West Park play area refurbishment                
Playbuilder Grant - project timeline                
                 
                 
 Duration2009        2010     
  AprilMayJuneJulyAugSeptOctNovDecJanFebMarAprilMayJune
Design period                
Initial outline design for bid submission6 wks               
Submission to WSCC - 22 May 20090 wks               
Consultation with various groups6 wks               
On site consultation event0 wks               
Final design submitted to WSCC0 wks               
Compile & approve tender6 wks               
Final costs submitted to WSCC4 wks               
Award of Playbuilder funding0 wks               
                 
On award of funding                
                 
Procurement process                
Tenderers selection from select list1 wks               
                 
Tender Period                
Cabinet report & approval6 wks               
Tender issue & return4 wks               
Tender evaluation1 wks               
Appoint contactor2 wks               
Lead in period4 wks               
                 
Construction Period                
Site works period4 wks               
                 
Practical compeletion0 wks               
                 
Compeletion                
12 months defects liability period52 wks               
                 
                 
                 
                 
                 
                 
                 
                 
                 
                 
                 
                 