SCHEDULE G 
TRANSITION
Schedule G (Transition) 
 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman
 
Released under FOI in full on 15th July 2008 
CONTENTS 

OVERVIEW .............................................................................................................................1 

OBJECTIVES AND REQUIREMENTS ...............................................................................1 

RESPONSIBILITIES ..............................................................................................................2 

CONTRACTOR’S TRANSITION PLAN .............................................................................2 

TRANSITION CRITERIA......................................................................................................3 

RISK REGISTER ....................................................................................................................3 

TRANSITION DELAY............................................................................................................4 

SERVICE LEVEL TRANSITION ACTIVITIES.................................................................4 

REPORTING AND ESCALATION DURING TRANSITION ...........................................4 
ANNEX G-1 - TRANSITION MILESTONE PLAN..........................................................................6 
ANNEX G-2  DESCRIPTION OF TRANSITION...........................................................................14 
 
Schedule G (Transition) 

Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman
 
Released under FOI in full on 15th July 2008 
SCHEDULE G 
TRANSITION 

OVERVIEW 
1.1 
This Schedule:  
1.1.1  describes  the  approach  and  processes  that  the  Contractor  shall  follow  to  achieve 
Transition; 
1.1.2  describes  the  Transition  Services  and  defines  the  responsibilities  of  the  Contractor 
during  the  Transition  Period  to  achieve  Transition  both  by  TOR  and  FOC  (as 
applicable); 
1.1.3  sets out the requirements for the management and further detailed development of the 
Transition Plan to achieve the transfer of the Services from the Incumbent Supplier to 
the Contractor and to enable the Contractor to assume responsibility for the provision 
of the Services from the applicable Transfer Date; 
1.1.4  sets  out  the  objectives  to  be  met  and  the  Transition  Milestones  for  both  TOR  and 
FOC;  
1.1.5  prescribes  processes,  procedures  and  governance  principles  (in  accordance  with 
Clause 9 of this Schedule) to be followed by the Parties in further agreeing Transition 
Milestones  and  Transition  Criteria  and  escalating  problems  encountered  during 
Transition; 
1.1.6  prescribes the procedure to be followed by the Contractor in assessing CWIP prior to 
the  relevant  Transfer  Date  and  for  taking  responsibility  for  delivering  CWIP  from 
such Transfer Date; and  
1.1.7  prescribes procedures for maintaining and updating the Risk Register. 
1.2 
The  Contractor’s  charges  for  all  Transition  Services  provided  in  accordance  with  this 
Schedule  are  included  in  the  Service  Charges  as  set  out  in  Schedule  E  (Pricing)  and  the 
Contractor shall not make any additional charge to the Authority in respect of such Transition 
Services. 

OBJECTIVES AND REQUIREMENTS 
2.1 
The purpose of this Schedule is to ensure that Transition and the activities comprised therein 
shall meet the following objectives throughout Transition: 
2.1.1  Key  Transition  Milestones  shall  be  met  by  the  dates  set  out  in  Annex  G-1  of  this 
Schedule; 
2.1.2  any and all CWIP shall be delivered by the Contractor (with effect from the relevant 
Transfer  Date)  according  to  the  delivery  dates  and  costs  previously  agreed  between 
the Authority and the Incumbent Supplier;  
2.1.3  insofar as is reasonably practicable, disruption to the business and operations to the 
Authority shall be avoided; 
2.1.4  the objectives set out in Schedule A (Form of Contract) shall be met; and  
Schedule G (Transition) 

Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman
 
Released under FOI in full on 15th July 2008 
2.1.5  the  continuity  of  the  Authority’s  business  shall  be  safeguarded  and  a  Business 
Continuity Plan for all Services from the relevant Transfer Date(s) shall be delivered 
to  the  Authority  by  the  Contractor  by  the  date  identified  in  Annex  G-1  of  this 
Schedule. 

RESPONSIBILITIES 
3.1 
Transition Assistance 
3.1.1  The Authority shall use its Commercially Reasonable Efforts (subject to Clause 3.1.2 
below) to fulfil its responsibilities as expressly identified in this Schedule and/or the 
Transition  Plan  and/or  Schedule  V  (Authority’s  Responsibilities).  Any  changes 
subsequently  included  in  the  Transition  Plan  which  impose  additional  or  more 
onerous  obligations  on  the  Authority  shall  be  subject  to  and  conditional  upon  the 
prior  written  agreement  of  the  Authorised  Commercial  Representative  of  the 
Authority.  Any  such  changes  shall  be  agreed  by  the  Parties  in  accordance  with  the 
procedures set out in Schedule L (Change Control Procedure). 
3.1.2  Where  the  Authority  fails  to  meet  its  responsibilities  (as  such  responsibilities  are 
described  in  Clause  3.1.1  above),  the  Parties  shall  discuss  and  agree  any 
consequential changes to the Transition Milestone Plan required to achieve Transition 
in accordance with Clause 4.3 below.  
3.2 
Security 
All  Transition  activity  shall  be  performed  in  accordance  with  Schedule  K  (Security)  and 
Schedule Q (Contractor’s Solution).  

CONTRACTOR’S TRANSITION PLAN 
4.1 
The  Contractor  shall  achieve  Transition  by  meeting  the  Milestones  (the  “Key  Transition 
Milestones”) as set out in Annex G-1 and summarised as follows:  
4.1.1  the Contractor shall have completed the transfer of and assumed full responsibility for 
the fulfilment of all the Services that the Authority requires the Contractor to provide 
by TOR as identified in the Transition Plan; and 
4.1.2  the Contractor shall have completed the transfer of and assumed full responsibility for 
the fulfilment of all the Services that the Authority requires the Contractor to provide 
by FOC as identified in the Transition Plan. 
4.2 
Content of Transition Plan 
The  Transition  Plan  shall  be  provided  to  the  Authority  as  set  out  in  Schedule  O:31 
(Documentation). 
4.3 
Updating and Changing the Transition Plan  
4.3.1  The  Transition  Services,  Transition  Milestones  and  the  Transition  Criteria,  as 
identified at the Effective Date, are set out in Annex G-1 and the Transition Milestone 
Plan  (as  applicable)  and  Schedule  H  (Acceptance  Procedures),  as  applicable.  The 
Parties agree that each new Transition Milestone to be proposed by the Authority or 
the Contractor after the Effective Date shall: 
Schedule G (Transition) 

Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman
 
Released under FOI in full on 15th July 2008 
(a) 
be  entered  by  the  Contractor  in  the  Transition  Milestone  Plan  as  and  when 
agreed under this Clause 4.3 and shall:  
(i) 
be required to achieve the Key Transition Milestone occurring (A) on 
TOR (the “TOR Transition Milestones”) or (B) on FOC (the “FOC 
Transition Milestones”); or 
(ii) 
to  the  extent  not  described  in  Clause  4.2.1(a)(i)  above,  comprise  of 
those  activities  and  deliverables  which  shall  take  place  after  the 
relevant  Transfer  Date  (“Post  Transfer  Date  Transition 
Milestones”);  
(b) 
in  the  case  of  TOR  Transition  Milestones  and  FOC  Transition  Milestones, 
reflect  the  stages  to  be  achieved  during  the  Transition  Period  in  order  to 
achieve Transition by the relevant Key Transition Milestones;  
(c) 
take account of the activities and deliverables set out in Annex G-2, Schedule 
O (Documentation) or Schedule Q (Contractor’s Solution); and 
(d) 
correspond to the related information contained in the Transition Plan.  
4.3.2  The  Parties  agree  that  any  changes  to  the  Transition  Milestone  after  the  Effective 
Date shall be made in accordance with Schedule L (Change Control Procedure). 
4.3.3  Any changes to Annex G-1/G-2 which materially effect the products to be delivered 
under any Milestone are to be agreed via Schedule L (Change Control Procedure), 
such changes may be suggested by either Party. 
4.3.4  The Parties acknowledge that day to day changes to Annex G-2 will be dealt with via 
changes  to  the  IMS  and  shall  be  agreed  by  the  Parties  nominated  technical 
representative  or their  authorised  deputies.    In  addition  to  the  above,  the  Contractor 
shall keep the Authority’s nominated commercial representative updated regularly (at 
least monthly) of any such changes. 

TRANSITION CRITERIA 
The Contractor shall provide the Transition Services as required under Clause 9 of Schedule 
B  (Conditions  of  Contract)  and  the  Contractor  shall  meet  the  Transition  Milestones  in 
accordance  with  the  Transition  Plan  (including  the  applicable  Transition  Criteria).  Agreed 
deliverables shall, where set out in the Transition Plan (for example, as part of the applicable 
Transition  Criteria),  be  subject  to  acceptance  testing  in  accordance  with  Schedule  H 
(Acceptance Procedures).  

RISK REGISTER 
6.1 
The Contractor shall, throughout Transition, work with the Authority to maintain and update a 
risk  register  for  the  Transition  Services  for  the  purposes  of  tracking  identified  risks  against 
agreed  timetables  or  Transition  Milestones  and  resolving  or  escalating  problems  (“Risk 
Register”).  For  the  avoidance  of  doubt,  the  Risk  Register  and  any  provisions  contained 
within it are not, nor shall they be construed as being, legally binding on the Parties.  
6.2 
All changes to the Risk Register shall be managed and agreed between the Parties’ Transition 
managers  and  shall  not  be  subject  to  the  procedures  in  Schedule  L  (Change  Control 
Procedure).  
Schedule G (Transition) 

Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman
 
Released under FOI in full on 15th July 2008 

TRANSITION DELAY 
7.1 
The Contractor shall promptly draw the Authority’s attention to any actual or probable delay 
that the Contractor is or becomes aware of in the performance of either Party’s tasks under the 
Transition Plan likely to impact upon Transition timescales, in accordance with management 
method procedures in Clause 2 of Part A of Schedule Q (Contractor’s Solution). 
7.2 
As  soon  as  reasonably  practicable  following  the  Contractor  becoming  aware  of  such  delay 
under  Clause  7.1  above,  the  Contractor  shall  propose,  for  the  Authority’s  approval  at  the 
forthcoming Transition manager’s review meeting: 
7.2.1  a  plan  of  action  to  mitigate  any  risks  to  non-achievement  of  the  Key  Transition 
Milestones; 
7.2.2  a rigorous timetable for implementing the plan of action; 
7.2.3  whether or not escalation is required under Clause 9 of this Schedule at this stage; 
7.2.4  any necessary entries to the Risk Register to record the impact on the fulfilment of the 
Services and achievement of the Key Transition Milestones of any such delay; and 
7.2.5  whether any CCN is required to resolve the risk and any details relating to such CCN. 
7.3 
Any  inability  to  agree  the  items  set  out  in  Clause  7.2  above,  or  any  subsequent  problem  in 
implementing the plan of action within the timetable agreed between the Parties under Clause 
7.2 above, shall be promptly escalated by each Party in accordance with Clause 9 below. 
7.4 
The provisions of this Clause 7 shall be without prejudice to the Parties respective rights and 
remedies set out in the Contract including for the avoidance of doubt the liquidated damages 
set out in Clause 17 of Schedule B (Conditions of Contract). 

SERVICE LEVEL TRANSITION ACTIVITIES 
During the Transition Period the Contractor shall continue to comply with the Service Levels 
in accordance with Schedule F (Service Level Requirements). The Contractor shall update 
the  Service  Levels  and  corresponding  supporting  materials  to  reflect  any  changes  that  the 
Parties agree to make to the Service Levels during the Transition Period. 

REPORTING AND ESCALATION DURING TRANSITION 
9.1 
Transition Management Structure 
9.1.1  Each  Party  shall  appoint  suitably  qualified  personnel  and  officers  and,  if  relevant, 
agents and advisers, to the following levels for the purposes of managing Transition: 
(a) 
Transition managers who will be responsible for supervising the progress by 
the Transition team on each of the Transition work-streams set out in Annex 
G-2 and as otherwise appropriate; and  
(b) 
such other levels of Transition-related governance as the Parties shall agree. 
9.1.2  The  Contractor  shall  control  Transition  through  the  application  of  the  project  and 
programme  management  disciplines as set  in the  management  method provisions  of 
Clause 2 of Part A of Schedule Q (Contractor’s Solution).  
 
Schedule G (Transition) 

Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman
 
Released under FOI in full on 15th July 2008 
9.2 
Workshops and Reporting  
9.2.1  The Contractor shall provide the Authority with periodic Transition progress reports 
in  accordance  with  the  reporting  requirements  set  out  in  Schedule  Q  (Contractor’s 
Solution).  The  reports  shall  also  incorporate  material  from  the  project  and 
programme  management  disciplines  referred  to  in  Clause  1  of  Annex  G-2,  as 
appropriate. They shall identify both actual and anticipated problems and delays, the 
remedial  actions  being  taken,  and  the  contingency  options  (with  regard  to  time, 
deliverable quality or any combination thereof) that are being considered.  
9.2.2  The  Transition  managers  shall  meet  on  a  periodic  basis  as  mutually  agreed  (unless 
circumstances  require  more  or  less  frequent  meetings)  to  consider  the  Contractor’s 
progress report and update the Risk Register, if required.  
9.2.3  Where  workshops  are  used  by  the  Contractor  as  a  tool  to  deliver  Transition,  the 
Contractor  shall  be  responsible  for  the  initiation,  administration  and  leadership  of 
such  workshops  and  shall  provide  the  Authority  with  details  of  the  timing,  location 
and proposed agenda for such workshops, as appropriate.  
9.2.4  The Contractor shall manage Transition via periodic Transition meetings as mutually 
agreed between the Authority and the Contractor to discuss progress made, expected 
progress  in  the  upcoming  weeks  issues,  risks  and,  if  appropriate,  changes  to  the 
Transition Plan. Any unresolved matters shall be promptly escalated to the Authority 
as set out in Schedule I (Contract Management). 
9.2.5  On  a  monthly  basis,  the  Programme  Status  Review  Meeting  shall  meet  to  provide 
programme steering assistance and ensure that the objectives of Transition are being 
met. 
9.3 
Escalation 
9.3.1  During Transition, both Parties shall make every effort to ensure that all issues and 
disputes  are  resolved  between  the  Parties’  Transition  managers.  The  periodic 
Transition  management  meetings  shall  be  the  initial  route  for  raising  all  issues  and 
disputes. 
9.3.2  In the event that a dispute cannot be resolved by the Transition managers within one 
(1)  week  of  it  being  raised,  either  Party  may  escalate  the  issue  to  the  nominated 
representative as set out in Schedule I (Contract Management). 
Schedule G (Transition) 

Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman
 
Released under FOI in full on 15th July 2008 
ANNEX G-1 - TRANSITION MILESTONE PLAN 
The Transition Milestone Plan attached to this Annex G-1 contains the Transition Milestones agreed 
as at the Effective Date and shall be updated by the Contractor in accordance with the provisions of 
Clause 4.3 of Schedule G (Transition). 
Transition Milestones  
Milestone 
Delivery Date 
KEY MILESTONES 
 
The  Transition  Milestone  Plan  is  broken  down  into  the  following  “key 
milestones”: 
1.  Programme Initiation 
2.  TOR-NAFIS 
3.  Scottish Livescan 
4.  Palm Searching  
5.  TOR-SAFR  
6.  IDENT1 System HCI 
7.  Pre-FOC Checkpoint 
8.  FOC-Provisional 
9.  FOC 
STAGES OF MILESTONE DELIVERY 
The delivery of each Milestone set out below in this Annex G-1 has been broken 
down into the following stages: 
A)  Description  of  Milestone  –  a  summary  of  the  key  deliverable  of  the 
associated milestone. 
B)  Prior  Events  –  details  of  the  prior  events  which  need  to  have  been 
undertaken or achieved before the milestone can be completed. 
C) Products  Delivered  – the  list  of  products  which  should be  delivered under 
the  associated  milestone  as  detailed  in  the  Schedule  D  (Detailed  Operational 
Requirements) and Schedule Q (Contractor’s Solution). 
D) Project Management Products Delivered - the list of project management 
products which should be delivered under the associated milestone as detailed in 
the  Schedule  D  (Detailed  Operational  Requirements)  and  Schedule  Q 
(Contractor’s Solution). 
Schedule G (Transition) 

Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman
 
Released under FOI in full on 15th July 2008 

PROGRAMME INITIATION 
17th 
January 
2005 
1.1 
Description 
 
A sound basis for commencing the IDENT1 programme has been established. 
 
1.2 
Prior Events 
 
Contract Award. 
 
1.3 
Products Delivered 
 
For  this  Milestone  the  Contractor  shall  provide  an  overview  of  each  major 
functional  area  of  its  project  team,  with  an  introduction  of  key  personnel, 
programme 
and 
transition 
approach, 
key 
deliverables, 
and 
initial 
risks/mitigations. 
Risk Management Plan 
 
Programme Quality Plan 
Programme Initiation Review Documentation 
All detailed in Schedule O (Documentation) 
1.4 
Project Management Products 
 
Integrated Master Schedule 
 
Contractor-identified risks  
Contractor-identified issues. 
Schedule G (Transition) 

Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman
 
Released under FOI in full on 15th July 2008 

TOR - NAFIS  
1 April 2005 or 4 
Months ACA, 
whichever is 
greater  
2.1 
Description 
 
Responsibility for delivering the NAFIS Services transfers to the Contractor. 
 
2.2 
Prior Events 
 
Operational Acceptance Validation. 
 
Contractor staff trained on NAFIS. 
Staff recruited. 
 
2.3 
Products Delivered 
 
Security  Accreditation  Documents  from  Schedule  O  (Documentation)  (49,  50,   
51, 52, 53, 55, 56) 
Business Continuity Plan for TOR - NAFIS 
Glossary (Detailed Operational Requirements) 
Availability Plan 
Capacity Plan 
Configuration Management Plan 
Programme Documentation 
•  Communication Plan 
•  Operations and Maintenance Support Plan 
•  Training Plan 
•  Software Development Plan 
•  Requirements Management Plan 
xternal ICD’s for existing interfaces. 
 
2.4 
Project Management Products 
 
Next Stage plans. 
 
 
Schedule G (Transition) 

Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman
 
Released under FOI in full on 15th July 2008 

SCOTTISH LIVESCAN 
1st April 2005 
3.1 
Description 
 
The  Contractor  transitions  Scottish  Livescan  services  to  the  IDENT1  Service.   
The  Contractor  takes  on  full  operational  responsibility  for  provision  of  the 
Scottish Livescan Service. 
3.2 
Prior Events 
 
As a minimum, Scottish Livescan functionality shall be provided at a level equal   
to existing Scottish Livescan service. 
Comms connectivity in place to meet current SAFR locations to be migrated to 
MPLS by 30 April 2005.. 
Parallel Bureau or equivalent if agreed with Scotland established. 
Scottish Livescan Operational Readiness Review. 
3.3 
Products Delivered 
 
New IDENT1 Livescan units in Scotland and support for existing Livescan units   
in  Scotland  that  have  not  been  replaced  by  1  April  2005  is  provided,  with  the 
remainder  of  the  new  IDENT1  Livescan  units  to  be  installed  not  later  than  30 
April  2005.   Additional  Service  Desk  support  procedures  for  Scottish  Livescan 
in place. 
Scottish User training material available. 
Livescan User manual available. 
Software bridge between SAFR and IDENT1 in place. 
Detailed Business Process Model. 
 
Training Plan. 
 
Test Procedure Specification. 
 
3.4 
Project Management Products 
 
Product  Descriptions  for  Service  Desk  support  procedures,  User  training   
material and Livescan manual. 
Scotland Transition Project Plan. 
 
Schedule G (Transition) 

Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman
 
Released under FOI in full on 15th July 2008 

PALM SEARCHING 
 1st August 2005 
 
4.1 
Description 
 
Palm searching capability available to all installed Bureaux (England, Wales and   
Scotland). 
4.2 
Prior Events 
 
Benchmark Palm algorithms. 
 
Usability trials. 
Palm design review. 
Operational Readiness Review. 
4.3 
Products Delivered 
 
Pilot version of palm capability. 
 
Test Procedure Specification 
Training material for palm searching. 
User Manual 
Palm HCI 
Palm matchers for national searches 
4.4 
Project Management Products 
 
Palm Transition Plan. 
 
Updated IMS 
Acceptance Event Report (For Palm Project) 
IAR Closure Minutes 
 

TOR - SAFR  
15th 
January 
2006  
5.1 
Description 
 
Scottish Bureaux can access the full capabilities of IDENT1 system and SAFR is   
decommissioned. 
5.2 
Prior Events 
 
Schedule G (Transition) 
10 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman
 
Released under FOI in full on 15th July 2008 
ORR 
 
OAV 
Scottish Livescan milestone achieved. 
5.3 
Products Delivered 
 
External ICD. 
 
Use case for CHS integration. 
Training Material. 
5.4 
Project Management Products 
 
Updated IMS. 
 
Updated Scotland Transition Plan. 
Stage Plan. 
 

IDENT1 SYSTEM HCI 
 1st October 2006 
6.1 
Description 
 
New  Bureau  workstation  HCI  implemented  based  on  a  series  of  User   
evaluations/Livescan.  
6.2 
Prior Events 
 
User Input Evaluation 1. 
 
User Input Evaluation 2. 
User Input Evaluation 3. 
Acceptance Test. 
Regression test. 
ORR. 
OAV. 
6.3 
Products Delivered 
 
HCI Style Guide. 
 
Test Procedures 
Transition Plan (SISP) 
Schedule G (Transition) 
11 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman
 
Released under FOI in full on 15th July 2008 
HCI training materials. 
Acceptance Event Report 
User Manual 
Detailed Business Process Model. 
IAR Closure Minutes 
6.4 
Project Management Products 
 
HCI deployment plan. 
 
Updated IMS. 
 

PRE-FOC CHECKPOINT 
1st 
November 
2006 
7.1 
Description 
 
Checkpoint for delivered functional capabilities prior to FOC. 
 
7.2 
Prior Events 
 
ORR. 
7.3 
Products Delivered 
 
Updated System Architecture Model. 
 
Test Procedures 
Stage Plan 
Acceptance Event Report 
IAR Closure Minutes 
Complete Business Process Model. 
7.4 
Project Management Products 
 
Updated IMS. 
 
 

FOC-PROVISIONAL 
 1st 
December 
2006 
8.1 
Description 
 
Schedule G (Transition) 
12 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman
 
Released under FOI in full on 15th July 2008 
Full operational capability of IDENT1 established. 
 
8.2 
Prior Events 
 
Updated IMS. 
 
Relevant documentation in Schedule O (Documentation) updated to reflect the 
proposed system to be delivered at FOC. 
Full operational Service Level capability achieved in accordance with Schedule 
F (Service Level Requirements). 
8.3 
Products Delivered 
 
Services for IDENT1 FOC capability. 
 
8.4 
Project Management Products 
 
Updated IMS. 
 
IAR Closure Minutes. 
 

FOC 
 1st January 2007 
9.1 
Description 
 
Full operational capability validated and accepted. 
 
9.2 
Prior Events  
 
FOC-Provisional achieved 
 
OAV 
IAR Closure Minutes 
9.3 
Products Delivered 
 
Validated IDENT1 FOC Service. 
 
9.4 
Project Management Products 
 
Updated IMS 
 
Updates  to  relevant  documentation  in  Schedule  O  (Documentation)  to  reflect 
the actual system delivered at FOC. 
Full operational Service Level capability achieved in accordance with Schedule 
F (Service Level Requirements). 
 
Schedule G (Transition) 
13 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman
 
Released under FOI in full on 15th July 2008 
ANNEX G-2 
 
DESCRIPTION OF TRANSITION  

TRANSITION OVERVIEW 
The  Contractor  shall  produce  a  Transition  Plan  as  described  in  Schedule O:31 
(Documentation) for the Term of the Contract that covers FOC and any succeeding services. 
The Contractor is intending to use the legacy architecture, including the System Architecture 
Document and System Design Description of NAFIS, as the foundation from which to evolve 
the Services. 
The  Contractor  shall  achieve  TOR  from  NAFIS  to  the  IDENT1  Service  at  the  end  of  the 
Contract  for  NAFIS  Services.  This  includes  the  transfer,  management,  and  technical 
responsibility for all NAFIS Services requirements. 
The  Contractor  shall  manage  the  transition  via  the  following  four  independent  transition 
projects: 
• 
The Migration Transition Project,  
• 
The Palms Transition Project,  
• 
The Scotland Transition Project, and 
• 
The Strategic Identification Services Platform (SISP) Transition Project. 
The  transition  projects  shall  be  coordinated  in  an  integrated  fashion  for  economies  of  scale 
without creating any unnecessary interdependencies. Each project shall have detailed project 
plans  prepared  and  approved  by  the  Authority  as  described  in  Schedule O:11 
(Documentation). 
Each  transition  project  shall  be  implemented  in  stages  to  minimise  technical  risk  and 
disruption to operational Users. Stage plans and progress shall be monitored and reported to 
the Authority and stakeholders in accordance with approved project reporting procedures (as 
specified  in  management  methods  provisions  of  Clause  2  of  Part  A  of  Schedule  Q 
(Contractors Solution). 
The  Contractor  shall  conduct  Operational  Readiness  Reviews  (ORRs)  and  Operational 
Acceptance Validations (OAVs) with the Authority for all transition stage events that alter the 
system infrastructure. 
The  Contractor  shall  conduct  a  formal  acceptance  test  as  described  in  Schedule H 
(Acceptance  Procedures)  and  OAVs  with  the  Authority  for  stage  events  that  deliver 
functional enhancements or implement User changes.  
The  Contractor  shall  manage  all  transition  events  in  accordance  with  the  Authority’s 
processes that address technical, programmatic, and operational impacts. 
The  Contractor  shall  provide  a  Transition  Manager,  as  set  out  in  Part  A  of  Schedule  Q 
(Contractors  Solution),  to  oversee  all  transition  activities  and  serve  as  the  main  point  of 
contact between the Contractor and the Authority in relation to transition activities. 
The  Contractor’s  transition  activities  shall  include  personnel  with  practical  experience  in 
Schedule G (Transition) 
14 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman
 
Released under FOI in full on 15th July 2008 
transitioning operational systems within the UK police and fingerprint environments. 
1.1 
Migration Transition Project 
The  Contractor’s  Migration  Transition  Project  shall  transition  NAFIS  Services  to 
Services for IDENT1 FOC capability and shall include functional enhancements. 
Stage  1  will  provide  the  Authority  and  (if  directed  by  the  Authority)  stakeholders 
with  the  ability  to  define  and  track  key  performance  indicators  such  as  MIS 
Dashboard,  etc  and  other  enhanced  MIS  reporting  to  the  Authority.  A  MIS 
workstation shall be installed at NKBH and HDC to allow the Authority to monitor 
and analyse business performance. The Contractor shall provide onsite assistance to 
the Authority on the use of the business intelligence tool for the first month following 
installation. 
The  Contractor’s  Stage  2  shall  deliver  hardware and COTS  upgrades  which  include 
but shall not be limited to, the following: 
• 
Lightweight  Directory  Access  Protocol (LDAP)  to support  IDENT1 
directory information and security mechanisms. 
• 
Transition  of  the  central  and  bureaux  databases  from  Informix  to 
Oracle. 
• 
Upgrade of the servers to support new IDENT1 functionality, where 
appropriate. 
• 
Upgrade of legacy RAID at bureaux and central segments, to support 
increased workload under Services. 
• 
Upgrade of the existing network backbone at central sites to support 
the addition of new hardware. 
• 
Conducting  a  business  process  review of  bureau  mark  scanning  and 
printing activities as an element of business effectiveness. 
Stage  3  shall  provide  functional  enhancement  described  in  Schedule  D  (Detailed 
Operational Requirements) required to evolve the NAFIS Services to the Services 
that are not already provided under the other transition projects. Such enhancements 
shall  include  but  not  be  limited  to  the  ability  to  search  free  text  fields  /  using 
keywords, and to allow individual bureaux to configure workflow for confirmation of 
identifications within the context of business rules. 
Stage 4 shall provide upgrades to the ten (10) print and mark scanners which includes 
but shall not be limited to the following: 
• 
at  a  minimum,  the  front  side  scanner  shall  capture  10  bits/pixel  at 
500dpi and the back side shall simultaneously capture 8 bits/pixel at 
500dpi. 
• 
all flatbed scanners. At a minimum, the scanners shall output up to 16 
bits/pixel to the workstations. Deployment of upgraded scanners shall 
be  concurrent  with  deployment  of  PC  workstations  to  minimise 
disruption to the bureaux. 
Schedule G (Transition) 
15 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman
 
Released under FOI in full on 15th July 2008 
Stage  5  shall  provide  upgrades  to  the  legacy  WAN  which  include  but  shall  not  be 
limited to the following: 
• 
the  conversion  of  the  legacy  Police  National  Computer  (PNC) 
interface to Internet Protocol. 
• 
transition of the legacy frame relay WAN to MPLS. 
1.2 
Palms Transition Project 
The  Contractor’s  Palms  Transition  Project  shall  be  broken  down  into  4  stages  and 
shall  deliver  a  national,  integrated  palm-searching  capability.  The  Contractor  shall 
develop  a  Transition  Plan  for  this  project  as  detailed  in  Schedule  O:31  that  shall 
address the following areas: 
• 
Palm Human Computer Interface (HCI) changes,  
• 
Palm matchers for national palm searching,  
• 
Palm searching at bureaux, and 
• 
Encoding of existing palm prints. 
Stage 1 shall address the following: 
• 
The Contractor shall deploy a pilot version of the palm capability to 
the 
Usability 
Laboratory. 
The 
Contractor 
shall 
conduct 
demonstrations,  at  the  discretion  of  the  Authority,  with  Users  to 
obtain feedback on the proposed HCI. 
• 
The Contractor shall conduct benchmarking and testing of new palm 
algorithms. 
• 
The Contractor shall conduct an Operational Evaluation of the palm 
matching algorithms. 
• 
The  Contractor  shall  upgrade  training  systems  and  the  Test  and 
Development configurations to support palm-searching capability. 
Stage 2 shall deploy the operational palm-searching capability as follows:  
• 
The Contractor shall conduct an ORR as a formal transition meeting 
to assess and determine readiness to deploy. 
• 
The ORR shall review results of development and testing. 
• 
The  ORR  shall  also  address  a  deployment  schedule,  including  pre-
release orientation and a review of training documentation. 
• 
The  deployment  planning  shall  include  the  deployment  of  Print  Set 
scanner upgrades required to support palm searching. 
• 
The  Contractor  shall  deploy  palm  matching  algorithms  and 
processors to the operational system. 
Schedule G (Transition) 
16 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman
 
Released under FOI in full on 15th July 2008 
• 
The Contractor shall provide onsite training and assistance to bureau 
staff as part of the deployment process. 
Stage 3 shall include the capability to import palm data from standalone palm systems 
at Avon and Somerset, Kent, Bedfordshire, Leicestershire, and West Yorkshire. 
• 
The  Contractor  shall  define  an  AIS  data  exchange  format,  in 
accordance with ANSI NIST. 
• 
The  bureau  shall  be  responsible  for  delivering  legacy  data  in  the 
approved format. 
Stage  4  shall  encode  palm  prints  and  palm  marks  currently  stored  in  the  national 
collection.   This conversion  shall be  undertaken  by  the  Contractor.   The  conversion 
process shall provide the capability for bureaux personnel to monitor the process for 
quality purposes. 
1.3 
Scotland Transition Project 
The Contractor shall provide accommodation for the training system for the transition 
training of the SFS until transition from SAFR to  IDENT1. The training system for 
the  SFS shall be located  either  at  the  same  premises as  the  Glasgow  Bureau  or at  a 
mutually agreed-upon alternate location. 
The  Contractor’s  Scotland  Transition  Project  shall  integrate  Scotland  into  the 
Services.  This  project  shall  deploy  Livescan  units  with  palm  capture  capability  at 
Scottish charging stations and fully integrate SAFR into the IDENT1 Services. 
The Contractor shall develop a Transition Plan for the Scotland Transition Project as 
detailed  in  Schedule  O:31  (Documentation).    The  transition  plan  shall  address  the 
overall  transition  approach  and  detail  the  stages  within  the  project.  The  Scotland 
Transition Project shall be divided into the following six stages: 
(1) 
Stage 1—Parallel Bureau Configuration. 
(2) 
Stage 2—Existing Livescan Service Transition. 
(3) 
Stage 3—Data Migration. 
(4) 
Stage 4—Scottish Transition to IDENT1. 
(5) 
Stage 5—Deploy Additional Livescan EIUs. 
(6) 
Stage 6—Scotland Criminal History Link. 
Stage  1  shall  establish  a  parallel  IDENT1  bureau  configuration  at  Glasgow.    This 
stage includes the development and installation of a software bridge that provides the 
ability  to  process  print  sets  from  IDENT1  Livescan  EIUs  on  both  IDENT1  and 
SAFR. 
• 
Stage  1  shall  deploy  the  initial  IDENT1  bureau  system  within  the 
current  SCRO  facility  space,  or  in  a  mutually  agreed-upon  alternate 
location in close proximity to SCRO. The bureau shall be configured 
with  a  server,  RAID,  local  area  network,  and  a  minimum  two 
workstations. The Contractor shall be responsible for all facility costs 
should the alternate location be required. 
Schedule G (Transition) 
17 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman
 
Released under FOI in full on 15th July 2008 
• 
Stage  1  activities  shall  provide  the  capability  to  test  Livescan  EIU 
connectivity  to  SAFR  prior  to  replacing  existing  Scotland  Livescan 
units with IDENT1 Livescan units. 
• 
Stage  1  installation  shall  provide  the  ability  to  support  early 
familiarisation  training  of  operators  in  the  basic  functionality 
provided by IDENT1 Print Sets. 
• 
Stage  1  shall  extend  the  IDENT1  Comms  WAN  to  existing  SAFR 
locations. 
Stage  2  shall  transition  Scottish  Livescan  service  to  IDENT1  and  shall  install  (  or 
takeover)  and  make  operational  IDENT1  Livescan  EIUs  at  each  current  Scotland 
Livescan location.  Deliverables shall include but not be limited to: 
• 
installing  (or  takeover  )and  making  operational  IDENT1  Livescan 
EIUs at remaining locations in Scotland during Stage 2;  

developing  a  rollout  plan  with  the  SFS  and  the  Authority; 
and 

providing onsite training for each deployed location; 
• 
assuming full operational responsibility for each Livescan EIU upon 
installation or takeover of existing units; 
• 
enabling  the  capture  of  palms  and  the  retention  of  a  copy  of  palm 
images of the new installed units in IDENT1; 
• 
allowing  print  sets  to  be  searched  against  both  the  SAFR  and 
IDENT1 Print Set databases; and 
• 
enabling  searching  of  IDENT1  and  SAFR  unidentified  marks 
databases. 
Stage  3  shall  provide  for  the  migration  of  legacy  SAFR  data  to  IDENT1,  including 
BRC  of  palm  images  held  in  paper  format  by  SCRO.  The  Contractor  shall  perform 
the BRC on all existing SAFR records.  Deliverables shall include but not be limited 
to: 
• 
the capability to hold records in a Unified Collection and to maintain 
selected records in the SAFR; 
• 
establishing,  in  coordination  with  SFS  and  the  Authority,  weeding 
rules specific to Scotland records; 
• 
ensuring  that  each  SAFR  Print  Set  record  is  searched  against  the 
IDENT1  Unified  Collection  to  ensure  that  no  duplicates  exist.  SFS 
Fingerprint  Experts  shall  be  required  to  review  respondents  and 
confirm  identity  and  disposition.  Support  the  transfer  of  legacy 
Scottish SAFR MIS and audit data to IDENT1; and 
• 
providing a business continuity capability for Scotland AFR records 
through the IDENT1 central facilities. 
Schedule G (Transition) 
18 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman
 
Released under FOI in full on 15th July 2008 
Stage  4  shall  transfer  Scottish  fingerprint  services to IDENT1.  The  Contractor shall 
work with SFS to coordinate the decommissioning of the legacy SAFR.  Deliverables 
shall include but not be limited to: 
• 
deploying  IDENT1  bureau  systems  at  Aberdeen,  Edinburgh,  and 
Dundee; 
• 
providing  an  IDENT1  suite  of  equipment  in  Scotland  to  support 
transition training. The Contractor shall provide onsite training of the 
IDENT1  system,  and  usage  to  bureau  and  SCRO  staff  to  support 
initial operations; 
• 
providing  an  OAV  in  accordance  with  Schedule  H  (Acceptance 
Procedures); and 
• 
providing for a 30-day operational period under the IDENT1 Service 
Level  Request  (SLR)  to  verify  that  the  system  meets  performance 
and availability requirements. 
At the completion of Stage 4, the full TOR for Scotland is complete. 
Stage 5 shall deploy any remaining Livescan EIUs to the Scottish forces that were not 
deployed during Stage 2.  
If  requested  by  the  Authority,  Stage  6  shall  provide  an  electronic  interface  between 
IDENT1 and the Scottish CHS. This stage shall provide the capability to update both 
the IDENT1 database and the Scottish Criminal History database as a result of arrest 
processing. 
The  Contractor  shall  develop  a  Use  Case  in  conjunction  with  the  SCRO  and  the 
Authority.  Upon  agreement  of  the  Use  Case,  the  Contractor  shall  develop  an 
inception review  and  prepare  an  ICD.  Full  implementation  shall  include elaboration 
and  construction  reviews  prior  to  transition.  The  Contractor  shall  work  with  the 
Authority to ensure that IDENT1 can access both CHS and PNC . 
1.4 
SISP Transition Project 
The Contractor’s SISP Transition Project shall deliver the strategic platform for full 
IDENT1 Services at FOC. The Contractor shall initially develop a transition plan for 
the  SISP  Transition  Project  as  detailed  in  Schedule  O:31.  This  project  shall  build 
upon  the  system  upgrades  from  the  Contractor’s  Migration  Transition  Project  and 
shall be based on Web application server technology and standardised Simple Object 
Access Protocol (“SOAP”), interfaces. The project shall modify the Services through 
functional  enhancements  as  described  in  Schedule  D  (Detailed  Operational 
Requirements),  COTS  software  upgrades,  delivery  of  new  hardware,  security 
upgrades, and communications upgrades. 
The  Contractor’s  SISP  transition  project  approach  shall  emphasise  business 
continuity during normal operations and during system evolution through incremental 
design  and  delivery  of  new  capabilities  and  functionality.    The  Contractor’s  SISP 
Transition Project shall be delivered via the following four (4) subprojects: 
(1) 
Central Architecture Subproject; 
(2) 
Matcher Upgrade Subproject; 
Schedule G (Transition) 
19 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman
 
Released under FOI in full on 15th July 2008 
(3) 
Bureau Architecture Subproject; and 
(4) 
Bureau Workstation HCI Subproject. 
Each subproject shall be implemented via stages. 
Any  stage  with  an  ITED  release  within  the  SISP  Transition  Project  that  alters  the 
infrastructure shall include regression tests, an internal Contractor ORR, and an OAV 
with the Authority. 
Any  stage  within  the  SISP  Transition  Project  that  delivers  new  functionality  or 
changes  that  impact  Users  shall  conclude  with  formal  acceptance  tests  with  the 
Authority,  followed  by  an  Authority-witnessed  OAV  as  detailed  in  Schedule  H 
(Acceptance Procedures). 
The  Central  Architecture  Subproject  shall  deliver  and  install  Web  services  and 
application  servers,  with  load  balancing  between  central  facilities.  This  subproject 
shall be divided into two (2) stages: 
(1) 
High Availability Live ID Searches Stage. 
The  Contractor  shall  implement  two  additional  applications  servers  at  the 
primary  and  secondary  central  sites,  for  hosting  central  web  services.  The 
Services  shall  be  configured  to  support  load  balancing  between  sites  and  to 
provide automatic failover for web-hosted services. 
The Contractor shall reconfigure Livescan EIUs to send Live ID requests to 
applications servers. The Contractor shall configure internal and external web 
portals  and  the central sites  for entry  points  for the MIS  Dashboard,  system 
status  and  monitoring,  service  desk  ticket  status,  and  data  management 
functions. 
(2) 
Web Services for All Searches Stage. 
The Contractor shall transition all search transactions to use high-availability 
web services, with associated load-sharing and failover features. 
The  Matcher  Upgrade  Subproject  builds  upon  the  legacy  scalable  matching 
subsystem to provide higher accuracy and increased flexibility. This subproject shall 
be divided into three stages: 
(1) 
Matcher Platform Enhancement Stage. 
The  Contractor  shall  expand  the  Services  to  handle  multiple  encoding  and 
matching algorithms. The Contractor shall implement new feature extraction 
as  a  BRC  process,  without  interruption  to  the  operational  system.  Software 
deployments  of  new  capabilities  shall  be  conducted  in  incremental  releases 
that  are  planned  and  coordinated  with  the  Authority.  The  Contractor  shall 
conduct database integrity checks as an integral aspect of this stage. 
(2) 
Data Fusion Stage. 
The  Contractor  shall  deploy  data  fusion  between  the  SAGEM  and  legacy 
algorithms. The Services shall use features from both algorithms. The System 
shall  retain  tracking  of  resultant  search  score  as  to  whether  it  comes  from 
legacy, SAGEM or fused algorithms. 
Schedule G (Transition) 
20 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman
 
Released under FOI in full on 15th July 2008 
The Contractor shall begin storing, on a day one forward basis, all available 
friction  ridge  detail  from  each  arrest  form.  The  Contractor  shall  conduct 
operational testing of the accuracy and performance improvements associated 
with using multiple rolls, and rolls with flats. 
(3) 
Person Fusion Stage. 
The Contractor shall deploy the fusion of searches against flats and multiple 
rolls,  into  a  single  fused  score  for  a  person.  The  matching  subsystem  shall 
indicate whether the respondent was a plain or a roll and the associated FIN 
as  defined  in  Schedule  D  (Detailed  Operational  Requirements).  The 
corresponding plain or roll shall be returned to the User for verification. 
The Bureau Architecture Subproject develops a new bureau architecture suitable for 
IDENT1  applications  with  web  services.  This  subproject  shall  be  divided  into  three 
stages: 
(1)  Port to Linux Stage. 
The  Contractor  shall  port  the  existing  HCI  to  PCs  running  the  Linux 
operating system. A phased deployment plan of PCs to the bureaux shall be 
developed in coordination with the Authority. 
The  deployment  shall  be managed  as  a  production release  and  shall  include 
the deployment of the agreed-upon number of additional workstations. 
(2) 
Application Server Infrastructure Stage. 
The  Contractor  shall  develop  and  deploy  the  Application  Server  as  the 
repository  for  the  business  logic  accessed  by  the  bureau  workstations.  The 
bureau Application Server shall provide standard J2EE services, including: 
(i) 
Security; 
(ii)  Messaging; 
(iii)  Networking; 
(iv)  Database connectivity; 
(v)  Web services connectivity with SOAP; 
(vi)  Connections to legacy systems; and 
(vii)  Transaction management. 
(3) 
Bureau Services Stage. 
The  Contractor shall transition the  business  logic from  the  workstation  HCI 
to the bureau services on the bureau Application Server. 
The Contractor’s transition shall allow the new architecture to coexist at the 
bureau with legacy architecture to minimise impact on Users. 
The deployment of the architecture shall be piloted at the Contractor’s bureau 
configuration prior to rollout to operational forces 
The  Contractor  shall  develop,  in  coordination  with  the  Authority,  a 
deployment schedule with the forces. The deployment schedule shall address 
bureau training implications. 
Schedule G (Transition) 
21 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman
 
Released under FOI in full on 15th July 2008 
The  Contractor’s  Bureau  Workstation  HCI  Subproject  shall  provide  a  new 
workstation  HCI,  based  on  a  series  of  User  evaluations.  This  subproject  shall  be 
divided into four (4) stages: 
(1)   
User Input Evaluation (UIE) 1 Stage. 
The  Contractor  shall  conduct  a  UIE  to  gain  feedback  from  Users  on  the 
Contractor’s  initial  prototype.  The  UIE  shall  contain  mockups  of  the  main 
screens  and  shall  contain  demonstrations  of  the  main  threads  for  Ten  Print 
and Mark transactions. 
(2) 
UIE 2 Stage. 
The  Contractor  shall  incorporate  comments  from  UIE 1  and  shall  conduct  a 
second UIE to gain additional feedback on the updated prototype. This UIE 
shall  contain  mockups  of  additional,  lower  level  screens,  as  well  as  new 
screen functionality and enhancements. 
(3) 
UIE 3 Stage. 
The  Contractor  shall  incorporate  comments  from  UIE 2  and  shall  conduct  a 
final  UIE.  The  Contractor  shall  incorporate  comments  from  UIE 3  and 
provide mockups of all screens, as well as IDENT1 capabilities. 
(4) 
Integration with Bureau Web Services Stage. 
The  Contractor  shall  integrate  the  standalone  workstation  HCI  with  the 
bureau  server,  using  web  services.  The  new  HCI  shall  be  deployed  in  a 
planned  release  to  the  bureaux.  Bureau  PCs  running  Linux  shall  be 
transitioned to the Windows OS if requested by the Authority. 
The  Contractor  shall  conduct  acceptance  and  regression  testing.  The 
Contractor  shall  develop  deployment  plans,  in  coordination  with  the 
Authority  and  the  forces.  The  deployment  plans  shall  address  rollout 
activities, including User training. 
1.5 
Data Migration and Back Record Conversion (BRC) 
Data Migration and Back Record Conversion activity are included within each of the 
above projects.  The following information summarises these activities. 
The  Contractor  shall  prepare  a  Data  Migration  and  BRC  plan  for  the  conversion  of 
NAFIS and SAFR records. 
The  Data  Migration  plan  will  include  the  migration  of  the  MIS,  Audit,  Archive, 
Image and Encoding, ORD, Serious Crime Cache, and Police Eliminations data. 
The Contractor shall use ISO Standard 2859-1 for sampling methodology for quality 
and data integrity. 
The  Stage  Plan  (O:18)  shall  define  roles  and  responsibilities  for  the  Contractor,  the 
Authority, and all relevant stakeholders in relation to DM and BRC activity. 
The Contractor shall derive the IDENT1 Services Unified Collection of Print Sets and 
palms from legacy NAFIS Services and SAFR Services records. The Contractor shall 
ensure that encoding of the IDENT1 Services Unified Collection of Print Sets is done 
automatically.  The  Contractor  shall  provide  access  for  the  Authority  and  bureaux 
Schedule G (Transition) 
22 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman
 
Released under FOI in full on 15th July 2008 
staff to review samples for quality and data integrity. 
The  Contractor  shall  perform  paper  BRC  of  SAFR  palm  image  records.  The 
Contractor  personnel  shall  perform  the  BRC  tasks,  with  Authority  approval  and 
oversight. BRC for Scotland palm image records shall be completed by TOR-SAFR. 
The  Contractor  shall  provide  the  capability  and  processes  to  transfer  Leicestershire, 
Bedfordshire  and  West  Yorkshire  bureaux  palm  system  records  to  the  IDENT1 
Services. These records were created with NAFIS Services record identifications and 
shall be added to the Unified Collection. 
The  Contractor  shall  provide  a  record  format  and  interface  for  the  transfer  of  Avon 
and Somerset and Kent Bureaux palm system records and automatically encode those 
records. Upon agreement of an AIS data exchange format, in accordance with ANSI 
NIST,  the  bureaux  may  elect  to  transfer  all  or  selected  records.  Records  that  are 
transferred will be encoded and images will be stored in IDENT1 Services formats. 
The Contractor shall perform BRC activities of NIST formatted palm records for the 
Staffordshire bureau. 
The Contractor shall perform the automated data migration of the unified unidentified 
marks collection from existing records held on NAFIS Services and SAFR Services 
systems.  All  marks  shall  be  retained  as  encoded  by  the  Fingerprint  Officers  (FPOs) 
on those systems. 
 
Schedule G (Transition) 
23 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008