Thank you for your email which was received by the University on 7 September 2009 timed 
12:43 hours, requesting the following: 
 
In relation to the Student Lifecycle Project could you please answer the following queries: 
 
1. How many vendors tendered for this project? 
 
2. What were your selection criteria? Please provide the model that you used for comparing 
and ranking the vendor proposals. This should include the categories that were important and 
the weighting factor for each category. 
 
3. For each vendor please provide the score for each individual category. 
 
4. What areas were covered during the due diligence phase for the selected vendor? 
 
In addition I would like further information with regard to two previous FoI requests. 
 
Your response to the first FoI request was: 
"The total costs charged to the Student Lifecycle Project account to 21/11/08 are £241,171. 
This breaks down into salary costs of £88,877(to 31/10/08) and non pay costs of £152,294 
(including travel expenses)." (see 
http://www.whatdotheyknow.com/request/3953/response/9702/attach/2/RESPONSE%20F004
3217.pdf) 
 
At a later date, as part of your response to the second request: 
http://www.whatdotheyknow.com/request/12499/response/36179/attach/5/attachment3%20_2
_.pdf 
You replied: 
DATA PROTECTION AND FREEDOM OF INFORMATION OFFICE 
Main Building, University of Glasgow, Glasgow G12 8QQ 
Data Protection: Telephone: 0141-330-3111 E-Mail: [email address] 
Freedom of Information: Telephone:
 0141-330-2523 E-Mail: foi@gla.ac.uk 
The University of Glasgow, charity number SC004401 

 
 
"The total cost to the project for staffing costs in this phase (October 2007 to May 2009) was 
£272,190. In most cases the costs related to backfill for departments and services from which 
team members were seconded. The only posts which were fully funded by the project were 
the fixed term project office posts. The total cost of external programme management 
consultancy support during this phase was £235,483. During the due diligence phase 
consultancy was also provided by a specialist IT consultancy working in partnership with the 
supplier. The costs of this were £293,982." 
 
This indicates that £560,484 was charged to the Student Lifecycle Project Account between 
21/11/08 and May 2009. 
 
Could you please provide a breakdown of the £560,484? In the breakdown I would like the 
following information: the recipient, the amount, the date of transaction and the purpose of 
each item. I understand that salary costs cannot be broken down per individual. 
 
 
As the University of Glasgow is a Scottish Public Authority, your request is subject to the 
terms of the Freedom of Information (Scotland) Act 2002 (“FOISA”).  The University 
acknowledges receipt of your request and confirms a response will be sent to you promptly; 
and in any event not later than 5 October 2009. The Freedom of Information Office will 
contact you if we require any further information.  
 
Yours sincerely, 
 
 
 
Data Protection and Freedom of Information Office 
 
The information that you supplied with your Request for information will be entered into 
a  filing  system  and  will  only  be  accessed  by  authorised  persons  of  the  University  of 
Glasgow or its agents. The information will be retained by the University and will only 
be  used  for  the  purpose  of  (a)  processing  your  Request  for  information,  and  (b)  for 
statistical  and  audit  purposes.  By  supplying  such  information  you  consent  to  the 
University storing the information for the stated purpose. The information is held by the 
 
University in accordance with the provisions of the Data Protection Act 1998.