relocation?
Residential Planning Application
Development of Land North of Cherry Hinton
Residential Planning Application
Development of Airfield
Planning Application
Transport
TIF Announcement
A14 route & junctions final announcement
A14 construction
Newmarket Road
Guided Busway Extension
Waste
Local Recyling Centre
Utilities
Gas
Water supply
Electric Mains
Storm Drainage/SUDS
Sewerage
Telecomms
Education
Primary School 1
Primary School 2
Primary School 3
Primary School 4
Primary School 5
Primary School 6
Primary School 7
Primary School 8
Secondary School 1
Sixth Form provision
Community Facilities
Housing Trajectory
Other to be added:
Marshall Centenary year
Olympics
Cambridge Southern Fringe Delivery Plan - Key Personnel
to be completed:
Format to be determined
Developers
Cambridgeshire County Council
Cambridge City Council
South Cambs District Council
This page will include a summary of the resources available to enable the
delivery of the developments in Southern Fringe, including people, finances.
Environment Agency
Housing Corporation
Cambridgeshire PCT
Highways Agency
Cambridgeshire Horizons
Finances
Cambridge Southern Fringe Delivery Plan 2008-2011 - Risk Log
No
Topic
Risk P
I
Mitigation
Owner
Owner
Owner
Date to
Status
Authority
Director
Officer
Complete
(RAG)
ER1
Transport
Lack of progress with Transport Innovation
Fund bid and decisions lead to funding
County
A
shortage for key schemes
ER2
Transport
Inadequate transport infrastructure is in place
to support communities
County
A
ER3
Resources Lack of leadership undermines progress
Horizons
A
ER4
Resources Inadequate resources (people and early
funding) to progress project
All
A
ER5
Funding
Development is not viable, with insufficient
funds to bridge viability gap
Horizons
A
ER6
Planning
Failure to agree the masterplan
All
A
ER7
Planning
Failure to agree with MOD on relocation of
operations, leading to site availability being
Marshall
A
delayed
ER8
Transport
Concerns over capacity of A14
County
A
ER9
Resources Ineffective governance and participation in
place to progress development
Horizons
A
ER10
Planning
Failure to ensure high quality early phases of
development results in loss of confidence in
City and
A
overall masterplan
District
ER11
Planning
Failure to complete necessary pre-application
work delays planning applications
City and
A
District
Cambridge Southern Fringe Delivery Plan 2008-2011 - Issues Log
No
Date
Topic
Issue
Impact
Mitigation
Date to
Owner
Owner
Owner
Status
Raised
Complete
Authority
Director
Officer
(RAG)
EI1
R
EI2
A
EI3
G
EI4
EI5
EI6
EI7
EI8
EI9
EI10
EI11
Cambridge Southern Fringe Delivery Plan 2008-2011 - Communications
Plan
This page will include a summary of the communictaions strategy and how
key stakeholders will work to communicate the delivery, benefits, decisions
and progress with the developments in Southern Fringe.
Cambridge Southern Fringe Delivery Plan 2008-2011 - Projects Associated with Development
Project
Description
Timescale
Budget
Project lead
Progress
HGF contribution to Addenbrooke's Access Road
Rolling Fund contribution to Addenbrooke's Access
Road
Cambridge Southern Fringe Delivery Plan - Version Control
This is Version:
0.1
Previous Version:
n/a
Dated
09-May-08
Changes since previous version:
Change# Changes made
Sheet
Comments
by
Document Outline
-
- Minutes Cambridge East Delivery Board 12June08.pdf
- Item 3 Cambridge East Workshop 4thMarch08 Report.pdf