SCHEDULE G
TRANSITION
Schedule G (Transition)
Version 1.0
FINAL
18 July 2005
Released under FOI in full on 15th July 2008
PITO
IDENT1 CONTRACT
Northrop Grumman
Released under FOI in full on 15th July 2008
CONTENTS
1
OVERVIEW .............................................................................................................................1
2
OBJECTIVES AND REQUIREMENTS ...............................................................................1
3
RESPONSIBILITIES ..............................................................................................................2
4
CONTRACTOR’S TRANSITION PLAN .............................................................................2
5
TRANSITION CRITERIA......................................................................................................3
6
RISK REGISTER ....................................................................................................................3
7
TRANSITION DELAY............................................................................................................4
8
SERVICE LEVEL TRANSITION ACTIVITIES.................................................................4
9
REPORTING AND ESCALATION DURING TRANSITION ...........................................4
ANNEX G-1 - TRANSITION MILESTONE PLAN..........................................................................6
ANNEX G-2 DESCRIPTION OF TRANSITION...........................................................................14
Schedule G (Transition)
i
Version 1.0
FINAL
18 July 2005
Released under FOI in full on 15th July
PITO
IDENT1 CONTRACT
Northrop Grumman
Released under FOI in full on 15th July 2008
SCHEDULE G
TRANSITION
1
OVERVIEW
1.1
This Schedule:
1.1.1 describes the approach and processes that the Contractor shall follow to achieve
Transition;
1.1.2 describes the Transition Services and defines the responsibilities of the Contractor
during the Transition Period to achieve Transition both by TOR and FOC (as
applicable);
1.1.3 sets out the requirements for the management and further detailed development of the
Transition Plan to achieve the transfer of the Services from the Incumbent Supplier to
the Contractor and to enable the Contractor to assume responsibility for the provision
of the Services from the applicable Transfer Date;
1.1.4 sets out the objectives to be met and the Transition Milestones for both TOR and
FOC;
1.1.5 prescribes processes, procedures and governance principles (in accordance with
Clause 9 of this Schedule) to be followed by the Parties in further agreeing Transition
Milestones and Transition Criteria and escalating problems encountered during
Transition;
1.1.6 prescribes the procedure to be followed by the Contractor in assessing CWIP prior to
the relevant Transfer Date and for taking responsibility for delivering CWIP from
such Transfer Date; and
1.1.7 prescribes procedures for maintaining and updating the Risk Register.
1.2
The Contractor’s charges for all Transition Services provided in accordance with this
Schedule are included in the Service Charges as set out in Schedule E (Pricing) and the
Contractor shall not make any additional charge to the Authority in respect of such Transition
Services.
2
OBJECTIVES AND REQUIREMENTS
2.1
The purpose of this Schedule is to ensure that Transition and the activities comprised therein
shall meet the following objectives throughout Transition:
2.1.1 Key Transition Milestones shall be met by the dates set out in Annex G-1 of this
Schedule;
2.1.2 any and all CWIP shall be delivered by the Contractor (with effect from the relevant
Transfer Date) according to the delivery dates and costs previously agreed between
the Authority and the Incumbent Supplier;
2.1.3 insofar as is reasonably practicable, disruption to the business and operations to the
Authority shall be avoided;
2.1.4 the objectives set out in Schedule A (Form of Contract) shall be met; and
Schedule G (Transition)
1
Version 1.0
FINAL
18 July 2005
Released under FOI in full on 15th July 2008
PITO
IDENT1 CONTRACT
Northrop Grumman
Released under FOI in full on 15th July 2008
2.1.5 the continuity of the Authority’s business shall be safeguarded and a Business
Continuity Plan for all Services from the relevant Transfer Date(s) shall be delivered
to the Authority by the Contractor by the date identified in Annex G-1 of this
Schedule.
3
RESPONSIBILITIES
3.1
Transition Assistance
3.1.1 The Authority shall use its Commercially Reasonable Efforts (subject to Clause 3.1.2
below) to fulfil its responsibilities as expressly identified in this Schedule and/or the
Transition Plan and/or Schedule V (Authority’s Responsibilities). Any changes
subsequently included in the Transition Plan which impose additional or more
onerous obligations on the Authority shall be subject to and conditional upon the
prior written agreement of the Authorised Commercial Representative of the
Authority. Any such changes shall be agreed by the Parties in accordance with the
procedures set out in Schedule L (Change Control Procedure).
3.1.2 Where the Authority fails to meet its responsibilities (as such responsibilities are
described in Clause 3.1.1 above), the Parties shall discuss and agree any
consequential changes to the Transition Milestone Plan required to achieve Transition
in accordance with Clause 4.3 below.
3.2
Security
All Transition activity shall be performed in accordance with Schedule K (Security) and
Schedule Q (Contractor’s Solution).
4
CONTRACTOR’S TRANSITION PLAN
4.1
The Contractor shall achieve Transition by meeting the Milestones (the “Key Transition
Milestones”) as set out in Annex G-1 and summarised as follows:
4.1.1 the Contractor shall have completed the transfer of and assumed full responsibility for
the fulfilment of all the Services that the Authority requires the Contractor to provide
by TOR as identified in the Transition Plan; and
4.1.2 the Contractor shall have completed the transfer of and assumed full responsibility for
the fulfilment of all the Services that the Authority requires the Contractor to provide
by FOC as identified in the Transition Plan.
4.2
Content of Transition Plan
The Transition Plan shall be provided to the Authority as set out in Schedule O:31
(Documentation).
4.3
Updating and Changing the Transition Plan
4.3.1 The Transition Services, Transition Milestones and the Transition Criteria, as
identified at the Effective Date, are set out in Annex G-1 and the Transition Milestone
Plan (as applicable) and Schedule H (Acceptance Procedures), as applicable. The
Parties agree that each new Transition Milestone to be proposed by the Authority or
the Contractor after the Effective Date shall:
Schedule G (Transition)
2
Version 1.0
FINAL
18 July 2005
Released under FOI in full on 15th July 2008
PITO
IDENT1 CONTRACT
Northrop Grumman
Released under FOI in full on 15th July 2008
(a)
be entered by the Contractor in the Transition Milestone Plan as and when
agreed under this Clause 4.3 and shall:
(i)
be required to achieve the Key Transition Milestone occurring (A) on
TOR (the “TOR Transition Milestones”) or (B) on FOC (the “FOC
Transition Milestones”); or
(ii)
to the extent not described in Clause 4.2.1(a)(i) above, comprise of
those activities and deliverables which shall take place after the
relevant Transfer Date (“Post Transfer Date Transition
Milestones”);
(b)
in the case of TOR Transition Milestones and FOC Transition Milestones,
reflect the stages to be achieved during the Transition Period in order to
achieve Transition by the relevant Key Transition Milestones;
(c)
take account of the activities and deliverables set out in Annex G-2, Schedule
O (Documentation) or Schedule Q (Contractor’s Solution); and
(d)
correspond to the related information contained in the Transition Plan.
4.3.2 The Parties agree that any changes to the Transition Milestone after the Effective
Date shall be made in accordance with Schedule L (Change Control Procedure).
4.3.3 Any changes to Annex G-1/G-2 which materially effect the products to be delivered
under any Milestone are to be agreed via Schedule L (Change Control Procedure),
such changes may be suggested by either Party.
4.3.4 The Parties acknowledge that day to day changes to Annex G-2 will be dealt with via
changes to the IMS and shall be agreed by the Parties nominated technical
representative or their authorised deputies. In addition to the above, the Contractor
shall keep the Authority’s nominated commercial representative updated regularly (at
least monthly) of any such changes.
5
TRANSITION CRITERIA
The Contractor shall provide the Transition Services as required under Clause 9 of Schedule
B (Conditions of Contract) and the Contractor shall meet the Transition Milestones in
accordance with the Transition Plan (including the applicable Transition Criteria). Agreed
deliverables shall, where set out in the Transition Plan (for example, as part of the applicable
Transition Criteria), be subject to acceptance testing in accordance with Schedule H
(Acceptance Procedures).
6
RISK REGISTER
6.1
The Contractor shall, throughout Transition, work with the Authority to maintain and update a
risk register for the Transition Services for the purposes of tracking identified risks against
agreed timetables or Transition Milestones and resolving or escalating problems (“Risk
Register”). For the avoidance of doubt, the Risk Register and any provisions contained
within it are not, nor shall they be construed as being, legally binding on the Parties.
6.2
All changes to the Risk Register shall be managed and agreed between the Parties’ Transition
managers and shall not be subject to the procedures in Schedule L (Change Control
Procedure).
Schedule G (Transition)
3
Version 1.0
FINAL
18 July 2005
Released under FOI in full on 15th July 2008
PITO
IDENT1 CONTRACT
Northrop Grumman
Released under FOI in full on 15th July 2008
7
TRANSITION DELAY
7.1
The Contractor shall promptly draw the Authority’s attention to any actual or probable delay
that the Contractor is or becomes aware of in the performance of either Party’s tasks under the
Transition Plan likely to impact upon Transition timescales, in accordance with management
method procedures in Clause 2 of Part A of Schedule Q (Contractor’s Solution).
7.2
As soon as reasonably practicable following the Contractor becoming aware of such delay
under Clause 7.1 above, the Contractor shall propose, for the Authority’s approval at the
forthcoming Transition manager’s review meeting:
7.2.1 a plan of action to mitigate any risks to non-achievement of the Key Transition
Milestones;
7.2.2 a rigorous timetable for implementing the plan of action;
7.2.3 whether or not escalation is required under Clause 9 of this Schedule at this stage;
7.2.4 any necessary entries to the Risk Register to record the impact on the fulfilment of the
Services and achievement of the Key Transition Milestones of any such delay; and
7.2.5 whether any CCN is required to resolve the risk and any details relating to such CCN.
7.3
Any inability to agree the items set out in Clause 7.2 above, or any subsequent problem in
implementing the plan of action within the timetable agreed between the Parties under Clause
7.2 above, shall be promptly escalated by each Party in accordance with Clause 9 below.
7.4
The provisions of this Clause 7 shall be without prejudice to the Parties respective rights and
remedies set out in the Contract including for the avoidance of doubt the liquidated damages
set out in Clause 17 of Schedule B (Conditions of Contract).
8
SERVICE LEVEL TRANSITION ACTIVITIES
During the Transition Period the Contractor shall continue to comply with the Service Levels
in accordance with Schedule F (Service Level Requirements). The Contractor shall update
the Service Levels and corresponding supporting materials to reflect any changes that the
Parties agree to make to the Service Levels during the Transition Period.
9
REPORTING AND ESCALATION DURING TRANSITION
9.1
Transition Management Structure
9.1.1 Each Party shall appoint suitably qualified personnel and officers and, if relevant,
agents and advisers, to the following levels for the purposes of managing Transition:
(a)
Transition managers who will be responsible for supervising the progress by
the Transition team on each of the Transition work-streams set out in Annex
G-2 and as otherwise appropriate; and
(b)
such other levels of Transition-related governance as the Parties shall agree.
9.1.2 The Contractor shall control Transition through the application of the project and
programme management disciplines as set in the management method provisions of
Clause 2 of Part A of Schedule Q (Contractor’s Solution).
Schedule G (Transition)
4
Version 1.0
FINAL
18 July 2005
Released under FOI in full on 15th July 2008
PITO
IDENT1 CONTRACT
Northrop Grumman
Released under FOI in full on 15th July 2008
9.2
Workshops and Reporting
9.2.1 The Contractor shall provide the Authority with periodic Transition progress reports
in accordance with the reporting requirements set out in Schedule Q (Contractor’s
Solution). The reports shall also incorporate material from the project and
programme management disciplines referred to in Clause 1 of Annex G-2, as
appropriate. They shall identify both actual and anticipated problems and delays, the
remedial actions being taken, and the contingency options (with regard to time,
deliverable quality or any combination thereof) that are being considered.
9.2.2 The Transition managers shall meet on a periodic basis as mutually agreed (unless
circumstances require more or less frequent meetings) to consider the Contractor’s
progress report and update the Risk Register, if required.
9.2.3 Where workshops are used by the Contractor as a tool to deliver Transition, the
Contractor shall be responsible for the initiation, administration and leadership of
such workshops and shall provide the Authority with details of the timing, location
and proposed agenda for such workshops, as appropriate.
9.2.4 The Contractor shall manage Transition via periodic Transition meetings as mutually
agreed between the Authority and the Contractor to discuss progress made, expected
progress in the upcoming weeks issues, risks and, if appropriate, changes to the
Transition Plan. Any unresolved matters shall be promptly escalated to the Authority
as set out in Schedule I (Contract Management).
9.2.5 On a monthly basis, the Programme Status Review Meeting shall meet to provide
programme steering assistance and ensure that the objectives of Transition are being
met.
9.3
Escalation
9.3.1 During Transition, both Parties shall make every effort to ensure that all issues and
disputes are resolved between the Parties’ Transition managers. The periodic
Transition management meetings shall be the initial route for raising all issues and
disputes.
9.3.2 In the event that a dispute cannot be resolved by the Transition managers within one
(1) week of it being raised, either Party may escalate the issue to the nominated
representative as set out in Schedule I (Contract Management).
Schedule G (Transition)
5
Version 1.0
FINAL
18 July 2005
Released under FOI in full on 15th July 2008
PITO
IDENT1 CONTRACT
Northrop Grumman
Released under FOI in full on 15th July 2008
ANNEX G-1 - TRANSITION MILESTONE PLAN
The Transition Milestone Plan attached to this Annex G-1 contains the Transition Milestones agreed
as at the Effective Date and shall be updated by the Contractor in accordance with the provisions of
Clause 4.3 of Schedule G (Transition).
Transition Milestones
Milestone
Delivery Date
KEY MILESTONES
The Transition Milestone Plan is broken down into the following “key
milestones”:
1. Programme Initiation
2. TOR-NAFIS
3. Scottish Livescan
4. Palm Searching
5. TOR-SAFR
6. IDENT1 System HCI
7. Pre-FOC Checkpoint
8. FOC-Provisional
9. FOC
STAGES OF MILESTONE DELIVERY
The delivery of each Milestone set out below in this Annex G-1 has been broken
down into the following stages:
A) Description of Milestone – a summary of the key deliverable of the
associated milestone.
B) Prior Events – details of the prior events which need to have been
undertaken or achieved before the milestone can be completed.
C) Products Delivered – the list of products which should be delivered under
the associated milestone as detailed in the Schedule D (Detailed Operational
Requirements) and Schedule Q (Contractor’s Solution).
D) Project Management Products Delivered - the list of project management
products which should be delivered under the associated milestone as detailed in
the Schedule D (Detailed Operational Requirements) and Schedule Q
(Contractor’s Solution).
Schedule G (Transition)
6
Version 1.0
FINAL
18 July 2005
Released under FOI in full on 15th July 2008
PITO
IDENT1 CONTRACT
Northrop Grumman
Released under FOI in full on 15th July 2008
1
PROGRAMME INITIATION
17th
January
2005
1.1
Description
A sound basis for commencing the IDENT1 programme has been established.
1.2
Prior Events
Contract Award.
1.3
Products Delivered
For this Milestone the Contractor shall provide an overview of each major
functional area of its project team, with an introduction of key personnel,
programme
and
transition
approach,
key
deliverables,
and
initial
risks/mitigations.
Risk Management Plan
Programme Quality Plan
Programme Initiation Review Documentation
All detailed in Schedule O (Documentation)
1.4
Project Management Products
Integrated Master Schedule
Contractor-identified risks
Contractor-identified issues.
Schedule G (Transition)
7
Version 1.0
FINAL
18 July 2005
Released under FOI in full on 15th July 2008
PITO
IDENT1 CONTRACT
Northrop Grumman
Released under FOI in full on 15th July 2008
2
TOR - NAFIS
1 April 2005 or 4
Months ACA,
whichever is
greater
2.1
Description
Responsibility for delivering the NAFIS Services transfers to the Contractor.
2.2
Prior Events
Operational Acceptance Validation.
Contractor staff trained on NAFIS.
Staff recruited.
2.3
Products Delivered
Security Accreditation Documents from Schedule O (Documentation) (49, 50,
51, 52, 53, 55, 56)
Business Continuity Plan for TOR - NAFIS
Glossary (Detailed Operational Requirements)
Availability Plan
Capacity Plan
Configuration Management Plan
Programme Documentation
• Communication Plan
• Operations and Maintenance Support Plan
• Training Plan
• Software Development Plan
• Requirements Management Plan
xternal ICD’s for existing interfaces.
2.4
Project Management Products
Next Stage plans.
Schedule G (Transition)
8
Version 1.0
FINAL
18 July 2005
Released under FOI in full on 15th July 2008
PITO
IDENT1 CONTRACT
Northrop Grumman
Released under FOI in full on 15th July 2008
3
SCOTTISH LIVESCAN
1st April 2005
3.1
Description
The Contractor transitions Scottish Livescan services to the IDENT1 Service.
The Contractor takes on full operational responsibility for provision of the
Scottish Livescan Service.
3.2
Prior Events
As a minimum, Scottish Livescan functionality shall be provided at a level equal
to existing Scottish Livescan service.
Comms connectivity in place to meet current SAFR locations to be migrated to
MPLS by 30 April 2005..
Parallel Bureau or equivalent if agreed with Scotland established.
Scottish Livescan Operational Readiness Review.
3.3
Products Delivered
New IDENT1 Livescan units in Scotland and support for existing Livescan units
in Scotland that have not been replaced by 1 April 2005 is provided, with the
remainder of the new IDENT1 Livescan units to be installed not later than 30
April 2005. Additional Service Desk support procedures for Scottish Livescan
in place.
Scottish User training material available.
Livescan User manual available.
Software bridge between SAFR and IDENT1 in place.
Detailed Business Process Model.
Training Plan.
Test Procedure Specification.
3.4
Project Management Products
Product Descriptions for Service Desk support procedures, User training
material and Livescan manual.
Scotland Transition Project Plan.
Schedule G (Transition)
9
Version 1.0
FINAL
18 July 2005
Released under FOI in full on 15th July 2008
PITO
IDENT1 CONTRACT
Northrop Grumman
Released under FOI in full on 15th July 2008
4
PALM SEARCHING
1st August 2005
4.1
Description
Palm searching capability available to all installed Bureaux (England, Wales and
Scotland).
4.2
Prior Events
Benchmark Palm algorithms.
Usability trials.
Palm design review.
Operational Readiness Review.
4.3
Products Delivered
Pilot version of palm capability.
Test Procedure Specification
Training material for palm searching.
User Manual
Palm HCI
Palm matchers for national searches
4.4
Project Management Products
Palm Transition Plan.
Updated IMS
Acceptance Event Report (For Palm Project)
IAR Closure Minutes
5
TOR - SAFR
15th
January
2006
5.1
Description
Scottish Bureaux can access the full capabilities of IDENT1 system and SAFR is
decommissioned.
5.2
Prior Events
Schedule G (Transition)
10
Version 1.0
FINAL
18 July 2005
Released under FOI in full on 15th July 2008
PITO
IDENT1 CONTRACT
Northrop Grumman
Released under FOI in full on 15th July 2008
ORR
OAV
Scottish Livescan milestone achieved.
5.3
Products Delivered
External ICD.
Use case for CHS integration.
Training Material.
5.4
Project Management Products
Updated IMS.
Updated Scotland Transition Plan.
Stage Plan.
6
IDENT1 SYSTEM HCI
1st October 2006
6.1
Description
New Bureau workstation HCI implemented based on a series of User
evaluations/Livescan.
6.2
Prior Events
User Input Evaluation 1.
User Input Evaluation 2.
User Input Evaluation 3.
Acceptance Test.
Regression test.
ORR.
OAV.
6.3
Products Delivered
HCI Style Guide.
Test Procedures
Transition Plan (SISP)
Schedule G (Transition)
11
Version 1.0
FINAL
18 July 2005
Released under FOI in full on 15th July 2008
PITO
IDENT1 CONTRACT
Northrop Grumman
Released under FOI in full on 15th July 2008
HCI training materials.
Acceptance Event Report
User Manual
Detailed Business Process Model.
IAR Closure Minutes
6.4
Project Management Products
HCI deployment plan.
Updated IMS.
7
PRE-FOC CHECKPOINT
1st
November
2006
7.1
Description
Checkpoint for delivered functional capabilities prior to FOC.
7.2
Prior Events
ORR.
7.3
Products Delivered
Updated System Architecture Model.
Test Procedures
Stage Plan
Acceptance Event Report
IAR Closure Minutes
Complete Business Process Model.
7.4
Project Management Products
Updated IMS.
8
FOC-PROVISIONAL
1st
December
2006
8.1
Description
Schedule G (Transition)
12
Version 1.0
FINAL
18 July 2005
Released under FOI in full on 15th July 2008
PITO
IDENT1 CONTRACT
Northrop Grumman
Released under FOI in full on 15th July 2008
Full operational capability of IDENT1 established.
8.2
Prior Events
Updated IMS.
Relevant documentation in Schedule O (Documentation) updated to reflect the
proposed system to be delivered at FOC.
Full operational Service Level capability achieved in accordance with Schedule
F (Service Level Requirements).
8.3
Products Delivered
Services for IDENT1 FOC capability.
8.4
Project Management Products
Updated IMS.
IAR Closure Minutes.
9
FOC
1st January 2007
9.1
Description
Full operational capability validated and accepted.
9.2
Prior Events
FOC-Provisional achieved
OAV
IAR Closure Minutes
9.3
Products Delivered
Validated IDENT1 FOC Service.
9.4
Project Management Products
Updated IMS
Updates to relevant documentation in Schedule O (Documentation) to reflect
the actual system delivered at FOC.
Full operational Service Level capability achieved in accordance with Schedule
F (Service Level Requirements).
Schedule G (Transition)
13
Version 1.0
FINAL
18 July 2005
Released under FOI in full on 15th July 2008
PITO
IDENT1 CONTRACT
Northrop Grumman
Released under FOI in full on 15th July 2008
ANNEX G-2
DESCRIPTION OF TRANSITION
1
TRANSITION OVERVIEW
The Contractor shall produce a Transition Plan as described in Schedule O:31
(Documentation) for the Term of the Contract that covers FOC and any succeeding services.
The Contractor is intending to use the legacy architecture, including the System Architecture
Document and System Design Description of NAFIS, as the foundation from which to evolve
the Services.
The Contractor shall achieve TOR from NAFIS to the IDENT1 Service at the end of the
Contract for NAFIS Services. This includes the transfer, management, and technical
responsibility for all NAFIS Services requirements.
The Contractor shall manage the transition via the following four independent transition
projects:
•
The Migration Transition Project,
•
The Palms Transition Project,
•
The Scotland Transition Project, and
•
The Strategic Identification Services Platform (SISP) Transition Project.
The transition projects shall be coordinated in an integrated fashion for economies of scale
without creating any unnecessary interdependencies. Each project shall have detailed project
plans prepared and approved by the Authority as described in Schedule O:11
(Documentation).
Each transition project shall be implemented in stages to minimise technical risk and
disruption to operational Users. Stage plans and progress shall be monitored and reported to
the Authority and stakeholders in accordance with approved project reporting procedures (as
specified in management methods provisions of Clause 2 of Part A of Schedule Q
(Contractors Solution).
The Contractor shall conduct Operational Readiness Reviews (ORRs) and Operational
Acceptance Validations (OAVs) with the Authority for all transition stage events that alter the
system infrastructure.
The Contractor shall conduct a formal acceptance test as described in Schedule H
(Acceptance Procedures) and OAVs with the Authority for stage events that deliver
functional enhancements or implement User changes.
The Contractor shall manage all transition events in accordance with the Authority’s
processes that address technical, programmatic, and operational impacts.
The Contractor shall provide a Transition Manager, as set out in Part A of Schedule Q
(Contractors Solution), to oversee all transition activities and serve as the main point of
contact between the Contractor and the Authority in relation to transition activities.
The Contractor’s transition activities shall include personnel with practical experience in
Schedule G (Transition)
14
Version 1.0
FINAL
18 July 2005
Released under FOI in full on 15th July 2008
PITO
IDENT1 CONTRACT
Northrop Grumman
Released under FOI in full on 15th July 2008
transitioning operational systems within the UK police and fingerprint environments.
1.1
Migration Transition Project
The Contractor’s Migration Transition Project shall transition NAFIS Services to
Services for IDENT1 FOC capability and shall include functional enhancements.
Stage 1 will provide the Authority and (if directed by the Authority) stakeholders
with the ability to define and track key performance indicators such as MIS
Dashboard, etc and other enhanced MIS reporting to the Authority. A MIS
workstation shall be installed at NKBH and HDC to allow the Authority to monitor
and analyse business performance. The Contractor shall provide onsite assistance to
the Authority on the use of the business intelligence tool for the first month following
installation.
The Contractor’s Stage 2 shall deliver hardware and COTS upgrades which include
but shall not be limited to, the following:
•
Lightweight Directory Access Protocol (LDAP) to support IDENT1
directory information and security mechanisms.
•
Transition of the central and bureaux databases from Informix to
Oracle.
•
Upgrade of the servers to support new IDENT1 functionality, where
appropriate.
•
Upgrade of legacy RAID at bureaux and central segments, to support
increased workload under Services.
•
Upgrade of the existing network backbone at central sites to support
the addition of new hardware.
•
Conducting a business process review of bureau mark scanning and
printing activities as an element of business effectiveness.
Stage 3 shall provide functional enhancement described in Schedule D (Detailed
Operational Requirements) required to evolve the NAFIS Services to the Services
that are not already provided under the other transition projects. Such enhancements
shall include but not be limited to the ability to search free text fields / using
keywords, and to allow individual bureaux to configure workflow for confirmation of
identifications within the context of business rules.
Stage 4 shall provide upgrades to the ten (10) print and mark scanners which includes
but shall not be limited to the following:
•
at a minimum, the front side scanner shall capture 10 bits/pixel at
500dpi and the back side shall simultaneously capture 8 bits/pixel at
500dpi.
•
all flatbed scanners. At a minimum, the scanners shall output up to 16
bits/pixel to the workstations. Deployment of upgraded scanners shall
be concurrent with deployment of PC workstations to minimise
disruption to the bureaux.
Schedule G (Transition)
15
Version 1.0
FINAL
18 July 2005
Released under FOI in full on 15th July 2008
PITO
IDENT1 CONTRACT
Northrop Grumman
Released under FOI in full on 15th July 2008
Stage 5 shall provide upgrades to the legacy WAN which include but shall not be
limited to the following:
•
the conversion of the legacy Police National Computer (PNC)
interface to Internet Protocol.
•
transition of the legacy frame relay WAN to MPLS.
1.2
Palms Transition Project
The Contractor’s Palms Transition Project shall be broken down into 4 stages and
shall deliver a national, integrated palm-searching capability. The Contractor shall
develop a Transition Plan for this project as detailed in Schedule O:31 that shall
address the following areas:
•
Palm Human Computer Interface (HCI) changes,
•
Palm matchers for national palm searching,
•
Palm searching at bureaux, and
•
Encoding of existing palm prints.
Stage 1 shall address the following:
•
The Contractor shall deploy a pilot version of the palm capability to
the
Usability
Laboratory.
The
Contractor
shall
conduct
demonstrations, at the discretion of the Authority, with Users to
obtain feedback on the proposed HCI.
•
The Contractor shall conduct benchmarking and testing of new palm
algorithms.
•
The Contractor shall conduct an Operational Evaluation of the palm
matching algorithms.
•
The Contractor shall upgrade training systems and the Test and
Development configurations to support palm-searching capability.
Stage 2 shall deploy the operational palm-searching capability as follows:
•
The Contractor shall conduct an ORR as a formal transition meeting
to assess and determine readiness to deploy.
•
The ORR shall review results of development and testing.
•
The ORR shall also address a deployment schedule, including pre-
release orientation and a review of training documentation.
•
The deployment planning shall include the deployment of Print Set
scanner upgrades required to support palm searching.
•
The Contractor shall deploy palm matching algorithms and
processors to the operational system.
Schedule G (Transition)
16
Version 1.0
FINAL
18 July 2005
Released under FOI in full on 15th July 2008
PITO
IDENT1 CONTRACT
Northrop Grumman
Released under FOI in full on 15th July 2008
•
The Contractor shall provide onsite training and assistance to bureau
staff as part of the deployment process.
Stage 3 shall include the capability to import palm data from standalone palm systems
at Avon and Somerset, Kent, Bedfordshire, Leicestershire, and West Yorkshire.
•
The Contractor shall define an AIS data exchange format, in
accordance with ANSI NIST.
•
The bureau shall be responsible for delivering legacy data in the
approved format.
Stage 4 shall encode palm prints and palm marks currently stored in the national
collection. This conversion shall be undertaken by the Contractor. The conversion
process shall provide the capability for bureaux personnel to monitor the process for
quality purposes.
1.3
Scotland Transition Project
The Contractor shall provide accommodation for the training system for the transition
training of the SFS until transition from SAFR to IDENT1. The training system for
the SFS shall be located either at the same premises as the Glasgow Bureau or at a
mutually agreed-upon alternate location.
The Contractor’s Scotland Transition Project shall integrate Scotland into the
Services. This project shall deploy Livescan units with palm capture capability at
Scottish charging stations and fully integrate SAFR into the IDENT1 Services.
The Contractor shall develop a Transition Plan for the Scotland Transition Project as
detailed in Schedule O:31 (Documentation). The transition plan shall address the
overall transition approach and detail the stages within the project. The Scotland
Transition Project shall be divided into the following six stages:
(1)
Stage 1—Parallel Bureau Configuration.
(2)
Stage 2—Existing Livescan Service Transition.
(3)
Stage 3—Data Migration.
(4)
Stage 4—Scottish Transition to IDENT1.
(5)
Stage 5—Deploy Additional Livescan EIUs.
(6)
Stage 6—Scotland Criminal History Link.
Stage 1 shall establish a parallel IDENT1 bureau configuration at Glasgow. This
stage includes the development and installation of a software bridge that provides the
ability to process print sets from IDENT1 Livescan EIUs on both IDENT1 and
SAFR.
•
Stage 1 shall deploy the initial IDENT1 bureau system within the
current SCRO facility space, or in a mutually agreed-upon alternate
location in close proximity to SCRO. The bureau shall be configured
with a server, RAID, local area network, and a minimum two
workstations. The Contractor shall be responsible for all facility costs
should the alternate location be required.
Schedule G (Transition)
17
Version 1.0
FINAL
18 July 2005
Released under FOI in full on 15th July 2008
PITO
IDENT1 CONTRACT
Northrop Grumman
Released under FOI in full on 15th July 2008
•
Stage 1 activities shall provide the capability to test Livescan EIU
connectivity to SAFR prior to replacing existing Scotland Livescan
units with IDENT1 Livescan units.
•
Stage 1 installation shall provide the ability to support early
familiarisation training of operators in the basic functionality
provided by IDENT1 Print Sets.
•
Stage 1 shall extend the IDENT1 Comms WAN to existing SAFR
locations.
Stage 2 shall transition Scottish Livescan service to IDENT1 and shall install ( or
takeover) and make operational IDENT1 Livescan EIUs at each current Scotland
Livescan location. Deliverables shall include but not be limited to:
•
installing (or takeover )and making operational IDENT1 Livescan
EIUs at remaining locations in Scotland during Stage 2;
o
developing a rollout plan with the SFS and the Authority;
and
o
providing onsite training for each deployed location;
•
assuming full operational responsibility for each Livescan EIU upon
installation or takeover of existing units;
•
enabling the capture of palms and the retention of a copy of palm
images of the new installed units in IDENT1;
•
allowing print sets to be searched against both the SAFR and
IDENT1 Print Set databases; and
•
enabling searching of IDENT1 and SAFR unidentified marks
databases.
Stage 3 shall provide for the migration of legacy SAFR data to IDENT1, including
BRC of palm images held in paper format by SCRO. The Contractor shall perform
the BRC on all existing SAFR records. Deliverables shall include but not be limited
to:
•
the capability to hold records in a Unified Collection and to maintain
selected records in the SAFR;
•
establishing, in coordination with SFS and the Authority, weeding
rules specific to Scotland records;
•
ensuring that each SAFR Print Set record is searched against the
IDENT1 Unified Collection to ensure that no duplicates exist. SFS
Fingerprint Experts shall be required to review respondents and
confirm identity and disposition. Support the transfer of legacy
Scottish SAFR MIS and audit data to IDENT1; and
•
providing a business continuity capability for Scotland AFR records
through the IDENT1 central facilities.
Schedule G (Transition)
18
Version 1.0
FINAL
18 July 2005
Released under FOI in full on 15th July 2008
PITO
IDENT1 CONTRACT
Northrop Grumman
Released under FOI in full on 15th July 2008
Stage 4 shall transfer Scottish fingerprint services to IDENT1. The Contractor shall
work with SFS to coordinate the decommissioning of the legacy SAFR. Deliverables
shall include but not be limited to:
•
deploying IDENT1 bureau systems at Aberdeen, Edinburgh, and
Dundee;
•
providing an IDENT1 suite of equipment in Scotland to support
transition training. The Contractor shall provide onsite training of the
IDENT1 system, and usage to bureau and SCRO staff to support
initial operations;
•
providing an OAV in accordance with Schedule H (Acceptance
Procedures); and
•
providing for a 30-day operational period under the IDENT1 Service
Level Request (SLR) to verify that the system meets performance
and availability requirements.
At the completion of Stage 4, the full TOR for Scotland is complete.
Stage 5 shall deploy any remaining Livescan EIUs to the Scottish forces that were not
deployed during Stage 2.
If requested by the Authority, Stage 6 shall provide an electronic interface between
IDENT1 and the Scottish CHS. This stage shall provide the capability to update both
the IDENT1 database and the Scottish Criminal History database as a result of arrest
processing.
The Contractor shall develop a Use Case in conjunction with the SCRO and the
Authority. Upon agreement of the Use Case, the Contractor shall develop an
inception review and prepare an ICD. Full implementation shall include elaboration
and construction reviews prior to transition. The Contractor shall work with the
Authority to ensure that IDENT1 can access both CHS and PNC .
1.4
SISP Transition Project
The Contractor’s SISP Transition Project shall deliver the strategic platform for full
IDENT1 Services at FOC. The Contractor shall initially develop a transition plan for
the SISP Transition Project as detailed in Schedule O:31. This project shall build
upon the system upgrades from the Contractor’s Migration Transition Project and
shall be based on Web application server technology and standardised Simple Object
Access Protocol (“SOAP”), interfaces. The project shall modify the Services through
functional enhancements as described in Schedule D (Detailed Operational
Requirements), COTS software upgrades, delivery of new hardware, security
upgrades, and communications upgrades.
The Contractor’s SISP transition project approach shall emphasise business
continuity during normal operations and during system evolution through incremental
design and delivery of new capabilities and functionality. The Contractor’s SISP
Transition Project shall be delivered via the following four (4) subprojects:
(1)
Central Architecture Subproject;
(2)
Matcher Upgrade Subproject;
Schedule G (Transition)
19
Version 1.0
FINAL
18 July 2005
Released under FOI in full on 15th July 2008
PITO
IDENT1 CONTRACT
Northrop Grumman
Released under FOI in full on 15th July 2008
(3)
Bureau Architecture Subproject; and
(4)
Bureau Workstation HCI Subproject.
Each subproject shall be implemented via stages.
Any stage with an ITED release within the SISP Transition Project that alters the
infrastructure shall include regression tests, an internal Contractor ORR, and an OAV
with the Authority.
Any stage within the SISP Transition Project that delivers new functionality or
changes that impact Users shall conclude with formal acceptance tests with the
Authority, followed by an Authority-witnessed OAV as detailed in Schedule H
(Acceptance Procedures).
The Central Architecture Subproject shall deliver and install Web services and
application servers, with load balancing between central facilities. This subproject
shall be divided into two (2) stages:
(1)
High Availability Live ID Searches Stage.
The Contractor shall implement two additional applications servers at the
primary and secondary central sites, for hosting central web services. The
Services shall be configured to support load balancing between sites and to
provide automatic failover for web-hosted services.
The Contractor shall reconfigure Livescan EIUs to send Live ID requests to
applications servers. The Contractor shall configure internal and external web
portals and the central sites for entry points for the MIS Dashboard, system
status and monitoring, service desk ticket status, and data management
functions.
(2)
Web Services for All Searches Stage.
The Contractor shall transition all search transactions to use high-availability
web services, with associated load-sharing and failover features.
The Matcher Upgrade Subproject builds upon the legacy scalable matching
subsystem to provide higher accuracy and increased flexibility. This subproject shall
be divided into three stages:
(1)
Matcher Platform Enhancement Stage.
The Contractor shall expand the Services to handle multiple encoding and
matching algorithms. The Contractor shall implement new feature extraction
as a BRC process, without interruption to the operational system. Software
deployments of new capabilities shall be conducted in incremental releases
that are planned and coordinated with the Authority. The Contractor shall
conduct database integrity checks as an integral aspect of this stage.
(2)
Data Fusion Stage.
The Contractor shall deploy data fusion between the SAGEM and legacy
algorithms. The Services shall use features from both algorithms. The System
shall retain tracking of resultant search score as to whether it comes from
legacy, SAGEM or fused algorithms.
Schedule G (Transition)
20
Version 1.0
FINAL
18 July 2005
Released under FOI in full on 15th July 2008
PITO
IDENT1 CONTRACT
Northrop Grumman
Released under FOI in full on 15th July 2008
The Contractor shall begin storing, on a day one forward basis, all available
friction ridge detail from each arrest form. The Contractor shall conduct
operational testing of the accuracy and performance improvements associated
with using multiple rolls, and rolls with flats.
(3)
Person Fusion Stage.
The Contractor shall deploy the fusion of searches against flats and multiple
rolls, into a single fused score for a person. The matching subsystem shall
indicate whether the respondent was a plain or a roll and the associated FIN
as defined in Schedule D (Detailed Operational Requirements). The
corresponding plain or roll shall be returned to the User for verification.
The Bureau Architecture Subproject develops a new bureau architecture suitable for
IDENT1 applications with web services. This subproject shall be divided into three
stages:
(1) Port to Linux Stage.
The Contractor shall port the existing HCI to PCs running the Linux
operating system. A phased deployment plan of PCs to the bureaux shall be
developed in coordination with the Authority.
The deployment shall be managed as a production release and shall include
the deployment of the agreed-upon number of additional workstations.
(2)
Application Server Infrastructure Stage.
The Contractor shall develop and deploy the Application Server as the
repository for the business logic accessed by the bureau workstations. The
bureau Application Server shall provide standard J2EE services, including:
(i)
Security;
(ii) Messaging;
(iii) Networking;
(iv) Database connectivity;
(v) Web services connectivity with SOAP;
(vi) Connections to legacy systems; and
(vii) Transaction management.
(3)
Bureau Services Stage.
The Contractor shall transition the business logic from the workstation HCI
to the bureau services on the bureau Application Server.
The Contractor’s transition shall allow the new architecture to coexist at the
bureau with legacy architecture to minimise impact on Users.
The deployment of the architecture shall be piloted at the Contractor’s bureau
configuration prior to rollout to operational forces
The Contractor shall develop, in coordination with the Authority, a
deployment schedule with the forces. The deployment schedule shall address
bureau training implications.
Schedule G (Transition)
21
Version 1.0
FINAL
18 July 2005
Released under FOI in full on 15th July 2008
PITO
IDENT1 CONTRACT
Northrop Grumman
Released under FOI in full on 15th July 2008
The Contractor’s Bureau Workstation HCI Subproject shall provide a new
workstation HCI, based on a series of User evaluations. This subproject shall be
divided into four (4) stages:
(1)
User Input Evaluation (UIE) 1 Stage.
The Contractor shall conduct a UIE to gain feedback from Users on the
Contractor’s initial prototype. The UIE shall contain mockups of the main
screens and shall contain demonstrations of the main threads for Ten Print
and Mark transactions.
(2)
UIE 2 Stage.
The Contractor shall incorporate comments from UIE 1 and shall conduct a
second UIE to gain additional feedback on the updated prototype. This UIE
shall contain mockups of additional, lower level screens, as well as new
screen functionality and enhancements.
(3)
UIE 3 Stage.
The Contractor shall incorporate comments from UIE 2 and shall conduct a
final UIE. The Contractor shall incorporate comments from UIE 3 and
provide mockups of all screens, as well as IDENT1 capabilities.
(4)
Integration with Bureau Web Services Stage.
The Contractor shall integrate the standalone workstation HCI with the
bureau server, using web services. The new HCI shall be deployed in a
planned release to the bureaux. Bureau PCs running Linux shall be
transitioned to the Windows OS if requested by the Authority.
The Contractor shall conduct acceptance and regression testing. The
Contractor shall develop deployment plans, in coordination with the
Authority and the forces. The deployment plans shall address rollout
activities, including User training.
1.5
Data Migration and Back Record Conversion (BRC)
Data Migration and Back Record Conversion activity are included within each of the
above projects. The following information summarises these activities.
The Contractor shall prepare a Data Migration and BRC plan for the conversion of
NAFIS and SAFR records.
The Data Migration plan will include the migration of the MIS, Audit, Archive,
Image and Encoding, ORD, Serious Crime Cache, and Police Eliminations data.
The Contractor shall use ISO Standard 2859-1 for sampling methodology for quality
and data integrity.
The Stage Plan (O:18) shall define roles and responsibilities for the Contractor, the
Authority, and all relevant stakeholders in relation to DM and BRC activity.
The Contractor shall derive the IDENT1 Services Unified Collection of Print Sets and
palms from legacy NAFIS Services and SAFR Services records. The Contractor shall
ensure that encoding of the IDENT1 Services Unified Collection of Print Sets is done
automatically. The Contractor shall provide access for the Authority and bureaux
Schedule G (Transition)
22
Version 1.0
FINAL
18 July 2005
Released under FOI in full on 15th July 2008
PITO
IDENT1 CONTRACT
Northrop Grumman
Released under FOI in full on 15th July 2008
staff to review samples for quality and data integrity.
The Contractor shall perform paper BRC of SAFR palm image records. The
Contractor personnel shall perform the BRC tasks, with Authority approval and
oversight. BRC for Scotland palm image records shall be completed by TOR-SAFR.
The Contractor shall provide the capability and processes to transfer Leicestershire,
Bedfordshire and West Yorkshire bureaux palm system records to the IDENT1
Services. These records were created with NAFIS Services record identifications and
shall be added to the Unified Collection.
The Contractor shall provide a record format and interface for the transfer of Avon
and Somerset and Kent Bureaux palm system records and automatically encode those
records. Upon agreement of an AIS data exchange format, in accordance with ANSI
NIST, the bureaux may elect to transfer all or selected records. Records that are
transferred will be encoded and images will be stored in IDENT1 Services formats.
The Contractor shall perform BRC activities of NIST formatted palm records for the
Staffordshire bureau.
The Contractor shall perform the automated data migration of the unified unidentified
marks collection from existing records held on NAFIS Services and SAFR Services
systems. All marks shall be retained as encoded by the Fingerprint Officers (FPOs)
on those systems.
Schedule G (Transition)
23
Version 1.0
FINAL
18 July 2005
Released under FOI in full on 15th July 2008