This is an HTML version of an attachment to the Freedom of Information request 'IDENT1 contract'.
PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
SCHEDULE H 
ACCEPTANCE PROCEDURES
Schedule H (Acceptance Procedures) 
 
Version 1.0 
CCN004 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
CONTENTS 

INTRODUCTION................................................................................................................... 1 

PRINCIPLES........................................................................................................................... 2 

GENERIC ACCEPTANCE APPROACH............................................................................ 6 

ACCEPTANCE ROLES AND RESPONSIBILITIES....................................................... 22 

ACCEPTANCE PROCEDURES AND TIME PERIODS................................................. 23 
ANNEX H-1   ACCEPTANCE AND TRANSITION MILESTONES .......................................... 33 
 
Schedule H (Acceptance Procedures) 

Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 

INTRODUCTION 
1.1 
The purpose of this Schedule is to describe the extent and scope of work to be undertaken by 
the  Contractor  in  relation  to  Acceptance  Testing  of  the  Transition  Milestones  identified  in 
Schedule G (Transition), and to set out the Parties' agreement in adopting a generic approach 
for Acceptance Testing of the Services at TOR, from TOR to FOC, at FOC, and from FOC to 
the end of the Term.   
1.2 
This  Schedule  defines  the  procedures  which  allow  for  effective  Acceptance  of  the  Service, 
such that the Authority can be satisfied that Transition as set out in Schedule G (Transition) 
is complete, that the Services are capable of meeting the Service Levels as set out in Schedule 
F  (Service  Level  Requirements),  that  the  Services  provide  the  functionality  and  other 
attributes as set out in Schedule D (Detailed Operational Requirements) and that all other 
work is performed in accordance with Schedule Q (Contractor’s Solution). 
1.3 
The aim of Acceptance Testing is for the Contractor to demonstrate to the Authority that the 
Services:  
1.3.1  are available;  
1.3.2  are capable of operating; and  
1.3.3  actually  operate  and  are  likely  to  continue  to  operate,  in  accordance  with  the 
Requirements of the Contract.   
1.4 
Although one of the main aims of this Schedule is to enable the Contractor to progress to and 
achieve  FOC  for  the  Services,  through  the  Acceptance  of  the  Transition  Milestones  in 
accordance with Annex H-1 of this Schedule, the principles set out hereunder shall apply to 
Acceptance Testing of all New Services developed and delivered after FOC and any changes 
introduced  through  Schedule  L  (Change  Control  Procedures)  where  the  Parties  agree  that 
this  Schedule  is  to  apply  to  the  relevant  change  being  introduced  through  Schedule  L 
(Change Control Procedures). 
1.5 
An incremental approach to Acceptance Testing has been adopted as described in Clauses 2 
and  3  below  which  contains  six  standard  Incremental  Acceptance  Reviews  (“IAR”)  one  or 
more of which shall be required for Acceptance Testing of particular Transition Milestones. 
Each  IAR  carried  out  will  generally  take  the  form  of  one  or  more  Standard  Acceptance 
Reviews (“SAR”) and will be preceded by defined events for Acceptance Testing (“Events”), 
the  outcomes  of  which  will  be  presented  at  the  IAR.  The  process  is  further  described  in 
Clause 3 below. Such Events may include specified testing activities to satisfy the Authority 
that  the  functionality,  specification  and  operational  stability  of  the  Services  meet  the 
Requirements of the Contract. The Authority does not wish to be prescriptive in determining 
what  the  testing  activities  might  be,  however,  they  could  include  such  activities  as  Factory 
Acceptance  Tests  (FATs)  or  Acceptance  Testing  where  appropriate.  A  Progressive 
Acceptance  Review  (“PAR”)  may  be  used  in  certain  circumstances  for  specific  purposes 
when the generic Acceptance Testing approach is inappropriate. 
1.6 
The  Services  accepted  at  the  passing  of  the  FOC  Transition  Milestone  shall  constitute  the 
FOC  baseline  for  the  Services  (“IDENT1  Baseline  Service”)  upon  which  future  Services 
shall  build.  Each  time  a  new  Service  which  constitutes  an  amendment  to  Schedule  D 
(Detailed Operational Requirements) becomes operational, it shall be added to the existing 
IDENT1  Baseline  Service  and  upgrades  thereof  to  create  a  new  IDENT1  Baseline  Service. 
Each  revision  of  the  IDENT1  Baseline  Service  shall  be  ascribed  a  new  version  number  in 
order to provide a full audit trail of changes. 
Schedule H (Acceptance Procedures) 

Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
1.7 
Upon the successful completion of each IAR prior to FOC in accordance with Clause 5.5 of 
this  Schedule,  the  Contractor  shall  issue  an  appropriate  Certificate  of  Acceptance  or 
confirmation  letter  to  the  Authority  for  signature  by  both  Parties.  The  date  of  signature  by 
both Parties of the Certificate of IDENT1 Services Acceptance at FOC as described in Clause 
5.6 shall be the formal start date in relation to the Services to be provided by the Contractor 
under this Contract.   
1.8 
Acceptance  testing  of  future  Services  shall  be  undertaken  in  accordance  with  the  same 
principles  as  are  set  out  in  this  Schedule  for  the  Acceptance  of  the  Transition  Milestones. 
Prior to placing a CCN (in accordance with Schedule L (Change Control Procedure) for an 
additional new Service, the Authority and Contractor shall discuss and agree the process for 
Acceptance  Testing  of  the  New  Services,  including  which  IARs  shall  apply  to  agreed 
Milestones for the relevant service. Subject to the Authority’s approval of acceptance for such 
New  Services,  a  Certificate  of  Acceptance  for  a  New  Service  may  be  issued  where 
appropriate and relevant as agreed between the Parties. 
1.9 
Acceptance of any Milestone shall enable the Contractor to progress to succeeding Milestones 
or  claim  payment,  as  applicable  under  Schedule  E  (Pricing).    However,  Acceptance  (or 
waiver  of  any    Defect  or  Failure  at  Acceptance)  of  any  Milestone,  New  Services  or  any 
changes introduced in accordance with Schedule L (Change Control Procedure) pursuant to 
this  Schedule  (including  circumstances  where  an  Acceptance  Certificate  has  been  issued) 
shall  not  relieve  the  Contractor  of  its  obligation  to  meet  the  requirements  of  Schedule  D 
(Detailed  Operational  Requirements)  and  shall  be  without  prejudice  to  the  rights  and 
remedies available to the Authority under the Contract.   
1.10 
In accordance with Clause 5.9.2, the Authority reserves the right (at its sole discretion) either 
to  waive  or  defer  any  Defect  or  Failure  resolution  at  any  Milestone,  or  to  allow  an  agreed 
period for the Defect or Failure resolution prior to re-submitting a Milestone for Acceptance 
Testing.  If, after the Authority has extended the Acceptance Testing Period, the Acceptance 
Testing  Procedures  have  not  been  recorded  as  successful  by  the  end  of  that  period,  the 
Authority  shall  have  the  right  to  terminate  for  the  Contractor’s  default  in  accordance  with 
Clause 43 of Schedule B (Conditions of Contract). 

PRINCIPLES 
2.1 
Incremental Acceptance 
2.1.1  The Parties shall apply the Generic Acceptance Approach as described in Clause 3 of 
this Schedule to all development work leading to FOC and also apply it to future New 
Services.  This approach shall align with the RUP model and shall use an incremental 
approach to achieving Acceptance.  
2.1.2  The Contractor shall use the Incremental Acceptance approach to: 
(a) 
balance the workload associated with Acceptance activities across time; 
(b) 
provide assurance that capabilities meet the specified Requirements;  
(c) 
provides evidence towards achieving the milestones identified in Schedule G 
(Transition); 
(d) 
bring  into  operational  service  new  capabilities  with  consequent  operational 
benefits as early as practicable; 
Schedule H (Acceptance Procedures) 

Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
(e) 
enable Pilot or Proof of Concept of new capabilities to support user centred 
design and the early assessment of operational and business benefits; and 
(f) 
identify  and  resolve  Defects  against  specification  and  other  potential 
problems as operational and business benefits as early as possible;  
2.1.3  The  Parties  shall  conduct  Incremental  Acceptance  Reviews  (“IAR”)  and  preceding 
Acceptance Events, as described in Clause 3 of this Schedule. 
2.1.4  Notwithstanding  any  Acceptance  by  the  Authority  of  a  satisfactory  delivery  of  any 
Services or New Service, the Authority retains the right to invoke the remedies set out 
in Clause 5 in the event that such Services or New Services are subsequently shown 
to be failing to meet the Requirement(s) of the Contract. 
2.2 
Requirements 
2.2.1  For the purposes of this Schedule, the term “Requirement” shall refer to and include, 
but  not  be  limited  to,  the  DOR  and  Requirements  derived  from  the  DOR,    most 
notably  those  derived  from  the  Use  Cases  during  the  development  process.  In 
addition,  this  shall  include  the  statements  made  by  the  Contractor  in  Schedule  Q 
(Contractor’s Solution). 
2.2.2  Verification and Validation of Requirements 
The  Contractor  shall  provide  evidence  by  means  of  IARs,  to  the  satisfaction  of  the 
Authority  and  through  the  procedures  set  out  in  this  Schedule,  that  each  of  the 
Requirements of Schedule D (Detailed Operational Requirements), of Schedule F 
(Service Level Requirements), of the Requirements derived from the Requirements 
of  Schedule  D  (Detailed  Operational  Requirements)  during  the  development 
process are performed and delivered under this Contract.  The evidence so provided 
shall  be  produced  by  the  Contractor  through  processes  of  Verification  and  of 
Validation, where: 
(a) 
the  “Verification  of  Requirements”  shall  mean  the  process  whereby  the 
appropriateness  of  each  Requirement  with  respect  of  the  corresponding 
business and operational need is established; and 
(b) 
the  “Validation  of  Requirements”  shall  mean  the  process  whereby  the 
delivery into operational service of the capability meeting each Requirement 
is confirmed and corroborated. 
2.2.3  Continuous Verification and Validation 
Notwithstanding formal Acceptance by the Authority, once the Authority accepts that 
the Requirements have been Verified and Validated and subsequent to the IAR with 
which that Requirement is associated, the Contractor shall continue to ensure that the 
Services  continue  to  meet  each  Requirement  and  shall  take  remedial  action  at  the 
Contractor’s  expense  should  any    Defect  or  Failure  against  the  Requirements  be 
determined, as set out in Clause 5 of this Schedule. Unless otherwise indicated by the 
Authority,  all  Requirements  shall  apply  for  the  duration  of  the  Contract.    For  the 
avoidance  of  doubt,  acceptance  by  the  Authority  that  the  Requirements  have  been 
verified and validated shall not remove the Authority’s right to re-address any issues 
raised in relation to the Requirements and request Reverification and Revalidation if, 
in the Authority’s opinion it is necessary or appropriate. 
Schedule H (Acceptance Procedures) 

Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
2.3 
Transition Acceptance 
Annex  H-1  of  this  Schedule  describes  how  the  Generic  Acceptance  Approach  described  in 
Clause 3 of this Schedule applies to the specific Transition milestones identified in Schedule 
G (Transition). 
2.3.1  TOR – NAFIS 
Notwithstanding  the  items  described  in  Annex  H-1  of  this  Schedule,  the  goal  of 
achieving  the  full  delivery  of  Transfer  of  Responsibility  for  the  existing  NAFIS 
service  is  represented  by  the  TOR–NAFIS  milestone,  as  described  in  Schedule  G 
(Transition).    The  achievement  of  TOR–NAFIS  shall  be  determined  by  the  OAV 
which includes, but is not limited to: 
(a) 
a written statement by the Contractor to the Authority no later than 30 days 
prior  to  TOR-NAFIS  fully  evidencing,  to  the  reasonable  satisfaction  of  the 
Authority,  its  complete  readiness,  preparedness  and  ability  to  take  full 
operational  responsibility  for  continuity  of  the  existing  operational  NAFIS 
Service; 
(b) 
the continuity of existing services currently provided by the NAFIS systems 
and associated NAFIS Livescan technology; 
(c) 
the delivery of capabilities compliant with each aspect of the NAFIS Service 
Level Requirements; and 
(d) 
the  completion  of  all  activities  and  Deliverables  relating  to  Transfer  of 
Responsibility as set out in Schedule G (Transition). 
2.3.2  Scottish Livescan 
Notwithstanding  the  items  described  in  Annex  H-1  of  this  Schedule,  the  goal  of 
achieving  full  delivery,  testing  and  installation  of  new  or  takeover  of  existing 
Livescan in Scotland is represented by the Scottish Livescan Milestone, as described 
in  Schedule  G  (Transition).  The  achievement  of  Scottish  Livescan  shall  be 
determined by the OAV which includes, but is not limited to: 
(a) 
a written statement by the Contractor to the Authority no later than 30 days 
prior  to  the  delivery  date  for  Scottish  Livescan  as  set  out  in  Schedule  G 
(Transition) fully evidencing, to the reasonable satisfaction of the Authority, 
its  complete  readiness,  preparedness  and  ability  to  take  full  operational 
responsibility for provision of the Scottish Livescan Service; 
(b) 
completion  of  device  approval  and  testing  of  IDENT1  Scottish  Livescan 
units; and 
(c) 
confirmation  of  successful  takeover  of  all  existing  Livescan  units  by  each 
Scottish Force, with the remainder of the new IDENT1 Livescan units to be 
installed no later than 30 April 2005. 
2.3.3  TOR – SAFR 
Notwithstanding  the  items  described  in  Annex  H-1  of  this  Schedule,  the  goal  of 
achieving  the  full  delivery  of  Transfer  of  Responsibility  for  the  existing  SAFR 
service  is  represented  by  the  TOR–SAFR  milestone,  as  described  in  Schedule  G 
Schedule H (Acceptance Procedures) 

Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
(Transition).    The  achievement  of  TOR–SAFR  shall  be  determined  by  the  OAV 
which includes, but is not limited to: 
(a) 
a written statement by the Contractor to the Authority no later than 30 days 
prior  to  TOR-SAFR  fully  evidencing,  to  the  reasonable  satisfaction  of  the 
Authority,  its  complete  readiness,  preparedness  and  ability  to  take  full 
operational  responsibility  for  the  Services  (including  Livescan)  in  Scotland 
while maintaining Business Continuity; 
(b) 
the delivery of capabilities compliant with each aspect of the Service Levels  
as set out in Schedule F (Service Level Requirements); 
(c) 
the  completion  of  all  activities  and  Deliverables  relating  to  Transfer  of 
Responsibility as set out in Schedule G (Transition); and 
(d) 
confirmation of successful installation of all Livescan units by each Scottish 
Force. 
2.3.4  FOC – Baseline Service 
Notwithstanding  the  items  described  in  Annex  H-1  of  this  Schedule,  the  goal  of 
achieving  the  full  delivery  of  the  Baseline  Service  is  represented  by  the  FOC 
milestone, as described in Schedule G (Transition).  The achievement of FOC shall 
be determined by the OAV which includes, but is not limited to: 
(a) 
the  continuity  of  existing  services  currently  provided  by  the  NAFIS,  SAFR 
and SLS systems and the full delivery of Schedule D (Detailed Operational 
Requirements); 
(b) 
the completion of Service Transition as set out in Schedule G (Transition); 
(c) 
the Verification and Validation of the Requirements described in Clause 2.2 
of  this  Schedule  (subject  to  the  exception  of  progressive  improvements  set 
out  in  Clause  3.3.5  and  of  CJX/PNN  Contract  Transition,  which  are 
scheduled to be delivered post-FOC); and 
(d) 
any other activities or Deliverables required under the Contract. 
2.3.5  Changes to Transition Services 
(a) 
Changes  to  this  Schedule,  as  agreed  under  Schedule  L  (Change  Control 
Procedure),  prior  to  FOC,  shall  be  subject  to  the  Generic  Acceptance 
Approach as described in this Schedule. 
(b) 
The  Contractor  may  integrate  the  Acceptance  of  these  changes  into 
previously  agreed  project  plans,  subject  to  the  further  approval  of  the 
Authority. 
2.4 
Acceptance of Changes to the IDENT1 Baseline Service 
2.4.1  Changes  to  the  IDENT1  Baseline  Service,  as  agreed  under  Schedule  L  (Change 
Control Procedure), whether defined prior to or subsequent to FOC, shall be subject 
to the Generic Acceptance Approach as described in this Schedule. 
Schedule H (Acceptance Procedures) 

Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
2.4.2  Acceptance  Events,  Reviews  and  Acceptance  Criteria  associated  with  Changes 
following the Acceptance of the IDENT1 Baseline Service at FOC shall be mutually 
agreed by the Parties in advance of any new work commencing. 
2.5 
Transparency 
The  Contractor’s  Acceptance  Procedures  shall  provide  and  allow  for  sample  quality  checks 
and audit trail analysis. 
2.6 
Acceptance of Options 
2.6.1  All  Optional  Services  ordered  under  the  Contract  shall  be  subject  to  Generic 
Acceptance Approach as described in this Schedule. 
2.6.2  Acceptance  Events,  Incremental  Acceptance  Reviews  and  associated  Acceptance 
Criteria  shall  be  mutually  agreed  by  the  Parties  prior  to  ordering  the  Optional 
Services.    However,  Acceptance  of  Optional  Services  shall  include  sufficient 
Regression  Testing  to  ensure  that  evidence  is  available  that  the  deployment  of  an 
Optional Service does not compromise the integrity of the IDENT1 Baseline Service. 
2.7 
Oversight of Acceptance  
2.7.1  The  Authority  shall  have  the  right  to  full,  free  and  unfettered  oversight  of  the 
provision of the Services.  
2.7.2  The  Authority  may,  with  reasonable  notice  to  the  Contractor,  inspect,  examine  and 
audit  all  aspects  of  the  provision  of  the  Services,  including  but  not  limited  to 
information,  plans,  drawings,  notes,  correspondence,  agreements,  work  in  progress 
and assets. The Authority may apply its own interpretation of any of this information 
and use this to determine Acceptance of any component of the Services. 
2.7.3  The Contractor shall invite the Authority to attend and witness all Acceptance Events.  
The  Authority  may,  on  a  case  by  case  basis,  waive  its  right  to  witness  Acceptance 
Events.    Should  the  Authority  waive  its  right  to  witness  any  Acceptance  Event,  the 
Contractor’s independent QA Authority shall represent the interests of the Authority 
in  respect  of  the  witness  of  Acceptance  Testing  activities  and  the  keeping  of  a  true 
record of the Event.  For the avoidance of doubt, in all matters relating to Acceptance 
of the Services, the Authority’s decision shall be final. 

GENERIC ACCEPTANCE APPROACH 
3.1 
Incremental Acceptance Reviews 
3.1.1  Acceptance of the Services shall be on an incremental basis.  Incremental Acceptance 
shall be measured and controlled by Incremental Acceptance Review (“IAR”) points.     
3.1.2  IARs shall take one of the following two forms; either: 
(a) 
Standard  Acceptance  Review  (“SAR”)  –  An  IAR  predominantly  relating  to 
Transition  Milestones  up  to  Acceptance  of  the  IDENT1  Baseline  Service  at 
FOC, or to the development of new capabilities (i.e. changes to the IDENT1 
Baseline Service), or both; or: 
(b) 
Progressive  Acceptance  Review  (“PAR”)  –  An  IAR  predominantly  relating 
to  progressive  improvements  in  capability,  to  system  upgrades,  to  the  in-
Schedule H (Acceptance Procedures) 

Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
service  management  of  Security  Accreditation,  and  to  transition  events 
defined  as  being  subsequent  to  the  achievement  of  the  IDENT1  Baseline 
Service at FOC and which augment the IDENT1 Baseline Service. 
3.1.3  The  development  of  the  IDENT1  Services  up  to  FOC,  and  any  future  development 
projects, shall be subject to the SARs set out hereunder.  
3.1.4  Before  each  IAR  the  Contractor  shall  conduct  one  or  more  Acceptance  Events.  
Evidence  of  successful  completion  of  each  Acceptance  Event  shall  be  presented  by 
the Contractor to the Authority at the associated IAR. 
3.1.5  An Acceptance Event is defined in Clause 3.4 below. 
3.1.6  Evidence of Acceptance Events shall be in the form of an Acceptance Event Report, 
as  described  in  Clause  3.6.3  hereunder,  provided  by  the  Contractor  that  records  the 
outcome of the Acceptance Event. Such Acceptance Event Reports shall be subject to 
verification and approval by the Authority. 
3.1.7  When all the prior constituent Acceptance Events have successfully taken place, the 
IAR shall be held.  
3.1.8  An  IAR  will  typically  be  a  day’s  review  meeting  between  the  Authority  and  the 
Contractor,  held  within reasonable  proximity  of  the Authority’s premises  (including 
Scotland)  at  a  venue  provided  by  the  Contractor,  or  by  audio  or  video  conference, 
unless otherwise agreed in writing by the Authority.  More than one IAR may be held 
consecutively on the same  day or consecutive days, in order to give an economy of 
scale  with  respect  to  attendance  by  both  the  Contractor’s  and  the  Authority’s 
representatives.  An IAR may be also be scheduled consecutively on the same day or 
days with other project events such as Project Management Review meetings in order 
to enable an economy of scale with respect to attendance by both the Contractor’s and 
the Authority’s representatives. 
3.1.9  At  the  IAR  the  Contractor  shall  provide  evidence  from  the  Acceptance  Events 
required  under  the  relevant  Milestone  in  Annex  H-1.  The  Authority  will  decide 
whether to grant acceptance of this IAR by considering the Evidence presented by the 
Contractor against the Criteria for the IAR. 
3.1.10  The  Acceptance  Events  that  lead  up  to  an  IAR  shall  be  defined  in  the  Software 
Development  Plan  (SDP)  and/or  Project  Stage  Plan  as  appropriate  as  described  in 
Schedule O (Documentation), and shown in the Integrated Master Schedule, stating 
when a particular Acceptance Event will take place and the procedure for acceptance 
for that Event. This shall include the relevant Acceptance Events set out in Annex H-
1.  Clause 3.5 provides a generic list of Acceptance Methods that may be employed 
for an Acceptance Event. 
3.1.11  Each IAR is defined below, including the following description: 
(a) 
Purpose – the reason for holding the IAR. 
(b) 
Acceptance Criteria – the criteria which must be met in order for the review 
to be deemed complete. 
(c) 
Evidence  –  the  input  required  for  the  IAR  which  provides  evidence  of  the 
Acceptance Criteria having been met. 
Schedule H (Acceptance Procedures) 

Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
3.2 
Standard Acceptance Reviews 
3.2.1  There shall be six Standard Acceptance Review (SAR) points.  The Contractor shall 
apply these SARs across the development lifecycle.  These SAR points, in sequential 
order, are: 
(a) 
Lifecycle Objective Milestone Review; 
(b) 
Lifecycle Architecture Milestone Review; 
(c) 
Design Review; 
(d) 
Product Verification Review; 
(e) 
Product Acceptance Review; and 
(f) 
Operational Acceptance Review. 
3.2.2  SAR1: Lifecycle Objective Milestone Review 
Purpose:  
The purpose of the Lifecycle Objective Milestone Review is to certify that the project 
scope and boundary conditions are fully understood. 
Acceptance Criteria:   
The  right  sets  of  Requirements  have  been  captured  and  there  is  a  shared 
understanding of these Requirements.  
Agreement by the Parties that the Requirements are testable.  
The key approaches to be used in test and evaluation have been agreed between the 
Parties. 
The current schedule estimates, priorities, risks, and development process have been 
agreed.   
Evidence:  
Evidence that management controls, as defined in Schedule Q, Part A (Contractor’s 
Solution), have been implemented including a review of Stage Plans. 
Results of reviews of Business Process Models.   
Results  of  Requirement  Verification  activities  as  stated  in  the  SDP,  including  as 
appropriate:  Use  Case  walkthroughs;  identification  of  test  method  and  Acceptance 
Criteria  for  each  Requirement  and;  evidence  of  the  completeness  of  Requirements 
using traceability analysis.  
Evidence of progressive work on development of test documentation. 
If  applicable,  results  of  one  or  more  proof  of  concepts  and  or  prototypes  to  support 
vision and business case and to address very specific risks. 
Schedule H (Acceptance Procedures) 

Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
Evidence  that  all  relevant  documentation  has  been  completed  and  approved  as  per 
Schedule  O  (Documentation)  to  the  level  of  detail  required  by  the  Authority  as 
described in Schedule D (Detailed Operational Requirements). 
3.2.3  SAR2: Lifecycle Architecture Milestone Review 
Purpose:  
The purpose of the Lifecycle Architecture Review is to certify that the architecture is 
appropriate and satisfies the Requirements.   
Acceptance Criteria:   
Agreement between the Parties that the Requirements and the architecture are stable.  
Any  major  risks  elements  have  been  sufficiently  mitigated  to  be  able to  predictably 
determine the schedule for the completion of the development.   
The Authority agrees that the objectives of the project can be met if the current plans 
are  executed  to  develop  the  complete  capabilities,  in  the  context  of  the  IDENT1 
system architecture. 
Evidence:  
Evidence that management controls, as defined in Schedule Q Part A (Contractor’s 
Solution), have been implemented including a review of Stage Plans. 
Written approval by the Authority of the IDENT1 system architecture. 
Results  of  tests  and  evaluations  (possibly  of  executable  prototypes)  which 
demonstrate that the major risk elements have been addressed and have been credibly 
resolved. 
Evidence that the SDP has sufficient detail to allow development work to proceed. 
Written approval by the Authority of the development environment established by the 
Contractor. 
Evidence that the Data Model has been reviewed and all major data model elements 
have been defined. 
Evidence that any changes to Requirements have been reviewed and accepted. 
Evidence  of  progressive  work  on  development  of  test  documentation  including 
Acceptance Testing documentation, as described in Schedule O (Documentation). 
Evidence  that  the  relevant  documentation  has  been  completed  and  approved  as  per 
Schedule  O  (Documentation)  to  the  level  of  detail  required  by  the  Authority  as 
described in Schedule D (Detailed Operational Requirements). 
Exhibiting, and, where possible and appropriate demonstrating, proposed architecture 
against some of the primary scenarios. 
3.2.4  SAR3:  Design Review 
Purpose:  
Schedule H (Acceptance Procedures) 

Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
The purpose of the  Design Review is to certify that the design is appropriate to the 
right set of Requirements and consistent with the architecture.  
Acceptance Criteria:  
Agreement  between  the  Parties  that  the  design  is  appropriate  to  the  agreed  set  of 
Requirements.  
Scope of development and testing is defined. 
Agreement between the Parties that the resources necessary to carry out development 
and testing are available. 
Evidence:  
Evidence that management controls, as defined in Schedule Q Part A (Contractor’s 
Solution), have been implemented including a review of Stage Plans. 
Written  approval  by  the  Authority  of  the  Contractor’s  detailed  Business  Process 
Models.  
Written approval by the Authority of the updated Requirements. 
Evidence  that  the  Requirements  which  are  to  be  satisfied  by  this  design  have  been 
clearly identified. 
Written approval by the Authority of any changes to the IDENT1 system architecture. 
Evidence  that  the  test  documentation  has  been  updated  and  identifies  the  scope  of 
testing for this design. 
Confirmation by the Authority that the design has been reviewed and is appropriate. 
Evidence  that  the  relevant  documentation  has  been  completed  and  approved  as  per 
Schedule  O  (Documentation)  to  the  level  of  detail  required  by  the  Authority  as 
described in Schedule D (Detailed Operational Requirements). 
3.2.5  SAR4: Product Verification Review 
Purpose:  
The purpose of the Product Verification Review is to certify that the product has been 
manufactured correctly in accordance with the agreed design and can be subjected to 
formal Acceptance Testing.   
Acceptance Criteria:   
Test scripts have been produced by the Contractor and accepted by the Authority. 
Factory Acceptance Testing has been successfully completed. 
The product has been built and successfully tested at a system level. 
Preparation is complete for Acceptance Testing. 
Evidence:  
Schedule H (Acceptance Procedures) 
10 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
Evidence that management controls, as defined in Schedule Q Part A (Contractor’s 
Solution), have been implemented including a review of Stage Plans. 
Written  confirmation  by  the  Authority  of  the  successful  completion  of  system  level 
testing  as  per  appropriate  test  documentation,  including  functional,  non-functional 
and integration testing. 
Provision  of  Test  Summary  Reports  for  any  low  level  testing  carried  out  by  the 
Contractor prior to each Acceptance Testing Event.  
Written  approval by the Authority of the proposed test environment for Acceptance 
Testing. 
Evidence of development of user manual. 
Evidence of development of training materials. 
Evidence of successful usability trials. 
Written  approval  by  the  Authority  that  the  test  documentation  is  appropriate  to 
Acceptance Testing.  
Evidence that  Acceptance Criteria have been set as an attribute for each Requirement 
that will be subject to Acceptance Testing. 
Evidence  that  the  relevant  documentation  has  been  completed  and  approved  as  per 
Schedule  O  (Documentation)  to  the  level  of  detail  required  by  the  Authority  as 
described in Schedule D (Detailed Operational Requirements). 
3.2.6  SAR5: Product Acceptance Review   
Purpose:  
The  purpose  of  the  Product  Acceptance  Review  is  to  certify  that  product  is  fit  for 
purpose and is ready to be deployed.   
Acceptance Criteria:  
Test scripts produced by the Contractor are accepted by the Authority. 
Acceptance Testing successfully completed. 
The  product  release  is  stable  and  mature  enough  to  be  deployed  in  the  user 
community. 
The Bureau are ready to receive the system. 
Evidence:  
Evidence that management controls, as defined in Schedule Q Part A (Contractor’s 
Solution), have been implemented including a review of Stage Plans. 
Evidence of traceability of Acceptance Test results to Requirements. 
Schedule H (Acceptance Procedures) 
11 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
Written  confirmation  by  the  Authority  of  the  successful  completion  of  Acceptance 
Testing as per appropriate test documentation, including the successful execution of 
key scenarios for each of the Use Cases and in accordance with Clause 5 hereunder.   
Written  confirmation  by  the  Authority  of  the  successful  completion  of  any 
benchmarking trials. 
Evidence of agreement to Memorandum of Understanding for each Bureaux. 
Evidence of the development and Authority approval of training plans. 
Evidence  that  the  deployment  plan  has  been  approved  by  the  Authority  and  Pilot 
Bureaux have been identified if required. 
Evidence of approval of any updates to end-user Manuals and training materials. 
Evidence  that  the  relevant  documentation  has  been  completed  and  approved  as  per 
Schedule  O  (Documentation)  to  the  level  of  detail  required  by  the  Authority  as 
described in Schedule D (Detailed Operational Requirements). 
3.2.7  SAR6: Operational Acceptance Review  
Purpose:  
The  purpose  of  the  Operational  Acceptance  Review  is  to  certify  that  the  system  is 
fully operational and is satisfying the business needs. 
Acceptance Criteria:   
The system has been fully deployed in accordance with the deployment plan. 
The system is running successfully in accordance with the Requirements. 
Evidence:  
Evidence  that  the  system  has  been  successfully  deployed  in  each  Bureaux  in 
accordance with the deployment plan.  
Evidence  of  successfully  deployment  of  fully  operational  pilots  (where  required  by 
the deployment plan)  
Evidence that the Requirements are continuing to be met in particular all functionality 
continues to be provided with no degradation in performance. 
Evidence  that  training  is  being  received  and  is  effective  in  accordance  with  the 
Training Plan (Schedule O:23 (Documentation)). 
Evidence  that  the  relevant  documentation  has  been  completed  and  approved  as  per 
Schedule  O  (Documentation)  to  the  level  of  detail  required  by  the  Authority  as 
described in Schedule D (Detailed Operational Requirements). 
3.3 
Progressive Acceptance Reviews 
PARs  shall  be  used  in  certain  circumstances  for  specific  purposes  when  SARs  are  not 
appropriate as a means of measuring and controlling Incremental Acceptance. 
Schedule H (Acceptance Procedures) 
12 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
These PARs include, but are not limited to: 
3.3.1  PAR: Programme Initiation Review (PIR) 
Purpose: 
The  purpose  of  the  Programme  Initiation  Review  is  to  establish  the  IDENT1 
programme on a sound basis, by means of a Contractor briefing to the Authority. 
Acceptance Criteria: 
(a) 
PIR presentation event complete 
(b) 
Issues and risks are discussed and recorded. 
(c) 
Associated documentation has been delivered in accordance with Schedule O 
(Documentation). 
Evidence: 
PIR minutes have been delivered to the Authority by the Contractor. 
3.3.2  PAR: Continuity of Service Review  
Purpose:  
The purpose of the Continuity of Service Review is to certify that upon TOR of the 
existing NAFIS Service still meets its operational and service level Requirements.   
Acceptance Criteria:   
(a) 
A written statement by the Contractor to the Authority no later than 30 days 
prior  to  TOR-NAFIS  fully  evidencing,  to  the  reasonable  satisfaction  of  the 
Authority,  its  complete  readiness,  preparedness  and  ability  to  take  full 
operational  responsibility  for  continuity  of  the  associated  existing 
Operational Services to be transferred at that Milestone. 
(b) 
The continuity of existing services currently provided by the NAFIS systems 
and associated NAFIS Livescan technology. 
(c) 
The delivery of capabilities compliant with each aspect of the NAFIS Service 
Level Requirements. 
(d) 
The  completion  of  all  activities  and  Deliverables  relating  to  Transfer  of 
Responsibility as set out in Schedule G (Transition). 
Evidence:  
Confirmation  that  the  operational  system  has  been  successfully  tested  against  the 
NAFIS Requirements.  
3.3.3  PAR: Periodic Interface Review  
Purpose:  
Schedule H (Acceptance Procedures) 
13 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
The  purpose  of  the  Periodic  Interface  Review  is  to  certify  that  data  integrity, 
synchronisation  and  reconciliation  is  maintained  between  IDENT1  system  and  peer 
systems and services, e.g. PNC.   
Acceptance Criteria:   
The  infrastructure,  messaging,  error  and  exception  handling  of  the  interfaces  with 
other systems and services, especially PNC, operate in accordance with the relevant 
ICDs. 
Evidence:  
Evidence that the relevant communications infrastructure operates in accordance with 
the  relevant  ICDs  and  meets  the  appropriate  security  requirements  for  that 
connection.  
Evidence that messages are conveyed in accordance with the relevant ICDs.  
Evidence that data integrity is maintained.  
3.3.4  PAR: BRC Completion Review  
Purpose:  
The purpose of the BRC Completion Review is to certify that completeness and data 
integrity  of  data  permanently  introduced  and  converted  into  the  Unified  Collection 
from other sources. 
Acceptance Criteria:   
All records have been ingested, converted and verified. 
Use of the records has been operationally validated. 
Evidence:  
Record counts are correct and all records for which are accounted. 
Test transactions indicated that the records are available and usable.  
3.3.5  PAR: Progressive Improvement Review 
Purpose:  
To  assure  that  planned  progressive  improvements  are  successfully  implemented and 
deliver the expected additional Services or benefits. 
To  validate  improvements  in  search  accuracy,  in  accordance  with  Schedule  F 
(Service Level Requirement), at each of: 
(a) 
FOC 
(b) 
FOC+1 (one year following FOC); and 
(c) 
FOC+4 (four years following FOC). 
Schedule H (Acceptance Procedures) 
14 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
Acceptance Criteria: 
For each Search Accuracy Benchmark (SAB) (that is, at FOC, FOC+1 and FOC+4) 
the  corresponding  Target  Accuracy  Levels  stated  in  Figure  2.5-4  Search  Accuracy 
Target  Values  of  Schedule  F  (Service  Level  Requirement)  have  been  met  or 
exceeded. 
Evidence: 
A  Search  Accuracy  Benchmark  (SAB)  has  been  conducted  for  the  corresponding 
Progressive  Search  Accuracy  Improvement  Review  at  each  of  FOC,  FOC+1  and 
FOC+4, in accordance with Schedule F (Service Level Requirement), such that the 
search  accuracy  for  each  search  type  is  demonstrated,  within  statistical  confidence 
bounds,  to  meet  or  exceed  the  corresponding  target  range  stated  in  Figure  2.5-4 
Search Accuracy Target Values of Schedule F (Service Level Requirement). 
3.3.6  PAR: Security Accreditation Review 
Purpose:  
Periodically, or as instructed by the National Accreditor, and as set out in Schedule K 
(Security), to achieve Accreditation by the National Accreditor and to assure that the 
Security  Requirements,  as  defined  in  Schedules  D  (Detailed  Operational 
Requirements),  K  (Security),  and  Q  (Contractor’s  Solution)  continue  to  be 
satisfied. 
Acceptance Criteria:   
The  issue  of  a  Certificate  of  Accreditation  by  the  National  Accreditor  for  Police 
Information Systems and Communication Security. 
Evidence:  
Certificate of Accreditation by the National Accreditor. 
The  Accreditation  Documentation  Set (“ADS”)  as set  out in  Schedules  D (Detailed 
Operational Requirements), K (Security), and Q (Contractor’s Solution). 
The  outcome  of  a  Health  Check,  as  required  under  Schedules  D  (Detailed 
Operational Requirements) and K (Security). 
A  supporting  action  plan  to  resolve  any  deficiencies,  waivers  or  deviations  with 
respect to continued Accreditation. 
3.3.7  PAR: PNN/CJX Migration Review 
Purpose:  
To ensure that if the incumbency of the PNN Framework Contract changes during the 
term  of  the  Contract  that  the  Services’  use  of  the  CJX  services  under  the  PNN 
Framework Contract is seamlessly migrated to the new CJX supplier. 
Acceptance Criteria:  
Sufficient service continuity planning. 
Schedule H (Acceptance Procedures) 
15 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
Seamless  migration  of  Services’  use  of  CJX  services  with  full  performance, 
functionality and service continuity. 
Evidence: 
Service continuity plans. 
Service monitoring metrics. 
3.3.8  PAR: Business Continuity Review 
Purpose:  
To  assure  that  the  Business  Continuity  Plan  has  been  implemented  as  agreed  in 
Schedule Q part A (Contractor’s Solution) 
Acceptance Criteria:   
Successful dry-run testing of the Business Continuity Plan as defined in Schedule O 
(Documentation). 
Evidence:  
Business Continuity Plan as detailed in Schedule O (Documentation). 
Dry-run test scripts. 
Business monitoring metrics. 
3.4 
Acceptance Events 
3.4.1  An Acceptance Event shall be defined as an activity, the successful completion of one 
or more of which culminates in an IAR. All Acceptance Events shall be carried out in 
accordance  with  the  procedures  set  out  in  Clause  5.2  below.  The  Contractor  shall 
identify  which  Acceptance  Event(s)  it  considers  should  be  employed  by  the 
Contractor  for  each  IAR.  The  decision  as  to  which  Acceptance  Events  to  be 
employed  for  each  IAR  shall  be  mutually  agreed  between  the  Parties  during  the 
planning  process  leading  to  Acceptance  Testing  of  the  relevant  Milestone.  For  the 
avoidance  of  doubt,  the  Acceptance  Events  already  listed  in  Annex  H-1  of  this 
Schedule shall be included within the relevant IAR in addition to any others agreed 
during the planning process referred to above. 
3.4.2  The following are potential Acceptance Events, although this list is not exhaustive: 
(a) 
DDR – Deliverable Document Review; 
(b) 
SRR – System Requirements Review; 
(c) 
PDR – Preliminary Design Review; 
(d) 
CDR – Critical Design Review; 
(e) 
SHC – Security Health Check; 
(f) 
SAB – Search Accuracy Benchmark; 
Schedule H (Acceptance Procedures) 
16 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
(g) 
PAT – Pilot Acceptance Test; 
(h) 
PCE – Proof of Concept Evaluation; 
(i) 
UCT – User Centred Test; 
(j) 
FAT – Factory Acceptance Test; 
(k) 
SAT – Site Acceptance Test; 
(l) 
ICT – Installation Checkout Test; 
(m) 
ORR – Operational Readiness Review; and 
(n) 
OAV – Operational Acceptance Validation. 
3.5 
Acceptance Methods 
3.5.1  The Contractor shall apply the following list of the potential Acceptance Method(s) 
that shall be employed for an Acceptance Event:   
(a) 
Product Reviews; 
(b) 
Analysis; 
(c) 
Acceptance Tests; 
(d) 
Witnessed Installation and Checkout of Equipment; and 
(e) 
Pilot and Proof of Concept. 
3.5.2  The decision as to which Acceptance Methods, and all the component parts thereof,  
that shall be employed for each Acceptance Event shall be mutually agreed between 
the Parties during the planning process leading to Acceptance Testing of the relevant 
Milestone. 
3.5.3  The Acceptance Methods shall be in accordance with the IEEE Standard for Software 
Reviews (IEEE Std 1028-1997), where appropriate. 
3.5.4  The Contractor shall identify which Acceptance Method(s) will be employed during 
each  Acceptance  Event.    The  Contractor  shall  describe  these  in  the  Acceptance 
Documentation, as set out in Clause 3.6. 
3.5.5  Product Reviews 
The  Product  Review  types  that  shall  be  employed  as  Acceptance  Methods  shall 
include: 
(a) 
Management Reviews; 
(b) 
Technical Reviews; 
(c) 
Inspections; 
(d) 
Walkthroughs; and 
Schedule H (Acceptance Procedures) 
17 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
(e) 
Audits. 
3.5.6  Analysis 
(a) 
Analysis shall be employed as an Acceptance Method where mutually agreed 
between the Parties.    
(b) 
The  Contractor  shall  supply  all  mathematical  models,  algorithms, 
simulations,  engineering  drawings,  software  and  hardware  specifications, 
calculations  and  supporting  materials  in  order  to  facilitate  analysis  by  the 
Authority. 
3.5.7  Acceptance Tests 
(a) 
The  purpose  of  each  Acceptance  Test  is  Validation  of  a  defined  set  of 
Requirements by Demonstration. 
(b) 
The Contractor shall organize and manage each Acceptance Test.  The types 
of  Acceptance  Tests  that  may  be  employed  as  Acceptance  Events  shall 
include a subset of the Acceptance Events described in Clause 3.4 above. 
(c) 
The substance of each Acceptance Test may be one or more of the following: 
(i) 
Functional Tests; 
(ii) 
Performance Tests; 
(iii) 
Usability Tests; 
(iv) 
Search Accuracy Tests; and 
(v) 
Security Tests. 
(d) 
Tests  of  other  attributes  of  the  Service  and  the  Acceptance  Criteria  shall 
relate to fitness for purpose and the Acceptance Criteria in Clause 3 above. 
(e) 
As  part  of  each  Acceptance  Test,  the  Contractor  shall  conduct  Regression 
Tests by exercising an appropriate subset of previous Acceptance Tests with 
sufficient  coverage  to  ensure  that  the  introduction  of  New  Services  and 
capabilities does not result in Defects against the Requirements for Services 
and capabilities which have already been accepted. 
3.5.8  Functional Tests 
Functional  Tests  shall  be  based  upon  the  Use  Cases  in  Schedule  D  (Detailed 
Operational Requirements) and the Criteria shall be based upon the Requirements. 
3.5.9  Performance Tests 
Performance Tests shall include START, STRESS and SOAK as defined in Schedule 
D (Detailed Operational Requirements) and the Acceptance Criteria shall relate to 
Schedule F (Service Level Requirements). 
3.5.10  Usability Tests 
Schedule H (Acceptance Procedures) 
18 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
Usability  Tests  shall  involve  end-user  Representatives  and  the  Acceptance  Criteria 
shall relate to quantifiable and demonstrable improvement in the business process. 
3.5.11  Search Accuracy Tests 
Search  Accuracy  Tests  shall  involve  end-user  Representatives  and  the  Criteria  shall 
be  derived  from  the  Requirements  set  out  in  Schedule  D  (Detailed  Operational 
Requirements) and from the Criteria used by the Authority in the Search Accuracy 
Evaluation  Benchmarks  and  shall  relate  to  quantifiable  and  demonstrable 
improvement in business benefits. 
3.5.12  Security Tests 
Security Tests shall include the Health Check as referenced in Schedule D (Detailed 
Operational Requirements) and the Acceptance criteria shall relate to HMG Infosec 
standards. 
3.5.13  Witnessed Installation and Checkout of Equipment 
(a) 
The Contractor shall provide an Installation Checklist, as set out in Schedule 
O:8 (Documentation), to demonstrate that all necessary equipment has been 
provided,  installed,  configured  and  can  been  shown  to  be  working.    The 
Contractor shall invite  the Authority  and,  where relevant,  IDENT1  end-user 
Organisations to witness installation and checkout Acceptance Events. 
(b) 
The Acceptance Criteria shall be the successful completion of the Installation 
Checklist and subsequent evidence of expected system and service behaviour 
under controlled conditions. 
3.5.14  Pilot and Proof of Concept  
The  Authority  may  permit  Pilot  Services  and  Proof  of  Concept  Services  in  the 
Operational Environment to support user centred design and the early assessment of 
operational and business benefits.  
(a) 
“Pilot  Services”  shall  mean  the  introduction  into  the  Operational 
Environment  of  planned  new  capabilities  pending  full  Verification  and 
Validation.   
(b) 
“Proof  of  Concept  Services”  shall  mean  the  introduction  of  potential  new 
capabilities  of  strictly  limited  scope  and  of  strictly  limited  duration  into  the 
Operational Environment on an experimental basis. 
(c) 
The deployment of Pilot Services and of Proof of Concept Services shall be 
at  the  sole  discretion  of  the  Authority  and  shall  satisfy  minimum  standards 
including,  but  not  limited  to,  standards  of  security  and  of  data  integrity,  as 
defined by the Authority on a case by case basis. 
(d) 
The Acceptance Criteria shall be those developed to evidence operational and 
business benefit. 
3.5.15  System Upgrades 
(a) 
The Contractor shall conduct regression tests to Verify and Validate upgrades 
to the Services. 
Schedule H (Acceptance Procedures) 
19 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
(b) 
The scope of upgrade testing and the associated Criteria shall be analogous to 
those used to Verify and Validate the original service capabilities. 
3.6 
Acceptance Documentation 
The  Contractor  shall  develop  and  deliver  to  the  Authority  documentation  associated  with 
Acceptance as in accordance with the following provisions: 
3.6.1  Test Strategy 
The  Contractor  shall  deliver  a  Test  &  Acceptance  Strategy,  as  set  out  in  the 
Programme  Initiation  Review  Documentation  in  Schedule  O  (Documentation), 
which shall define the Contractor’s general approach to Acceptance of the Service. 
3.6.2  Acceptance Event Plan 
(a) 
The Contractor shall provide an Acceptance Event Plan for each Acceptance 
Event  as  part  of  the  Stage  Plan  at  O:18,  as  set  out  in  Schedule 
O(Documentation). 
(b) 
At a minimum the Acceptance Event Plan shall include: 
(i) 
a description of the Acceptance Event environment; 
(ii) 
criteria for Acceptance Event readiness; 
(iii) 
a description of Acceptance Event scripts, which the Contractor shall 
develop from Use Case scenarios and associated functional and non-
functional  Requirements  to  ensure  complete  coverage  of  the 
capability or product under test; 
(iv) 
a description of the scope of Regression Testing; 
(v) 
criteria for successful Acceptance Event completion; and 
(vi) 
the  Requirements  to  be  verified  and/or  validated  by  the  Acceptance 
Event. 
3.6.3  Acceptance Event Report 
(a) 
The  Contractor  shall  provide  an  Acceptance  Event  Report  for  each 
Acceptance Event, as set out in O:6 of Schedule O (Documentation). 
(b) 
This Report shall be a true record of the Acceptance Event, and at a minimum 
it shall include: 
(i) 
names and roles of participants and attendees; 
(ii) 
the status of the Acceptance Event environment; 
(iii) 
the  achievement  of  the  Acceptance  Criteria  for  Acceptance  Event 
readiness; 
(iv) 
the Acceptance Event conduct; 
(v) 
the outcome of Regression Testing; 
Schedule H (Acceptance Procedures) 
20 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
(vi) 
the  achievement  of  the  Acceptance  Criteria  for  successful 
Acceptance Event completion; 
(vii) 
any  deviations  from  the  Acceptance  Criteria  for  successful 
Acceptance Event completion; 
(viii)  any  Defects  and  deficiencies  in  the  Services  or  capabilities 
undergoing acceptance, and an associated resolution plan; and 
(ix) 
the Requirements verified and/or validated by the Acceptance Event. 
3.6.4  IAR Closure Report  
(a) 
For each IAR, the Contractor shall produce a Closure Report (“IAR Closure 
Report”)  as  set  out  in  Schedule  O:7  (Documentation).  This  shall  apply 
equally to both types of IAR; whether a SAR or a PAR. 
(b) 
At a minimum each set of IAR Closure Report shall contain: 
(i) 
the name and role of the participants in the IAR; 
(ii) 
a description of the Acceptance Events culminating in the IAR; 
(iii) 
a statement confirming that the required QA procedures (as detailed 
in Schedule Q (Contractor’s Solution) have been followed; 
(iv) 
the outcome of the Acceptance Event(s) culminating in the IAR; 
(v) 
a  description  of  exceptions  during  the  Acceptance  Event(s) 
culminating in the IAR; and 
(vi) 
the  disposition  of  any  Defects  recorded  during  the  Acceptance 
Event(s) culminating in the IAR. 
(c) 
Furthermore, each set of IAR Closure Report shall also contain either: 
(i) 
a  description  of  any  Defects  and  the  completed  resolution  of  each 
such Defects; or 
(ii) 
a description of any Defects and, where agreed with the Authority, a 
firm commitment by the Contractor to correct such Defects as part of 
a subsequent IAR; or 
(iii) 
a  statement  of  exception,  justifying  why  the  Defect(s)  does  not 
compromise Acceptance. 
3.6.5  Acceptance Event Locations 
(a) 
The  Contractor  shall  conduct  Acceptance  Events  at  one  or  more  of  the 
following locations: 
(i) 
Authority Premises; 
(ii) 
IDENT1 end-user premises; and 
Schedule H (Acceptance Procedures) 
21 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
Hendon Data Centre 
Northrop Grumman 
Northrop Grumman 
Peel Estate 
Stratford Road 
12900 Federal Systems Park Drive 
Aerodrome Road 
Shirley 
Fairfax, VA 22033 
Colindale 
Solihull 
NWG 5JE 
West Mids B904ZS 
(b) 
Proposals  to  use  Authority  Premises  or  IDENT1  end-user  premises  shall  be 
subject  to  their  suitability,  to  their  availability  and  to  the  prior  written 
approval of the Authority. 
(c) 
Proposals  to  use  premises  other  than  Authority  Premises,  IDENT1  end-user 
premises  or  Contractor  nominated  locations  above  shall  be  subject  to  the 
Requirements of Schedule K (Security) and to the prior written approval of 
the Authority. 
3.7 
Acceptance Test Environment 
Use  of  the  Operational  Environment  for  Acceptance  Test  activities  will  not  usually  be 
possible  or  permissible  for  operational  and  policy  reasons  (unless  determined  by  the 
Authority  to  be  otherwise).    Therefore,  the  Contractor  shall  provide  a  Non  Operational 
Acceptance  Test  Environment  which  replicates  the  Operational  Environment  as  far  as  is 
practicable.    The  Non  Operational  Acceptance  Test  Environment  shall  be  sufficiently 
representative  of  the  Operational  Environment  to  give  the  Authority  and  end-users  the  full 
assurance that the capability undergoing test is of high quality, is fit for purpose, and is fit for 
deployment into the Operational Environment. 

ACCEPTANCE ROLES AND RESPONSIBILITIES 
4.1 
The Contractor 
4.1.1  The Contractor shall be responsible for the provision of: 
(a) 
The Test Environment – including premises and all supporting equipment. 
(b) 
Test Engineer(s) – individual(s) who shall exercise the Test Scripts. 
(c) 
QA Representative(s) - individual(s) who shall record a true account of each 
Acceptance Event as detailed in Schedule Q (Contractor’s Solution). 
(d) 
Test  Documentation  –  which  shall  include  Acceptance  Event  Plans  and 
Acceptance  Event  Reports  as  detailed  in  Schedule  O  (Documentation), 
together  with  any  other  procedures,  scenarios  or  scripts  required  by  the 
Authority. 
(e) 
Test Data. 
4.1.2  The Contractor shall make all efforts, on a reasonable endeavours basis, to secure the 
cooperation of IDENT1 end-user organisations with respect to: 
(a) 
the  agreement  of  an  end-user  organisation  Memorandum  of  Understanding 
for each end-user Organisation. 
Schedule H (Acceptance Procedures) 
22 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
4.2 
The Authority 
4.2.1  As  the  Authority  has  the  right  to  observe,  witness  and  participate  in  Acceptance 
Events,  the  Authority  shall  provide  representatives  for  this  purpose  on  a  reasonable 
endeavours basis. 
4.2.2  The Authority shall be responsible for the selection and nomination to the Contractor 
of a reasonable and appropriate number and type of User Representatives to observe 
FATs, Acceptance Testing and ICTs or to participate in UCTs. 
4.2.3  The Authority shall make all efforts, on a Commercially Reasonable Efforts basis, to 
secure the cooperation of IDENT1 end-user organisations with respect to: 
(a) 
the agreement of an end-user organisation Memorandum of Understanding as 
defined in Schedule O (Documentation) for each end-user organisation; 
(b) 
the provision by end-user organisations Test Data and Training Data; and 
(c) 
the  provision  by  end-user  organisations  of  a  reasonable  and  appropriate 
number  of  end-user  Representatives  to  observe  FATs,  Acceptance  Testing 
and ICTs or to participate in UCTs. 
4.3 
Third Party IDENT1 Stakeholders 
4.3.1  Third  party  IDENT1  stakeholders  include  IDENT1  end-user  organisations  (most  of 
which  are  individual  Police  Forces).    The  Authority  shall  use  its  reasonable 
endeavours to obtain the cooperation of the stakeholders. 
4.3.2  Each  IDENT1  end-user  organisation  is  expected  to  enter  into  a  Memorandum  of 
Understanding,  which  shall  be  a  tri-partite  agreement  between  the  end-user 
organisation,  the  Authority  and  the  Contractor  concerning  the  installation, 
configuration and checkout of Contractor equipment and the use by the Contractor of 
IDENT1  end-user  organisations  facilities,  as  defined.  The  template  for  the  end-user 
organisation  Memorandum  of  Understanding  is  defined  in  Schedule  O 
(Documentation). 
4.3.3  IDENT1  end-user  organisations  are  expected  to  provide,  at  the  request  of  the 
Authority,  a  reasonable  and  appropriate  number  of  end-user  Representatives  to 
observe FATs, Acceptance Testing and ICTs or to participate in UCTs. 
4.3.4  IDENT1 end-user organisations are expected to lend assistance with the provision of 
Training Data and Test Data. 

ACCEPTANCE PROCEDURES AND TIME PERIODS 
5.1 
General 
5.1.1  In all matters relating to Acceptance, the Authority will comply with the terms of this 
Schedule and the Authority shall be entitled to withhold Acceptance or approval for 
the  Contractor  to  proceed  in  the  event  the  Contractor  has  not  met  the  Acceptance 
Criteria  in  accordance  with  the  provisions  of  this  Clause  5.    However,  in  the  event 
that  the  Authority  withholds  Acceptance  or  approval  to  proceed,  then  an  Exception 
will be deemed to have occurred.   
Schedule H (Acceptance Procedures) 
23 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
5.1.2  In the event of such an Exception the Authority shall state the reasons for so doing in 
writing  to  the  Contractor  within  2  working  days  of  the  Authority’s  decision  to 
withhold  Acceptance  to  proceed  and  shall  inform  the  Contractor  which  option  it 
wishes to adopt under Clause 5.9.2 below.   
5.1.3  In the event of such an Exception, the Contractor shall be liable for consequent costs, 
delays, re-work and re-testing. 
5.2 
Acceptance Events 
The following procedure shall apply to all Acceptance Events. 
5.2.1  Procedures 
(a) 
The Contractor shall confirm to the Authority the date and location for each 
Acceptance Event, together with any needs such as rnd-user support, no later 
than  60  calendar  days  prior  to  the  commencement  of  the  first  day  of  that 
Acceptance Event, unless otherwise agreed in writing by the Authority. 
(b) 
The  Contractor  shall  deliver  to  the  Authority  a  draft  Test  Procedures 
Specification, as set out in Schedule O (Documentation), including Pass/Fail 
Criteria,  for  each  Acceptance  Event,  no  later than  45 calendar  days  prior  to 
the  commencement  of  the  first  day  of  that  Acceptance  Event,  unless 
otherwise agreed in writing by the Authority. 
(c) 
The  Authority  shall  submit  consolidated  comments  on  the  draft  Test 
Procedures Specification to the Contractor, including any deficiencies in the 
scope or quality of the Contractor’s plans, no later than 30 calendar days prior 
to the commencement of the first day of that Acceptance Event. 
(d) 
The  Contractor  shall  take  the  Authority’s  comments  on  the  draft  Test 
Procedures Specification into account and the Contractor shall re-submit the 
Test  Procedures  Specification  for  final  approval  by  the  Authority,  for  each 
Acceptance Event, no later than 15 calendar days prior to the commencement 
of the first day of that Acceptance Event, unless otherwise agreed in writing 
by the Authority. 
(e) 
At the commencement of each Acceptance a Readiness Review will be held, 
during which the Contractor shall brief the Authority on the state of readiness 
for  the  Acceptance  Event.    The  Contractor  shall  keep  minutes  of  each 
Readiness Review, as set out in Schedule O (Documentation). 
(f) 
At this Readiness Review the Authority shall assert its view of readiness for 
the Acceptance Event.  In the event that the Authority and the Contractor do 
not agree that there is a state of readiness for the Acceptance Event, then an 
Exception  will  be  deemed  to  have  occurred  and  the  Parties  shall  agree  the 
items  that  need  to  be  actioned  by  the  Contractor  (as  applicable)  in  order  to 
achieve the required state of readiness for the relevant Acceptance Event.  In 
the event of such an Exception, the Contractor shall be liable for consequent 
costs, delays, re-work and re-testing. 
(g) 
Upon  completion  of  the  Acceptance  Event,  a  Completion  Review  will  be 
held, in which the Contractor shall brief the Authority on the outcome of the 
Acceptance  Event,  which  shall  be  a  ‘Pass’  or  ‘Fail’  according  to  the  pre-
Schedule H (Acceptance Procedures) 
24 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
agreed Acceptance Criteria for the Event.  The Contractor shall keep minutes 
of each Completion Review, as set out in Schedule O (Documentation).     
(h) 
The  Contractor  shall  provide  an  Acceptance  Event  Report  for  each 
Acceptance  Event  in  draft  version,  as  set  out  in  Schedule  O 
(Documentation), within 14 working days of the Completion Review. 
(i) 
The  Authority  shall  submit  consolidated  comments  to  the  Contractor  on the 
draft  Acceptance  Event  Report  for  each  Acceptance  Event,  noting  any 
deficiencies in the outcome, within 30 calendar days of receipt. 
(j) 
The Contractor shall take the Authority’s comments on the draft Acceptance 
Event Report into account and the Contractor shall re-submit the Acceptance 
Event Report for final approval by the Authority, for each Acceptance Event, 
within 30 calendar days of receipt, unless otherwise agreed in writing by the 
Authority. 
(k) 
The  Authority  shall,  within  30  calendar  days  of  receipt  of  the  Acceptance 
Event Report in final version, assert its definitive view of the outcome of the 
Acceptance  Event  in  writing  to  the  Contractor.  If,  in  the  view  of  the 
Authority,  the  Acceptance  Event  has  passed  Acceptance,  then  it  shall  be 
included  in  the  relevant  IAR  as  part  of  the  assessment  as  to  whether  a 
relevant  Milestone  has  been  passed.  If  the  Authority  considers  that  the 
Acceptance  Event  has  not  passed  Acceptance,  then  an  Execption  will  be 
deemed  to  have  occurred  and  the  Authority  shall  decide  which  option  it 
wishes to adopt under Clause 5.9.2 below. 
(l) 
In  the  event  of  such  an  Exception,  the  Contractor  shall  be  liable  for 
consequent costs, delays, re-work and re-testing. 
5.2.2  Criteria 
Successful Acceptance event completion, Verification and Validation of requirements 
according  to  the  specific  criteria  developed  and  set  out  in  the  Test  Procedures 
Specification. 
5.3 
Incremental Acceptance Reviews 
5.3.1  Procedures 
(a) 
IARs, whether each is a SAR or a PAR, shall provide the means by which the 
Verification  and  Validation  of  Requirements  can  be  evidenced  by  the 
Contractor,  and  the  means  by  which  the  Authority  can  consider  such 
evidence, with a view to Accepting services and capabilities. 
(b) 
The  Contractor  shall  call  each  IAR  when  the  corresponding  Acceptance 
Events have successfully completed and have been deemed by the Authority 
to have passed the pre-agreed Criteria for the relevant Event.  The Contractor 
shall call each IAR provided it gives the Authority with at least 10 working 
days  notice.    Each  IAR  can  be  conducted  as  a  face-to-face  meeting,  or  a 
videoconference,  an  audio  conference,  as  mutually  agreed  between  the 
Parties. 
(c) 
The  Contractor  shall  submit  an  IAR  Closure  agenda/items  (contents  to  be 
agreed with the Authority) no less than 5 working days in advance of the first 
Schedule H (Acceptance Procedures) 
25 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
day  of  the  IAR  (typically  IARs  will  have  a  duration of  less  than  one  day  if 
agreed by the Parties). 
(d) 
At  the  IAR,  the  Contractor  will  conduct  a  walkthrough  presentation  of  the 
IAR Closure items above.  The IAR shall provide an opportunity for an open 
discussion  between  the  Authority  and  the  Contractor  concerning  the  IAR 
Closure Report as a true record of Acceptance Events culminating in the IAR.  
The  Contractor  shall  keep  minutes  of  each  IAR,  as  set  out  in  Schedule  O 
(Documentation).   
(e) 
No  later  than  2  working  days  after  each  IAR,  the  Authority  shall  assert  its 
provisional  view  of  Acceptance  as  determined  by  the  scope  of  the  IAR. 
Following  the  assertion  of  the  Authority’s  provisional  view,  the  Authority 
shall be entitled to either or accept or reject the IAR.  If the Authority rejects 
the  IAR,  then  an  Exception  will  be  deemed  to  have  occurred  and  the 
Authority  shall  decide  which  option  it  wishes  to  adopt  under  Clause  5.9.2 
below. 
5.3.2  Criteria 
The Acceptance Criteria shall be as set out in Clause 3 of this Schedule for the IAR in 
question. 
5.4 
Deliverable Documentation 
5.4.1  Procedures 
(a) 
Schedule O (Documentation) sets out the Deliverable Documentation under 
this Contract which shall each be subject to deliverable document review. 
(b) 
Unless otherwise specified in Schedule O (Documentation) Clause 5 of this 
Schedule, defines the required timing/timescales or periodicity of the delivery 
of each document relative to IARs, Milestones or other reference points. 
(c) 
The Contractor shall deliver each Deliverable Document in draft version, as 
set  out  in  Schedule  O  (Documentation).    The  Authority  shall  have  the 
opportunity  to  provide  written  comments  on  each  document,  including  the 
identification of deficiencies. 
(d) 
The  Authority  shall  submit  consolidated  comments  to  the  Contractor  on the 
draft Deliverable Document within 30 calendar days of receipt. 
(e) 
The Contractor shall take the Authority’s comments in the draft Deliverable 
Document into account and the Contractor shall re-submit within 15 calendar 
days  the  Deliverable  Document  for  final  approval  by  the  Authority,  unless 
otherwise agreed in writing by the Authority. 
(f) 
The  Authority  shall,  within  15  calendar  days  of  receipt  of  the  Deliverable 
Document in final version, assert its definitive view of the fitness for purpose 
of  the  Deliverable  Document.    If,  in  the  view  of  the  Authority,  the  relevant 
Deliverable  Document,  has  passed  the  Acceptance  Event  then  it  shall  be 
included  in  the  relevant  IAR  as  part  of  the  assessment  as  to  whether  a 
relevant  Milestone  has  been  passed.    If  the  Authority  considers  that  the 
Documentation has not passed Acceptance, then an Exception will be deemed 
Schedule H (Acceptance Procedures) 
26 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
to  have  occurred  and  the  Authority  shall  decide  which  option  it  wishes  to 
adopt under Clause 5.9.2 below. 
(g) 
In  the  event  that  the  Authority  and  the  Contractor  do  not  concur  that  a 
Deliverable Document is fit for purpose, then an Exception will be deemed to 
have  occurred.    In  the  event  of  such  an  exception,  the  Contractor  shall  be 
liable for consequent costs, delays and re-work. 
5.4.2  Criteria 
The  Acceptance  Criteria  for  the  Deliverable  Documents  are  set  out  in  this  Clause 
5.4.2.  The Deliverable Documents shall: 
(a) 
meet the relevant product description in Schedule O (Documentation); 
(b) 
be  delivered  to  the  Authority  on  the  dates  set  out  in  Schedule  O 
(Documentation); 
(c) 
be clearly written and intelligible, with good spelling and grammar, clear and 
consistent formatting, convenient indexing and navigation; 
(d) 
be appropriate to the target readership; 
(e) 
be  available  in  both  hard  (printed)  and  soft  (electronic)  copy,  in  formats 
mutually agreed between the parties; 
(f) 
bear  the  correct  protective  marking  under  the  GPMS  in  accordance  with 
Schedule K (Security); and 
(g) 
correctly reflect the design and other attributes of the Service to be conveyed. 
5.5 
Issue of Certificates of IAR Acceptance 
5.5.1  Upon  successful  conclusion  and  acceptance  by  the  Authority  (under  Clause  5.3.1 
above) of the IARs for Transition Milestones in Clauses 2.3.1, 2.3.2 and 2.3.3 above 
the Contractor shall issue a written "Certificate of IAR Acceptance" to the Authority 
for  signature  by  both  Parties,  supported  by  a  written  statement  signed  at  Director 
level  that  the  Contractor's  quality  assurance  procedures  as  set  out  in  Schedule  Q 
(Contractor’s  Solution)  have  been  followed  and  that  the  Acceptance  Events  have 
been undertaken in accordance with the Requirements of the Acceptance Procedures 
set  out  in  Clauses  5.2  and  5.3  above.  The  Authority  shall  use  its  reasonable 
endeavours  to  sign  and  return  the  relevant  and  valid  Certificate  of  IAR  Acceptance 
within 15 calendar days of receipt from the Contractor.   
5.5.2  Acceptance of other Transition Milestones prior to FOC shall be subject to a written 
IAR  confirmation  letter  that  all  Acceptance  Events  required  under  the  relevant 
Milestone have been satisfactorily completed. The Authority shall use its reasonable 
endeavours  to  confirm  acceptance  of  the  relevant  and  valid  IAR  confirmation  letter 
within 15 calendar days of receipt from the Contractor.  
5.5.3  Without  prejudice  to  the  rights  and  remedies  available  to  the  Authority  under  the 
Contract or at Law, in the event that the Authority decides to defer resolution of any 
Defects or Failures existing at an IAR to a later Milestone, an IAR “fixlist” shall be 
attached to the relevant Certificate of IAR Acceptance or IAR confirmation letter. 
Schedule H (Acceptance Procedures) 
27 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
5.5.4  Acceptance of the IAR for the Services at FOC shall be subject to Clause 5.9.4 below 
and  a  written  Certificate  of  IDENT1  Services  Acceptance  (as  issued  in  accordance 
with Clause 5.6 below).  
5.6 
Certificate of IDENT1 Services Acceptance 
5.6.1  The Certificate of IDENT1 Services Acceptance shall contain, as a minimum: 
Statements that, inter alia: 
(a) 
the Contractor considers that the associated IAR has now been completed in 
accordance with Annex H-1 of this Schedule. 
(b) 
the  Acceptance  Criteria  upon  which  the  Contractor  has  issued  the  written 
“Certificate of IDENT1 Services Acceptance” to the Authority, for signature 
by  the  Parties  is  as  set  out  in  this  Schedule  and  that  it  is  accepted  by  the 
Authority  and  the  Contractor  that  Acceptance  has  been  fully  carried  out  in 
accordance  with  this  Schedule  and  meets,  in  full,  the  Requirement  for 
Acceptance as specified in this Schedule. 
(c) 
therefore, the Contractor confirms that all the specified records in relation to 
Acceptance Testing are complete and available, for the relevant Acceptance 
Event or Milestone (as applicable).   
(d) 
agreement  by  the  Parties  that,  in  signing  and  dating  the  Certificate  of 
IDENT1  Services  Acceptance,  the  Contractor  has  provided,  and  the 
Authority  has  accepted,  that  the  Services,  are  available  from  the  date  of 
signing the Certificate of IDENT1 Services Acceptance and are fully ready in 
accordance with Requirements, as described in Clause 2.2 of this Schedule. 
(e) 
the  backstop  dates  for  completion  of  any  remedial  work  on  the  IDENT1 
Fixlist that may have been agreed. 
5.6.2  The Authority shall use its reasonable endeavours to sign and return the Certificate of 
IDENT1 Services Acceptance within 36 calendar days of receipt from the Contractor.   
5.7 
Acceptance by Default 
If  all  of  the  relevant  Acceptance  Criteria  have  been  met  by  the  Contractor  for  the  relevant 
Acceptance Event but the Authority has not issued the Certificate of IDENT1 Services by the 
end  of  the  prescribed  periods  of  15  or  36  calendar  days  respectively  in  Clause  5.5  and  5.6 
above, or the Authority has not notified the Contractor in writing that it is not satisfied that 
the IAR has been successfully completed (and, if so, giving reasonable justification), then the 
IAR  shall  be deemed  to  have  been  accepted  upon the  expiry  of  such  15  or  36  calendar  day 
period.   
5.8 
[NOT USED]  
5.9 
Acceptance Failure 
5.9.1  Major and Minor Defects 
In  determining  whether  or  not  Defects  are  Major  or  Minor,  and/or  Failures  for 
Acceptance Events are Material or Non-Material the Parties shall take account of any 
agreement between the Parties reached in relation to an appropriate course of action 
Schedule H (Acceptance Procedures) 
28 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
as  set  out  elsewhere  in  this  Schedule.    Further,  in  relation  to  the  definitions  set  out 
above,  if  the  Parties  disagree  as  to  whether  Defects  are  Major  Defects  or  Minor 
Defects and/or Failures for Acceptance Event  are Material Acceptance Event Failure 
or  Non-Material  Acceptance  Event  Failure    with  or  without  a  significant  adverse 
effect  on  the  provision  or  performance  of  the  Services,  the  Parties  shall  promptly 
escalate such issue in accordance with the escalation procedure set out in Clause 5.13 
below in order to resolve the relevant issue.  
5.9.2  Failure Resolution 
(a) 
During  Acceptance  Events  and  IARs,  in  the  event  that  any  Defects  and/or 
Failures  are  identified,  the  Parties  shall  discuss  and  agree  procedures  in 
respect  of  remedial  action  with  a  view  to  re-performance  of  the  affected 
Acceptance Event(s) as set out in Clause (i) and (ii) below and the effect of 
the results of the Acceptance Event upon the IDENT1 programme.  
(i) 
Subject to Clauses 5.9.2(b), 5.9.3 and 5.9.4 below, if an Acceptance 
Event,  or  any  part  thereof,  does  not  pass  the  relevant  Acceptance 
Criteria  set  out  under  the  associated  IAR,  the  Contractor  shall 
promptly  take  appropriate  action  to  remedy  the  relevant  Defect  or 
Failure  and/or  perform  the  Acceptance  Event  (or  the  relevant  part 
thereof)  and,  upon  completion  of  the  agreed  remedial  action,  at  the 
Contractor’s  own  expense,  shall  repeat  the  procedures  in  the 
Acceptance  Event,  to  enable  the  Acceptance  Event  to  pass  the 
relevant  Acceptance  Testing  Criteria  set  out  in  Annex  H-1  of  this 
Schedule. 
(ii) 
Unless otherwise agreed between the Parties, the Contractor shall re-
perform  the  Acceptance  Event  within  15  (fifteen)  working  days  of 
the  date  such  Acceptance  Event  failed  to  pass  the  IAR  Acceptance 
Criteria.  
(b) 
In  the  event  of  failure  by  the  Contractor  to  pass  the  Acceptance  Testing 
/Acceptance  Criteria  with  respect  to  IARs  prior  to  FOC  requiring  only  a 
written confirmation letter, the provisions of this Clause 5.9.2(b) shall apply 
as follows: 
(i) 
if,  following  no  more  than  two  re-performances  of  the  relevant 
Acceptance  Event,  the  Acceptance  Event  (or  any  part  thereof)  still 
fails  the  Acceptance  Testing  Criteria  set  out  in  this  Schedule  (as 
applicable),  then  the  Authority  shall,  at  its  sole  discretion  have  the 
right  to,  and  without  prejudice  to  any  other  rights  or  remedies 
available to the Contractor under the Contract: 
(A) 
request  that  the  Contractor  remedy,  replace  or  perform  the 
Acceptance  Event  again,  as  applicable  and  repeat  the 
evaluation under the Acceptance Testing Criteria; or 
(B) 
allow  the  Contractor  to  continue  to  the  next  Milestone, 
subject  to  agreement  of  a  firm  remedial  plan  (to  be  agreed 
between the Parties) for the non-conforming Deliverables to 
be corrected so that it meets the Acceptance Testing Criteria; 
or 
Schedule H (Acceptance Procedures) 
29 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
(C) 
issue  an  interim  confirmation  letter  with  an  IAR  fixlist 
setting out the outstanding actions and agreed timescales for 
the remedial plan, subject to Clause 5.9.6 below. 
5.9.3  TOR: 
(a) 
In  the  event  of  failure  by  the  Contractor  to  pass  the  Acceptance  Testing 
/Acceptance  
(b) 
Criteria with respect to IARs for TOR-NAFIS, Scottish Livescan and TOR-
SAFR, the provisions of this Clause 5.9.3 shall apply as follows: 
(i) 
if,  following  no  more  than  two  re-performances  of  the  relevant 
Acceptance  Event,  the  Acceptance  Event  (or  any  part  thereof)  still 
fails  the  Acceptance  Testing  Criteria  set  out  in  this  Schedule  (as 
applicable),  then  the  Authority  shall,  at  its  sole  discretion  have  the 
right  to,  and  without  prejudice  to  any  other  rights  or  remedies 
available to the Authority under the Contract: 
(A) 
request  that  the  Contractor  remedy,  replace  or  perform  the 
Acceptance  Event  again,  as  applicable  and  repeat  the 
evaluation under the Acceptance Testing Criteria; or 
(B) 
allow  the  Contractor  to  continue  to  the  next  Milestone, 
subject  to  agreement  of  a  firm  remedial  plan  for  the  non-
conforming Deliverables to be agreed between the Parties; 
(C) 
issue  an  interim  Certificate  of  Acceptance  (“Interim 
Acceptance  Certificate”)  with  an  IAR  fixlist  setting  out  the 
outstanding  actions  and  agreed  timescales  for  the  remedial 
plan, subject to Clause 5.9.6 below. 
(D) 
Subject  to  the  expiry  of  the  Liquidated  Damages  period  in 
Clause  17  of  Schedule  B  (Conditions  of  Contract),  reject 
the  relevant  Deliverable(s)  and  terminate  the  Contract  in 
accordance  with  Clause  43  of  Schedule  B  (Conditions  of 
Contract).    For  the  avoidance  of  doubt,  such  termination 
under  this  Clause 5.9.3 shall be a  termination  for  a  material 
Default by the Contractor. 
5.9.4  FOC:   
In the event of failure by the Contractor to pass the Acceptance Testing /Acceptance 
Criteria  with  respect  to  FOC,  the  provisions  of  this  Clause  5.9.4  shall  apply  as 
follows: 
(a) 
if,  following  no  more  than  two  re-performances  of  the  relevant  Acceptance 
Event,  the  Acceptance  Event  (or  any  part  thereof)  still  fails  the  Acceptance 
Testing  Criteria  set  out  in  this  Schedule  (as  applicable),  then  the  Authority 
shall,  at  its  sole  discretion,  have  the  right  to,  and  without  prejudice  to  any 
other rights or remedies: 
(i) 
request  that  the  Contractor  remedy,  replace  or  perform  the 
Acceptance  Event  again,  as  applicable  and  repeat  the  evaluation 
under the Acceptance Testing Criteria; 
Schedule H (Acceptance Procedures) 
30 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
(ii) 
require  the  Contractor  to  implement  fully  (within  the  timescales 
agreed by the Parties) any solutions to problems identified during the 
Transition period of IDENT1 development which the Parties agreed 
to defer until the IAR associated with the FOC Transition Milestone 
(or  beyond),  such  obligations  being  collectively  known  as  the 
"IDENT1 Fix List".   
(iii) 
issue  an  interim  Certificate  of  Services  Acceptance  (“Interim 
IDENT1 Acceptance Certificate”) with an IDENT1 Fixlist setting out 
the outstanding actions and agreed timescales for the remedial plan, 
subject to Clause 5.9.6 below; 
(iv) 
subject to the expiry of the Liquidated Damages period in Clause 17 
of  Schedule  B  (Conditions  of  Contract),  reject  the  relevant 
Deliverable(s) and terminate the Contract in accordance with Clause 
43  of  Schedule  B  (Conditions  of  Contract).    For  the  avoidance  of 
doubt, such termination under this Clause 5.9.4 shall be a termination 
for a material Default by the Contractor.    
5.9.5  The issue of a Certificate of Acceptance or confirmation letter shall not prejudice any 
claim of the Authority in respect of any Defects or Failures which may subsequently 
become apparent or be discovered. In addition, the Parties may agree that, if the cause 
for a particular occurrence is clear and the Contractor has done whatever is necessary 
to ensure that such cause does nor recur, then the required Acceptance Criteria have 
been achieved. 
5.9.6  The  Authority  may  issue  a  relevant  Certificate  of  Acceptance  or  IAR  confirmation 
letter with resolution of some or all outstanding  Defects or Failures attached as a lien 
against  future  IARs  or  Acceptance  Events.    For  instance,    Minor  Defects  might  be 
more  efficiently  corrected and  retested in  a  future  delivery  rather  than  retesting  and 
delaying the current milestone.  If the Defects are not resolved, as agreed, by the time 
of  the  future  Milestone,  then  the  Certificate  of  Acceptance  for  the  future  Milestone 
might be withheld until they are resolved. 
5.9.7  The Authority reserves the right not to issue a relevant Certificate of Acceptance or 
IAR  confirmation  letter  until  some  or  all  of  the    Major  Defects  and/or  Material 
Acceptance  Event  Failure  are  resolved.    Successful  resolution  of  both  Major  and  
Minor  Defects  shall  be  agreed  upon  based  on  inspection,  successful  rerunning  a 
subset  of  the  Acceptance  Event,  or  successful  rerunning  the  complete  set  of 
Acceptance Events. For the avoidance of doubt, in the event of any Defect or Failure, 
the  Contractor  shall  be  liable  for  all  costs  and  delays,  and  the  Authority  shall  be 
entitled,  unless  otherwise  agreed,  to  hold  the  Contractor  to  the  original  dates  of  the 
subsequent Milestones. 
5.9.8  For  the  avoidance  of  doubt,  the  Authority  reserves  the  right  to  request  all 
Defects/Failures to be resolved by the date for the FOC Milestone. 
5.10 
Delay 
In respect of any delay in the achievement of the IDENT1 FOC Milestone by the TOR and/or 
FOC dates (as applicable) which is due to the Default of the Contractor the Authority shall be 
entitled  to  claim  against  the  Contractor  in  accordance  with  Condition  17  of  Schedule  B 
(Conditions of Contract). 
Schedule H (Acceptance Procedures) 
31 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
5.11 
FOC Default 
If  the  Services  have  not  been  accepted  by  the  end  of  all  extensions  to  the  SAR6  IAR 
associated with the FOC Transition Milestone provided in this Schedule, the Contractor shall 
(except to the extent due to a Default of the Authority) be in Default under this Contract and 
the Authority shall have the right to terminate this Contract in accordance with Condition 43 
of Schedule B (Conditions of Contract).   
5.12 
Failure to Remedy 
In the event that any elements of the IDENT1 fixlist have not been remedied by the backstop 
date(s)  agreed  following  Acceptance  of  Services  at  FOC,  the  Authority  shall  be  entitled  to 
seek a commensurate permanent reduction to the Services Charges. 
5.13 
Dispute Resolution 
In  the  event  of  any  dispute  or  disagreement  in  relation  to  any  aspect  of  Acceptance,  the 
Parties  shall  immediately  escalate  such  issue  in  accordance  with  the  agreed  escalation 
procedures set out in Schedule P (Dispute Resolution Procedures). 
Schedule H (Acceptance Procedures) 
32 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
ANNEX H-1  
 
ACCEPTANCE AND TRANSITION MILESTONES 
The tables below show the Transition Milestones, as identified in Schedule G (Transition), and the 
IARs that will have been successfully completed in order to achieve the milestone.  
The IARs for a given Transition Milestone relate to those elements of the Services to be operationally 
deployed at that milestone. 
For each IAR within a given Transition Milestone, currently identified Acceptance Event(s) are listed.  
The Acceptance Events identified are not comprehensive (for example, PARs which do not relate to a 
specific  Transition  Milestone  in  Schedule  G  (Transition)  are  not  listed)  and  will  be  subject  to 
agreement  between  the  Contractor  and  the  Authority  during  the  preceding  stage  of  the  project. 
However, as a minimum, they will include the Acceptance Events detailed below. 
The Use Cases and other Requirements listed for each Transition Milestone indicates the scope to be 
covered by the associated IAR(s). 
Transition Milestone 
Programme Initiation 
IARs 
Acceptance Events 
Milestone Transition 
Checklist 
PAR – Programme Initiation Review 
• 
Programme 
• 
Issues  and  risks  are 
Initiation  Review 
discussed 
and 
This  review  covers  the  Contractor’s  approach 
presentation  event 
recorded 
to: 
complete 
•  Management Methods 
• 
PIR  minutes  have 
been delivered 
•  Service Delivery 
• 
Documentation  has 
•  Requirements Management 
been  delivered  in 
accordance 
with 
•  Development 
Schedule 

•  Test & Acceptance 
(Documentation). 
• 
Scope 
of 
development 
projects agreed. 
• 
Quality 
Management 
System established. 
Applicable Use Cases/Requirements 
Not Applicable. 
 
Transition Milestone 
TOR-NAFIS 
IARs 
Acceptance Events 
Milestone Transition 
Checklist 
• 
 
• 
 
• 
 
PAR – Continuity of Service Review 
• 
Validation 
by   
means  of  an  OAV 
This  review  covers  TOR-NAFIS  and  SARs  1,,  2, 
Schedule H (Acceptance Procedures) 
33 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
3, 4, 5 and 6 do not apply.   
of  the  criteria  set 
out 
in 
section 
2.3.1 above 
Applicable Use Cases/Requirements 
NAFIS requirements as of start of TOR-NAFIS and all Use Cases to set the scope. 
 
Transition Milestone 
Scottish Livescan 
IARs 
Acceptance Events 
Milestone Transition 
Checklist 
SAR3 – Outline Design Review 
• 
System 
design  • 
ICD 
approved 
review. 
(Livescan 
to 
This review covers Scottish Livescan.   
SAFR). 
• 
Updated 
Data 
Model reviewed if  • 
Scope  of  testing 
applicable. 
agreed. 
• 
Identify 
and  • 
Documents 
review 
updated 
and 
requirement set.   
reviewed  as  per 
Schedule 

• 
Detailed  Business 
(Documentation). 
Process 
Model 
and  task  analysis  • 
Scottish  Livescan 
agreed. 
as 
detailed 
in 
Schedule 

• 
Updated 
(Acceptance 
Development 
Procedures), 
plans  reviewed  if 
section 2.3.2. 
applicable.   
• 
Performance 
• 
Ability  to  capture 
Model  Reviewed 
Palm images. 
if applicable. 
SAR4 – Product Verification Review 
• 
Testing  of  ability  • 
Acceptance 
test 
to search print sets 
environment 
This review covers Scottish Livescan.   
against  the  ten-
established. 
print 
and 
unidentified  mark  • 
Validation  of  user 
manuals 
and 
collections 
of 
training materials. 
SAFR. 
• 
Training 
Plan 
agreed. 
• 
Approval 
of 
acceptance 
tests 
documentation. 
• 
Documents 
updated 
and 
reviewed  as  per 
Schedule 

(Documentation). 
• 
Traceability 
of 
global  functional 
Schedule H (Acceptance Procedures) 
34 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
and 
non-
functional 
requirements 
to 
Test Cases. 
• 
Traceability 
of 
Use 
Cases 
to 
derived 
requirements 
to 
Test Cases. 
SAR5 – Product Acceptance Review 
• 
ORR. 
• 
Type  approval  of 
IDENT1  Scottish 
This review covers Scottish Livescan.   
Livescan units. 
• 
MOUs agreed.  
• 
Deployment  plan 
agreed. 
• 
Scottish 
Users 
trained  in  use  of 
Livescan 
unit, 
including 
palm 
capture. 
• 
Documents 
updated 
and 
reviewed  as  per 
Schedule 

(Documentation). 
SAR6 – Operational Acceptance Review 
• 
Validation 
by  • 
New 
IDENT1 
means  of  an  OAV 
Livescan 
unit’s 
This review covers Scottish Livescan.   
of  the  criteria  set 
installed, 
tested 
out 
in 
section 
and  operational  at 
2.3.2 above. 
current 
Scottish 
Livescan 
locataions 
that 
have 
not 
been 
replaced 
by 

April  2005,  with 
the  remainder  of 
the  new  IDENT1 
Livescan  units  to 
be  installed  not 
later than 30 April 
2005. 
• 
MOU’s signed off 
• 
Review 
against 
Schedule 

(SLR). 
• 
Review 
of 
training 
effectiveness 
in 
accordance 
with 
Schedule H (Acceptance Procedures) 
35 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
the Training Plan.  
• 
Documents 
updated 
and 
reviewed  as  per 
Schedule 

(Documentation). 
Applicable Use Cases/Requirements 
Use Cases 1, 2 and 3 
 
Transition Milestone 
Palm Searching 
IARs 
Acceptance Events 
Milestone Transition 
Checklist 
SAR1 – Lifecycle Objective Milestone Review 
• 
Use  Case  Model  • 
Glossary review 
review 
This review covers full IDENT1 capability. 
• 
Project 
risks 
identified 
• 
Validation of requirements 
• 
Development 
plans  scoped  and 
• 
Scope of development project agreed 
reviewed 
• 
Identification 
of 
test  criteria  for 
• 
Requirements  allocated  to  development  • 
System 
each requirement.  
projects 
requirement 
review 
• 
Documents 
• 
Test criteria for requirements agreed 
updated 
and 
• 
Initial Data Model 
reviewed  as  per 
review 
Schedule 

(Documentation). 
• 
Initial 
Business 
Process 
Model  • 
Requirements 
review. 
allocated 
to 
development 
projects. 
• 
Test  criteria  for 
requirements 
agreed. 
• 
Project 
Configuration 
Control 
Board 
established. 
• 
Test 
and 
Development 
facilities 
established. 
• 
Service 
Management 
capability 
operational 
including  Service 
Desk, 
User 
support 
and 
installation 
and 
Schedule H (Acceptance Procedures) 
36 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
management 
support. 
• 
Business 
Vision 
review. 
SAR2 – Lifecycle Architecture Milestone Review 
•  Updated 
• 
System 
Architecture 
Architecture  risks 
This review covers full IDENT1 capability.    
Model reviewed. 
mitigated. 
This  review  precedes  SAR3  for  Pre-FOC 
Checkpoint Transition Milestones.   
•  Updated 
Data  • 
Review 
of 
Model reviewed. 
requirement 
changes.   
• 
Updated 
Development 
• 
System 
plans reviewed.   
architecture 
stable.  
•  Performance 
Model Reviewed. 
• 
System 
design 
aligned 
with 
Authority's 
IT 
strategies 
and 
policies. 
• 
Updated  Business 
Vision 
• 
Documents 
updated 
and 
reviewed  as  per 
Schedule 

(Documentation). 
SAR3 – Outline Design Review 
• 
System 
design  • 
Updated 
review. 
Development 
This review covers Palms.   
plans reviewed.   
 
• 
Updated 
Data 
Model reviewed. 
• 
Documents 
updated 
and 
• 
Identify 
and 
reviewed  as  per 
review 
Schedule 

requirement set.   
(Documentation). 
• 
Detailed  Business  •  Palm 
data 
Process 
Model 
exchange  format 
and  task  analysis 
agreed 
(based 
agreed. 
upon 
• 
Scope  of  testing 
ANSI/NIST). 
agreed. 
• 
Performance 
Model Reviewed. 
• 
Usability Trials. 
SAR4 – Product Verification Review 
• 
Testing  the  ability  • 
Acceptance 
test 
to  capture  and 
environment 
This review covers Palms.   
search palms. 
established. 
 
• 
Training 
Plan 
agreed. 
Schedule H (Acceptance Procedures) 
37 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
• 
Approval 
of 
Acceptance  tests 
documentation. 
• 
Documents 
updated 
and 
reviewed  as  per 
Schedule 

(Documentation). 
• 
Traceability 
of 
global  functional 
and 
non-
functional 
requirements 
to 
Test Cases. 
• 
Traceability 
of 
Use 
Cases 
to 
derived 
requirements 
to 
Test Cases. 
SAR5 – Product Acceptance Review 
• 
Testing  the  ability  • 
FPOs  trained  for 
to  capture  and 
palm searching. 
This review covers Palms.   
search palms. 
 
• 
Validation  of  user 
• 
 
manuals 
and 
training materials. 
• 
Deployment  plan 
agreed. 
• 
Documents 
updated 
and 
reviewed  as  per 
Schedule 

(Documentation). 
SAR6 – Operational Acceptance Review 
• 
Validation 
by  • 
Successful rollout. 
means  of  an  OAV 
This review covers the Palms.   
in accordance with  • 
Ability  to  capture 
 
and  search  palms 
the  Schedule  O 
from  any  installed 
(Documentation) 
Bureau 
in 
Acceptance  Event 
England,  Scotland 
Report. 
or Wales. 
• 
Scanners 
upgraded, 
as 
required. 
• 
National 
palm 
searching enabled. 
• 
Encoding 
of 
existing  National 
Palm 
collection 
completed. 
Schedule H (Acceptance Procedures) 
38 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
• 
Local 
palm 
collections 
encoded, 
if 
appropriate. 
• 
Review 
against 
Schedule 

(SLR). 
• 
Review 
of 
training 
effectiveness 
in 
accordance 
with 
the Training Plan. 
• 
Documents 
updated 
and 
reviewed  as  per 
Schedule 

(Documentation). 
Applicable Use Cases/Requirements 
Use Cases 4, 6, 7, 9, 15, 12, 13, 14 
 
Transition Milestone 
TOR-SAFR 
IARs 
Acceptance Events 
Milestone Transition 
Checklist 
SAR3 – Outline Design Review 
• 
System 
design  • 
Updated 
review. 
Development 
This  review  covers  IDENT1  full  capability  for 
plans reviewed.   
Scotland. 
• 
Updated 
Data 
Model reviewed. 
• 
Documents 
updated 
and 
• 
Identify 
and 
reviewed  as  per 
review 
Schedule 

requirement set.   
(Documentation). 
• 
Detailed  Business 
Process 
Model 
and  task  analysis 
agreed. 
• 
Scope  of  testing 
agreed. 
• 
Performance 
Model Reviewed. 
SAR4 – Product Verification Review 
• 
Testing  the  SAFR  • 
Acceptance 
test 
capability. 
environment 
This  review  covers  IDENT1  full  capability  for 
established. 
Scotland. 
• 
Scottish  weeding 
rules 
implemented. 
• 
Training 
Plan 
Schedule H (Acceptance Procedures) 
39 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
agreed (Scotland). 
• 
Approval 
of 
acceptance 
tests 
documentation. 
• 
Documents 
updated 
and 
reviewed  as  per 
Schedule 

(Documentation). 
• 
Traceability 
of 
global  functional 
and 
non-
functional 
requirements 
to 
Test Cases. 
• 
Traceability 
of 
Use 
Cases 
to 
derived 
requirements 
to 
Test Cases. 
SAR5 – Product Acceptance Review 
• 
Operational 
• 
MOUs agreed.  
readiness  review 
This  review  covers  IDENT1  full  capability  for 
prior  to  SAFR  • 
Permanent 
Scotland. 
Glasgow  Bureau 
decommissioning.  
established. 
• 
Deployment  plan 
agreed. 
• 
Bureaux  systems 
provided 
for 
Aberdeen, 
Edinburgh 
and 
Dundee. 
• 
Scottish  Bureaux 
staff  trained  on 
IDENT1 system. 
• 
Documents 
updated 
and 
reviewed  as  per 
Schedule 

(Documentation). 
SAR6 – Operational Acceptance Review 
• 
Validation 
by  • 
Successful  rollout 
means  of  an  OAV 
confirmed by each 
This  review  covers  IDENT1  full  capability  for 
of  the  criteria  set 
force  by  signed 
Scotland. 
out 
in 
section 
MOU. 
2.3.3 above 
• 
Legacy 
SAFR 
data  migrated  to 
IDENT1  to  form 
part  of  Unified 
Collection. 
• 
BRC of the SCRO 
paper 
Palm 
Schedule H (Acceptance Procedures) 
40 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
collection 
is 
complete. 
• 
Scottish 
SAFR 
MIS  and  audit 
data  migrated  to 
IDENT1. 
• 
Business 
continuity 
provided 
for 
Scotland. 
• 
Review 
against 
Schedule 

(SLR). 
• 
Review 
of 
training 
effectiveness 
in 
accordance 
with 
the Training Plan. 
• 
Documents 
updated 
and 
reviewed  as  per 
Schedule 

(Documentation). 
Applicable Use Cases/Requirements 
All 
 
Transition Milestone 
IDENT1 System HCI 
IARs 
Acceptance Events 
Milestone Transition 
Checklist 
SAR3 – Outline Design Review 
• 
Identify 
and  • 
Demonstration 
review 
facility  of  UIEs 
This review covers usability of IDENT1.   
requirement set.   
established 
• 
Outline  Business  • 
Scope  of  usability 
Process 
Model 
trials agreed. 
and  task  analysis 
agreed 
and  • 
Updated 
Development 
presented. 
plans reviewed.    
• 
Performance 
of 
the UIEs. 
• 
Documents 
updated 
and 
reviewed  as  per 
Schedule 

(Documentation). 
SAR4 – Product Verification Review 
• 
Testing 
of  • 
Acceptance 
test 
finalized UIEs. 
environment 
This review covers usability of IDENT1.   
established. 
• 
Approval 
of 
Schedule H (Acceptance Procedures) 
41 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
usability 
tests 
documentation. 
• 
Documents 
updated 
and 
reviewed  as  per 
Schedule 

(Documentation). 
• 
Training 
Plan 
agreed. 
• 
Training  materials 
approved. 
• 
Traceability 
of 
global  functional 
and 
non-
functional 
requirements 
to 
Test Cases. 
• 
Traceability 
of 
Use 
Cases 
to 
derived 
requirements 
to 
Test Cases. 
SAR5 – Product Acceptance Review 
• 
Deployment  plan  • 
Deployment 
of 
agreed. 
new 
PC 
This review covers usability of IDENT1.   
workstations  and 
• 
ORR 
upgrades  to  ten 
print  and  mark 
scanners. 
• 
Users  trained  on 
new Bureau HCI. 
• 
Users  trained  on 
new 
Livescan 
HCI. 
• 
Documents 
updated 
and 
reviewed  as  per 
Schedule 

(Documentation). 
SAR6 – Operational Acceptance Review 
• 
Validation 
by  • 
Successful rollout. 
means  of  an  OAV 
This review covers usability of IDENT1.   
in accordance with  • 
Review 
against 
This  review  may  be  combined  with  SAR6  for 
Schedule 

the  Schedule  O 
FOC-Provisional 
Transition 
Milestone 
if 
(SLR). 
(Documentation) 
mutually agreed. 
Acceptance  Event  • 
Review 
of 
Report. 
training 
effectiveness 
in 
accordance 
with 
the Training Plan. 
• 
Documents 
Schedule H (Acceptance Procedures) 
42 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
updated 
and 
reviewed  as  per 
Schedule 

(Documentation). 
Applicable Use Cases/Requirements 
All (interface scenarios only) 
 
Transition Milestone 
Pre - FOC Checkpoint 
IARs 
Acceptance Events 
Milestone Transition 
Checklist 
SAR3 – Outline Design Review 
• 
System 
design  • 
Updated 
review. 
Development 
This  review  covers  the  IDENT1  full  capability 
plans reviewed.   
(including Scotland). 
• 
Updated 
Data 
 
Model reviewed. 
• 
Documents 
updated 
and 
• 
Identify 
and 
reviewed  as  per 
review 
Schedule 

requirement set.   
(Documentation)
• 
Detailed  Business 

Process 
Model 
and  task  analysis 
agreed. 
• 
Scope  of  testing 
agreed. 
• 
Performance 
Model reviewed. 
SAR4 – Product Verification Review 
• 
All  Use  Cases  • 
Acceptance 
test 
tested 
in 
environment 
This  review  covers  the  IDENT1  full  capability. 
development 
established. 
(A  separate  SAR4  has  been  assumed  for  TOR-
environment. 
SAFR  but  may  be  combined  with  this  SAR  if 
• 
Training 
Plan 
mutually agreed) 
agreed. 
 
• 
Approval 
of 
Acceptance  tests 
documentation. 
• 
Documents 
updated 
and 
reviewed  as  per 
Schedule 

(Documentation). 
• 
Traceability 
of 
global  functional 
and 
non-
functional 
requirements 
to 
Test Cases. 
• 
Traceability 
of 
Use 
Cases 
to 
Schedule H (Acceptance Procedures) 
43 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
derived 
requirements 
to 
Test Cases. 
SAR5 – Product Acceptance Review 
• 
ORR. 
• 
Validation  of  user 
manuals 
and 
This  review  covers  the  IDENT1  full  capability.  • 
Deployment  plan 
training materials. 
(A  separate  SAR5  has  been  assumed  for  TOR-
agreed. 
SAFR  but  may  be  combined  with  this  SAR  if 
• 
Web  services  for 
mutually agreed) 
all 
searches 
 
enabled. 
• 
Search 
fusion 
achieved. 
• 
Central 
and 
Bureau 
architectures 
rolled out. 
• 
All BRC activities 
completed. 
• 
External  interface 
testing complete. 
• 
Schedule  F/SLR 
updated  to  reflect 
FOC  metrics  and 
thresholds 
• 
All 
Bureaux 
furniture installed 
• 
Documents 
updated 
and 
reviewed  as  per 
Schedule 

(Documentation). 
Applicable Use Cases/Requirements 
All 
 
Transition Milestone 
FOC-Provisional 
IARs 
Acceptance Events 
Milestone Transition 
Checklist 
SAR6 – Operational Acceptance Review 
• 
 Operational 
• 
Successful 
evaluation 
installation. 
This  review  covers  IDENT1  full  capability  to 
validate  that  the  full  functionality  has  been 
• 
Users  trained  on 
successfully deployed to all Bureau. 
IDENT1 system. 
• 
Documents 
updated 
and 
reviewed  as  per 
Schedule 

(Documentation. 
Schedule H (Acceptance Procedures) 
44 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
• 
All  functionality 
deployed  on  the 
operational 
system. 
Applicable Use Cases/Requirements 
All 
 
 
Transition Milestone 
FOC 
IARs 
Acceptance Events 
Milestone Transition 
Checklist 
PAR – BRC Completion Review 
 
• 
Data 
integrity 
checks  as  deemed 
This  review  validates  that  all  expected  data  is 
appropriate. 
available. 
 
•   
PAR – Business Continuity Review 
 
• 
Business 
Continuity  Plan  is 
This  review  covers  business  continuity  for  the 
in 
place 
as 
whole IDENT1 services 
detailed 
in 
Schedule 

(Documentation) 
and  plans  have 
been tested. 
SAR6 – Operational Acceptance Review 
• 
Operational 
• 
User  Satisfaction 
evaluation. 
Survey. 
This  review  covers  IDENT1  full  capability  to 
validate that the system is running successfully. 
• 
Validation 
by  • 
All system design 
means 
of 
an 
documents 
OAV 
of 
the 
agreed. 
criteria  set  out  in 
section 
2.3.4  • 
Electronic 
above. 
interface 
established 
between  IDENT1 
and Scottish CHS 
if  requested  by 
the Authority. 
• 
Service  transition 
complete. 
• 
Stable  operation 
under 
full 
operational 
Service 
Levels 
(in 
accordance 
with  Schedule  F 
(Service 
Level 
Schedule H (Acceptance Procedures) 
45 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
Requirements)). 
• 
All  functionality 
deployed 
under 
the 
IDENT1 
Services 
• 
Review 
of 
training 
effectiveness 
in 
accordance  with 
the Training Plan.  
• 
Documents 
updated 
and 
reviewed  as  per 
Schedule 

(Documentation)

Applicable Use Cases/Requirements 
All 
 
Other Milestone Activity 
 
IARs 
Acceptance Events 
Milestone Transition 
Checklist 
PAR – Periodic Interface Review 
 
• 
Operations 
and 
integrity 
of 
Covers PNC, PIFE and other key interfaces. 
external  interfaces 
reviewed 
and 
tested  as  agreed 
from  time  to  time 
between 
the 
Authority  and  the 
Contractor. 
PAR – Progressive Improvement Review 
 
• 
Search  Accuracy 
Benchmark 
at 
Covers search accuracy 
FOC+1  validates 
accuracy 
targets 
in 
accordance 
with  Schedule  F 
(Service 
Level 
Requirements). 
PAR – Progressive Improvement Review 
 
• 
Search  Accuracy 
Benchmark 
at 
Covers search accuracy 
FOC+4  validates 
accuracy 
targets 
in 
accordance 
with  Schedule  F 
(Service 
Level 
Requirements). 
Schedule H (Acceptance Procedures) 
46 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 15th July 2008 
PAR – Security Accreditation Review 
 
• 
Accreditation 
in 
accordance 
with 
Covers security requirements 
Schedule 

(Security). 
PAR – PNN/CJX Migration Review 
 
• 
Validation 
of 
migration 
of 
WAN  services  to 
PNN/CJX. 
 
Schedule H (Acceptance Procedures) 
47 
Version 1.0 
FINAL 
 
18 July 2005 
 
Released under FOI in full on 15th July 2008