SCHEDULE N 
EXIT STRATEGY
Schedule N (Exit Strategy) 
 
Signature Version 
 
Released under FOI in full on 13th December 2005 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 13th December 2005 
CONTENTS 
 
1. 
OVERVIEW ..................................................................................................................................1 
2. 
SUPPORT FOR A PROCUREMENT PROCESS.....................................................................1 
3. 
ASSISTANCE PRIOR TO TRANSFER OF THE SERVICES................................................2 
4. 
ASSISTANCE ON TERMINATION ..........................................................................................2 
5. 
OUTLINE EXIT PLAN................................................................................................................2 
6. 
ORDINARY COURSE OF BUSINESS.......................................................................................3 
7. 
CHARGES FOR TERMINATION ASSISTANCE ...................................................................3 
ANNEX N-1  ASSISTANCE WITH A PROCUREMENT PROCESS ............................................5 
ANNEX N-2   ASSISTANCE IN THE PERIOD PRIOR TO THE TERMINATION DATE........8 
ANNEX N-3  TERMINATION AND TRANSITION TO THE SUCCESSOR CONTRACTOR13 
ANNEX N-4  OUTLINE EXIT PLAN ..............................................................................................14 
 
Schedule N (Exit Strategy) 

Signature Version 
 
Released under FOI in full on 13th December 2005 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 13th December 2005 
SCHEDULE N 
 
EXIT STRATEGY 
1. 
OVERVIEW 
1.1 
The  objective  of  the  exit  management  process  is  to  facilitate  the  smooth  transfer  of  the 
Services  to  a  Successor  Contractor  in  a  way  that  preserves  business  continuity  for  the 
Authority.  
1.2 
This Schedule sets out the process by which the Contractor shall provide assistance in respect 
of Services that are to be provided through a third party or by the Authority itself. 
1.3 
The  Contractor  shall  provide  the  assistance  set  out  in  this  Schedule  commencing  from  the 
following dates:  
1.3.1  where the Authority wishes to hold a Procurement Process in relation to any of the 
Services, from the date that the Authority first gives public notice of that process;  
1.3.2  if  one  Party  has  served  notice  of  Termination,  from  the  date  that  such  notice  is 
received  by  the  recipient  Party  or  the  date  six  (6)  months  prior  to  the  Termination 
Date in the case of the expiry of the Contract; or 
1.3.3  where,  pursuant to  any  right  under  the  Contract  or at  Law,  the  Authority  has  given 
such notice as is required to remove Services from the scope of the Contract (whether 
following  a  competitive  bid  process  or  otherwise),  from  the  date  on  which  the 
Contractor received such notice,  
(each  or  all  of  the  above  commencement  dates  shall  be  know  as  the  “Assistance 
Commencement Date”).   
1.4 
The  Contractor  shall  comply  with  the  Exit  Plan  from  the  applicable  Assistance 
Commencement Date, and/or shall comply with any mutually agreed Services Transition Plan 
from the date of its agreement, until the Services Transfer Date or the date of removal of the 
particular Services, as applicable.  
1.5 
Notwithstanding the generality of Clause 1.4 above, at the Authority’s request, the Contractor 
shall continue to comply with its obligations under the Exit Plan and/or any agreed Services 
Transition Plan for up to twelve (12) months, or such longer period that is mutually agreed to 
transition the relevant Services, following the Termination Date or removal of the Services (as 
the case may be).  
1.6 
The Parties agree and acknowledge that this Schedule shall continue in full force and effect 
notwithstanding the Termination of the Contract.  
2. 
SUPPORT FOR A PROCUREMENT PROCESS 
In  the  case  of  a  Procurement  Process,  the  Contractor  shall  assist  and  support  the  Authority 
with the Procurement Process from the Assistance Commencement Date in accordance with 
the provisions of Annex N-1.  
Schedule N (Exit Strategy) 

Signature Version 
 
Released under FOI in full on 13th December 2005 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 13th December 2005 
3. 
ASSISTANCE PRIOR TO TRANSFER OF THE SERVICES  
The Contractor agrees to continue to provide the Services, and to assist with exit management 
and  Termination  Assistance  during  the  Exit  Period,  in  accordance  with  the  provisions  of 
Annex N-2.  
4. 
ASSISTANCE ON TERMINATION 
If  the  Authority  appoints  a  Successor  Contractor,  other  than  the  Contractor,  to  provide  the 
Services then, with effect from the Services Transfer Date, the provisions of Annex N-3 shall 
apply. 
5. 
OUTLINE EXIT PLAN 
5.1 
Annex N-4 sets out the initial areas to be included in the Outline Exit Plan and the elements 
which shall, at a minimum (unless otherwise agreed), be part of such Outline Exit Plan.  
5.2 
The Parties shall review and update the Outline Exit Plan annually, on the anniversary of the 
Effective Date, to ensure that it remains relevant as the Contractor’s Solution develops and to 
reflect changes to the Services.  
5.3 
Whenever either Party decides that changes are required to the Outline Exit Plan, they shall 
discuss,  and  agree  pursuant  to  Schedule  L  (Change  Control  Procedure)    a  new  document 
that shall replace the current Outline Exit Plan set out in Annex N-4. 
5.4 
In terms of the scope of the Outline Exit Plan, the Contractor must address: 
5.4.1  the  activities  required  to  enable  the  Authority  to  re-tender  the  provision  of  the 
Services; 
5.4.2  the  activities  necessary  to  support  any  Successor  Contractor  in  carrying  out  any 
necessary due diligence; 
5.4.3  details of the transition services to be provided by the Contractor prior to the Services 
Transfer Date; 
5.4.4  support for the Successor Contractor during its preparation of any relevant transition 
plan for the transition of the Services to the Successor Contractor, including prior to 
and  during  such  reasonable  transition  period  as  may  be  required  by  the  Successor 
Contractor; and 
5.4.5  the  maintenance  of  a  ‘business  as  usual’  environment  for  the  Authority  during  all 
transition  activities  for  such  reasonable  transition  period  as  may  be  required  by  the 
Successor Contractor. 
5.5 
Unless otherwise agreed by the Authority, the Outline Exit Plan shall relate to the following 
general activities: 
5.5.1  production and updating of the initial Outline Exit Plan to include, as a minimum, the 
elements  specified  in  this  Schedule  and  Annex  N-4.  This  activity  is  anticipated  to 
support  any  Procurement  Process  and  preferred  Contractor/bidder  due-diligence 
activities; 
5.5.2  updating and review of the Outline Exit Plan, in accordance with Clause 5.3 above, 
and there will be the following phases as a minimum:  
Schedule N (Exit Strategy) 

Signature Version 
 
Released under FOI in full on 13th December 2005 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 13th December 2005 
(a) 
the first phase of implementation activity, triggered by the need for transfer, 
is anticipated to be due diligence and transition planning activity to be carried 
out by the Successor Contractor within the period leading up to the Services 
Transfer Date including staggered transfer of required business knowledge; 
(b) 
the  second  phase  of  implementation  which  will  be  mainly  concerned  with 
support to the Successor Contractor in the actual transitioning of the Services; 
and 
(c) 
the final phase is post-transfer support and consultancy. 
6. 
ORDINARY COURSE OF BUSINESS 
6.1 
Throughout any Procurement Process and/or Exit Period, the Contractor shall:  
6.1.1  not embark on any actions related to the provision of the Services that fall outside the 
Ordinary  Course  of  Business,  without  the  Authority’s  prior  written  consent  (which 
consent shall not be unreasonably withheld);  
6.1.2  continue to devote such time and resources to the continued provision of the Services, 
so as to ensure that there is no disruption to the Services and no reduction in Service 
Levels;  
6.1.3  notify  the  Authority  of  any  act,  omission  or  conduct  which  adversely  affects  the 
Assets or personnel required to deliver any of the Services during and after the Term; 
and  
6.1.4  take active steps as reasonable  to monitor the Contractor Personnel to ensure there is 
no degradation in the quality of the Services. 
7. 
CHARGES FOR TERMINATION ASSISTANCE 
7.1 
Procurement Process 
The  Contractor  shall  provide  the  Termination  Assistance  described  in  Annex  N-1  to  a 
potential  Successor  Contractor  and  the  Authority  for  a  Procurement  Process  from  the 
Assistance Commencement Date to the Services Transfer Date at no cost to the Authority.   
7.2 
Expiry of the Term 
In relation to the expiry of the Term (or in respect of part of the Services removed from the 
Contract in circumstances which do not amount to a Termination in accordance with Clause 
43  of  Schedule  B  (Conditions  of  Contract)),  the  Contractor  shall  provide  the  Termination 
Assistance  set  out  in  Annex  N-2  from  the  Assistance  Commencement  Date  to  the  Services 
Transfer Date as part of the Service Charges.   
7.3 
Termination Assistance after the Services Transfer Date 
Where, at any time after the applicable Services Transfer Date, the Contractor: 
7.3.1  makes available any Contractor Personnel who do not transfer to the Authority or a 
Successor  Contractor  in  order  to  facilitate  the  transfer  of  knowledge  and  skills  (as 
described in Clause 2 of Annex N-3); 
7.3.2  provides services or resources (as described in Annex N-3); or 
Schedule N (Exit Strategy) 

Signature Version 
 
Released under FOI in full on 13th December 2005 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 13th December 2005 
7.3.3  provides  any  other  assistance  in  accordance  with  this  Schedule  after  the  Services 
Transfer  Date,  including  without  limitation  to  the  obligations  under  the  Exit  Plan 
and/or any agreed Services Transition Plan.  
The  Contractor  shall  be  entitled  to  charge  the  Authority  or  the  Successor  Contractor,  as 
applicable,  for  such  assistance  at  the  prevailing  contractual  rates  set  out  in  Schedule  E 
(Pricing) for a period of up to twelve (12) months starting on the Services Transfer Date. 
7.4 
Termination 
The  provisions  of  Clauses  7.1  to  7.3  above  shall  be  without  prejudice  to  the  Parties’  rights 
under Clause 44 of Schedule B (Conditions of Contract) if:   
7.4.1  there is a Termination by the Authority in accordance with Clauses 43.1.1 or 43.1.2 of  
Schedule B (Conditions of Contract); or  
7.4.2  there is a Termination by the Contractor in accordance with Clause 43.2 of Schedule 
B (Conditions of Contract).  
Schedule N (Exit Strategy) 

Signature Version 
 
Released under FOI in full on 13th December 2005 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 13th December 2005 
ANNEX N-1 
 
ASSISTANCE WITH A PROCUREMENT PROCESS 
1. 
GENERAL CO-OPERATION DURING THE PROCUREMENT PROCESS  
1.1 
Whenever it is notified that the Authority is going to re-tender the Services or any part of the 
Services,  the  Contractor  shall  co-operate  (fully  and  in  good  faith)  with  the  Procurement 
Process. 
1.2 
With  effect  from  the  Assistance  Commencement  Date  of  the  Procurement  Process  until  the 
Services  Transfer  Date,  the  Contractor  shall  provide  to  the  Authority  such  Information  and 
other  co-operation  regarding  the  Contractor’s  provision  of  the  Services  (as  and  when 
reasonably requested by the Authority unless otherwise specified in this Annex, including for 
the purposes of providing Information to any bidders involved in the Procurement Process so 
that they can carry out a due diligence exercise) as would be reasonably necessary for a third 
party to: 
1.2.1  prepare an informed, non-qualified offer for those Services; and  
1.2.2  not be disadvantaged in the Procurement Process compared to the Contractor (if the 
Contractor is invited to participate).  
1.3 
Where  used  in  this  Clause  1,  “Information”  shall  mean  any  written  or  oral  information 
(including information for due diligence purposes) which is material in detail or in substance 
and which describes the nature of any of the Services provided to the Authority or the method 
by which those Services are provided by the Contractor.   
1.4 
With effect from the date on which the Authority publishes official notice of the Procurement 
Process,  or  with  effect  from  the  date  on  which  the  Contractor  notifies  the  Authority  of  an 
intention to bid pursuant to the Procurement Process (whichever is the earlier), the Contractor 
shall  ensure  that  (except  with  the  Authority’s  prior  written  consent)  no  individual  who 
participates in its Operations Team is also a member of (nor is transferred into) its bid team in 
respect of the services covered by the Procurement Process.  
1.5 
At  the  reasonable  request  of  the  Authority  and  subject  to  the  relevant  potential  Successor 
Contractor entering into an appropriate confidentiality undertaking with the Contractor, such 
potential  Successor  Contractor  shall  be  entitled  to  carry  out  a  site  visit  on  any  of  the 
Contractor’s sites being used in the delivery of the Services. 
2. 
CONTRACTOR PERSONNEL 
2.1 
The Contractor shall comply with its obligations to provide Information about its Contractor 
Personnel as described in Clause 6 of Schedule M (HR and TUPE). 
2.2 
Notwithstanding Clause 2.1 of this Annex N-1, the Parties agree that Information relating to 
the  Contractor  Personnel  Costs  shall,  at  a  minimum,  be  broken  down  by  reference  to 
organisational  groupings  and  full-time  equivalent  positions  and  other  relevant  detailed 
information  reasonably  required  by  a  third  party  to  make  an  unqualified  bid  to  provide 
services that are similar to the Services.  
3. 
THIRD PARTY CONTRACTS 
3.1 
Within  one  (1)  month  of  the  Assistance  Commencement  Date,  the  Contractor  shall  provide 
the  Authority  with  an  up-to-date  list  of  the  Third  Party  Contracts  identified  in  Schedule  S 
Schedule N (Exit Strategy) 

Signature Version 
 
Released under FOI in full on 13th December 2005 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 13th December 2005 
(Software,  IPR  and  Third  Party  Contracts).    With  effect  from  the  Assistance 
Commencement Date, the Contractor shall notify the Authority of any material changes to the 
Third Party Contracts identified in Schedule S (Software, IPR and Third Party Contracts) 
which may adversely impact the provision of any of the Services and shall consult with the 
Authority regarding such proposed material changes. 
4. 
INTELLECTUAL PROPERTY RIGHTS  
4.1 
With  effect  from  the  Assistance  Commencement  Date,  the  Contractor  shall  not  make  any 
material  changes  in  the  position  as  regards  the  Intellectual  Property  Rights  and/or  Software 
created or used during the provision of any of the Services, which may adversely impact the 
provision  of  any  of  the  Services  without  first  obtaining  the  prior  written  consent  of  the 
Authority regarding such proposed material changes. 
4.2 
The  Contractor  shall  maintain  and  update  a  list  of  all  relevant  Software  (including  any 
Intellectual  Property  Rights  therein)  created  or  used  by  the  Contractor,  including  any  Work 
Product  created  during  the  Term,  and  shall  provide  such  list  within  one  (1)  month  of  the 
Assistance  Commencement  Date  for  the  Procurement  Process.    Such  list  of  Software  shall 
also include the Software listed in Schedule S (Software, IPR and Third Party Contracts). 
5. 
ASSETS  
5.1 
The  Contractor  shall  maintain  a  list  of  all  Assets  used  in  relation  to  the  delivery  of  the 
Services  whether  Contractor-owned  or  Contractor-leased  and  shall  provide  such  list  to  the 
Authority within one (1) month of the Assistance Commencement Date for the Procurement 
Process.  This list will be a snapshot in time and is subject to change. 
5.2 
The  Parties  shall  agree  the  level  of  detail  and  content  to  be  provided  by  the  Contractor  in 
connection  with  the  list  referred  to  in  Clause  5.1  of  this  Annex  N-1.    Notwithstanding  the 
foregoing, the Parties agree that the list shall include, as reasonable, the items listed in Clause 
4.2 of Schedule T (Assets). 
5.3 
If  the  Contractor  wishes  to  provide  any  of  the  Services  through  the  use  of  Assets  not 
exclusively  dedicated  to  the  Services,  it  shall  first  obtain  the  prior  written  consent  of  the 
Authority (which consent shall not be unreasonably withheld).  
6. 
USE OF SERVICES INFORMATION 
6.1 
The  lists  and  information  to  be  compiled  and  provided  pursuant  to  Clauses  2  to  5  of  this 
Annex N-1 as well as any information obtained during the Term, including volumes, Service 
Level  information,  system  information  and  the  relevant  documentation  may  be  used  by  the 
Authority  at  any  time  for  its  or  any  potential  Successor  Contractor’s  information  (and,  in 
particular, may be disclosed by the Authority at any time as part of its Procurement Process), 
subject  to  the  appropriate  confidentiality  undertakings  being  given  and  put  in  place  by  any 
potential Successor Contractor.   
7. 
DISPUTES 
7.1 
During any Procurement Process, the Contractor shall maintain and update a list of on-going 
and/or threatened disputes with third parties in relation to the provision of the Services and/or 
Third  Party  Contracts,  and  shall  use  its  Commercially  Reasonable  Efforts  to  resolve  such 
disputes. 
7.2 
During any Procurement Process, the Contractor shall not settle disputes in Clause 7.1 above 
with a third party, nor accept any liability (either on its own behalf or that of the Authority) 
Schedule N (Exit Strategy) 

Signature Version 
 
Released under FOI in full on 13th December 2005 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 13th December 2005 
without  obtaining  the  Authority’s  prior  written  consent  (which  consent  shall  not  be 
unreasonably withheld). 
Schedule N (Exit Strategy) 

Signature Version 
 
Released under FOI in full on 13th December 2005 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 13th December 2005 
ANNEX N-2  
 
ASSISTANCE IN THE PERIOD PRIOR TO THE TERMINATION DATE 
1. 
INTRODUCTION 
1.1 
This  Annex  N-2  sets  out the Termination  Assistance  to be  provided  by  the  Contractor from 
the Assistance Commencement Date to the Services Transfer Date if there is a Termination or 
a removal of any of the Services from the Contract in accordance with Clause 43 of Schedule 
B (Conditions of Contract). 
1.2 
The  Contractor  shall  use  its  Commercially  Reasonable  Efforts  to  minimise  the  Authority’s 
costs and management time resulting from any Termination or removal of the Services (as the 
case  may  be)  and  to  minimise  the  implementation  time  for  the  agreed  Exit  Plan  and/or 
Services Transition Plan.  
2. 
TRANSITION PLANNING  
2.1 
Within fourteen (14) days of the applicable Assistance Commencement Date, the Contractor 
shall  provide  the  Authority  with  a  draft  Exit  Plan.  At  a  minimum,  the  draft  Exit  Plan  shall 
contain provisions covering the items listed in the Outline Exit Plan as set out in Annex N-4. 
2.2 
The Authority will respond within seven (7) days with its comments on the draft Exit Plan. 
2.3 
The Contractor shall respond to any of the Authority’s suggestions to improve or amend the 
draft Exit Plan within seven (7) days of receipt of the same.  Unless otherwise agreed, within 
four  (4)  weeks  of  the  Assistance  Commencement  Date,  the  Parties  shall  meet  to  discuss  in 
good faith and agree the final form Exit Plan.  
2.4 
The Parties shall review and update the Exit Plan quarterly throughout the Exit Period, on the 
rolling  tri-monthly  anniversary  of  the  Assistance  Commencement  Date,  to  ensure  that  it 
remains relevant.  
2.5 
On  the  appointment  of  a  Successor  Contractor,  the  Contractor  shall  commence  discussions 
with the Authority and the Successor Contractor concerning a detailed transition plan, to be 
based on the Exit Plan agreed by the Contractor and the Authority, with a view to the Services 
Transition  Plan  being  agreed  and  finalised  at  least  six  (6)  months  prior  to  the  Termination 
Date.  
2.6 
The  final  form  of  the  Services  Transition  Plan  shall  be  agreed  between  the  Parties  after 
consultation  with  the  Successor  Contractor  (if  any)  and  shall  only  become  effective  once 
approved in writing by the Authority.  The Contractor shall then commence implementation 
of the Services Transition Plan.  The approved Services Transition Plan shall be incorporated 
into  this  Contract  as  an  Annex  to  this  Schedule  as  soon  as  reasonably  practicable  after  the 
Authority’s approval.   
3. 
GENERAL TERMINATION ASSISTANCE 
3.1 
Both  Parties  shall  comply  fully  with  their  obligations  under  the  Exit  Plan  and/or  Services 
Transition Plan and this Schedule. 
3.2 
Both Parties shall appoint a suitable representative (“Exit Manager”) to manage the process 
of transition on a day-to-day basis. The appointment of the Contractor’s Exit Manager shall 
be  subject  to  the  Authority’s  prior  approval  (which  approval  will  not  be  unreasonably 
withheld). 
Schedule N (Exit Strategy) 

Signature Version 
 
Released under FOI in full on 13th December 2005 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 13th December 2005 
3.3 
The  Contractor’s  Termination  Assistance  may  include  training  for  the  Authority  and/or  the 
Successor Contractor personnel, consultants or subcontractors, as agreed. 
3.4 
If  the  Contractor  fails  to  comply  with  any  of  its  obligations  with  respect  to  the  Exit  Plan 
and/or Services Transition Plan, it shall arrange (at its own cost) all such additional resources 
as are necessary to fulfil the applicable obligation as soon as reasonably practicable. 
3.5 
Unless otherwise agreed, the Contractor shall be responsible for the overall management of all 
the transfer and exit activities envisaged in this Schedule and the Contractor shall: 
3.5.1  keep the tasks on schedule in accordance with any timetable set out in the Exit Plan 
and/or Services Transition Plan; and  
3.5.2  identify  and  resolve,  or  assist  the  Authority  and  the  Successor  Contractor  in  the 
resolution  of,  any  problems  encountered  in  the  timely  completion  of  each  task 
identified  in  the  Exit  Plan  and/or  Services  Transition  Plan,  whether  the  task  is  the 
responsibility of the Contractor or not. 
4. 
SUCCESSOR CONTRACTOR SHADOWING 
4.1 
If  a  party  other  than  the  Contractor  is  appointed  as  a  Successor  Contractor,  the  Contractor 
agrees to reasonably co-operate with the Authority and the Successor Contractor, as directed 
by the Authority, in relation to arrangements to effect a smooth transfer of the Services, the 
Transferring  Employees  and  the  Core  Personnel.    Such  co-operation,  subject  to  appropriate 
confidentiality  provisions  being  put  in  place  and  the  Data  Protection  Act,  shall  include 
reasonably  assisting  the  Successor  Contractor  to  familiarise  itself  as  to  the  method  of 
provision of those Services in the period prior to the Services Transfer Date. In particular, the 
Contractor agrees that in the six (6) month period prior to the Services Transfer Date, it shall 
allow the Successor Contractor reasonable access to:  
4.1.1  its facilities used to provide the Services (subject to compliance by the Authority and 
the Successor Contractor with any applicable security restrictions and confidentiality 
undertakings being put in place);  
4.1.2  the Contractor Personnel; and  
4.1.3  such Information as the Authority may deem necessary to ensure a seamless transfer 
of the relevant Services on the Services Transfer Date. 
4.2 
During the six (6) months prior to the Services Transfer Date, the Contractor agrees to allow 
the Authority and/or Successor Contractor’s personnel, as directed by the Authority, to work 
alongside the Contractor, so that: 
4.2.1  the Authority and/or Successor Contractor, as directed by the Authority,  can observe 
the  provision  of  the  relevant  Services  and  prepare  for  the  transition  of  the  Services 
from the Contractor; 
4.2.2  the  facilitation  of  knowledge  transfer  from  the  Contractor  to  the  Authority  and/or 
Successor Contractor, as directed by the Authority, occurs as early as possible; and 
4.2.3  the  Authority  and  the  Successor  Contractor,  as  directed  by  the  Authority,  can 
participate in decisions that will affect the Services after the Services Transfer Date.  
4.3 
The Contractor shall make available (to the extent that it does not impact upon the delivery of 
the Service) sufficient numbers of suitably experienced and skilled Contractor Personnel for 
Schedule N (Exit Strategy) 

Signature Version 
 
Released under FOI in full on 13th December 2005 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 13th December 2005 
such time as is reasonably necessary during the six (6) month period described in Clause 4.2 
of  this  Annex  N-2,  to  explain  relevant  procedures  and  operations  (including  management 
processes  and  other  standards  and  procedures)  to  the  operations  personnel  of  the  Authority 
and/or Successor Contractor, as directed by the Authority.  
4.4 
The  information  and  assistance  which  the  Contractor  shall  provide  to  the  Authority  and/or 
Successor Contractor, as directed by the Authority, under Clause 4 of this Annex N-2 shall, 
subject to any confidentiality obligations or licence restrictions to which the Contractor may 
be subject, as a minimum include: 
4.4.1  available  product  information  and  detailed  system  documentation,  including  user 
manuals,  technical  manuals,  operations  procedures  and  applicable  vendor 
correspondence; 
4.4.2  relevant available information about proprietary products, tools and methods; 
4.4.3  information about current project work; 
4.4.4  copies  of  Third  Party  Contracts  which  are  to  be  transferred  to  the  Successor 
Contractor; and 
4.4.5  information regarding unresolved faults in the Contractor’s Solution in progress at the 
commencement  of  the  Termination  Assistance  as  well  as  those  expected  to  be  in 
progress at the Services Transfer Date.  
This information shall be updated by the Contractor at the Services Transfer Date.  
After the appointment of the Successor Contractor, the Authority may be accompanied by the 
Successor  Contractor  at  project  meetings  with the  Contractor  regarding  the  provision  of  the 
Services.  The Contractor shall also consult the Authority (and allow the Authority to involve 
the Successor Contractor) about planned changes to the provision of any of the Services.  
5. 
SECURITY 
The  Contractor  shall  continue  to  comply  with  its  security  obligations  in  accordance  with 
Schedule K (Security) in carrying out its obligations under this Schedule.  
6. 
ASSETS 
6.1 
The  Contractor  shall  sell  or  transfer  the  Assets  to  the  Authority  and/or  the  Successor 
Contractor in accordance with Clause 21 of Schedule B (Conditions of Contract) and Clause 
5 or 6 of Schedule T (Assets), as applicable.  
6.2 
Within four (4) weeks from the commencement of the Exit Period, the Parties shall agree the 
contents of the physical Asset list (a snapshot in time), being maintained by the Contractor in 
accordance  with  Clause  5  of  Annex  N-1.  The  list  shall  include  details  of  all  Assets,  as  is 
reasonable, in addition to the list of items identified in Clause 4.2 of Schedule T (Assets).  
6.3 
The Contractor shall then freeze the Asset list and update it (with the Authority’s prior written 
consent, which consent shall not be unreasonably withheld) only as and when Asset changes 
are required in order to continue the Services in the Ordinary Course of Business.  
6.4 
The  Contractor  shall  provide  copies  of  the  Asset  list  to  the  Authority  and/or  any  Successor 
Contractor, whenever requested by the Authority. 
Schedule N (Exit Strategy) 
10 
Signature Version 
 
Released under FOI in full on 13th December 2005 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 13th December 2005 
6.5 
Subject  to  Clause  2.4  of  Schedule  T  (Assets),  the  Parties  shall  agree  the  treatment  of  any 
Assets that are not used exclusively in the performance of the Services.  
7. 
REPORTING DURING THE EXIT PERIOD 
The Contractor shall provide progress reports detailing the status of the exit tasks as against 
the  Exit  Plan  and/or  Services  Transition  Plan  (as  applicable),  setting  out  any  actual  or 
anticipated  problems  or  delays  and  the  actions  that  the  Contractor  is  taking  to  resolve  such 
problems 
8. 
THIRD PARTY CONTRACTS 
8.1 
Within four (4) weeks from the commencement of the Exit Period, the Parties shall agree the 
contents of the Third Party Contracts list as set out in Schedule S (Software, IPR and Third 
Party Contracts) being maintained by the Contractor in accordance with Clause 3 of Annex 
N-1.  The Contractor shall then freeze the Third Party Contracts list and shall update it (with 
the Authority’s prior written consent, which consent shall not be unreasonably withheld) only 
as and when changes are required in order to continue the Services in the Ordinary Course of 
Business. 
8.2 
During  the  Exit  Period  and  in  accordance  with  the  Exit  Plan,  the  Contractor  shall  not  vary, 
terminate, assign, novate, purport to vary, nor allow any of the listed Third Party Contracts to 
expire without the Authority’s prior written consent, which consent shall not be unreasonably 
withheld. 
8.3 
The  Contractor  shall  provide  a  list  of  the Third  Party  Contracts  to  the  Authority  and/or  any 
Successor Contractor, as directed by the Authority, if requested by the Authority during the 
Exit Period.  
8.4 
As part of the planning process for the implementation of the Exit Plan and, if any, Services 
Transition Plan, the Parties shall agree which of the Third Party Contracts (if any) need to be 
assigned,  novated  or  otherwise  transferred  from  the  Contractor  to  the  Authority  and/or 
Successor Contractor.  
8.5 
The  Contractor  shall  liase  with  the  relevant  third  parties  to  ensure  the  successful  transfer, 
assignment  or  novation  (as  required)  of  the  Third  Party  Contracts,  including  obtaining  any 
transfer,  assignment  or  novation  agreements  (as  applicable)  in  a  comparable  form  that  is 
acceptable to the Authority.  
8.6 
The  Contractor  shall  also  ensure  that  the  benefits  of  all  warranties,  indemnities  and  similar 
protections under the Third Party Contracts shall pass to the Authority and/or the Successor 
Contractor (as the case may be).  
8.7 
Any  fees  due  in  connection  with  the  transfer  of  the  Third  Party  Contracts  shall  be  paid  in 
accordance with Clause 43 and 44 (as applicable) of Schedule B (Conditions of Contract). 
8.8 
At  any  time  during  the  twelve  (12)  months  prior  to  the  Services  Transfer  Date,  if  the 
Contractor  proposes  to  make  any  material  changes  to  any  Third  Party  Contract  which  may 
have a materially adverse impact on the provision of any of the Services, it agrees to notify 
the Authority. 
9. 
INTELLECTUAL PROPERTY RIGHTS 
9.1 
The  Contractor  shall  maintain  and  update  a  list  of  all  relevant  Software  (including  any 
Intellectual  Property  Rights  therein)  created  or  used  by  the  Contractor,  including  any  Work 
Schedule N (Exit Strategy) 
11 
Signature Version 
 
Released under FOI in full on 13th December 2005 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 13th December 2005 
Product  created  during  the  Term,  and  shall  provide  such  list  within  one  (1)  month  of  the 
commencement of the Exit Period for the Procurement Process.  Such list of Software shall 
also include the Software listed in Schedule S (Software, IPR and Third Party Contracts). 
9.2 
The Contractor shall grant the licences described in Clause 29 of Schedule B (Conditions of 
Contract) and provide the Authority and/or the Successor Contractor (as applicable) with a 
copy of the Source Code in accordance with the escrow provisions in Clause 29.7 of Schedule 
B (Conditions of Contract).  
10. 
RESTRICTIONS PRIOR TO TERMINATION 
10.1 
The Contractor shall maintain an open and proactive communication line with the Contractor 
Personnel.  
10.2 
From the Assistance Commencement Date, the Contractor shall comply with its obligations in 
Clause 7 of Schedule M (HR and TUPE). 
11. 
DISPUTES 
11.1 
During  the  Exit  Period,  the  Contractor  shall  maintain  and  update  a  list  of  on-going  and/or 
threatened  disputes  with  third  parties  in  relation  to  any  of  the  Services  or  Third  Party 
Contracts, and shall use its Commercially Reasonable Efforts to resolve such disputes. 
11.2 
During any Procurement Process, the Contractor shall not settle disputes in Clause 11.1 above 
with a third party, nor accept any liability (either on its own behalf or that of the Authority) 
without obtaining the Authority’s prior written consent (which consent shall not be 
unreasonably withheld).
Schedule N (Exit Strategy) 
12 
Signature Version 
 
Released under FOI in full on 13th December 2005 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 13th December 2005 
ANNEX N-3 
 
TERMINATION AND TRANSITION TO THE SUCCESSOR CONTRACTOR 
1. 
INTRODUCTION 
This  Annex  sets  out  the  Termination  Assistance  to  be  provided  by  the  Contractor  to  the 
Successor Contractor as directed by the Authority from the Termination Date. 
2. 
AVAILABILITY OF THE CONTRACTOR PERSONNEL AFTER TERMINATION 
2.1 
Notwithstanding the provisions of Clause 44.1 of Schedule B (Conditions of Contract), on 
or after the Termination Date, and at the Successor Contractor’s request, the Contractor shall 
make available to the Successor Contractor, for the continued support of the Services on a full 
time basis or any other basis as may be agreed between the Contractor, the Authority or the 
Successor  Contractor,  any  Contractor  Personnel  (including,  for  the  avoidance  of  doubt,  any 
Core Personnel) who do not transfer to the Authority or a Successor Contractor in accordance 
with TUPE or for any reason, for a period of not greater than twelve (12) months following 
termination of the Contract. 
2.2 
Such  availability  of  the  Contractor  Personnel  shall  be  provided  as  reasonable  in  order  to 
facilitate  the  transfer  of  knowledge  and  skills  in  relation  to  providing  the  Services  to  the 
Successor Contractor’s personnel as directed by the Authority, as shall be necessary to ensure,  
uninterrupted continuity in the provision of the Services. 
2.3 
Upon  expiry  or  termination  of  the  Contract  and  at  the  direction  of  the  Authority,  the 
Contractor shall return to the Authority or destroy the Authority Data, the Authority Personal 
Data,  applicable  Material,  Software,  Work  Product  and  Equipment  and/or  return  to  the 
Authority or destroy any other third party data, as may be designated by the Authority. 
3. 
TRANSFERRED AND PURCHASED ASSETS 
3.1 
In the event that the Contractor transfers Assets to the Successor Contractor as directed by the 
Authority in accordance with Schedule T (Assets), it shall provide, as reasonable: 
3.1.1  all relevant documentation, user manuals and other such information;  
3.1.2  suitable warranties regarding condition and title; and 
3.1.3  that all leasing, rental or other similar arrangements have been fully terminated so that 
full and unencumbered title is passed. 
3.2 
The  Contractor  shall  certify  to  the  Successor  Contractor  that  it  has  complied  with  its 
obligations under this Clause 3, in such format as the Authority shall reasonably request. 
4. 
INTELLECTUAL PROPERTY RIGHTS 
4.1 
With effect from the end of the Termination Date or date of removal of the relevant Services, 
the Contractor shall cease all use of, and either destroy or return (at the Authority’s option), 
the  Authority  Software  and  the  Authority  Materials  (and  all  Intellectual  Property  Rights 
therein).  
4.2 
Upon request from the Authority to do so, the Contractor shall confirm in writing that it has 
complied in full with its obligations under Clause 4.1 of this Annex N-3. 
Schedule N (Exit Strategy) 
13 
Signature Version 
 
Released under FOI in full on 13th December 2005 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 13th December 2005 
ANNEX N-4 
 
OUTLINE EXIT PLAN 
The Contractor shall provide a suggested format for the Outline Exit Plan to cover, as a minimum, the 
following areas: 
1. 
THE CONTRACTOR ACTIVITIES 
1.1 
The Contractor shall provide, as reasonable, further details:  
1.1.1  of  how  the  transition  of  the  Services  will  be  managed  and  conducted  and  the 
information required to support this; and 
1.1.2  describing how each relevant part of the Services will be transferred.  
2. 
MANAGEMENT AND INFORMATION REQUIREMENTS 
2.1 
The Contractor shall provide, as reasonable: 
2.1.1  all  information  for  governance  and  reporting  arrangements  including  project 
management,  escalation  and  notification,  Change  Control  Procedures,  approval, 
quality control, risk and issues management and actions management; 
2.1.2  a fully populated and resourced project plan; 
2.1.3  a completed risk and issues logs; 
2.1.4  provision  of  information  and  data  (including  for  relevant  staff  and  the  overall 
Contractor’s Solution); 
2.1.5  details of where information and data is stored and/or available; 
2.1.6  an outline of dependencies and interoperability of subject areas; 
2.1.7  the Authority resources required to enact the Outline Exit Plan, (e.g., by types, skills, 
numbers and timeframes); and 
2.1.8  details of relevant review processes. 
3. 
SERVICE AND STAFF ITEMS 
3.1 
In  relation  to  the  transition  of  the  Services  to  the  Successor  Contractor  as  directed  by  the 
Authority, the Contractor shall detail, as reasonable: 
3.1.1  how  and  when  each  of  the  Services  will  transfer  with  minimal  disruption  and  how 
each  Service  will  be  provided  throughout  the  transfer  in  a  secure  environment, 
disaster  recovery  arrangements  and  arrangements  to  ensure  a  seamless  transfer  of 
Services to the Successor Contractor, including those with external interfaces; 
3.1.2  transfer of the technical infrastructure; 
3.1.3  operational environments; 
3.1.4  Asset tracking and recording methods; 
Schedule N (Exit Strategy) 
14 
Signature Version 
 
Released under FOI in full on 13th December 2005 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 13th December 2005 
3.1.5  what infrastructure Assets will transfer including application software; 
3.1.6  when and how these Assets transfer; 
3.1.7  what specific security tasks are necessary at Termination; 
3.1.8  migration of data; and 
3.1.9  staff transfer. 
3.2 
Without  prejudice  to  the  Contractor’s  obligations  in  Schedule  M  (HR  and  TUPE),  the 
Contractor  shall  provide  details  of  the  TUPE  consultation  and  notification  processes  and  a 
plan defining the key steps within a TUPE transfer. 
3.3 
In respect of Assets, the Contractor shall provide, details of:   
3.3.1  original purchase price and date of purchase; 
3.3.2  the level of depreciation to date; 
3.3.3  any leasing or other finance arrangements in place;  
3.3.4  the existing status of ownership of legal title;  
3.3.5  whether the Assets are used solely in the performance of the Services;  
3.3.6  IT equipment and software transfer; 
3.3.7  non-IT equipment transfer; 
3.3.8  transfer/novation and expiry of software licences; 
3.3.9  escrow arrangements; 
3.3.10  apportionment and reconciliation of fees paid for any licences; and 
3.3.11  any other relevant information. 
3.4 
The  Contractor  shall  effect  Intellectual  Property  Rights  transfers  by  carrying  out  the 
following: 
3.4.1  identification of each Parties' Intellectual Property Rights; and 
3.4.2  processes  and  responsibilities  for  transfer  of  licences  to  use  and  ownership  of 
Intellectual Property Rights.  
3.5 
In  relation  to  the  Contractor  Premises,  the  Contractor  shall  provide  a  definition  of  the 
processes required to transfer occupation of such premises, including information, relating to: 
3.5.1  leases; 
3.5.2  rates; and 
3.5.3  utilities. 
3.6 
For Third Party Contracts, the Contractor shall provide: 
Schedule N (Exit Strategy) 
15 
Signature Version 
 
Released under FOI in full on 13th December 2005 

PITO 
IDENT1 CONTRACT 
Northrop Grumman 
 
Released under FOI in full on 13th December 2005 
3.6.1  contract identification; 
3.6.2  notifications of intent to assign/novate; and 
3.6.3  transfer request. 
3.7 
For  communications,  the  Contractor  shall  provide  reasonable  support  to  the  Authority  in 
preparing  and  disseminating  communications  material  for  key  stakeholders  and  external 
customers. 
Schedule N (Exit Strategy) 
16 
Signature Version 
 