SCHEDULE Q 
CONTRACTOR’S SOLUTION 
Schedule Q, Part A (Contractor’s Solution) 
 
Signature Version 
CCN001 
 
18 July 2005 
 
 
 
 
Released under FOI in full on 16th July 2009 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 16th July 2009 
CONTENTS 
 
PART A: 
CONTRACTOR’S SOLUTION 
PART B: 
SYSTEM DESCRIPTION 
PART C: 
GLOSSARY 
 
Schedule Q, Part A (Contractor’s Solution) 
 
Signature Version 
CCN001 
 
18 July 2005 
 
 
 
 
Released under FOI in full on 16th July 2009 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 16th July 2009 
SCHEDULE Q, PART A 
CONTRACTOR’S SOLUTION 
Schedule Q, Part A (Contractor’s Solution) 
 
Signature Version 
CCN001 
 
18 July 2005 
 
 
 
 
Released under FOI in full on 16th July 2009 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 16th July 2009 
CONTENTS 
 
 

INTRODUCTION....................................................................................................................1 

MANAGEMENT METHODS ................................................................................................1 

SERVICE DELIVERY ............................................................................................................9 

OPERATIONAL ENVIRONMENT ....................................................................................16 

LOCATION OF OPERATIONAL DATA...........................................................................18 

TRAINING .............................................................................................................................19 

DEVELOPMENT...................................................................................................................23 

TEST AND ACCEPTANCE APPROACH..........................................................................27 

CAPACITY MANAGEMENT..............................................................................................30 
10 
SECURITY .............................................................................................................................31 
11 
FUTURE VISION ..................................................................................................................33 
 
Schedule Q, Part A (Contractor’s Solution) 

Signature Version 
CCN001 
 
18 July 2005 
 
Released under FOI in full on 16th July 2009 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 16th July 2009 

INTRODUCTION 
For  the  avoidance  of  doubt,  should  any  conflict  occur  between  Schedule  Q,  Part  A  (Contractor’s 
Solution) and any other Contract Schedule then that other Contract Schedule shall take precedence. 

MANAGEMENT METHODS 
2.1 
Project Management 
2.1.1  Northrop Grumman shall be the Prime Contractor and systems integrator to meet the 
full  range  of  IDENT1  requirements  as  specified  in  Schedule  D  (Detailed 
Operational Requirements). 
2.1.2  The Contractor shall provide complete Contract and Subcontract management for: 
(a) 
Automated Fingerprint Recognition (AFR), including multiple vendors. 
(b) 
Maintenance, spares, logistics, and transportation. 
(c) 
Wide  Area  Network  (WAN)  for  England,  Wales,  and,  where  applicable, 
Scotland. 
(d) 
Livescan for England, Wales, and, where applicable, Scotland. 
2.1.3  The  Contractor’s  team  shall  include,  at  Contract  commencement,  the  following 
subcontractors who shall be known as Material Subcontractors: 
SUBCONTRACTOR 
PRIMARY ROLE ON IDENT1 
SAGEM 
AFIS Technology 
Phoenix IT Services 
Hardware Maintenance and Installation 
Energis 
WAN Communications Provider 
Smiths Heimann Biometrics 
Livescan Provider 
2.1.4  Any  changes  to  the  above-listed  Material  Subcontractors  are  subject  to  the  prior 
agreement  of  the  Authority,  as  set  out  in  Schedule  B  (Conditions  of  Contract), 
which consent shall not unreasonably be withheld.   
2.1.5  In  order  to  minimise  programme  transition  and  delivery  risk,  the  Contractor’s  team 
shall include key management staff who have had direct experience with the current 
National  Automated  Fingerprint  Identification  System  (NAFIS)  Services  design, 
development, and operations and relevant programme experience with the Authority 
and IDENT1 Services users. 
2.1.6  The Contractor shall participate in monthly Programme Status Reviews (PSRs) (see 
Schedule O:12 (Documentation) and Schedule I (Contract Management)) with the 
Authority. PSRs shall be conducted at Authority locations in the UK, unless mutually 
agreed  upon  otherwise.  The  Contractor  shall  ensure  that  the  above-listed  Material 
Subcontractors  shall  also  be  available  to  attend  such  reviews  when  required  by  the 
Authority. 
2.1.7  The  Contractor  shall  develop  an  IDENT1  service  plan  (as  part  of  Schedule  O:58 
(Documentation))  that  meets  the  IDENT1  Services  programme  needs  and  is  based 
Schedule Q, Part A (Contractor’s Solution) 

Signature Version 
CCN001 
 
18 July 2005 
 
Released under FOI in full on 16th July 2009 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 16th July 2009 
on  an  evolution  of  the  current  NAFIS  Services.  This  plan  shall  address  methods  to 
avoid disruption to ongoing service delivery and minimise impact on users. 
2.1.8  The  Contractor  shall  manage  the  entire  IDENT1  Service  in  accordance  with 
Contractor  policies  that  are  comparable  to  PRINCE2  methodology,  including 
exception management and reporting. 
2.1.9  The Contractor shall conduct quarterly internally independent project reviews by the 
Contractor’s  Project  Review  Authority  (PRA)  of  the  technical,  schedule,  and  cost 
performance  of  the  programme.  A  summary  of  the  outcome  of  any  PRA  shall  be 
included  for  discussion,  where  appropriate,  at  the  next  PSR  or  more  urgently  as 
required. 
2.1.10  The Contractor shall conduct monthly status reviews with its Material Subcontractors. 
2.1.11  The Contractor shall employ a range of its internally approved management tools to 
assist  programme  managers  in  the  management  of  the  IDENT1  Services.  At  a 
minimum,  the  Contractor  shall  use  a  requirements  management  tool  (DOORS  or 
equivalent) approved by the Authority and a configuration database tool (Accurev or 
equivalent). 
2.1.12  The  Contractor  shall  manage  the  delivery  of  requirements  and  will  provide  the 
interface  to  the  Authority  through  which  these  will  be  shared  (See  Schedule  O:33 
(Documentation)).  The  Authority  will  hold  the  master  copy  of  the  requirements 
baseline. 
2.1.13  The  Contractor  shall  implement  a  Risk  Management  Board  (RMB),  chaired  by  the 
Contractor’s  Systems  Engineering  Manager.  This  board  shall  be  responsible  for 
identification  of  risks;  assessment  of  risk;  and  planning,  selecting,  and  monitoring 
mitigation  approaches.  Outputs  from  the  RMB  shall  be  presented  at  the  PSRs  held 
monthly with the Authority, including full details of high-category risks. 
2.2 
Project Organisation 
2.2.1  In order to mimimise programme transition and delivery risk, the Contractor’s team 
shall  include  key  management  staff  who  have  direct  experience  with  the  current 
NAFIS design, development, and operations and relevant programme experience with 
the Authority and IDENT1 users. 
2.2.2  The following positions (“Key Contractor Positions”) shall be staffed by Contractor 
staff (“Key Contractor Personnel”) who shall not be substituted except in accordance 
with the provisions of Clause 6 of Schedule M (HR and TUPE). 
Key Contractor Positions 
Key Contractor Personnel 
Programme Director 
Rod Forry 
Deputy Programme Manager 
Richard Ginnett 
Chief Engineer/System Architect 
Phil Pedersen 
Systems Engineering Manager 
James Ling 
Development Manager 
Gerald Munizza 
Service Delivery Manager 
Mark Woodhouse 
Quality Assurance Manager 
Mark Keiffer 
Transition Manager 
Richard Ginnett (acting) 
User Advocate 
William Taylor 
Contracts Manager 
Karen Hatcher 
 
 
Schedule Q, Part A (Contractor’s Solution) 

Signature Version 
CCN001 
 
18 July 2005 
 
Released under FOI in full on 16th July 2009 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 16th July 2009 
2.2.3  The  Contractor’s  Programme  Director  shall  have  overall  responsibility  for  and 
authorisation  to  direct  resources  for  the  successful  management  and  delivery  of 
IDENT1 Services to the Authority. 
2.2.4  The Contractor shall, in coordination with the Authority, define interfaces and points 
of contact between Contractor’s staff and the Authority’s staff. 
2.2.5  The  Contractor  shall  ensure  that  roles  and  responsibilities  are  established  and 
maintained  for  all  Key  Contractor  Positions.  The  roles  and  responsibilities  shall 
include the escalation path and escalation procedures for all key positions. 
2.2.6  In order to assist in the management and delivery of IDENT1 Service in accordance 
with  the  Contract  requirements,  the  Contractor  will  implement  the  following 
measures:  
(a) 
The  Contractor  shall  have  a  dedicated  Implementation  Manager  for  the 
Transition activity in Scotland. 
(b) 
The  Contractor’s  project  organisation  shall  include  a  project  support 
functional area that provides contract management, subcontract management, 
and business and finance management. 
(c) 
The  Contractor  shall  have  a  configuration  management  activity  for  the 
control  and  management  of  all  IDENT1  Services  project-related  hardware, 
software, and project deliverables. 
(d) 
The Contractor’s project organisation shall include a Chief Engineer/System 
Architect  to  review  and  oversee  requirements  and  interface  definition, 
performance  and  capacity  modelling,  security,  logistics,  reliability, 
maintainability, availability analyses, and human factors analysis. 
(e) 
The Contractor’s project organisation shall include a development functional 
area  to  provide  system  development,  application  development,  integration 
and  test,  and  systems  support.  The  Contractor’s  development  organisation 
shall include co-located SAGEM technical staff at least until FOC. 
(f) 
The  Contractor’s  project  organisation  shall  include  a  Systems  Engineering 
functional area to provide requirements and interface definition; performance 
and  capacity  modelling;  security;  logistics;  reliability;  maintainability; 
availability  analyses; and  human  factors  analysis. The  Contractor’s  Systems 
Engineering functional area shall include a System Security Officer. 
(g) 
The  Contractor’s  project  organisation  shall  include  a  business  process 
engineering  capability.  The  Contractor’s  business  engineering  shall  provide 
initial  use  case  development  for  potential  new  functionality  within  IDENT1 
Services.  The  Contractor’s  business  process  engineering  activities  shall  be 
coordinated  with  the  Authority.  The  results  of  these  analyses  and 
developments  shall  be  provided  to  the  Authority  for  consideration  of 
implementation  under  formal  change  procedures  in  accordance  with 
Schedule L (Change Control Procedure). 
(h) 
The  Contractor’s  project  organisation  shall  include  a  Service  Management 
function  to  provide  daily  operations  to  IDENT1  Services,  including  service 
desk,  user  support,  and  installation  and  maintenance  support.  The 
Contractor’s  Service  Management  function  shall  include  regionally  based 
Schedule Q, Part A (Contractor’s Solution) 

Signature Version 
CCN001 
 
18 July 2005 
 
Released under FOI in full on 16th July 2009 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 16th July 2009 
user  support  staff  to  provide  onsite  assistance  to  the  user  community, 
including training, deployment planning, and technical assistance. 
(i) 
The  Contractor  shall  establish  a  senior  technology  review  board  to  provide 
technical  vision  in  the  areas  of  criminal  justice,  homeland  security, 
identification,  biometrics,  display  concepts,  and  security.  The  Contractor 
shall  provide  results  of  the  findings  and  recommendations  to  the  Authority. 
The  Authority  shall  also  be  invited  to  a  Contractor-hosted  annual 
identification technology forum. 
(j) 
The Authority shall be established as a full member of relevant Contractor or 
subcontractor  technology  user  groups,  including  but  not  limited  to  the 
SAGEM User Group. 
(k) 
The Authority’s membership in the technology user groups described above 
shall be at no charge to the Authority, except that the Authority shall bear the 
costs  for  all  associated  travel,  accommodations,  subsistence,  and 
out-of-pocket  expenses  incurred  by  it  or  its  representatives  should  they 
attend. 
2.3 
Planning and Reporting 
2.3.1  The  following  planning  and  reporting  shall  be  carried  out  by  the  Contractor,  the 
methods  and  means  utilised  to  achieve  this  shall  be  as  specified  in  Schedule  D 
(Detailed Operational Requirements). 
2.3.2  The  IMS  shall  divide  the  IDENT1  Service  deliverables  into  projects  that  shall  be 
further  subdivided  into  stages  for  development  and  implementation.  Stage  planning 
and reporting shall address exception planning, as appropriate. 
2.3.3  The  Contractor  shall  review  each  project  with  the  Authority  to  obtain  Authority 
approval  of  the  approach, method  of  delivery,  and  acceptance  criteria  as  detailed  in 
the Contract. 
2.3.4  In each project/stage plan, the Contractor shall include activity for regression testing 
and validation of requirements under controlled conditions. 
2.3.5  The  Contractor  shall  provide  information  on  individual  projects  as  well  as  overall 
programme status. Project status shall include identification of issues and risks. This 
information shall be provided in a PRINCE2-compliant format. 
2.3.6  The  Contractor  shall  develop  a  Risk  Management  Plan  in  accordance  with 
Schedule O:14 (Documentation). 
2.3.7  The  Contractor  shall  develop  a  Risk  Mitigation  Plan  for  risks  defined  in  the  Risk 
Management Plan. 
2.3.8  The Contractor shall conduct formal customer milestone reviews for each project. 
2.3.9  The  Contractor  shall  provide  a  list  of  product  descriptions  agreed  upon  as 
deliverables  in  the  next  Stage  Plan  in  accordance  with  Schedule O:18 
(Documentation). 
2.3.10  The  Contractor  shall  provide  a  Product  Checklist  as  defined  in  the  PRINCE2 
methodology. 
Schedule Q, Part A (Contractor’s Solution) 

Signature Version 
CCN001 
 
18 July 2005 
 
Released under FOI in full on 16th July 2009 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 16th July 2009 
2.3.11  The  Contractor  shall  work  with  the  Authority  to  identify  planning  and  reporting 
methods  to reduce  costs  or  improve  schedules to the mutual  benefit  of  both  parties.  
Changes  shall  be  agreed  upon through the  Programme  Configuration  Control  Board 
(PCCB) as described in Schedule L (Change Control Procedure). 
2.4 
Communication 
2.4.1  The  Contractor  shall  present  as  part  of  the  Programme  Initiation  Review  a 
communication strategy  which covers the following: 
(a) 
Geographic dispersion of users. 
(b) 
The variety of user roles and responsibilities. 
(c) 
The differing business processes. 
(d) 
Variations in training requirements. 
(e) 
Implementation schedules that extend over calendar and fiscal years. 
(f) 
Stakeholders from integrated external interfaces. 
2.4.2  The Contractor shall provide the Authority with a Communication Plan in accordance 
with Schedule O:15 (Documentation). 
2.4.3  The  Contractor  shall  support  and  coordinate  the  execution  of  the  Communication 
Plan with the Authority on a quarterly basis. 
2.4.4  The Contractor’s Communication Plan shall include the following items. The means 
of  delivery  and  content  of  the  items  shall,  except  where  otherwise  required  by  the 
Contract,  be  determined  by  the  Contractor  working  closely  with  the  Authority  and, 
where appropriate, with Authority approval: 
(a) 
User  Advocate.  The  Contractor  shall  provide  a  User  Advocate  to  provide 
senior  policing  experience  relating  to  the  identification  and  criminal  justice 
community.  The  User  Advocate  shall  actively  solicit  user  feedback  on  the 
needs and performance of the IDENT1 Service. The User Advocate shall not 
conduct  direct  marketing  or  sales  activities,  without  prior  approval  and 
coordination with the Authority. 
(b) 
Conferences.  The  Contractor  shall  attend  national  and  international 
conferences  relating  to  IDENT1.  The  Contractor  shall  be  a  sponsor  of  the 
National Fingerprint Conference. 
(c) 
Newsletters.  The  Contractor  shall  produce  and  disseminate  a  semi-annual 
user newsletter, similar to the legacy Ridgeway News. 
(d) 
Status Reports. The Contractor shall produce and disseminate status reports, 
usually  weekly,  but  as  frequently  as  necessary  to  keep  users  informed  of 
system status and operational activities. 
(e) 
Web  Portal.  The  Contractor  shall  develop  and  maintain  an  IDENT1  web 
portal to  provide  authorised  access to  documentation,  training  materials  and 
management data. 
Schedule Q, Part A (Contractor’s Solution) 

Signature Version 
CCN001 
 
18 July 2005 
 
Released under FOI in full on 16th July 2009 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 16th July 2009 
(f) 
Management Reviews. The Contractor shall hold regularly scheduled internal 
management  reviews  in  accordance  with  company  policies  and  monthly 
PSRs  with the Authority. 
(g) 
User  Groups.  The  Contractor  shall  provide  suitable  staff  to  attend  the 
following user groups, including but not limited to: 
(i) 
IDENT1 User Group 
(ii) 
Livescan Electronic Identification Unit (EIU) User Group 
(iii) 
Training User Group 
(iv) 
ACPO Regional User Meetings 
(h) 
User  Information  Days.  The  Contractor  shall  conduct  briefings  for  users  at 
the  Contractor’s  UK  facilities  for  transition  and  rollout  plans  for  new 
functionality. 
2.4.5  The Contractor shall provide web portal access to the Authority to relevant IDENT1 
Management  Information  System  (MIS)  data.  The  data  shall  be  displayed  using 
Business  Objects,  or  equivalent  COTS  business  intelligence  tools.  The  Contractor 
shall deliver, install, and support a workstation at the Authority’s premises for access 
to the MIS data. 
2.4.6  The Contractor shall provide training to Authority users on the business intelligence 
tool(s) and will provide onsite assistance for the first month after installation. 
2.5 
Controls 
2.5.1  The  Contractor  shall  prepare  a  Programme  Initiation  Review  Documentation  as 
described in Schedule O:9 (Documentation). 
2.5.2  The  Contractor  shall  employ  its  own  company  standard  tools  and  processes  for 
monitoring, tracking, and controlling the implementation of IDENT1 Services. 
2.5.3  The  Contractor  shall  develop,  deliver,  and  maintain  an  Integrated  Master  Schedule 
(IMS)  that  identifies  all  major  projects  and  their  associated  stages.  The  Contractor 
shall report progress and tolerance conditions against the IMS. The Contractor shall 
use the Earned Value System as an integral aspect of its project control process and 
provide  exception  visibility  to  the  Authority  as  agreed  (see  Schedule  O:11 
(Documentation)). 
2.5.4  The Contractor shall provide an exception plan to the Authority within a week of an 
exception being identified. 
2.5.5  The  Contractor  shall  not  proceed  to  the  next  stage  (see  Schedule  O:18 
(Documentation))  without  approval  from  the  Authority.  Where  approval  is  not 
granted,  the  Authority  shall  provide  written  notice  of  such  rejection  together  with 
detailed  reasons  therefore  within  ten  days  (or  as  otherwise  specified  in  Schedule  H 
(Acceptance Procedures)). 
2.5.6  The Contractor shall monitor and track task status on a weekly basis. 
Schedule Q, Part A (Contractor’s Solution) 

Signature Version 
CCN001 
 
18 July 2005 
 
Released under FOI in full on 16th July 2009 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 16th July 2009 
2.5.7  The Contractor shall support, as reasonably required, IDENT1 Project Boards. Senior 
contractor  representation  shall  be  provided  at  the  Project  Board,  as  required  by  the 
Authority  as set out in Schedule I (Contract Management). 
2.6 
Quality 
2.6.1  The  Contractor’s  project  QA  organisation  shall  have  an  independent  reporting 
channel to the Contractor’s business unit. 
2.6.2  The Quality Management System (QMS) used in the delivery of the IDENT1 Service 
shall  be  based  on  company  standards  that  are  compliant  with  ISO: 9001  and 
Capability  Maturity  Model  Integration  (CMMI)  and  updated  as  described  in 
Schedule O:10 (Documentation). 
2.6.3  The QMS shall define standards, methods, and processes that apply to the IDENT1 
Service  and  provide  procedures  for  maintaining  compliance  for  the  duration  of  the 
Contract. 
2.6.4  The  QMS  shall  comprise  the  following  components:  quality  planning,  quality 
training,  Quality  Control  (QC),  Corrective  and  Preventive  Action  System  (CPAS), 
quality reviews, and quality system performance and improvement. 
2.6.5  A  Quality  Plan  for  the  programme  shall  be  developed  in  accordance  with 
Schedule O:10 (Documentation). 
2.6.6  The Quality Plan shall be required to be approved by the Authority and maintained 
for the term of the contract. 
2.6.7  The  development  plans  for  stages/projects  shall  describe  quality  requirements  and 
activities specific to stages/projects. 
2.6.8  The  Contractor  shall  implement  QC  through  scheduled  evaluations  and  audits  of 
process, product, and service delivery as specified in the Quality Plan as follows: 
(a) 
The results of evaluations and audits shall be documented and all results shall 
be available for Authority review. 
(b) 
Nonconformities shall be subject to corrective action. 
2.6.9  A CPAS shall be established and used to manage actions logged in response to QC 
findings. 
2.6.10  The  Contractor  shall  conduct  formal  quality  reviews  whenever  a  significant  change 
occurs throughout the term of the contract  to include the service delivery phase. 
2.6.11  The Contractor shall monitor and measure QMS performance against quality metrics 
as defined in the Quality Plan. 
2.6.12  The Contractor shall report on QMS performance status as requested. 
2.6.13  Based  on  the  results  of  QMS  performance  assessments,  the  Contractor  shall  where 
reasonable to do so identify opportunities for QMS improvement. 
2.6.14  The  Contractor  shall  use  structured  methodologies  of  its  choice  for  process 
improvement activities that management approves for implementation. 
Schedule Q, Part A (Contractor’s Solution) 

Signature Version 
CCN001 
 
18 July 2005 
 
Released under FOI in full on 16th July 2009 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 16th July 2009 
2.7 
Change Management 
2.7.1  The Contractor shall employ a formal change management process that is integrated 
with  the  Contractor’s  Configuration  Management  System.    The  Contractor  shall 
propose and agree with the Authority on a configuration management process for the 
IDENT1  Service  and  document  this  in  accordance  with  Schedule O:34 
(Documentation) and subject to Schedule L (Change Control Procedures). 
2.7.2  Formal Contract changes shall be managed in accordance with procedures outlined in 
Schedule L  (Change  Control  Procedures),  which  shall,  where  there  is  a  conflict, 
take precedence over this part of this Schedule. 
2.7.3  The Contractor shall apply change management to all configuration controlled items 
and  baselines.  The  change  control  process  shall  be  applied  to  IDENT1  hardware, 
software, and documents. 
2.7.4  The Contractor shall maintain a Programme Configuration Control Board (PCCB) to 
control  all  system  change  requests.  A  list  of  proposed  changes  will  be  readily 
available to the Authority with detail of any Schedule and/or Quality impacts. 
2.7.5  The  Contractor’s  PCCB  shall  perform  an  assessment  of  each  change  request  to 
evaluate: 
(a) 
Operational impact of the change. 
(b) 
Importance of the change. 
(c) 
Cost, quality, and timescale impact of the change. 
2.7.6  The  Contractor  shall  ensure  that  approved  changes  are  reflected  in  corresponding 
technical and programmatic documentation. 
2.7.7  The Contractor shall apply audit controls to verify that following approved changes, 
the functional requirements are met and the physical content of changes are consistent 
with documentation. 
2.7.8  The  Contractor  shall  maintain  configuration  status  controls  to  ensure  that 
configuration  items  are  maintained  during  all  project  phases  and  that  changes  are 
traceable to applicable products. 
2.7.9  The  Contractor  shall  ensure  that  where  any  changes  adversely  affect  overall 
programme milestones, the IMS shall be updated by the next programme cycle. 
2.7.10  The  Contractor  shall  employ  COTS  tools  in  the  change  management  process.  The 
tools  shall  generate  reports  comparable  to  PRINCE2  reports  to  provide  visibility  of 
current  information  and  to  demonstrate  completeness  of  product  traceability  to  the 
required standard. 
2.8 
Delivery Management 
2.8.1  The Contractor shall act as the design authority and service provider for the IDENT1 
Services, working in the context of the Authority’s overall IT strategies.  
2.8.2  The Contractor shall develop/agree with the Authority a stage plan for each stage of 
the IDENT1 Services in accordance with Schedule O:18 (Documentation). 
Schedule Q, Part A (Contractor’s Solution) 

Signature Version 
CCN001 
 
18 July 2005 
 
Released under FOI in full on 16th July 2009 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 16th July 2009 
2.8.3  The  Contractor  shall  provide  project  documentation  to  other  groups  as  agreed  with 
the Authority for information or review purposes. 

SERVICE DELIVERY 
3.1 
Service Availability and Business Continuity 
3.1.1  Availability 
(a) 
The  Contractor  shall  implement  and  deliver  an  Availability  Management 
process that ensures that the IDENT1 Services meet  the IDENT1 operational 
availability  requirements.  The  Availability  Management  Process  shall  be 
ITIL  compliant.  The  Contractor  shall  be  responsible  for  full  system 
availability,  including  the  WAN  as  set  out  in  Schedule F  (Service  Level 
Requirements).  The  Contractor  shall  be  responsible  for  implementing 
system  and  component  changes  and  enhancements,  as  may  be  required  to 
meet system operational availability goals. 
(b) 
The  Contractor’s  Availability  Management  process  shall  incorporate  key 
elements of the Contractor’s existing design and support structure, including: 
(i) 
Uninterruptible Power Supplies (UPSs) for IDENT1 kit at the Central 
Sites and  Bureaux locations  except where the UPS was provided by 
the bureau. 
(ii) 
Distributed  spares  warehouses  and  supplies  to  reduce  maintenance 
downtimes. 
(iii) 
Onsite  technicians  at  Contractor  determined  locations,  based  on 
availability and response time requirements. 
(iv) 
Multiple  test  beds  to  evaluate  new  products  and  component 
reliability. 
(c) 
The Contractor’s availability management activities shall: 
(i) 
Review  and  analyse  availability  requirements  through  its  systems 
engineering  process.  This  shall  include  the  use  of  availability 
mathematical models, where appropriate. 
(ii) 
Review impacts to business functions arising from availability issues, 
including identifying critical system components. 
(iii) 
Set and review targets for availability, reliability, and maintainability 
of the IDENT1 Services system, including recovery time. 
(iv) 
Monitor and evaluate availability trends. 
(v) 
Investigate underlying reasons associated with availability issues. 
(vi) 
Maintain  and  update  an  Availability  Plan  in  accordance  with 
Schedule O:63  (Documentation)  that  includes  plans  for  availability 
improvements.  This  plan  shall  include  periodic  vendor  assessments 
of current and new products and technologies. 
Schedule Q, Part A (Contractor’s Solution) 

Signature Version 
CCN001 
 
18 July 2005 
 
Released under FOI in full on 16th July 2009 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 16th July 2009 
(d) 
The  Contractor  shall  designate  an  Availability  Manager  who  shall  interface 
with  the  Authority’s  Availability  Manager  for  IDENT1.  The  Contractor’s 
Availability  Manager  shall  report  to  the  Contractor’s  Service  Delivery 
Manager. 
(e) 
The Contractor’s Availability Management process shall be an integral aspect 
of  its  overall  Systems  Engineering  process  to  ensure  that  availability  is 
considered within the IDENT1 life cycle.  
(f) 
The  Contractor’s  availability  Management  process  shall  include  both 
operational data and engineering design assessments. 
(g) 
The Contractor’s Availability Management process shall include mechanisms 
for delivering increased system operational availability, primarily through the 
reduction of planned downtime. 
(h) 
The Contractor’s Availability Management process shall include mechanisms 
for  communicating  lack  of  availability  and  likely  recovery  period  to 
appropriate users. 
3.1.2  Business Continuity 
(a) 
The Contractor shall provide Business Continuity Management as an integral 
aspect of its Systems Engineering process, a key element of which shall be IT 
Service  Continuity  Management.  The  Contractor  shall  implement  Business 
Continuity Management in accordance with ITIL procedures. 
(b) 
The Contractor shall develop, implement, and maintain a Business Continuity 
Plan as described in Schedule O:65 (Documentation). 
(c) 
The  Contractor’s  Business  Continuity  management  shall  be  based  on  the 
existing NAFIS Services business continuity plans and procedures, including 
the  Contractor’s  secondary  site  to  provide  intermediate  and  immediate 
recovery capabilities. 
(d) 
IT  Service  continuity  considerations  shall  be  inherent  in  the  design  of  the 
IDENT1 Services System. 
(e) 
The  Contractor  shall  ensure  that  Business  Continuity  management  includes 
communication  and  coordination  with  the  bureaux  and  addresses  their  local 
business continuity needs and plans. 
(f) 
The  Contractor  shall  coordinate  IDENT1  Services  business  continuity 
planning with integrated external system interface providers. 
(g) 
The  Contractor  shall  conduct  annual  testing  of  the  business  continuity 
procedures,  including  integrated  external  system  interfaces  (see  Schedule 
O:66 (Documentation)). 
3.2 
Service Management 
3.2.1  The  Contractor  shall  have  in  place  ITIL-compliant  service  delivery  systems  and 
procedures for the term of the contract. These shall include but not be limited to: 
(a) 
Service Level Management 
Schedule Q, Part A (Contractor’s Solution) 
10 
Signature Version 
CCN001 
 
18 July 2005 
 
Released under FOI in full on 16th July 2009 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 16th July 2009 
(b) 
Availability Management 
(c) 
Capacity Management 
(d) 
Financial Management for IT Services 
(e) 
IT service continuity management 
3.2.2  The  Contractor  shall  have  in  place  ITIL-compliant  service  support  systems  and 
procedures for the term of the contract. These shall include but not be limited to: 
(a) 
Configuration Management 
(b) 
Change Management 
(c) 
Incident Management 
(d) 
Problem Management 
(e) 
Release Management 
3.2.3  The  Contractor  shall  achieve  BS 15000  or  equivalent  certification  by  its  service 
delivery organisation by FOC, and shall maintain such certification for the duration of 
the Contract (see Schedule O:61 (Documentation)). 
3.2.4  The  Contractor  shall  ensure  that  new  capabilities  are  integrated  into  the  service 
management structure. 
3.2.5  The  Contractor  shall  manage  all  aspects  of  the  delivery  of  IDENT1,  providing 
availability  to  the  users  in  accordance  with  Schedule  F  (Service  Level 
Requirements)  ensuring  minimal  disruption  to  the  users.    The  Contractor  shall 
ensure that staff involved in service delivery and service support have clearly defined 
roles  and  responsibilities,  supported  by  role/job  descriptions  in  accordance  with 
contract requirements. 
3.2.6  The  Contractor  shall  carry  out  regular  reviews  of  performance  and  service 
improvement initiatives. 
3.3 
Service Delivery 
3.3.1  Service Level Management 
Service  provision  shall  be  managed  according  to  Schedule  F  (Service  Level 
Requirements) (which in the event of conflict or inconsistency shall take precedence 
over this Schedule) and will cover the services and service levels to be delivered. The 
Service Level Requirement criteria shall cover: 
(a) 
Search Accuracy 
(b) 
Response Times 
(c) 
Throughput 
(d) 
Availability 
(e) 
Support 
Schedule Q, Part A (Contractor’s Solution) 
11 
Signature Version 
CCN001 
 
18 July 2005 
 
Released under FOI in full on 16th July 2009 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 16th July 2009 
(f) 
Other Service Quality Measures (to be agreed upon) 
3.3.2  Measurement of overall performance shall include a measure of the effectiveness of 
the  IDENT1  Service  (e.g.,  the  number  of  identifications  and  the  timeliness  with 
which they are made) in accordance with Schedule F (Service Level Requirements). 
3.3.3  The Contractor shall provide the Authority with a monthly service report. 
3.3.4  The  SLR  report  shall  be  sufficiently  detailed  to  demonstrate  that  the  SLR 
requirements are being met and/or to report any exceptions. 
3.3.5  The Contractor shall work with the Service Control Board to consider: 
(a) 
Changes in working practices. 
(b) 
The continued validity of measures. 
(c) 
Improvement initiatives. 
3.3.6  The Contractor shall develop and manage its own SLR’s with its Subcontractors. 
3.3.7  The  Contractor shall  develop  SLR’s  with  any  third  party  provider  of interfaces and 
shall  seek  Authority  approval  for  associated  SLR’s  (see  Schedule  O:62 
(Documentation)). 
3.4 
Financial Management for IT Services 
3.4.1  The  Contractor  shall  have  full  financial  responsibility  for  delivery  of  IDENT1 
Service. 
3.5 
Service Support 
The  Contractor  shall  document  their  service  support  processes  in  the  Operations  and 
Maintenance Support Plan (see Schedule O:58 (Documentation)). 
3.5.1  Incident Management 
(a) 
All  incidents  reported  to  the  service  desk  shall  be  logged  on  the  service 
management support tool and an incident report created. 
(b) 
All incidents shall be categorised and prioritised in accordance with Schedule 
F (Service Level Requirements). 
(c) 
Calls shall be assessed and assigned to the appropriate member of the support 
team. 
(d) 
Wherever incidents cannot be resolved by staff on the service desk, they will 
be  escalated  to  second-  or  third-level  support  or  assigned  to  a  third-party 
subcontractor. 
(e) 
Procedures  shall  support  the  escalation  of  incidents,  either  technically  or 
hierarchically. 
(f) 
A Work Log shall be maintained for each incident. All entries shall be time 
stamped and the identity of the individual making the entry shall be logged. 
Schedule Q, Part A (Contractor’s Solution) 
12 
Signature Version 
CCN001 
 
18 July 2005 
 
Released under FOI in full on 16th July 2009 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 16th July 2009 
(g) 
The Work Log shall contain details of, for example: 
(i) 
Investigative work undertaken. 
(ii) 
Remedial action carried out. 
(iii) 
Time taken to resolve the incident. 
(iv) 
Interactions with the user. 
(v) 
Association with a known problem if appropriate. 
(h) 
The service desk shall provide users with updates on the status of incidents. 
(i) 
Incidents shall only be closed after satisfactory resolution of the incident has 
been confirmed with the user who reported the incident. 
(j) 
The  service  desk  team  leader  shall  monitor  progress  on  incidents  and 
maintain  ownership  of  the  incident  through  closure,  to  ensure  that  SLR 
response times are met. 
(k) 
Procedures  for  incident  resolution  and  any  workarounds  in  place  shall  be 
contained  in  the  Operations  and  Manintenance  Support  Plan  (see  Schedule 
O.58 (Documentation)). 
(l) 
The  Contractor  shall  define  the  process  for  reporting  and  managing  major 
incidents.    This  process  shall  be  documented  in  the  Operations  and 
Maintenance Support Plan (see Schedule O.58 (Documentation)). 
3.5.2  Problem Management 
(a) 
Problem management procedures shall be in place to detect underlying causes 
of an incident or incidents and to identify a path for resolution or prevention. 
(b) 
Problem management shall be both proactive and reactive. 
(c) 
Problems shall be logged in an Issues log, which shall contain details of, for 
example: 
(i) 
Incident counts against the problem. 
(ii) 
Workarounds in place. 
(iii) 
Status of work on problem resolution. 
(d) 
Following  implementation  of  remedial  action,  the  success  of  the 
implementation  shall  be  measured  and  reviewed  at  the  monthly  contract 
review. 
(e) 
The  Contractor  shall  maintain  an  operations  issue  log,  which  contains  a 
record of known system conditions which impact operations.  
3.5.3  Release Management 
(a) 
All  new  components  introduced  into  the  IDENT1  environment  shall  be 
subject to Release Management controls. 
Schedule Q, Part A (Contractor’s Solution) 
13 
Signature Version 
CCN001 
 
18 July 2005 
 
Released under FOI in full on 16th July 2009 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 16th July 2009 
(b) 
All releases shall be planned to minimise the impact on the user community. 
(c) 
Details  of  the  contents  of  each  release  shall  be  maintained  on  the 
Configuration Management database. 
(d) 
Each release shall be uniquely identified. 
(e) 
Each release shall be built according to the documented build process. 
(f) 
Each release shall undergo testing prior to acceptance (as set out in Schedule 
H (Acceptance Procedures)). This testing shall include: 
(i) 
Functional Testing 
(ii) 
Backward Compatibility 
(iii) 
Regression Testing 
(iv) 
SCR Thread Testing 
(v) 
Interfaces 
(vi) 
System Administration 
(g) 
Backout plans shall be in place for each release. 
(h) 
An  ORR  shall  be  held  for  each  release  to  ensure  that  the  following  are  in 
place: 
(i) 
Deployment Schedule 
(ii) 
Estimated Duration of Deployment 
(iii) 
Estimate of Downtime 
(iv) 
Resources 
(v) 
Documentation 
(vi) 
Operational Procedures 
(vii) 
Details of Testing Carried Out 
(viii)  User Training 
(ix) 
Operational Checkout Complete 
(x) 
Release Notes 
(xi) 
Backout Plans 
(i) 
Progress and status of release deployment shall be tracked via a work ticket 
on the service management support tool. 
3.5.4  Service Desk 
Schedule Q, Part A (Contractor’s Solution) 
14 
Signature Version 
CCN001 
 
18 July 2005 
 
Released under FOI in full on 16th July 2009 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 16th July 2009 
(a) 
The  Contractor  shall  provide  a  24x7  service  desk,  which  shall  provide 
first-line incident support, day-to-day contact with users, help with using the 
service, and management information. 
(b) 
Automated maintenance and support systems shall be in place for the service 
desk. 
(c) 
The  IDENT1  service  desk  shall  be  contactable  by  phone,  fax,  the  IDENT1 
user  interface,  and  the  service  management  support  tool.  Remote  access  to 
the IDENT1 Services system shall conform to CESG guidelines. 
(d) 
The  service  desk  shall  provide  regular  updates  to  users  on  the  status  of 
current  incidents.  The  Contractor  shall  have  in  place  escalation  procedures, 
allowing for calls to be passed to third-level and/or subcontractor support in a 
timely fashion, to ensure that incidents are handled effectively. 
(e) 
The majority of support shall be provided from within the UK; however, the 
Contractor  shall  obtain  Authority  approval  for  any  support  required  from 
outside  the  UK.  The  Contractor  shall  provide  an  alternate  location  for  the 
service  desk  in  the  event  of  any  downtime  that  may  result  in  its  being 
unavailable for more than four hours. 
3.5.5  MIS Reporting 
(a) 
The  Contractor  shall  provide  comprehensive  MIS  capabilities  to  the 
Authority  to include  measurement  of the  performance  of  the  system  against 
the SLR as set out in Schedule F (Service Level Requirements). 
(b) 
The Contractor shall store audit data for at least two years online and up to 10 
years of data in archive. 
(c) 
The  Contractor  shall  run  acceptance  tests  with  the  Authority  to  ensure  the 
validity of this data as set out in Schedule H (Acceptance Procedures). 
(d) 
The Contractor will provide the Authority with access to all MIS data on the 
service being delivered. 
(e) 
The  Contractor  will  provide  the  Authority  with  its  own  workstation  for  the 
purposes of accessing MIS data. 
(f) 
Users with appropriate access privileges shall be able to access MIS data. 
(g) 
The  level  of  data  that  users  can  access  will  be  controlled  by  their  access 
privileges. 
(h) 
The  Contractor  will  pilot  an  initial  set  of  reports  with  the  Authority  and 
develop  more  comprehensive  sets  based  on  operational  experience  in 
accordance with the Contract. 
3.5.6  Operations and Maintenance (O&M) 
(a) 
The  Contractor  shall  be  responsible  for  the  maintenance  and  support, 
including  technology  refreshes,  of  IDENT1  equipment,  software,  licences, 
infrastructure,  and  interfaces  provided  under  this  Contract  to  ensure 
compliance  with  the  Service  Levels  set  out  in  Schedule  F  (Service  Level 
Schedule Q, Part A (Contractor’s Solution) 
15 
Signature Version 
CCN001 
 
18 July 2005 
 
Released under FOI in full on 16th July 2009 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 16th July 2009 
Requirements).  The  following  shall  be  carried  out  on  a  reasonable  and  as 
required basis in order to achieve this objective: 
(i) 
The  Contractor  shall,  wherever  possible,  avoid  conflict  between 
maintenance/release activities and Police Force events/initiatives. 
(ii) 
The  Contractor  shall  comply  with  Health  and  Safety  and  other 
appropriate legislation. 
(iii) 
The Contractor shall review technological advancements and changes 
in 
standards 
and 
dependencies 
and 
make 
appropriate 
recommendations for change. 
(iv) 
The Contractor shall provide a user support team, distributed across 
the  country,  to  provide  additional  onsite  support  to  the  user 
community  for  the  purposes  of  training;  installation  management, 
onsite support to the operations team, and general user liaison. 
(v) 
The  Contractor  shall  provide  field  support  for  installation  and 
maintenance.  This  shall  consist  of  centrally  and  regionally  based 
staff. 
(vi) 
Onsite  maintenance  resources  shall  be  provided  at  Contractor 
selected operational sites. 
(vii) 
The Contractor shall at its discretion and on a reasonable basis have 
in place remote spares holdings. 
(viii)  The  Contractor  shall  ensure  that  day-to-day  consumables,  not 
provided  under  the  Service  are,  wherever possible, readily  available 
from a variety of commercial outlets. 
(ix) 
The  Contractor  shall  provide  consumables  of  limited  availability  or 
high value.  

OPERATIONAL ENVIRONMENT 
4.1 
Fingerprint Bureaux 
4.1.1  The  Contractor  shall  provide  all  IDENT1  equipment  and  accommodation 
modifications for the Bureaux of England, Wales  and Scotland. The equipment shall 
include  servers,  workstations,  monitors,  peripherals,  printers,  scanners,  local  area 
networks, wide area network connections, desks, chairs, desk lighting, and UPSs for 
supplied  equipment.  The  Contractor  shall  minimise  the  impact  to  the 
accommodations at Bureaux of England, Wales  and Scotland. 
4.1.2  The  Contractor  shall  transition  the  existing  Bureaux  systems  within  the  existing 
accommodations  for  space,  weight,  and  power.  The  transition  for  the  SAFR  system 
shall  be  accomplished  to  the  extent  reasonably  possible  with  the  minimum 
interruption  of  operations  during  the  transition.  The  Contractor  shall  provide 
temporary facilities for the transition of SAFR should it be necessary. 
4.1.3  The  Contractor  shall  agree  with  the  Authority  upon  the  specific  configuration  for 
workstation peripherals, for example, optical or magnetic tape and disk drives, prior 
Schedule Q, Part A (Contractor’s Solution) 
16 
Signature Version 
CCN001 
 
18 July 2005 
 
Released under FOI in full on 16th July 2009 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 16th July 2009 
to  installation  at  a  Bureau.  The  rollout  schedule  for  the  workstations  (quantity  and 
timing) at the Bureau shall be agreed upon with the Authority and the Bureau. 
4.1.4  The  Contractor  shall  conduct  site  surveys  for  each  IDENT1  Bureau  in  England, 
Wales and Scotland and define the specific accommodations needed at each Bureau. 
The  Contractor  shall  document  the  results  of  the  site  survey  in  a  Memorandum  of 
Understanding  (MOU)  that  documents  the  roles,  responsibilities,  and  time  lines  for 
any planned site activity. The MOU shall be agreed upon with the Authority and the 
bureau (as set out in Schedule O:19 (Documentation)). 
4.2 
Custody Suites 
4.2.1  The Contractor shall use reasonable efforts to support the Authority’s efforts to obtain 
device approval for IDENT1 Livescan/EIUs in Scotland. 
4.2.2  Accommodation  planning  shall  be  supported  by  a  site  survey,  MOU,  and  project 
planning meetings. These activities shall ensure that any works to be carried out, and 
responsibility for those works, are clearly defined. 
4.2.3  Plans for accommodation and site preparation shall be approved by individual forces 
and by the Authority. 
4.2.4  The  Contractor  shall  provide  the  Authority  with  documentation  associated  with 
accommodation planning. 
4.2.5  Relocation of existing equipment in custody stations shall not be required. 
4.2.6  The Contractor shall ensure that all equipment installed in Custody Suites: 
(a) 
Shall not interfere with other equipment in the environment. 
(b) 
Shall not pose a health and safety risk to staff in the suite. 
(c) 
Shall not require a specialist environment. 
4.3 
Other Accommodation and Equipment 
4.3.1  The  Contractor  shall  obtain  the  Authority’s  approval  of  the  location  of  all 
accommodation  for  the  IDENT1  Services.  All  accommodation  provided  by  the 
Contractor  for  the  provision  of  the  IDENT1  Services  shall  be  physically  secure  in 
accordance  with  the  security  requirements  in  this  Schedule  Q  and  Schedule  K 
(Security). 
4.3.2  The  Contractor  shall  provide  the  Authority  with  access  to  its  IDENT1  facilities,  by 
arrangement. 
4.3.3  The Contractor shall ensure that the electrical supplies for centrally supplied service 
shall be supported by UPS and generator power supplies. 
4.3.4  The Contractor shall ensure that equipment installed on its premises shall require no 
special  environmental  controls  or  building  modifications,  other  than  those  normally 
expected for a data room. 
4.3.5  Bureau  equipment  and  any  equipment  on  the  Authority’s  premises  provided  by  the 
Contractor for the provision of the IDENT1 Service shall be designed for operating in 
a normal office environment. 
Schedule Q, Part A (Contractor’s Solution) 
17 
Signature Version 
CCN001 
 
18 July 2005 
 
Released under FOI in full on 16th July 2009 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 16th July 2009 
4.3.6  The  Contractor  shall  provide  Primary  site  and  Secondary  site  facilities  for  the 
IDENT1  Service.  The  facilities  at  the  Primary  and  Secondary  sites  shall  be 
collectively referred to as the Central Facilities. 
4.3.7  The  Contractor  shall  provide  a  workstation  at  New  Kings  Beam  House  and  at  the 
Hendon Data Centre (HDC) for use by the Authority’s personnel or designated other 
parties. 
4.3.8  The  Contractor  shall  provide  a  Bureau  system  (including  a  Livescan/EIU)  at  the 
Primary  site.  This  Bureau  system  shall  be  used  for  the  purposes  of  testing, 
demonstration and have the potential for use as a training system if required. 
4.3.9  The  Contractor  shall  provide  a  suite  of  equipment  at  the  Secondary  site  facility  for 
use as a demonstration and training facility. It shall also be used for the presentation 
of new functionality during user Information days. 
4.3.10  The  Contractor  shall  maintain  a  test  and  development  environment  in  its  Fairfax 
Facility in the USA. 

LOCATION OF OPERATIONAL DATA 
5.1.1  The  Contractor  shall  provide  data  management  functionality  that  focuses  on 
availability, reliability, and consistency. 
5.1.2  The Contractor shall maintain redundant copies of the Unified Collection and related 
data to ensure reliability. 
5.1.3  The  Contractor  shall  perform  the  following  activities  as  an  integral  aspect  of  its 
operational activities in the UK: 
(a) 
Archiving 
(b) 
Backups 
(c) 
Integrity checks 
(d) 
Cleansing 
5.1.4  Unless otherwise agreed with the Authority, the Contractor shall use non-operational 
data for all IDENT1 testing performed within its test and acceptance facilities.. 
5.1.5  If, under exceptional circumstances, a need arises to use operational data outside the 
operational system, the Contractor shall implement controls to protect the data from 
deliberate or accidental compromise. 
5.1.6  The Contractor’s System Security Officer (SSO) shall coordinate with, and seek the 
approval  of,  the  Authority  before  any  operational  data  are  transmitted  outside  the 
system. 
5.1.7  All operational data and information assets provided to the Contractor by or on behalf 
of  the  Authority  shall,  unless  otherwise  specified,  remain  the  property  of  the 
Authority  or,  where  applicable,  of the  party  providing  that information on  behalf  of 
the Authority. 
5.1.8  The Contractor’s SSO shall ensure that the rightful owner can recover all original or 
derived operational data and information assets. 
Schedule Q, Part A (Contractor’s Solution) 
18 
Signature Version 
CCN001 
 
18 July 2005 
 
Released under FOI in full on 16th July 2009 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 16th July 2009 
5.1.9  The Contractor’s SSO shall develop and ensure compliance with ISO 17799 policies 
for  backup  and  recovery  of  all  operational data  and information  assets,  including  in 
the event of unforeseen disasters. 
5.1.10  The  Contractor’s  SSO  shall  develop  procedures  in  accordance  with  established 
policies for backup and recovery of operational data and information assets. 
5.1.11  The Contractor shall train personnel on the security policies in place for the contract 
as follows: 
(a) 
New  staff  shall  be  required  to  review  programme  security  policies  and 
procedures—including  security  and  the  Security  Operating  Procedures 
(SyOPs)—and  to  sign  a  certification  acknowledging  receipt  and 
understanding of the documentation. 
(b) 
Project personnel shall undergo annual security awareness training to ensure 
continuing compliance with the relevant security policies. 

TRAINING 
6.1 
Training Systems 
6.1.1  The Contractor shall provide and maintain training systems for the NTC for Scientific 
Support  to  Crime  Investigation  in  Durham,  the  Metropolitan  Police  Fingerprint 
Training  School  in  Hendon,  and  the  proposed  NTC  training  site  in  Wyboston, 
Bedfordshire. 
6.1.2  The training systems shall mirror the full functionality of IDENT1 Services and shall 
be updated with all baseline IDENT1 functionality as it is deployed and shall provide 
a safe environment for students to be trained and practice Bureau operations. 
6.1.3  The  training  systems  configuration  shall  include  one  EIU,  as  installed  in  Custody 
Suites, at each of the three locations. 
6.1.4  Each  training  system  shall  have  its  own  discrete  Print  Set  and  Marks  databases, 
together  with  other  databases  as  appropriate  for  the  functionality  provided  under 
IDENT1. 
6.1.5  The configuration of the training systems, including databases, shall be deployed in 
accordance  with  the  procedures  detailed  in  the  Contractor’s  Configuration 
Management Plan (as set out in Schedule O:34 (Documentation)). 
6.1.6  Use  of  the  training  systems  shall  not  impact  the  performance  of  other  Bureau 
operations. 
6.1.7  The  Contractor  shall  provide  training  for  the  trainers  at  the  training  schools  in  the 
functionality of IDENT1. This shall include accreditation and ongoing assessment on 
an annual basis (as set out in Schedule O:27 (Documentation)). 
6.1.8  The  Contractor’s  design  for  the  training  systems,  as  a  business  continuity  measure, 
shall  provide  for  them  to  be  reconfigured  as  an  operational  Bureau  measure.  This 
capability shall be implemented by FOC. 
6.2 
Ongoing Training of Users 
Schedule Q, Part A (Contractor’s Solution) 
19 
Signature Version 
CCN001 
 
18 July 2005 
 
Released under FOI in full on 16th July 2009 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 16th July 2009 
6.2.1  The Contractor shall carry out a comprehensive Training Needs Analysis (TNA), as 
agreed  upon  with  the  Authority,  at  the  commencement  of  the  IDENT1  Services 
programme,  which  will  feed  directly  into  the  Training  Programme  (as  set  out  in 
Schedule O:29 (Documentation)). 
6.2.2  Following completion of the TNA, the Contractor shall produce a Training Plan to be 
agreed upon with the Authority. 
6.2.3  The Training Plan shall be produced as detailed in Schedule O:23 (Documentation). 
The TNA shall be reviewed by the Contractor and the Authority on an annual basis 
throughout the term of the Contract in order to ensure that the appropriate training has 
been identified and is being delivered to users and, further, that the training continues 
to be relevant and appropriate. 
6.2.4  The  Contractor  shall  design  and  develop  training  courses,  in  consultation  with  the 
Authority, for all baseline IDENT1 capabilities. 
6.2.5  The Contractor shall maintain training records for the training courses that they carry 
out.  These  training  records  will  include  the  courses  and  the  specific  personnel 
attending them which shall be available to the Authority if requested. 
6.3 
Transition Training 
6.3.1  The  Contractor  shall  provide  training  to  FPOs  in  England  and  Wales  on  all  new 
capabilities  implemented  within  IDENT1,  where  this  does  not  conflict  with  the 
strategy of the National Training school. 
6.3.2  Training shall be delivered on a “just-in-time” basis as agreed between the Parties. 
6.3.3  The  Contractor  shall  provide  initial  IDENT1  training  to  the  FPOs  of  Scotland.  The 
Contractor shall provide further training on all new IDENT1 capabilities to the FPOs 
of Scotland. 
6.4 
Ongoing Training 
6.4.1  The Contractor shall provide training in new capabilities to Bureau Trainers. 
6.4.2  The  Contractor shall provide  a  catalogue  of  additional training  courses,  which shall 
be optionally available to users and are additional to those already catered for in the 
Contractor’s baseline, that shall include, but not be limited to: 
(a) 
MIS/Audit—Advanced Courses 
(b) 
Advanced Management of Livescan 
(c) 
Livescan—Print Capture Quality 
(d) 
Legacy Livescan/Custody Interface 
(e) 
Generic Mark Camera Interface 
(f) 
Palm Processing 
(g) 
Serious Crime Cache 
(h) 
Operational Response Database 
Schedule Q, Part A (Contractor’s Solution) 
20 
Signature Version 
CCN001 
 
18 July 2005 
 
Released under FOI in full on 16th July 2009 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 16th July 2009 
(i) 
Identification Technology 
6.4.3  The Contractor shall provide reasonable levels of training for the Authority and other 
approved third parties to facilitate the collection of Management Information. 
6.4.4  The  Contractor  shall  provide  reasonable  levels  of  training  to  Bureau  managers  to 
enable them to collect business metrics on Bureau performance. 
6.4.5  The Contractor shall provide training at the following locations: 
(a) 
Contractor facilities at Solihull. 
(b) 
Onsite at Bureaux/within force. 
(c) 
Ad  hoc  locations  as  mutually  agreed  upon  between  the  Contractor  and  the 
Authority. 
6.4.6  The Contractor shall provide any necessary additional equipment to carry out onsite 
training. 
6.4.7  The  Contractor  shall  provide  qualified  trainers  to  carry  out  user/system/support 
training under the Contract. 
6.4.8  The  Contractor’s  trainers  shall  have  a  combination  of  training  and  domain 
experience. The Contractor’s trainers shall have appropriate training qualifications. 
6.4.9  The Contractor will provide a temporary training system for Scotland, at or close to 
Glasgow, which will stay in place until TOR-SAFR. 
6.5 
Computer Based Training (CBT) 
6.5.1  The  Contractor  shall  work  with  the  Authority  to  define  the  most  appropriate  CBT 
solution  (as  detailed  in  Schedule  O:28  (Documentation);  however,  the  Contractor 
shall provide the user with, at a minimum: 
(a) 
Information screens 
(b) 
An overview of processes 
(c) 
Pictures of equipment 
(d) 
Diagrams naming parts of the system 
(e) 
Instructions on how to perform particular tasks 
(f) 
Exercises to perform actions 
(g) 
A review of what the user has done 
(h) 
Feedback on performance 
6.5.2  Development of the CBT shall be undertaken in conjunction with the Authority and 
shall  be  subject  to  the  Test  and  Acceptance  procedures  defined  in  Schedule  H 
(Acceptance Procedures). 
Schedule Q, Part A (Contractor’s Solution) 
21 
Signature Version 
CCN001 
 
18 July 2005 
 
Released under FOI in full on 16th July 2009 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 16th July 2009 
6.5.3  CBT  shall  be  accessible  to  users  from  their  IDENT1  workstations  through  a  web 
interface. 
6.5.4  CBT shall be updated in line with system developments and changes. 
6.6 
Online Help and User Manuals 
6.6.1  Users  shall  be  provided  with  an  online  help  facility  at  their  workstations  for 
assistance on performing normal operational tasks. 
6.6.2  The Contractor will develop, in consultation with the Authority, User Manuals (as set 
out in Schedule O:24 (Documentation)) and an Operations and Maintenance Support 
Plan  (as  set  out  in  Schedule  O:58  (Documentation))  describing  the  use  and 
operational processes of the Services and all aspects of the system. 
6.6.3  All  documentation  and  training  material,  including  those  set  out  in  6.6.2,  shall  be 
available through a web portal. The Authority shall be authorised to freely distribute 
documentation and training materials amongst parties authorised by the Authority. 
6.7 
Training Manuals 
6.7.1  All courses developed by the Contractor shall include user guides and aides-memoirs, 
which  shall  be  made  available  to  students  and/or  to  accredited  force  trainers 
delivering IDENT1 training (see Schedule O:25 (Documentation)). 
6.7.2  The  Contractor  shall  develop,  in  consultation  with  the  Authority,  training 
documentation that shall cover  all  aspects  of  the  system  (see  Schedule  O:23 and  29 
(Documentation)). 
6.7.3  Training  Material  shall  be  updated  to  reflect  changes  to  the  system  (see  Schedule 
O:26 (Documentation)). 
6.7.4  All  training  documentation  shall  reflect  the  differences  in  terminology  among 
Scotland and England and Wales. 
6.7.5  Paper copies of training materials shall be provided in support of training courses run 
by the Contractor (see Schedule O:26 (Documentation)). 
6.7.6  Electronic copies of training documentation shall be made available to the Authority 
and users so that additional copies can be produced locally, as required. 
6.7.7  The Authority shall be provided with the opportunity to review in a timely manner all 
training documentation and course structure before they are released. 
6.8 
Livescan/EIU Training 
6.8.1  The  Contractor  shall  provide  a  training  course  with  each  EIU  that  is  deployed  to  a 
Custody suite. Each training course shall accommodate up to eight students, who will 
then be accredited to provide cascade training to other custody suite staff. 
6.8.2  The  Contractor  shall  provide  training  in  other  EIUs  when  they  are  deployed.    The 
Contractor  shall  provide  an  EIU  training  system  at  each  of  the  regional  training 
centres in Hendon, Durham, and Wyboston. 
6.8.3  The  training  systems  shall  replicate  the  full  system  functionality  available  at  the 
custody  suite  and  will  be updated  with the  most  current  software  releases. The EIU 
Schedule Q, Part A (Contractor’s Solution) 
22 
Signature Version 
CCN001 
 
18 July 2005 
 
Released under FOI in full on 16th July 2009 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 16th July 2009 
training system at each of the regional training centres will interact with the installed 
training  systems  for  FPO  training  and  mimic  the  functionality  of  the  operational 
system. 
6.8.4  The  Contractor  shall  provide  hardcopy  training  materials  and  user  manuals  to 
students  attending  courses  run  by  the  Contractor.  Updates  to  user  manuals  will  be 
provided to each custody suite. These materials will be made available in electronic 
format  through  the  knowledge  portal  and  will  be  available  for  reproduction  by  the 
Authority or other parties as approved by the Authority. 
6.8.5  The Contractor shall develop, update, and maintain training and user manuals to be 
used  at  regional  training  centres.  The  Contractor  will  work  with  the  Authority  to 
produce the training materials and will obtain the Authority’s approval of materials to 
be provided to users. 
6.8.6  EIUs  at  custody  suites  shall  support  training  of  operational  personnel  in  a  training 
mode, which does not impact the operational system. 

DEVELOPMENT 
7.1 
Development 
7.1.1  The  Contractor’s  development  process  shall  conform  to  industry  best  practices  and 
include, at a minimum: 
(a) 
Developing software iteratively. 
(b) 
Managing requirements. 
(c) 
Visually modelling software. 
(d) 
Using component architecture. 
(e) 
Verifying software quality. 
(f) 
Controlling changes to software. 
7.1.2  The  Contractor  shall  use  Rational  Unified  Process  (RUP)  (in  particular,  RUP  for 
Systems Engineering) or an equivalent established development process. 
7.1.3  The  Contractor’s  development  process  shall  be  mature,  documented,  and  compliant 
with CMM.  
7.1.4  The  Contractor  shall  agree  upon  a  Development  Strategy  with  the  Authority  in 
accordance with Schedule O:9 (Documentation). 
7.1.5  The Contractor, in conjunction with the Authority, shall carry out further analysis and 
development of the Functional Requirements to ensure that they are a complete and 
accurate representation of the user’s then current needs. 
7.1.6  The Contractor shall carry out performance modelling of the IDENT1 Service.  The 
results  from  the  performance  modelling  shall  be  considered  in  the  development 
process during the Inception Phase . 
Schedule Q, Part A (Contractor’s Solution) 
23 
Signature Version 
CCN001 
 
18 July 2005 
 
Released under FOI in full on 16th July 2009 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 16th July 2009 
7.1.7  The Contractor shall construct a conceptual model for the IDENT1 Service, using the 
existing NAFIS Services System and DOR Use Cases as a starting point see Schedule 
Q Part B (System Description). 
7.1.8  The  Contractor  shall  catalogue  and  classify  the  IDENT1  Services  requirements  in 
accordance with the requirements management approach defined by the Authority. 
7.1.9  The  Contractor  shall  use  a  compatible  method  for  managing  requirements  and 
exchange  requirements  information  with  the  Authority  in  a  format  suitable  for 
importing, as defined by the Authority. 
7.1.10  The  Contractor  shall  work  with  the  Authority  and  the  user  community  to  capture, 
validate,  and  verify  new  requirements  emerging  during  the  lifetime  of  the  Services. 
Any new requirements will result in a change to the Services which shall be varied in 
accordance with Schedule L (Change Control Procedure). 
7.1.11  The Contractor shall assist the Authority in analysing new requirements by carrying 
out  impact  assessments  when  appropriate  in  accordance  with  Schedule L  (Change 
Control Procedure). 
7.1.12  The Contractor shall conduct a Lifecycle Objective Milestone review. 
7.1.13  The Contractor shall conduct a Lifecycle Architecture Milestone review. 
7.1.14  The Authority shall make the final assessment on whether new requirements are to be 
progressed to development. 
7.1.15  The Contractor shall provide and maintain a Software Development Plan that details 
all  analysis,  design,  build,  and  deployment  tasks  based  on  the  agreed-upon 
development strategy (as set out in Schedule O:32 (Documentation)). 
7.1.16  The  Contractor  shall  validate  and  enhance  the  business  requirements  to  ensure  that 
they have a firm basis for developing the system requirements. 
7.1.17  The Contractor shall provide the analysis and design methods to be used during the 
development  cycle,  clearly  stating  how  each  product  is  to  be  produced  and  used 
during each stage to produce the final system. 
7.1.18  The  Contractor  shall  provide  system  development  documentation  for  the  IDENT1 
Services to the Authority in RUP terms. 
7.1.19  All software products shall be subject to formal Quality Review as described in the 
Programme Quality Plan (as set out in Schedule O:10 (Documentation).   
7.1.20  The  Contractor  shall  develop  and  agree  upon  quality  criteria  with  the  Authority 
during the planning stage. 
7.1.21  The Contractor shall use system architecture principles to guide the development of 
the  system  architecture  that  shall  be  represented  in  a  model  in  order  to  facilitate 
reviews between the Authority and the Contractor. 
7.1.22  The  Contractor  shall  provide  the  Authority  with  a  System  Architecture  Model 
detailing  the  major  hardware,  software  and  network  components  of  the  IDENT1 
Service (see Schedule O:43 (Documentation)). 
Schedule Q, Part A (Contractor’s Solution) 
24 
Signature Version 
CCN001 
 
18 July 2005 
 
Released under FOI in full on 16th July 2009 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 16th July 2009 
7.1.23  The System Architecture Model shall clearly identify which components are existing 
infrastructure, which are COTS, and which are Contractor developed. 
7.1.24  The  System  Architecture  Model  shall  distinguish  between  functional  and  physical 
components. 
7.1.25  The  System  Architecture  Model  shall  clearly  identify  all  major  subsystems  and 
describe their purpose. 
7.1.26  The Contractor shall maintain the System Architecture Model during the term of the 
Contract and incorporate all enhancements and upgrades. 
7.1.27  The Authority shall have the right to reuse information from the System Architecture 
Model for future systems development. 
7.1.28  The  Contractor  shall  provide  the  Authority  with  full  access  to  all  Data  Models 
(conceptual,  logical,  or  physical)  produced  for  the  Service  (as  set  out  in  Schedule 
O:44 and 45 (Documentation)). 
7.1.29  The Authority shall have the right to reuse information from Data Models in future 
systems development. 
7.1.30  The  Contractor  shall  use  the  procedures  from  the  Quality  Plan  to  ensure  quality  in 
software development. 
7.1.31  The  Contractor  shall  ensure  that  any  developed  code  is  produced  according  to  the 
Quality Plan. 
7.1.32  The  Contractor  shall  agree  upon  escrow  arrangements  with  the  Authority,  in 
accordance with Schedule B (Conditions of Contract), to cover all developed code, 
together  with  supporting  design  documentation  and  any  proprietary  technology 
necessary to make use of the code. 
7.1.33  The Contractor shall document all interfaces and Application Programming Interfaces 
built for the Service in ICDs (as set out in Schedule O:46 (Documentation)). 
7.1.34  The Authority shall have the right to share information contained in ICDs with third 
parties where integration with the IDENT1 Services is required. 
7.1.35  The modelling notation used to communicate with the Authority during development 
shall be UML. 
7.1.36  The  Contractor’s  development  environment  shall  be  completely  separate  from  the 
live and test environments. 
7.1.37  The Contractor shall use a controlled process to move code, documentation, and data 
from  the  development  environment  through  to  the  test  and  subsequently  live 
environments. 
7.1.38  The Contractor shall agree upon the choice of development tools with the Authority, 
taking into account compatibility with other Authority development work. 
7.1.39  The  choice  of  development  tools  shall  be  consistent  with  the  IDENT1  Service 
Technical Architecture. 
Schedule Q, Part A (Contractor’s Solution) 
25 
Signature Version 
CCN001 
 
18 July 2005 
 
Released under FOI in full on 16th July 2009 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 16th July 2009 
7.1.40  The  Contractor  shall  establish,  implement,  and  maintain  a  Business  Process 
Engineering  (BPE)  capability,  responsible  for  assisting  the  Authority’s  Fingerprint 
Service  in  the  definition  and  the  development  of  their  business  processes  (see 
Schedule O:36 (Documentation)). 
7.1.41  The  Contractor  shall  provide  evidence  to  the  Authority  that  its  BPE  team  has  a 
proven process and methodology. 
7.1.42  The  Contractor  shall  work  with  the  Authority  to  define  business  process  design 
standards and procedures for implementation. 
7.1.43  The  Contractor  shall  work  with  the  Authority  to  review  the  current  processes  to 
identify problems and issues that need to be addressed. 
7.1.44  The Contractor shall work with the Authority to produce statements of new processes 
and to assist  the Authority in the  appropriate distribution and implementation.   
7.1.45  The  Contractor  shall  ensure  that  all  workflow  and  business  process  design  shall  be 
provided within a workflow modelling tool. 
7.1.46  The Contractor’s IDENT1 system shall contain a workflow solution. 
7.1.47  The Contractor’s workflow solution shall conform to relevant industry standards. 
7.1.48  The  workflow  modelling  tool  shall  be  capable  of  demonstrating  that  the  proposed 
solution is capable of delivering the overall performance objectives and how changes 
in workload shall impact response times and throughput. 
7.1.49  The workflow modelling tool shall be able to model a workflow that contains a mix 
of manual, semi-automated, and automated functions. 
7.1.50  The workflow modelling tool shall be able to measure total process times of minutes 
or hours—consisting of individual processes that take seconds or minutes—and total 
throughput volume under typical demand conditions and peak demand conditions. 
7.1.51  The  workflow  modelling  tool  shall  be  provided  through  commercially  available 
workflow management products and not through custom-built solutions. 
7.1.52  The  Contractor  shall  provide  the  Authority  with  justification  for  COTS  products 
chosen (as set out in Schedule O:41 (Documentation)). 
7.1.53  The  Contractor  shall  seek  the  approval  of  the  Authority  before  purchase  of  COTS 
products for use in the delivery of Service. 
7.1.54  The Contractor shall document COTS software products and version numbers that are 
required, incorporated, or included as part of its solution for delivery of the Service 
(as set out in Schedule O:42 (Documentation)). 
7.1.55  The  Contractor  shall  document  any  ratings,  certifications,  and  industry  standards 
achieved by the COTS software. 
7.1.56  The Contractor shall provide documentation describing all changes made to a COTS 
software product implemented as part of the Service. 
Schedule Q, Part A (Contractor’s Solution) 
26 
Signature Version 
CCN001 
 
18 July 2005 
 
Released under FOI in full on 16th July 2009 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 16th July 2009 
7.1.57  The  Contractor  shall  propose  and  agree  with  the  Authority  on  a  software 
configuration  management  process  for  the  Service  and  document  this in  accordance 
with Schedule O:34 (Documentation).  
7.1.58  The Contractor shall be permitted to choose appropriate tools to support the software 
configuration management process subject to approval by the Authority. 
7.2 
Usability 
7.2.1  The Contractor shall carry out any necessary rework resulting from usability testing 
to meet Contract requirements prior to implementing the HCI (as set out in Schedule 
O:70 (Documentation)). 
7.2.2  The Contractor shall design the Service to maximise the efficiency and effectiveness 
of users while providing a safe and comfortable work environment. 
7.2.3  The  Contractor  shall  ensure  that  the  usability  requirements  for  the  Services  System 
apply to all applications and equipment accessible to the user. 
7.2.4  The Contractor shall develop, document, and use a User Centred Design process for 
the development of the Service. 
7.2.5  The Contractor shall describe its approach to User Centred Design for the Services in 
the Programme Initiation Review Documentation. 
7.2.6  The Contractor shall include User Centred Design activities in the development plans. 
7.2.7  The Contractor shall include user representation from different groups of users in the 
User Centred Design process. 
7.2.8  The Contractor shall document usability requirements during the design phase so that 
the system can be tested for conformance to these requirements. 
7.2.9  The  Contractor  shall  make  available  such  documentation  produced  to  support  the 
usability  of  the  Service  to  the  Authority  (as  set  out  in  Schedule  O:48 
(Documentation)). 
7.2.10  The  IDENT1  Services  shall  continue  to  be  evaluated  on  a  reasonable  basis  by  the 
Contractor  after  implementation  to  ensure  that  it  continues  to  meet  usability 
requirements. 
7.2.11  The  Contractor  shall  on  a  reasonable  basis  improve  the  usability  of  the  system  for 
bureau  users  by  using  a  User  Centred  Design  process  in  which  the  usability 
requirements will be identified, the system evaluated against these requirements, and 
the system redesigned to meet the usability requirements through an iterative process. 
7.2.12  The  Contractor  shall  on  a  reasonable  basis  identify  and  analyse  the  types  of 
environment and tasks in which mobile access to the IDENT1 Service is required in 
order to design HCIs and equipment that address the specific usability needs of users 
with mobile access to the system. 

TEST AND ACCEPTANCE APPROACH 
8.1 
The  Contractor  shall  present  a  Test  and  Acceptance Strategy  to  the  Authority  at  the  project 
initiation event.  All testing will be done in accordance with this strategy. 
Schedule Q, Part A (Contractor’s Solution) 
27 
Signature Version 
CCN001 
 
18 July 2005 
 
Released under FOI in full on 16th July 2009 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 16th July 2009 
8.2 
The Contractor’s Test and Acceptance Strategy shall support delivery of new functionality in 
incremental releases. 
8.3 
The  Contractor  shall  be  responsible  for  the  performance  of  all  validation  and  verification 
activities,  including  formal  and  informal  testing  of  functionality,  performance,  usability, 
backward compatibility, PNC, and regression tests. 
8.4 
The  Authority  shall  be  entitled  to  attend  all  test  events  at  its  discretion,  and  the  Contractor 
shall reasonably facilitate such attendance. 
8.5 
The  Contractor  shall  incorporate  users  and  user  opinions  in  its  verification  and  validation 
activities. 
8.6 
Where  appropriate  and  to  retain  benefits  from  the  investment  in  the  NAFIS  Services,  the 
Contractor shall, at the Authority’s discretion, reuse test scripts, processes, data, and test beds 
used in the development and provision of the NAFIS Services. 
8.7 
The Contractor shall collect metrics to use in improving the development and test process in 
accordance with Schedule H (Acceptance Procedures). 
8.8 
The Contractor shall at its discretion and on a reasonable basis develop automated test tools to 
reduce the time and cost of regression testing. 
8.9 
The Contractor shall use IEEE 829 as a framework for test documentation in accordance with 
Schedule O:1, 2 and 4 (Documentation). 
8.10 
The Contractor shall identify and comply with the procedures used in recording the results of 
other verification activities, such as peer review, inspections, audits and analysis, and unit and 
integration testing, as described in Schedule H (Acceptance Procedures). 
8.11 
Subject  to  Schedule  H  (Acceptance  Procedures),  the  Contractor  shall  migrate  the  current 
NAFIS  Requirements  Database  and  all  associated  verification  data  to  an  appropriate  tool 
agreed  upon  between  parties.  The  Contractor  shall  use  test  material  used  for  the  NAFIS 
Services  to  test  IDENT1  requirements  that  map  directly  to  already  verified  NAFIS 
requirements. 
8.12 
The Contractor shall perform prerelease defect and regression testing to ensure that existing 
functionality has not been impacted as described in Schedule H (Acceptance Procedures). 
8.13 
The Contractor’s testing cycle shall include development tests, integration tests, informal and 
formal dry run tests, and formal acceptance tests. 
8.14 
The Contractor shall conduct a formal Test Readiness Review (TRR) (as set out in Schedule 
O:6 (Documentation)) with the Authority before proceeding with formal acceptance testing, 
as  described  in  Schedule  H  (Acceptance  Procedures).    This  TRR  will  result  in  the 
production of minutes (as set out in Schedule O:3 (Documentation)). 
8.15 
The  Contractor  shall  hold  a  Product  Acceptance  Review  at  the  conclusion  of  acceptance 
testing, as described in Schedule H (Acceptance Procedures). 
8.16 
The Contractor shall hold Operational Readiness Review’s (ORR’s) to affirm that releases are 
ready for deployment, as described in Schedule H (Acceptance Procedures). 
8.17 
The  Contractor  shall  maintain  configuration  management  of  all  test  documents  against  the 
project baseline. 
Schedule Q, Part A (Contractor’s Solution) 
28 
Signature Version 
CCN001 
 
18 July 2005 
 
Released under FOI in full on 16th July 2009 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 16th July 2009 
8.18 
The Contractor’s test programme shall ensure that test procedures are subject to peer review 
before release, as described in Schedule H (Acceptance Procedures). 
8.19 
The Contractor shall support upon the Authority’s request for specific program requirements, 
tailoring  of  the  standard  testing  processes.    The  Contractor  shall  conduct  and  document 
acceptance  testing  of  subcontractor-delivered  products.  The  Contractor’s  processes  and 
procedures shall be consistent with those used in the overall Contractor’s product life cycle. 
8.20 
Unless otherwise agreed with the Authority for all system upgrades, the Contractor shall as a 
minimum conduct regression and performance testing of existing capabilities.  
8.21 
For  the  Palms  Transition  Project,  the  Contractor  shall  perform  the  following  tests: 
demonstration  and  performance,  integration  and  formal  dry  runs,  regression,  validation  and 
acceptance. 
8.22 
Evidence of unit and integration testing shall be recorded in the programme filing system, and 
shall be made available to the Authority, upon request. 
8.23 
The  Contractor  shall  develop  and  maintain  regression  test  procedures  as  described  in 
Schedule H (Acceptance Procedures). 
8.24 
The Contractor shall conduct, where the Authority deems appropriate, other testing, including 
load testing scripts, external (e.g., PNC, Police Immigration Fingerprint Exchange), backward 
compatibility,  switchover,  and  defect  testing  as  described  in  Schedule  H  (Acceptance 
Procedures). 
8.25 
Configuration  Management  and  QA  roles  and  responsibilities  in  the  Test  and  Acceptance 
Process shall be defined in the respective Configuration Management and QA plans produced 
in accordance with Schedule O:10 and 34 (Documentation). 
8.26 
New  releases  shall  be  made  available  to  users  on  the  integration  test  bed  at  Hendon  or  the 
secondary site, to allow users and the Contractor user support group to become familiar with 
and  appraise  the  new  functionality  as  described  in  Schedule  H  (Acceptance  Procedures). 
User comments shall be incorporated into the test report. 
8.27 
The  Contractor  shall  develop  prototypes  and  demonstrations,  where  it  deems  appropriate  as 
described in  Schedule H (Acceptance Procedures). 
8.28 
The  Contractor  shall  establish  and  maintain  a  UK  prototyping  lab  to  support  systems 
engineering  activities,  as  described  in  Schedule  H  (Acceptance  Procedures).  A  link  to  the 
development facility in the US shall be provided. 
8.29 
The Contractor shall conduct checkout testing at the initially deployed bureaux by providing 
user support at each of these bureaux, as described in Schedule H (Acceptance Procedures). 
8.30 
The  Contractor  shall  seek  Authority  approval,  which  shall  not  be  unreasonably  withheld 
before  conducting  any  testing  involving  the  operational  system;  except  where  otherwise 
agreed upon between the parties, such testing will be performed in a manner that will have no 
impact on system performance as specified in Schedule F (Service Level Requirements). 
8.31 
The Contractor shall analyse all Services requirements to determine at which stage or stages 
of  the  Contract  they  can  be  most  logically  verified  and  included  in  the  next  Stage  Plan  for 
approval (as set out in Schedule O:18 (Documentation)). 
Schedule Q, Part A (Contractor’s Solution) 
29 
Signature Version 
CCN001 
 
18 July 2005 
 
Released under FOI in full on 16th July 2009 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 16th July 2009 
8.32 
Functional  requirements,  such  as  HCI,  critical  to  project  success  shall  be  verified  with  user 
evaluation, as described in Schedule H (Acceptance Procedures). 
8.33 
The Contractor shall tailor test procedures and resources to the type of activity performed for 
each  phase  of  testing  and  the  functionality  in  the  current  release  of  the  software  as  agreed 
with the Authority (as set out in Schedule O:2 (Documentation)). 
8.34 
The Contractor shall use test tools as agreed with the Authority to support test and acceptance 
activities. 
8.35 
The  Contractor  shall  establish  and  maintain  a  controlled  test  environment  that  mirrors  the 
operational  system,  including  bureau  and  central  configurations  as  described  in  Schedule  H 
(Acceptance Procedures). 
8.36 
The Contractor shall maintain test data comprising marks, ten prints, and palms. Test data for 
the  IDENT1  Services  shall  be  largely  derived  from  the  test  data  maintained  for  the  NAFIS 
Services and data provided to the Contractor by the Authority. 
8.37 
The Contractor shall maintain test data to support testing of new capabilities as described in 
Schedule H (Acceptance Procedures). 
8.38 
Insofar as it is within the Contractor’s control, the Contractor shall maintain a live connection 
with  the  PNC  in  the  test  bed  to  support  PNC  testing  on  an  as-required  basis.  Similar 
functionality shall be built to support other external interfaces. 
8.39 
The  Contractor  shall  conduct  testing  of  message-based  interfaces  through  scripts  simulating 
the target systems. 
8.40 
The  Contractor  shall  maintain  test  traceability,  including  test  procedures,  test  scripts, 
requirements,  and  verification  methods  as  described  in  Schedule  H  (Acceptance 
Procedures). 
8.41 
The  Contractor  shall  maintain  multiple  test  beds  to  support  IDENT1  test  and  acceptance 
activities. 
8.42 
As part of the acceptance test plan, the Contactor shall obtain the Authority’s approval for test 
locations, which approval shall not be unreasonably withheld. 
8.43 
The Contractor shall include testing of the Training Bureau functionality as part of regression 
testing. 

CAPACITY MANAGEMENT 
9.1 
The  Contractor  shall  deliver  a  Capacity  Management  Plan  as  set  out  in  Schedule  O:64 
(Documentation).    They  shall  implement  the  Capacity  Management  Process  as  part  of  its 
Systems Engineering process. The Capacity Management Plan shall be ITIL compliant. The 
Capacity Management Plan shall address the full range of IDENT1 Services, including central 
site(s), bureaux systems, and remote EIUs. The Capacity Management Plan shall also address 
the communications infrastructure and system interfaces. 
9.2 
The Capacity Management Process shall address the following elements: 
9.2.1  UPSs for IDENT1 kit at the Central Site and all bureaux locations. 
9.2.2  Monitoring of system resource utilisation. 
Schedule Q, Part A (Contractor’s Solution) 
30 
Signature Version 
CCN001 
 
18 July 2005 
 
Released under FOI in full on 16th July 2009 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 16th July 2009 
9.2.3  Trend analysis. 
9.2.4  Identification  of  elements  of  the  configuration  that  could  be  tuned  for  improved 
resource utilisation. 
9.2.5  Maintenance of capacity management data on key system resources. 
9.2.6  Forecast capacity and delivered capacity against actual usage. 
9.2.7  Demand management activities. 
9.2.8  System modelling that addresses capacity issues and planning. 
9.3 
The  Contractor  shall  designate  a  capacity  manager  who  shall  interface  with  the  Authority’s 
capacity  manager.  The  Contractor’s  capacity  process  shall  be  managed  under  the  Systems 
Engineering functional area. 
9.4 
The  capacity  management  process  shall  include  inputs  from  engineering  modelling  and 
performance  assessments,  as  well  as  operational  supportability  considerations.  The  capacity 
management process shall be documented in the Operations and Maintenance Support Plan. 
9.5 
The  capacity  management  process  shall  include  system  monitoring  capabilities.  The 
Authority  shall  be  provided  access  to  the  system  monitoring  facilities  via  a  web  portal 
interface. 
9.6 
The Contractor shall implement appropriate tools to record and analyse historic capacity and 
usage at a business, service, and resource level. The Authority shall be provided with access 
to the tools and data. 
10 
SECURITY 
10.1 
The Contractor shall implement and deliver a Security Management Process that ensures that 
the Services meet the IDENT1 operational security requirements. The Security Management 
Process  shall  be  ISO 17799  compliant.  The  Contractor  shall  be  responsible  for  full  system 
security,  including  the  WAN.  The  Contractor  shall  be  fully  responsible  for  implementing 
system  and  component  changes  and  enhancements  required  to  meet  system  operational 
security goals. 
10.2 
The  Contractor’s  Security  Management  Process  shall  incorporate  key  elements  of  the 
Contractor’s existing design and support structure, including: 
10.2.1  A  Chief  Engineer  responsible  for  ensuring  that  security  attributes  are  incorporated 
into the overall software and system design at every step of the systems engineering 
and implementation process. 
10.2.2  An  accredited  test  and  development  facility  connected  to  the  IDENT1  WAN  with 
CAPS-approved encryption. 
10.2.3  A single onward connection at each central site to the CJX, providing a clear security 
boundary between IDENT1 and external users and systems. 
10.2.4  The  use  of  LDAP  and  Simple  Authentication  and  Security  Layer  for  user 
authentication. 
10.2.5  The  use  of TACACS+ and  RADIUS  for remote  user access and system  component 
access. 
Schedule Q, Part A (Contractor’s Solution) 
31 
Signature Version 
CCN001 
 
18 July 2005 
 
Released under FOI in full on 16th July 2009 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 16th July 2009 
10.2.6  Flowdown  of  security  requirements  to  suppliers  such  as  the  WAN  provider  or  the 
maintenance provider. 
10.2.7  Multiple test beds to evaluate new products and component suitability. 
10.3 
The Contractor’s security management activities shall: 
10.3.1  Review and analyse security requirements, through its systems engineering process. 
10.3.2  Review  impacts  to  business  functions  arising  from  security  issues,  including 
identifying  critical  system  security  components  (as  set  out  in  Schedule  O:57 
(Documentation)). 
10.3.3  Arrange  annual  system  security  audits  by  external  parties  and  IT  health  checks 
annually or at the request of system accreditors. 
10.3.4  Form  Computer  Emergency  Response  Teams  (CERTs)  in  response  to  security 
incidents. 
10.3.5  Review  access  lists  of  users  and  administrators  on  a  monthly  basis  to  ensure 
appropriate access privileges and group assignments. 
10.3.6  Review of audit and accounting logs commensurate with the Protective Markings. 
10.3.7  Maintain  and  update  a  Security  Management  Plan  meeting  the  requirements  of 
ISO 17799.  This  plan  shall  include  periodic  vendor  assessments  of  current  and new 
products  and  technologies  applicable  to  security.  The  Security  Management  Plan 
shall be made available for the Authority for review and comment. 
10.3.8  Implement a Security Awareness Training Programme to provide annual documented 
training to all users (as set out in Schedule O:30 (Documentation)). 
10.4 
The Contractor shall designate a System Security Officer (SSO) who shall interface with the 
Authority’s  SSO  for  IDENT1.  The  SSO  shall  have  overall  responsibility  for  the  security 
operations of the IDENT1 programme. The Contractor’s SSO shall report to the Contractor’s 
Programme  Director.  Serious  security  issues  shall  be  escalated  to  the  Contractor’s  Chief 
Engineer  and/or  the  Contractor’s  Programme  Director.  The  SSO  shall  report  any  security 
breaches to the Programme Director and to UNIRAS if appropriate. 
10.5 
The  system  security  status  shall  be  reported  on  a  monthly  basis.  The  Authority  shall  be 
provided with reasonable access to MIS and system audit logs to assist in analysis of system 
security performance. 
10.6 
The  Contractor’s  Security  Management  Process  shall  be  an  integral  aspect  of  its  overall 
systems  engineering  activities  to  ensure  that  security  is  considered  within  the  IDENT1 
life cycle.  The  Security  Management  Process  shall  be  documented  in  the  Operations  and 
Maintenance Support Plan. 
10.7 
The  Contractor’s  Security  Management  Process  shall  include  mechanisms  for  delivering 
changes to the system resulting from security reviews and CERT findings. 
10.8 
The Contractor’s Security Management Process shall include mechanisms for communicating 
security incidents to the Authority and to users.  
Schedule Q, Part A (Contractor’s Solution) 
32 
Signature Version 
CCN001 
 
18 July 2005 
 
Released under FOI in full on 16th July 2009 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 16th July 2009 
11 
FUTURE VISION 
11.1 
The  Contractor  shall  design  the  IDENT1  system  architecture  to  support  a  Strategic 
Identification  Services  Platform  (SISP)  that  provides  the  capability  to  incorporate  new 
functionalities.  At  a  minimum,  the  capability  shall  be  provided  to incorporate  the  following 
new functionalities: 
11.1.1  Multi-Modal Biometrics 
11.1.2  Integrated Feature Management 
11.1.3  Multi-Classifier Systems 
11.1.4  Facial Image Collection and Recognition 
11.2 
The  Contractor’s  system  architecture  shall  support  algorithm  fusion.  The  architecture  shall 
support new AFR fusion algorithms and fusion of algorithms across multiple biometrics. 
11.3 
The Contractor’s IDENT1 architecture shall provide the capability to link and integrate with 
external systems within the criminal justice environment. 
11.4 
The  Contractor’s  IDENT1  architecture  shall  be  designed  so  as  to  enable  the  provision  of 
capability  in the future  for  IDENT1  users to  make  use  of  identification information  held  on 
other systems. 
11.5 
The Contractor’s IDENT1 architecture shall be designed so as to enable the support of  new 
delivery mechanisms to provide information at the point of need. The Contractor’s IDENT1 
architecture  shall  support  future  locations  and  new  roles  within  the  identification 
environment. 
11.6 
The  Contractor  shall  maintain  active  membership  with  such  international  biometrics 
organisations and standards bodies as it deems appropriate.  
11.7 
The Contractor shall work on a reasonable basis, in conjunction with the Authority, to address 
standards and implementation issues to support IDENT1 strategic identification services. 
11.8 
The  Contractor  shall  provide  BPE  teams  to  develop  use  cases  for  new  functionality.  The 
Contractor’s BPE team shall include relevant systems engineering, business process, change 
management, and operational user experience. 
11.9 
The  Contractor  shall  develop  a  strategic  plan  that  addresses  the  strategy  for  introducing 
changes to the IDENT1 Services System. The Contractor’s strategic plan shall consider and 
complement  PITO’s  Biometric  Technology  Roadmap  and  demonstrate  potential  future 
benefits of IDENT1 in terms of systems and services. The Contractor’s strategic plan shall be 
reviewed and updated, as appropriate, on an annual basis. 
11.10  The  Contractor  shall  employ  such  prototyping  and  piloting  of  new  functionality  as  agreed 
with the Authority within the Contractor’s facilities to facilitate user and stakeholder feedback 
and reduce implementation risk. 
11.11  The Contractor shall maintain an independent research and development (R&D) programme 
associated  with  strategic  identification  technologies.  The  Contractor  shall  provide  results  of 
R&D activities to the Authority. 
11.12  The  Contractor  shall  within  its  discretion  and  planning  host  an  annual  identification 
technology forum to provide technical vision in the areas of biometrics, display concepts, and 
Schedule Q, Part A (Contractor’s Solution) 
33 
Signature Version 
CCN001 
 
18 July 2005 
 
Released under FOI in full on 16th July 2009 
 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 16th July 2009 
security in relationship to the IDENT1 services strategic plan. The forum shall include senior 
managers  and  technologist  from  the  Contractor’s  team.  The  Authority  shall  be  invited  to 
participate in this forum at the Authority’s discretion. 
11.13  The Contractor shall deliver technology refreshes of the IDENT1 Services between FOC and 
EOC  to  support  the  agreed-upon  Schedule  F  (Service  Level  Requirements)  upgrades  and 
forecasted capacity increases. 
 
 