This is an HTML version of an attachment to the Freedom of Information request 'IDENT1 contract'.
PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 13th December 2005 
SCHEDULE L 
CHANGE CONTROL PROCEDURE
Schedule L (Change Control Procedure) 
 
Signature Version 
 
Released under FOI in full on 13th December 2005 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 13th December 2005 
CONTENTS 
1. 
INTRODUCTION..........................................................................................................................1 
2. 
CHANGE CLASSIFICATION.....................................................................................................1 
3. 
CHANGE CONTROL PROCEDURE.........................................................................................2 
4. 
CHANGE CLASSIFICATION.....................................................................................................5 
5. 
APPROVAL....................................................................................................................................7 
6. 
CHANGE MANAGEMENT .........................................................................................................8 
7. 
DISPUTES ......................................................................................................................................9 
8. 
PRIORITISING OF CHANGE CONTROL ...............................................................................9 
ANNEX L-1  REQUESTS FOR NEW SERVICES / ADDITIONAL WORK ....................................10 
ANNEX L-2  CHANGE CONTROL NOTE...........................................................................................11 
ANNEX L-3  FAST-TRACK CHANGE MANAGEMENT PROCEDURE ........................................14 
 
Schedule L (Change Control Procedure) 

Signature Version 
 
Released under FOI in full on 13th December 2005 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 13th December 2005 
SCHEDULE L 
CHANGE CONTROL PROCEDURE 
1. 
INTRODUCTION 
1.1 
Save as set out in Clause 1.5 below, the Parties agree that the process for changing, reducing 
or adding to the Services or implementing other changes or proposed changes to the Contract 
for which there is no other procedure expressly provided in the Contract (“Changes”) will be 
through the procedures set out in this Schedule.  
1.2 
This Schedule sets out the procedure that will apply to the classification, processing, approval 
or rejection of Changes.  
1.3 
It is the intention of the Parties that the procedure for classification and processing of Changes 
does  not  automatically  give  rise  to  a  change  in  the  Service  Charges,  but  that  the  review 
process set out in Clause 3.3.3 below (to the extent it applies under this Schedule) will include 
a review of any and all impact on costs, price, and time schedules as well as any other impact 
caused by a change request.  
1.4 
A Change request can emanate from either Party and (where the Change Control Procedure 
applies  as  opposed  to  any  of  the  other  procedures  described  in  this  Schedule)  will  be 
documented as a CCN (“Contract Change Note”) in accordance with Clause 3 below.  
1.5 
The  Parties  acknowledge  that  there  are  certain  Schedules  (other  that  this  Schedule)  of  the 
Contract  which  contain  separate  procedures  for  agreeing  specified  changes  and/or 
determining  whether  there  is  a  change  to  the  Services  Charges  in  relation  to  such  specified 
changes.  If the procedures in those other Schedules specify that the relevant change is to be 
made in accordance with this Schedule, then the procedures of this Schedule will apply to the 
decisions already determined by those other Schedules.  It is not the intention of this Schedule 
to contradict such procedures in those other Schedules, rather to provide a standard approach 
which shall apply to Changes unless stated otherwise.   
2. 
CHANGE CLASSIFICATION 
2.1 
Assessment of the type of Change 
The assessment of a Change is, firstly, to classify the Change in order to establish which of 
the  procedures  referred  to  in  Clause  2.2  below  applies  to  the  administration  and 
implementation of that Change, and secondly, to establish, where appropriate, whether such 
Change, as described in Clause 4.1 below:  
2.1.1  has the potential for an increase or a reduction in the Service Charges;  
2.1.2  has the potential for a one-off charge paid to the Contractor; or 
2.1.3  will be non-chargeable. 
2.2 
Applicable Procedure  
2.2.1  The  process  described  in  this  Schedule  recognises  that  there  are  two  (2)  main 
procedures  for  the  implementation  of  Changes  that  occur  in  the  fulfilment  of  the 
Services by the Contractor:   
Schedule L (Change Control Procedure) 

Signature Version 
 
Released under FOI in full on 13th December 2005 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 13th December 2005 
(a) 
the  Fast-Track  Change  Management  Procedure  is  the  procedure  by  which 
Changes  to  Schedule  Q  (Contractor’s  Solution)  are  implemented  where 
such  changes  do  not  modify,  add  to  or  reduce  the  scope  of  the  Services,  or 
adversely  affect  the  Services  or  the  Contract,  or  have  any  impact  on  the 
Service  Levels  and/or  the Transition  Plan,  and is intended to  be  a  fast-track 
process  for  the  implementation  of  day-to-day  Changes  (a  Change  that  falls 
within  this  description  shall  be  deemed  a  “Fast-Track  Change”).    There 
shall  be  no  associated  cost  to  the  Authority  for  these  Fast-Track  Changes. 
The Parties shall develop a detailed procedure for managing these Fast-Track 
Changes  in  accordance  with  Annex  L-3  which  may  be  incorporated  within 
this Schedule at a later date.  Subject to Clause 2.2.3 below, Clauses 3, 4 and 
6 below shall not apply to these Fast-Track Changes; and 
(b) 
the  Change  Control  Procedure,  described  in  Clause  3  below,  is  the  formal 
procedure for changing, reducing or adding to the Services or implementing 
other Changes to the Contract.  
In  addition  to  the  above  procedures,  Annex  L-1  details  the  additional  process  for 
adding New Services to the Contract and for requesting the Contractor to undertake 
specific pieces of one-off development work / study tasks in relation to the Services. 
2.2.2  The Fast-Track Change Management Procedure will be designed to operate alongside 
(and  interface  where  appropriate)  with  the  Change  Control  Procedure,  it  being  the 
Parties’ intention that the Fast-Track Change Management Procedures be developed 
to circumvent the need to raise a CCN for Fast-Track Changes.  
2.2.3  It is possible for a Change which starts as a Fast-Track Change or would otherwise be 
subject to the Fast-Track Change Management Procedure to become a Change which 
goes  through  the  Change  Control  Procedure,  where  such  implementation  alters  the 
scope  of  the  Services  or  some  other  material  aspect  of  the  Contract.  References  to 
“Changes” in Clauses 3 to 6 below shall not include Changes which are implemented 
in accordance with the Fast-Track Change Management Procedure unless the Change 
Control  Procedure is also required  for the  implementation  of  such  Changes.  For the 
avoidance  of  doubt  either  Party  may  request  a  Fast-Track  Change  be  raised  to  the 
Change Control Procedure. 
3. 
CHANGE CONTROL PROCEDURE  
This  Clause  sets  out  the  procedure  to  be  followed  to raise,  request,  record,  reject  and  agree 
Changes which are not implemented using the Fast-Track Change Management Procedure.  
3.1 
Change Control Notes 
3.1.1  An example of a blank CCN is set out in Annex L-2.  
3.1.2  All CCNs will be authorised by an authorised representative of the Party that requests 
the  Change  who  will  act  as  the  CCN  sponsor  throughout  the  Change  Control 
Procedure and who will complete Part A of the CCN.  The Contractor will complete 
Part  B  of  the  CCN.    CCNs  will  be  presented  to  the  appropriate  authorised 
representative who will acknowledge receipt of the CCN.  
3.1.3  All  Changes  under the  Change  Control  Procedure  will  further  be  classified  into  the 
following categories (“Priority Categories”) by the originator: 
(a) 
Priority 1 (urgent); or 
Schedule L (Change Control Procedure) 

Signature Version 
 
Released under FOI in full on 13th December 2005 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 13th December 2005 
(b) 
Priority 2 (normal). 
It is also possible that Changes may fall into more than one (1) Priority Category, in 
which case the CCN shall specify the Priority Categories into which the elements of 
the  Change  are  divided.    The  priority  classification  of  Changes  may  be  changed  by 
agreement  between  the  authorised  representatives  of  the  Parties’  at  the  PCCB  as 
detailed in Clause 8 below.  
3.1.4  The recipient of a Priority 1 CCN will acknowledge receipt within one (1) Working 
Day of receipt of Part A of the CCN.  Thereafter, the Parties will agree an accelerated 
timetable to ensure that a Priority 1 CCN is dealt with as quickly as practicable. 
3.1.5  For all other CCNs, the recipient shall acknowledge receipt within two (2) Working 
Days of receipt of Part A of the CCN. 
3.1.6  It  is  the  intention  of  the  Parties  that  the  Change  Control  Procedure  shall  not  cause 
unnecessary  administrative  burdens.    This  may  include  issuing  a  single  CCN  on  a 
quarterly basis to cover a number of small Changes. 
3.2 
Contractor’s Obligations 
Irrespective  of  which  Party  raises  the  CCN  under  this  Change  Control  Procedure,  for  each 
CCN the Contractor shall:  
3.2.1  agree with the Authority an appropriate timetable for the completion of its obligations 
under this Clause 3.2;  
3.2.2  assess  the  CCN  and  complete  Part  B  of  the  CCN  in  accordance  with  the  timetable 
agreed with the Authority pursuant to Clause 3.2.1 above; and  
3.2.3  in completing Part B of the CCN, provide, as a minimum:  
(a) 
a  description  of  the  Change  and  whether  the  Contractor  considers  that  the 
Change is a New Service and should be dealt with in accordance with Annex 
L-1; 
(b) 
where the Commercial Impact Procedure is applicable, the information that is 
required by Clause 4.3 below; 
(c) 
a list of deliverables required for implementing the Change; 
(d) 
a timetable for implementation of the Change; 
(e) 
an Impact Analysis as detailed in 3.3 below; 
(f) 
how the Change will be tested and accepted in accordance with Schedule H 
(Acceptance Procedures); 
(g) 
(for  Contractor  initiated  Changes)  an  assessment  of  the  added  value  of  the 
Change to the Authority; and 
(h) 
proposed amendments to the Contract / Schedules as required. 
Schedule L (Change Control Procedure) 

Signature Version 
 
Released under FOI in full on 13th December 2005 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 13th December 2005 
3.3 
Impact Analysis 
3.3.1  The purpose of an Impact Analysis is to provide a context for a discussion around the 
approval and implementation of the proposed Change. 
3.3.2  The Impact Analysis will consider the material effect of any proposed Change on any 
other  existing  Services  provided  under the  Contract.   The  Impact  Analysis  will also 
consider the effect on other applicable services provided by the Authority or a third 
party.  If the proposed Change has no such impact, a “no impact” statement will be 
made.  
3.3.3  The  Impact  Analysis  will  consider  the  impact  of  the  proposed  Change  with  the 
following factors taken into account as relevant to each particular Change: 
(a) 
scope of the Contract; 
(b) 
whether the proposed Change is a New Service (in which case the procedure 
set out in Annex L-1 will apply); 
(c) 
consideration of location; 
(d) 
Service Levels; 
(e) 
pricing elements; 
(f) 
delivery dates and milestone dates; 
(g) 
test  and  acceptance  procedure,  including  end-user  acceptance  where 
applicable; 
(h) 
any applicable disaster recovery services; 
(i) 
roll-out provision, including the cost and impact of such provision; 
(j) 
the Authority’s policies and standards; 
(k) 
infrastructure requirements including new Equipment and/or Software; 
(l) 
impact on Assets; 
(m) 
third party agreements;  
(n) 
the impact of the proposed Change on the scope of the then-existing baseline 
Services, including whether any of the then-existing baseline Services should 
be correspondingly reduced or eliminated; 
(o) 
if  applicable,  the  impact  of  the  proposed  introduction  of  any  Contractor 
Software (other  than  Contractor  Software  which  forms,  or  is  to  be  provided 
as,  part  of  the  Contractor’s  Solution  as  proposed  at  the  Effective  Date) 
including  an  assessment  of  whether  such  proposed  Contractor  Software 
satisfies  the  Authority’s  security  requirements  (as  set  out  in  Schedule  K 
(Security)  and  its  requirements  relating  to  exit  (as  set  out  in  Schedule  N 
(Exit Strategy));  
(p) 
the  Authority’s  objective  of  avoiding  lock-in  to  a  single  Contractor  and 
enabling  a  smooth  and  effective  transition  (upon  Termination  or  in 
Schedule L (Change Control Procedure) 

Signature Version 
 
Released under FOI in full on 13th December 2005 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 13th December 2005 
connection  with  any  Services  removed  from  the  scope  of  the  Contract)  to  a 
Successor Contractor; and  
(q) 
any  other  matter  reasonably  requested  by  the  Authority  at  the  time  of  the 
Impact Analysis or reasonably considered by the Contractor to be relevant. 
The Parties acknowledge that the above is not an exhaustive list.  There may be more 
factors  to  consider  in  the  context  of  a  particular  Change  and  some  of  the  factors 
described above may not be relevant to every Change. 
3.4 
Preparatory or Development Work  
3.4.1  Where  the  Authority  agrees  to  the  Contractor  undertaking  preparatory  or 
development work for a Change which is the subject of a CCN that has not yet been 
authorised  in  accordance  with  Clause  5  below,  the  charges  for  such  work  will  be 
mutually  agreed  and  must  be  authorised  by  the  Authority  nominated  commercial 
representative prior to the commencement of such work by the Contractor. 
3.4.2  Any  agreement  by  the  Authority  to  pay  the  Contractor  for  preparatory  or 
development  work  as  described  in  Clause  3.4.1  above  shall  be  without  prejudice  to 
the Authority’s right to refuse to authorise the relevant CCN.   
4. 
CHANGE CLASSIFICATION 
4.1 
Assessment of the Change (Chargeable or Non-Chargeable) 
All  Changes  shall  be  first assessed to  establish  whether  the  Change  has  the  potential  for  an 
increase or a reduction in the Service Charges (as applicable).  Subject to Clause 2.2.3 above, 
Fast-Track  Changes  are  non-chargeable  by  the  Contractor  and  are  included  within  the  then-
current Service Charges.  
4.2 
Non-Chargeable Changes 
4.2.1  Changes  that  go  through  the  Change  Control  Procedure  are  not  automatically 
chargeable.  The  following  are  classifications  of  Changes  for  which  the  Contractor 
shall  not  be  entitled  to  charge  and  for  which  the  Commercial  Impact  Procedure 
detailed in Clause 4.3 below will not apply:  
(a) 
Changes  that  are  required  to  incorporate  any  services,  function  and 
responsibilities  (including  any  incidental  service,  function-or  responsibility) 
not  specifically  described  in  Schedule  D  (Detailed  Operational 
Requirements)  but  which  are  reasonably  and  necessarily  required  for  or 
related  to  the  proper  performance  of  services  in  connection  with,  and  the 
fulfilment of, the Services;  
(b) 
Changes  that  only  impact  Schedule  Q  (Contractor’s  Solution)  and  do  not 
affect any other parts of the Contract;  
(c) 
Changes which were envisaged at the Effective Date as set out in Schedule Q 
(Contractor’s Solution);  
(d) 
Changes  required  for  the  Contractor  to  carry  out  its  obligations  under  the 
Contract  where  the  costs  and  expenses  associated  with  such  Changes  are 
already included in the Service Charges; 
Schedule L (Change Control Procedure) 

Signature Version 
 
Released under FOI in full on 13th December 2005 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 13th December 2005 
(e) 
Changes  that  are  part  of  any  disputes  resolution  procedure,  including  those 
set  out  in  Schedule  F  (Service  Level  Requirements),  to  the  extent  that  the 
problem or issue results from a Default of the Contractor; and   
(f) 
Changes  required  as  a  result  of  changes  in  Law  in  accordance  with  Clause 
30.2 of Schedule B (Conditions of Contract).  
4.2.2  Changes  that  are  not  excluded  from  the  application  of  the  Commercial  Impact 
Procedure  pursuant  to  Clause  4.2.1  above  will  be  assessed  in  accordance  with  the 
Commercial  Impact  Procedure  in  Clause  4.3  below  and  will  be  subject  to  the 
Authority’s approval in accordance with Clause 5 below.  
4.3 
The Commercial Impact Procedure (Chargeable Changes) 
4.3.1  General Changes 
The Commercial Impact Procedure is the only process by which the Contractor may 
increase  the  Service  Charges  or  request  a  one-off  charge  as  a  result  of  a  Change 
except for New Services (which are dealt with in accordance with Annex L-1) or as 
otherwise expressed to the contrary in the Contract.  
4.3.2  Procedure 
Where  the  Parties  consider  that  an  increase  or  decrease  in  the  Service  Charges  is 
applicable  as  a  result  of  a  Change,  the  following  information  will  be  provided  with 
the submission of Part B of the CCN in accordance with Clause 3.2 above to justify 
the basis of the increase or decrease: 
(a) 
an  analysis  of  the reasons why  the  Contractor  believes  that  its  costs  will  be 
materially  impacted  by  the  Change  and  any  applicable  supporting 
documentation; 
(b) 
reasonable evidence that the Contractor is performing in accordance with the 
Contract  requirements  as  set  out  in  Schedule  D  (Detailed  Operational 
Requirements)  and  that  it  has  reviewed  any  alternatives  (including 
utilisation  of  existing  Contractor  Personnel  and  resources  engaged  in  the 
fulfilment of the Services, together with information on the adverse impact on 
the  Services  or  the  Service  Levels  (if  any))  to  accommodate  the  requested 
Change; 
(c) 
details  of  proposed  one-off  charges  and/or  changes  to  the  Service  Charges 
based  upon  the  information  described  in  Clause  4.3.2  (a)  and  (b)  above, 
which  shall  remain  valid  for  a  period  of  six  (6)  months  from  submission  to 
the Authority or, in the case of components proposed to be provided by third 
parties, such shorter period as may be advised by the Contractor in the CCN 
(where the Contractor has been unable to obtain or unable to confirm that it 
will be able to obtain) the same for a three (3) month period); and 
(d) 
any  other  reasonably  relevant  information,  including  information  justifying 
any proposed one-off charges or changes to the Service Charges and any base 
data  and  charging  assumptions  required  by  the  Authority  to  verify  such 
proposed changes. 
Schedule L (Change Control Procedure) 

Signature Version 
 
Released under FOI in full on 13th December 2005 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 13th December 2005 
4.4 
Administering the Change at no cost to the Authority 
Each Party shall be responsible for its own costs incurred in the preparation and assessment of 
CCNs, including the costs of the Impact Analysis.  However, if a change is required due to 
the Default of the Contractor, the Contractor shall be responsible for the costs incurred by the 
Authority  in  the  preparation  and  assessment  of  CCNs,  including  the  costs  of  the  Impact 
Analysis.  
5. 
APPROVAL 
5.1 
Prior  to  submission  of  the  CCN  to  the  Authority,  the  Contractor  shall  undertake  its  own 
internal review of the proposal and obtain all necessary internal approvals.  As a part of this 
internal review process, the Contractor shall consider the materiality of the proposed Change 
in the context both of the Services affected by the Change and of the effects on the Contract 
as a whole that may arise from implementation of the Change.  For the avoidance of doubt, 
such review is not intended to replace an Impact Analysis.  
5.2 
Subject  to  agreement  on  the  price  of  a  Change  (where  applicable)  and  unless  any  of  the 
following apply: 
5.2.1  the Contractor is not technologically capable of providing a Change and such Change 
cannot be sourced from a third party; or 
5.2.2  the Change is prevented by Law, 
the Contractor is obliged to implement all Changes in accordance with the procedures set out 
in this Schedule where the Authority is the originating party. 
5.3 
The Authority shall review the CCN and, following such review, shall either:  
5.3.1  accept or reject the CCN; or  
5.3.2  request amendment  to  the CCN  providing  reasonable  details  and  explanation  of  the 
items that the Authority rejects in the notification requesting amendment; or  
5.3.3  request more information from the Contractor as may be reasonably required by the 
Authority to review the CCN.   
Any  CCN  accepted  by  the  Authority  pursuant  to  this  Clause  5.3  shall  be  considered  an 
amendment to the Contract and shall be incorporated into the Contract. 
5.4 
At  the  Authority’s  request,  the  Contractor  shall  re-submit  its  proposal  with  amendments  as 
discussed  between  the  Parties.    Any  agreed  one-off  charge,  on-going  separate  charges  or 
adjustment  to  the  Service  Charges  will  be  subject  to  the  prior  approval  of  the  Parties  (the 
Authority  acting  through  an  authorised  representative  of  the  Authority’s  nominated 
commercial  representative  and  the  Contractor  acting  through  its  nominated  commercial 
representative  named  in  Schedule  I  (Contract  Management)  by  signature  of  Part  C  of  the 
CCN in accordance with Clause 5.9 below. 
5.5 
Where the Authority requires the Contractor to resubmit the CCN, the Authority shall provide 
reasonable detail to the Contractor of the parts of the CCN that do not meet with its approval, 
setting out reasons for such rejection.  
5.6 
The Authority may, in its sole discretion, approve or reject the CCN where the Contractor is 
the originating party. 
Schedule L (Change Control Procedure) 

Signature Version 
 
Released under FOI in full on 13th December 2005 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 13th December 2005 
5.7 
Subject to Clause 5.6 above, the Authority shall be entitled to cancel the relevant CCN where 
the  New  Service  or  Change  does  not  meet  the  applicable  Test  and  Acceptance  criteria,  as 
determined in accordance with Schedule H (Acceptance Procedures).  
5.8 
During Transition, the Parties shall agree a stream-lined procedure for assessing, agreeing and 
implementing Changes to the Contractor’s Solution in accordance with Clause 2.2.1 above.  If 
any Changes to the Contactor’s Solution are being made in accordance with Clause 3 above, 
the  Commercial  Impact  Procedure  shall  not  apply  to  such  Changes  to  the  Contractor’s 
Solution to the extent that they do not affect other parts of the Contract.  The Authority shall 
not be entitled to reject a CCN which relates solely to the Contractor’s Solution unless such 
Change  has,  or  appears  to  have,  an  unreasonably  adverse  effect  on  the  fulfilment  of  the 
Services, on the Authority’s costs of running its business, or on the Authority’s objective of 
avoiding lock-in to a single Contractor and enabling a smooth and effective transition (upon 
Termination or in connection with any Services removed from the scope of the Contract) to a 
Successor Contractor.  
5.9 
Subject to Clause 5.10 below, following an internal process of approval by the Authority and 
agreement between the Authority and the Contractor, Part C of the CCN will be signed by a 
member  of  the  Authority’s  nominated  commercial  representative  and  the  Contractor’s 
nominated  commercial  representative  named  in  Schedule  I  (Contract  Management).    Any 
CCN accepted by the Authority pursuant to this Clause 5.9 shall be considered an amendment 
to the Contract and shall be incorporated into the Contract.   
5.10 
No  CCN  can  be  implemented  without  the  prior  written  authorisation  of  the  Authority  in 
accordance with Clause 5.9 above.  If the Contractor proceeds with the implementation of a 
CCN  without  receiving  prior  written  authorisation  from  an  authorised  commercial 
representative  of  the  Authority,  such  CCN  will  be  entirely  at  the  Contractor’s  cost  and  risk 
(and the Authority may require the Contractor to undo the CCN at the Contractor’s expense), 
except  in  emergencies  where  a  demonstrable  immediate  risk  of  material  loss  or  damage  to 
either  Party  exists.    In  the  event  of  an  emergency,  the  Contractor  shall  notify  an  authorised 
commercial representative of the Authority as soon as practicable after implementation of the 
CCN,  and  subject  to  the  Contractor  demonstrating  to  the  Authority  that  the  costs  incurred 
were  reasonable  in  all  the  circumstances,  the  Parties  shall  retrospectively  apply  the 
Commercial Impact Procedure (where appropriate). 
5.11 
Until such time as a CCN is formally authorised by the Authority (as described in Clause 5.3 
or  5.9  above),  the  Contractor  shall,  unless  otherwise  agreed  in  writing  by  the  Authority, 
continue to perform and be paid under the Contract as if such Change had not been requested. 
6. 
CHANGE MANAGEMENT 
6.1 
The Contractor shall record and track the progress of all CCNs and report the status of CCNs 
as part of its contract management reports to the Authority as set out in Schedule I (Contract 
Management).  
6.2 
The  Contractor  shall  retain  all  information  generated  by  or  on  behalf  of  the  Contractor  or 
made  available to  the  Contractor  by  the  Authority,  whether  written, electronic  or  otherwise, 
concerning  each  CCN,  whether  finally  authorised  or  not,  including  receipts  of  payments, 
work undertaken, and the time involved for its respective employees and third parties, for a 
period of seven (7) years following the date of the creation of each piece of information. 
6.3 
The  Authority  shall  have  the  right  to  review  the  information  retained  by  the  Contractor  in 
accordance  with  Clause  6.2  above  on  giving  the  Contractor  reasonable  prior  written  notice 
specifying the CCN or CCNs covered by the review.  
Schedule L (Change Control Procedure) 

Signature Version 
 
Released under FOI in full on 13th December 2005 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 13th December 2005 
6.4 
Without  prejudice  to  the  generality  of  Clause  6.2  above,  the  Contractor  shall  document  all 
relevant  costs  incurred  by  the  Contractor  in  undertaking  any  preparatory  work  and 
implementing  any  Change,  which  documentation  shall  be  supplied  to  the  Authority,  on  the 
Authority giving the Contractor reasonable prior written notice.   
7. 
DISPUTES 
All disputes relating to any CCN (whether or not finally authorised) or Change, including the 
charges for the implementation of any Change, shall be resolved in accordance with Schedule 
P (Dispute Resolution Procedure). 
8. 
PRIORITISING OF CHANGE CONTROL 
The schedule for CCN and Fast-Track Changes shall, wherever possible, be mutually agreed 
by  the  PCCB.    Where there  are  constraints  in delivery  of  multiple  changes,  due  to  resource 
(Contractor and/or Authority), technical limitations, funds or any other factor, the Authority 
shall  have  final  decision  on  overall  priority.    Should  the  Authority  invoke  their  right  to 
reprioritise previously agreed changes without further agreement of the Contractor, they may 
be  liable  for  reasonable  additional  costs  incurred  excluding  any  lost  or  delayed  savings  the 
Contractor  may  be  anticipating  as a  result  of a  change.  All  such  reasonable  additional  costs 
shall  be  agreed  in  writing  between  the  parties  prior  to  any  final  re-prioritisation  under  this 
clause. 
Schedule L (Change Control Procedure) 

Signature Version 
 
Released under FOI in full on 13th December 2005 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 13th December 2005 
ANNEX L-1 
 
REQUESTS FOR NEW SERVICES / ADDITIONAL WORK 
1. 
Request for New Services 
The  Contractor  and  the  Authority  shall  agree  on  the  nature  and  scope  of  any  New  Service, 
including  where  appropriate,  the  Service  Levels  for  performance,  the  related  pricing,  and 
appropriate  amendments to  the  affected  part(s) of the  Contract (if  any).    If  agreed, the  New 
Service shall be implemented through a CCN in accordance with this Schedule.  
2. 
Pricing for New Services 
2.1. 
The  unit  prices  or  other  charges  for  any  New  Services  shall  be  determined  in 
accordance with Schedule E (Pricing). To the extent that such New Services are not 
covered by the pricing in Schedule E, then: 
2.1.1  if such New Services are similar to the services provided under this Contract, 
the charges for such New Services shall be no more than the rates / prices set 
out in Schedule E; or 
2.1.2  if  such  New  Services  are  not  similar  to  the  Services  provided  under  this 
Contract, the charges for the New Services shall be at rates / prices that the 
Contractor would charge the Authority in a competitive procurement and / or 
at  preferential rates  as  an existing  customer. The  pricing  for  such  new  rates 
shall  also  comply  with  the  Value  for  Money  Mechanism  in  Schedule  E 
(Pricing).  
2.2. 
If the Authority’s request for New Services includes a corresponding request for the 
Contractor to reduce or eliminate the Services which the Contractor is providing, then 
the  Impact  Analysis  shall  consider  the  resources  and  expenses  required  to  provide 
such  New  Services,  including  implementation  and  on-going  support,  and  the 
reduction in resources and expenses related to the Services being replaced.  The net 
increase  or  decrease  in  resources  and  expenses  will  be  the  basis  on  which  the 
Contractor shall quote a price to the Authority for the New Services.  
3. 
Request for Additional Work 
The  Parties  agree  that  during  the  Term  of  this  Contract  the  Authority  may  request  certain 
specific  pieces  of  one-off  development  work  /  study  tasks  in  relation  to  the  Service  or 
potential Service scope. All such requests for additional work will need to be processed and 
agreed  on  a  case-by-case  basis  via  the  Change  Control  Procedure  detailed  in  this  Schedule, 
including but not limited to the need to provide an Impact Analysis as set out in Clause 3.3 
above.  These requests shall be priced according to the appropriate labour rates as detailed in 
Schedule E (Pricing) unless otherwise agreed by the Parties.  
Schedule L (Change Control Procedure) 
10 
Signature Version 
 
Released under FOI in full on 13th December 2005 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 13th December 2005 
ANNEX L-2 
 
CHANGE CONTROL NOTE 
Change Control Note 
CCN Number: 
Part A: Initiation 
 
Title: 
 
 
 
Originator: 
 
Contact Number: 
 
 
Sponsor: 
 
Contact Number: 
 
 
Date of Initiation: 
 
Required by date: 
 
 
Change Category: 
 
Priority Category: 
(Priority 1 - urgent, 
 
Priority 2- normal) 
 
Details of Proposed Change 
(To include reason for change and appropriate details/specifications. Identify any attachments as A1, 
A2, A3, etc.) 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Authorised by 
Date: 
AUTHORITY 
Name: 
 
 
Signature: 
 
 
Received by 
Date: 
CONTRACTOR 
Name: 
 
 
Signature: 
 
 
Schedule L (Change Control Procedure) 
11 
Signature Version 
 
Released under FOI in full on 13th December 2005 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 13th December 2005 
 
Change Control Note 
CCN Number: 
Part B : Evaluation 
(identify any attachments as B1, B2, B3, etc.) 
Changes to Services, terms of the Contract, personnel to be provided, charging structure, payment 
profile, documentation, training, Service Levels and component working arrangements and any other 
contractual issue. 
 
Brief Description of Change: 
 
 
 
 
 
Impact: 
(Refer to any impact analysis attachment where applicable) 
 
 
 
 
Deliverables: 
 
 
 
 
Timetable: 
 
 
 
 
Acceptance Procedure  
 
 
 
 
Charges for Implementation: 
(including a schedule of payments. If not applicable, mark “Not Applicable”) 
 
 
 
 
Other Relevant Information: 
(including value-added) 
 
 
 
 
Authorised by 
Date: 
CONTRACTOR 
Name: 
 
 
Signature: 
 
 
Schedule L (Change Control Procedure) 
12 
Signature Version 
 
Released under FOI in full on 13th December 2005 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 13th December 2005 
 
Change Control Note 
CCN Number : 
Part C : Authority to Proceed 
 
Implementation of this CCN as submitted in Part 
 
A, in accordance with Part B, is: 
(tick as appropriate) 
Approved 
 
 
Rejected 
 
Requires Further Information (as follows, as 
Attachment 1, etc.) 
 
 
 
 
 
 
 
 
 
For AUTHORITY 
For CONTRACTOR 
Signature 
Signature 
 
 
 
Name 
Name 
 
 
 
Title 
Title 
 
 
 
Date 
Date 
 
 
 
 
Schedule L (Change Control Procedure) 
13 
Signature Version 
 
Released under FOI in full on 13th December 2005 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 13th December 2005 
ANNEX L-3 
 
FAST-TRACK CHANGE MANAGEMENT PROCEDURE 
1. 
As detailed in Clause 2.2 of this Schedule the Fast-Track Change Management Procedure is 
the  process  for  the  planning,  testing,  co-ordinating,  implementing  and  monitoring  of  Fast-
Track  Changes.    The  Fast-Track  Change  Management  Procedure  shall  also  determine  the 
manner  in  which the  Contractor shall  control and  manage  changes  in  any  and  all  aspects  of 
those parts of Contractor’s Solution that do not fall within the Change Control Procedures.  
2. 
The Fast-Track Change Management Procedure shall meet the following requirements:  
2.1. 
provide a set of sub-processes designed to: 
2.1.1  manage and control the response to planned Changes;  
2.1.2  capture  the  required  information  from  service  requests  and  implementation 
reports for inclusion in the configuration database;  
2.1.3  create  and  control  execution  of  plans  for  approved  projects,  reporting  on 
progress and issues;  
2.1.4  provide  that  ownership  responsibilities  for  resources  will  be  properly 
exercised; and 
2.1.5  assess the potential business impact to the Authority. 
2.2. 
facilitate  co-ordination  and  communication  across  the  Authority  and  the  Police 
Forces and facilitate measures to reduce the business impact and risk to the Authority 
of any change activity;  
2.3. 
provide processes for managing conflicts of timing, resources and priorities; and  
2.4. 
provide  processes  to  establish  clear  ownership  for  individual  changes  to  be 
established  and  maintained  throughout  the  change  process,  with  regular  and 
appropriate progress updates communicated to those affected. 
3. 
The Contractor shall:  
3.1. 
document in the Configuration Management plan for the Contract, the procedures for 
interfacing with the Authority; 
3.2. 
review, schedule and communicate proposed Changes with the Authority to minimise 
disruption of normal business processes;  
3.3. 
conduct Change management meetings with the Authority at a frequency set forth in 
the Fast Track Management Procedure above;  
3.4. 
collect  data  on  each  Change  attempted,  including  the  cause  of  any  problems, 
measures taken to prevent reoccurrence, and impact on Police Forces.  This data will 
be  summarised  and  reported  to  the  Authority  on  a  quarterly  basis.    Promptly  after 
being  requested  by  the  Authority,  the  Contractor  shall  provide  the  details  of  all 
instances  and  records  of  all  Changes  to  the  live  environment  so  that  the  Authority 
may:  
Schedule L (Change Control Procedure) 
14 
Signature Version 
 
RESTRICTED - COMMERCIAL 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 13th December 2005 
3.4.1  determine that the Fast-Track Change Management Procedure was followed; 
and  
3.4.2  identify  from  whom  Changes  were  initiated  and  where  and  how  Changes 
occurred, including all relevant details;  
3.5. 
clearly  define  the  roles  and  responsibilities  of  the  areas  and/or  functional  groups 
involved  in  the  Change  process,  as  well  as  formalise  the  communication  process 
between affected Parties; and  
3.6. 
with the assistance of the Authority, develop a contingency plan for each Change to 
the  Authority’s  operations  or  business,  including  regression  procedures,  notification 
and escalation lists, work-around plans, affected resources and risk assessments. 
 
Schedule L (Change Control Procedure) 
15 
Signature Version 
 
RESTRICTED - COMMERCIAL