| | LOCAL AUTHORITY PFI PROJECTS | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | |
| | Updated: August 2008 | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | |
| | The value of central government support is shown in terms of PFI credits. This is the (real) value of the private sector capital investment incurred during the life of the contract towards which support is directed. It is not the full value of projects, nor is it the value of the grant actually provided to the local authorities.
Each tranche of a Building Schools for the Future (BSF) contract is here treated as a separate project. | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | |
| | ENDORSED: Projects which have been agreed by Project Review Group (or the equivalent panel ion the case of BSF projects) to be ready to enter into procurement, but where contracts have not yet been signed. The PFI credit value may change during the procurement process for a variety of reasons, but should be more fixed than pipeline projects. | | | | | | | | | | | | | | | |
| | Click here to move to the list of endorsed projects - arranged in order of endorsement, with the most recent at the top. | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | |
| | PIPELINE: Projects which have been invited to work up an outline business case. The PFI credit value may be more or less subject to variation (depending on the type of project) before the level is more formally set at endorsement. | | | | | | | | | | | | | | | |
| | Click here to move to the list of pipeline projects - arranged by sponsoring department. | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | |
| | SIGNED: Projects where the contract has been signed, but which are not yet operational.
OPERATIONAL: Projects where services are being delivered from at least some of the assets built or transferred. | | | | | | | | | | | | | | | |
| | Click here to move to the list of endorsed projects - arranged in alphabetical order. | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | |
| PROJECT ANALYSIS | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | |
| | Number of projects | Progress | | | | | | | | | | | | | | | | | | | | | | | |
| | Sponsoring Department(s) | Pipeline | Endorsed | Signed | Operational | Ended | Total | | | | | | | | | | | | | | | | | | |
| | DCSF | 9 | 31 | 19 | 95 | | 154 | | | | | | | | | | | | | | | | | | |
| | DCSF & CLG Other | | | | 9 | | 9 | | | | | | | | | | | | | | | | | | |
| | DCSF & DCMS | | | | 4 | | 4 | | | | | | | | | | | | | | | | | | |
| | DfT | 6 | 12 | | 23 | | 41 | | | | | | | | | | | | | | | | | | |
| | CLG Housing | 4 | 13 | 2 | 18 | | 37 | | | | | | | | | | | | | | | | | | |
| | CLG Housing & DH | | | 2 | 2 | | 4 | | | | | | | | | | | | | | | | | | |
| | CLG Fire | 1 | 4 | 1 | 7 | | 13 | | | | | | | | | | | | | | | | | | |
| | CLG Other | 4 | 5 | 4 | 16 | 3 | 32 | | | | | | | | | | | | | | | | | | |
| | DEFRA | 16 | 11 | | 18 | | 45 | | | | | | | | | | | | | | | | | | |
| | HO | 4 | 1 | | 20 | | 25 | | | | | | | | | | | | | | | | | | |
| | HO & CLG Fire | | | 1 | | | 1 | | | | | | | | | | | | | | | | | | |
| | DH | 2 | 4 | 1 | 12 | | 19 | | | | | | | | | | | | | | | | | | |
| | DH & CLG Other | | | | 1 | | 1 | | | | | | | | | | | | | | | | | | |
| | DCMS | | 3 | 1 | 10 | | 14 | | | | | | | | | | | | | | | | | | |
| | DCMS & CLG Other | 1 | 2 | 1 | 1 | | 5 | | | | | | | | | | | | | | | | | | |
| | Total | 47 | 86 | 32 | 236 | 3 | 404 | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | |
| | PFI credits (£ million) | Progress | | | | | | | | | | | | | | | | | | | | | | | |
| | Sponsoring Department | Pipeline | Endorsed | Signed | Operational | Ended | Grand Total | | Allocation | Unallocated | | | | | | | | | | | | | | | |
| | DCSF | 1128.389 | 2540.241 | 1566.636 | 4080.753586 | | 9316.019586 | | 11853 | 2536.980414 | | | | | | | | | | | | | | | |
| | DfT | 1868.7 | 1837.3 | | 958.307493 | | 4664.307493 | | 5988.9 | 1324.592507 | | | | | | | | | | | | | | | |
| | CLG Housing | 335 | 1155.7 | 179.734 | 1068.240483 | | 2738.674483 | | 4625.8 | 1887.125517 | | | | | | | | | | | | | | | |
| | CLG Fire | 52 | 190.3 | 54.82 | 120.947 | | 418.067 | | 549.6 | 131.533 | | | | | | | | | | | | | | | |
| | CLG Other | 35.534 | 113.185 | 27.289 | 253.8628 | 12.248 | 442.1188 | | 452.7 | 10.5812 | | | | | | | | | | | | | | | |
| | DEFRA | 1571.6 | 843.5 | | 786.851 | | 3201.951 | | 3280.1 | 78.1489999999999 | | | | | | | | | | | | | | | |
| | HO | 489.7 | 87.234 | 29.7 | 489.503297 | | 1096.137297 | | 1289.8 | 193.662703 | | | | | | | | | | | | | | | |
| | DH | 45.9 | 116.91 | 56.226 | 197.907171 | | 416.943171 | | 964.4 | 547.456829 | | | | | | | | | | | | | | | |
| | DCMS | 1.5 | 149.18 | 57.924 | 148.621103 | | 357.225103 | | 380.7 | 23.474897 | | | | | | | | | | | | | | | |
| | Grand Total | 5528.323 | 7033.55 | 1972.329 | 8104.993933 | 12.248 | 22651.443933 | | 29385 | 6733.556067 | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | |
| ENDORSED PROJECT DETAILS | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | |
| | Cambridgeshire & Northamptonshire: Street Lighting | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 145800000 | Date endorsed: | 39630 | | | | | | | | | | | | | | | |
| | Description: | The replacement of existing streetlight columns, illuminated signs, bollards and beacons, plus the installation of additional columns during an initial 5-year capital programme. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Martin Pettitt, 01604 236 524, [email address] | | | | | | | | | | | | | | | |
| | South Tyne & Wear Waste Partnership: Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 73500000 | Date endorsed: | 39630 | | | | | | | | | | | | | | | |
| | Description: | The South Tyne and Wear Waste Management Partnership (STWWMP) was established to enable the three partner authorities to jointly procure solutions for the treatment and disposal of residual municipal waste. The Partnership comprises three metropolitan councils, Gateshead, South Tyneside and Sunderland. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Alan Townsend 0191 433 7269 [email address] | | | | | | | | | | | | | | | |
| | Staffordshire: Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 122400000 | Date endorsed: | 39630 | | | | | | | | | | | | | | | |
| | Description: | Project W2R constitutes the design, construction and operation by 2013 of a 300,000tpa EfW plant to convert residual waste from the authorities of Staffordshire (lead), Warwickshire, Walsall and Sandwell primarily into electricity. This facility will be for the treatment of residual waste only, following kerbside and other recycling activities. Options to develop combined heat and power and further recycling have been assessed for technical and financial feasibility and will be explored further during the procourement process. Value of capital estimated at £151 million. The full capacity ofthe W2R plant will therefore be used for municipal waste. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Joy Currey 01785 276548 [email address] | | | | | | | | | | | | | | | |
| | Lancashire, Merseyside & Cumbria Fire Authorities: North West Fire and Rescue Authorities (NWFRA) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Fire | PFI credits: | 66400000 | Date endorsed: | 39600 | | | | | | | | | | | | | | | |
| | Description: | 16 Community Fire Stations on a mixture of new and existing sites in the North West of England (with Merseyside acting as lead Authority). The proposed locations are: Cumbria - Carlisle East, Carlisle West, Patterdale, Penrith (incorporating County Council Emergency Planning Unit & Emergency Control Room), and Workington; Lancashire - Blackburn, Burnley, Chorley, and Fleetwood; Merseyside - Belle Vale, Birkenhead, Bootle/Netherton, Formby, Kirkdale (incorporating Operational Resource Centre), Newton le Willows, and Southport (including an ambulance station with North West Ambulance Service as a partner). | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Colin Schofield, 0151 296 4203, [email address]
Lorraine Clarke, 0151 296 4231, [email address] | | | | | | | | | | | | | | | |
| | North Tyneside: Sheltered housing | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing | PFI credits: | 112400000 | Date endorsed: | 39600 | | | | | | | | | | | | | | | |
| | Description: | The scheme will cover all the Council’s sheltered housing on 32 sites across the Borough. It will refurbish 12 sheltered housing schemes, re-develop 13 schemes as new build and release 7 sites for development by the contractor. The overall number of apartments will be reduced from 1032 to 945, through the elimination of unpopular bed-sit accommodation and the provision of high quality one and two bedroom apartments. The contractor will be responsible for maintenance and some of the management functions. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Roy Marston, 0191 6437580, [email address] | | | | | | | | | | | | | | | |
| | Blackburn : Building Schools for the Future Phase 2 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 76286000 | Date endorsed: | 39569 | | | | | | | | | | | | | | | |
| | Description: | 0 | | | | | | | | | | | | | | | |
| | Local Authority Contact: | 0 | | | | | | | | | | | | | | | |
| | Blackburn: Building Schools for the Future Phase 1 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 42350000 | Date endorsed: | 39569 | | | | | | | | | | | | | | | |
| | Description: | 0 | | | | | | | | | | | | | | | |
| | Local Authority Contact: | | | | | | | | | | | | | | | | |
| | Barnsley/Doncaster/Rotherham: Waste (EfW) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 77400000 | Date endorsed: | 39508 | | | | | | | | | | | | | | | |
| | Description: | A partnership to procure the infrastructure for the residual waste treatment facilities. The preferred technology is a combination of Energy from Waste (EfW) for Barnsley and Rotherham and Mechanical Biological Treatment (MBT) with Refuse Derived Fuel (RDF) for Doncaster. The project has a 29-year concession. There are separate procurements for recycling, composting, landfill and transfer stations. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Karen Preiss, 07824 351268, [email address] | | | | | | | | | | | | | | | |
| | Barnsley: Joint Service Centre - Hoyland & Darton (LIFT) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Other | PFI credits: | 7830000 | Date endorsed: | 39508 | | | | | | | | | | | | | | | |
| | Description: | Joint services centre facilities in Hoyland and Darton to be developed by Barnsley Community Solutions LIFT Company providing: customer information services(inc. housing & benefits advice); library (Hoyland only); children & family services; adult social services; and a range of health services. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Jeremy Sykes, 01226 774607, [email address] | | | | | | | | | | | | | | | |
| | Bradford: Building Schools for the Future Phase 2 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 198782000 | Date endorsed: | 39508 | | | | | | | | | | | | | | | |
| | Description: | 0 | | | | | | | | | | | | | | | |
| | Local Authority Contact: | | | | | | | | | | | | | | | | |
| | Bradford: Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 62100000 | Date endorsed: | 39508 | | | | | | | | | | | | | | | |
| | Description: | A project to procure a contract to provide for the treatment of residual municipal waste with options within the standard bid to include transfer/transport, up to 2 HWRCs and a potential variant of transferring the trade waste service. The operational phase of the contract will run for up to 25 years. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Jill Campbell, 01274 432017, [email address] | | | | | | | | | | | | | | | |
| | Gloucestershire: Fire | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Fire | PFI credits: | 40000000 | Date endorsed: | 39508 | | | | | | | | | | | | | | | |
| | Description: | The project will deliver four new community fire stations in Cheltenham (2) and Gloucester (2) and a new build community life skills centre. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Peter Thorp, 01452 753221, [email address] | | | | | | | | | | | | | | | |
| | Knowsley: Street lighting | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 32700000 | Date endorsed: | 39508 | | | | | | | | | | | | | | | |
| | Description: | The replacement of existing streetlight columns, illuminated signs, bollards, beacons and subway lights; and the installation of additional columns during an initial 5-year capital programme. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Sue Callister, 0151 443 5819, [email address] | | | | | | | | | | | | | | | |
| | Leeds: HRA, Beeston Hill & Holbeck | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing | PFI credits: | 0 | Date endorsed: | 39508 | | | | | | | | | | | | | | | |
| | Description: | This HRA scheme involves the clearance of around 680 unsustainable, low demand Council homes, reprovision of around 350 new build Council homes and refurbishment of around 290 Council homes in the Beeston and Holbeck area. The contractor will be responsible for the ongoing maintenance of these properties over the contract term. The scheme will also facilitate the development for sale of around 350 homes. The scheme is being jointly procured with the Council’s Little London scheme. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Mark Denton, 0113 214 3930, [email address] | | | | | | | | | | | | | | | |
| | Leeds: Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 68600000 | Date endorsed: | 39508 | | | | | | | | | | | | | | | |
| | Description: | A project to procure a contract to provide treatment of residual municipal waste from household, kerbside and household waste sorting sites in Leeds, with an option of managing and operating a waste transfer station. The operational phase of the contract will run for 24 years. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Andrew Tate, 07891 271746, [email address] | | | | | | | | | | | | | | | |
| | Rochdale: Building Schools for the Future Phase 1 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 37427000 | Date endorsed: | 39508 | | | | | | | | | | | | | | | |
| | Description: | The Rochdale Wave 4 project will use the standard LEP model to procure its single wave BSF project. The project will rebuild, remodel or refurbish its secondary estate of 11 mainstream schools and 2 Pupil Referral Units. 4 schools will be built with funding by PFI credits. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | John Bollington, 01706 925046, [email address] | | | | | | | | | | | | | | | |
| | Rochdale: Building Schools for the Future Phase 2 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 94565000 | Date endorsed: | 39508 | | | | | | | | | | | | | | | |
| | Description: | The Rochdale Wave 4 project will use the standard LEP model to procure its single wave BSF project. The project will rebuild, remodel or refurbish its secondary estate of 11 mainstream schools and 2 Pupil Referral Units. 4 schools will be built with funding by PFI credits. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | John Bollington, 01706 925046, [email address] | | | | | | | | | | | | | | | |
| | Somerset: Building Schools for the Future | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 180442000 | Date endorsed: | 39508 | | | | | | | | | | | | | | | |
| | Description: | 0 | | | | | | | | | | | | | | | |
| | Local Authority Contact: | | | | | | | | | | | | | | | | |
| | Suffolk: Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 102000000 | Date endorsed: | 39508 | | | | | | | | | | | | | | | |
| | Description: | A project for waste infrastructure and residual waste disposal in Suffolk and involves the construction of a residual waste treatment facility. The service being procured through the PFI contract will cover residual waste processing and disposal only. The concession period for the contract is 25 years. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | David Gazeley, 01473 264465, [email address] | | | | | | | | | | | | | | | |
| | Woking: Non HRA Round 4 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing | PFI credits: | 44000000 | Date endorsed: | 39508 | | | | | | | | | | | | | | | |
| | Description: | This non-HRA scheme will deliver 190 new social rented homes. The PFI contractor will be responsible for the building and ongoing management and maintenance of the properties over the length of the contract. The scheme will also facilitate the delivery of around 95 shared ownership units and 190 homes for sale with tenure patterns mixed across the site, which is at Moor Lane. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Paola Capel-Williams, 01483 743257, [email address] | | | | | | | | | | | | | | | |
| | Cambridgeshire: Building Schools for the Future Phase 1 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 61553000 | Date endorsed: | 39479 | | | | | | | | | | | | | | | |
| | Description: | The Cambridgeshire Wave 4 project will use the standard LEP model to deliver the first of its three waves of BSF projects. In this Wave, one school will be built with funding by PFI credits; with another school (a PRU) to be rebuilt and 4 others refurbished using conventional capital funding. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Kevin Manley, 01223 714109, [email address] | | | | | | | | | | | | | | | |
| | Coventry: Street lighting | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 64300000 | Date endorsed: | 39417 | | | | | | | | | | | | | | | |
| | Description: | The replacement of existing streetlight columns and the installation of additional columns during an initial 5-year capital programme. Also the replacement of illuminated signs and bollards, and a proportion of authority owned cable network. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Karen Seager, 024 7683 1362, [email address] | | | | | | | | | | | | | | | |
| | Croydon & Lewisham: Street lighting | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 79500000 | Date endorsed: | 39417 | | | | | | | | | | | | | | | |
| | Description: | The replacement of existing streetlight columns, illuminated signs, bollards and beacons; and the installation of additional columns during an initial 5-year capital programme. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Martin Bonner, 020 8726 6000, [email address] | | | | | | | | | | | | | | | |
| | Hampshire, Southampton & W Sussex: Street lighting | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 225100000 | Date endorsed: | 39417 | | | | | | | | | | | | | | | |
| | Description: | The replacement of existing streetlight columns, illuminated signs, bollards and authority owned cable network; together with the installation of additional columns during an initial 5-year capital programme. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Trevor Wallis, 023 9244 6510, [email address] | | | | | | | | | | | | | | | |
| | Manchester: HRA Round 3, Collyhurst | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing | PFI credits: | 162000000 | Date endorsed: | 39417 | | | | | | | | | | | | | | | |
| | Description: | The existing Collyhurst estate consists of 1,418 units, 91% of which are in Council ownership, on a Radburn layout. There is a mix of archetypes - low and medium rise flats, traditional houses, non-traditional houses and 4 tower blocks - and all units are deemed to be non-decent or potentially non-decent. The scheme will demolish 837 units and reprovide 341 and refurbish 499 homes. Diversity of tenure will be increased by the building of 1,702 new homes for sale. All 4 tower blocks will be retained. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Martin Oldfield, 0161 234 4042, [email address] | | | | | | | | | | | | | | | |
| | Luton: Building Schools for the Future | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 33789000 | Date endorsed: | 39356 | | | | | | | | | | | | | | | |
| | Description: | 0 | | | | | | | | | | | | | | | |
| | Local Authority Contact: | | | | | | | | | | | | | | | | |
| | Sandwell: Oldbury Leisure Centre (LIFT) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DH | PFI credits: | 13000000 | Date endorsed: | 39356 | | | | | | | | | | | | | | | |
| | Description: | Social services for adults with disabilities being delivered via a purpose-built leisure centre, to be developed by the local LIFT Co with PCT services (GP, pharmacy) included. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Alan Dean, 0121 612 1525, [email address] | | | | | | | | | | | | | | | |
| | Blackpool: Street lighting | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 31900000 | Date endorsed: | 39326 | | | | | | | | | | | | | | | |
| | Description: | Replacement of existing streetlight columns, illuminated signs and bollards as well as new columns. Also, the replacement of traffic signal points. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Julian Kearsley, 01253 478500, [email address] | | | | | | | | | | | | | | | |
| | Nottingham: Street lighting | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 44600000 | Date endorsed: | 39326 | | | | | | | | | | | | | | | |
| | Description: | Replacement of street lighting units, illluminated signs and traffic bollards; as well as the installation of new columns. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Pat Armstrong, 0115 9156713, [email address] | | | | | | | | | | | | | | | |
| | Oldham & Rochdale: Street lighting | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 67000000 | Date endorsed: | 39326 | | | | | | | | | | | | | | | |
| | Description: | Replacement of existing streetlight columns, illuminated signs, bollards, beacons, subway lights, footbridge lights and authority owned cable network; as well as the installation of additional columns. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Rob Dawson, 01706 92 3379, [email address] | | | | | | | | | | | | | | | |
| | Southwark: Building Schools for the Future Phase 1 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 85292000 | Date endorsed: | 39295 | | | | | | | | | | | | | | | |
| | Description: | Southwark's extended Wave 3 project comprises five secondary schools - three of which will be rebuilt under PFI and the other two conventionally-funded refurbishments, three special schools and a split-site learning campus for pupils with social, emotional and behavioural difficulties to be provided through a mix of new build and refurbishmentconventionally-funded). Another secondary school will be
rebuilt as an Academy using conventional capital and there will be two new schools (also proposed to be Academies) associated with the two key
areas of regeneration in Aylesbury and Rotherhithe. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Sara Browning, 020 7525 5007, [email address] | | | | | | | | | | | | | | | |
| | Derbyshire: Building Schools for the Future Phase 1 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 64945000 | Date endorsed: | 39264 | | | | | | | | | | | | | | | |
| | Description: | The Derbyshire Wave 3 project will use the standard LEP model to deliver the first of its four waves of BSF projects. In this Wave, two schools will be built with funding by PFI credits; three schools will be majority new build using conventional capital funding and one school will be re-built as an academy using conventional capital funding. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Gerald Tommy, 01629 585346, [email address] | | | | | | | | | | | | | | | |
| | North Yorkshire & York: Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 65000000 | Date endorsed: | 39264 | | | | | | | | | | | | | | | |
| | Description: | A project for waste infrastructure in North Yorkshire & City of York. The project would deliver two key residual waste processing facilities, namely, a Mechanical Biological Treatment (MBT) facility and an Energy from Waste (EfW) facility. The precise detail of the technological solution would be determined through the procurement process. The project is to have a concession length of 24 years. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Lisa Cooper 01609-532880 [email address] | | | | | | | | | | | | | | | |
| | Sandwell: Building Schools for the Future Phase 1 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 62874000 | Date endorsed: | 39264 | | | | | | | | | | | | | | | |
| | Description: | The Sandwell BSF Wave 3 project will create five learning campuses, comprising 10 current educational establishments (secondary schools, PRUs, special schools), one in each of Rowley Regis, Smethwick, Tipton, Wednesbury and Oldbury. Sandwell has also received official confirmation that the rest of its secondary school address will be procured through Wave 5 of the BSF programme. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Paul Piddock, 0121 569 8399, [email address] | | | | | | | | | | | | | | | |
| | Durham: Building Schools for the Future Phase 1 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 79493000 | Date endorsed: | 39234 | | | | | | | | | | | | | | | |
| | Description: | Durham's BSF programme will be delivered over four waves: Wave 3; Wave 6 and; one wave each within waves 7-9 and waves 10-12. Wave 3 is based in the east of the county where three secondary schools are due to be rebuilt with funding by PFI credits. A further four secondary schools and one special school are due to be substantially remodelled using conventional capital. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Yvonne Edwards, 0191 383 4691, [email address] | | | | | | | | | | | | | | | |
| | Leeds: New Leaf Leisure Centres | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCMS | PFI credits: | 30000000 | Date endorsed: | 39234 | | | | | | | | | | | | | | | |
| | Description: | The creation of two multi sport community hubs, with a focus on swimming provision. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Angela Lawson, 0789 127 8061, [email address] | | | | | | | | | | | | | | | |
| | Salford: Building Schools for the Future | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 192199000 | Date endorsed: | 39234 | | | | | | | | | | | | | | | |
| | Description: | Salford is a one wave BSF project that will use the standard 10 year LEP model. The project involves 5 new build schools (4 of which are PFI) and 3 refurbishments. Overall, Salford's BSF programme includes 8 schools; its remaining five mainstream secondary and special schools already have new buildings or are part of an earlier PFI programme. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Stephen Bradbury, 0161 778 0367, [email address] | | | | | | | | | | | | | | | |
| | Manchester: HRA Round 4, Brunswick | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing | PFI credits: | 118100000 | Date endorsed: | 39203 | | | | | | | | | | | | | | | |
| | Description: | The Brunswick PFI area lies to the southeast edge of the City Centre. It is a residential area dominated by 1970s council housing. The area lies adjacent to the Plymouth Grove HRA PFI area and, following other major regeneration initiatives in the City, has become a priority area to deliver comprehensive regeneration and a sustainable neighbourhood. The housing layout and type of homes are predominantly in the radburn style, 385 two storey traditional (and 5 non-traditional) houses built in the late 1960s and early 1970s together with 244 maisonettes and 107 low and 255 high-rise flats. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Majella McLaughlin, 0161 234 4837, [email address] | | | | | | | | | | | | | | | |
| | Oldham: Gateways To Oldham HRA Housing | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing | PFI credits: | 131000000 | Date endorsed: | 39203 | | | | | | | | | | | | | | | |
| | Description: | The Gateways to Oldham project aims to regenerate three estates and will cover 711 social rented units under the PFI contract. 357 properties will be refurbished, 354 properties will be demolished/reoriented and re-provided and 22 additional properties for social rent will be built. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Chris Kelsall, 0161 770 1143, [email address] | | | | | | | | | | | | | | | |
| | Merseyside Waste Disposal Authority: Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 90000000 | Date endorsed: | 39173 | | | | | | | | | | | | | | | |
| | Description: | The Reference project is scoped as three separate contracts, of which the Recovery contract is a 25 year PFI contract to treat residual waste. It entails the delivery of a combination of MBT and EfW facilities. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Colin M. Mckenzie, 0151 255 2545, [email address] | | | | | | | | | | | | | | | |
| | Staffordshire & Stoke: Fire | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Fire | PFI credits: | 46000000 | Date endorsed: | 39173 | | | | | | | | | | | | | | | |
| | Description: | The provision of 10 new fire stations, consisting of 7 new community fire stations (2 on new sites – Tamworth and Sandyford) and 3 new response bases at Tamworth, Stafford and Kidsgrove. The remaining 23 fire stations in the Authority are planned to be refurbished through conventional procurement. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Steve Knight, 01785 898625, [email address] | | | | | | | | | | | | | | | |
| | Birmingham: Special Care Centres (LIFT) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DH | PFI credits: | 45110000 | Date endorsed: | 39142 | | | | | | | | | | | | | | | |
| | Description: | Phase 2 of the development of Special Care Centres for elderly people in Birmingham, to be developed by the LIFT Company, providing a mixture of residential and community care, with one-stop facilities and dementia resources. This phase will deliver four of the planned 10 centres (four of which are already being delivered by Phase 1 | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Charles Ashton-Grey, 07920 275315, [email address] | | | | | | | | | | | | | | | |
| | East Sussex: Age Well Project | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DH | PFI credits: | 39000000 | Date endorsed: | 39142 | | | | | | | | | | | | | | | |
| | Description: | Deliver four new residential care facilities in different parts of the county (Uckfield, Hastings, Ringmer and Rother) with a combined capacity of
188 places. The new residential care units will be designed to support a range of specialist residential care services (including nursing care)
together with rehabilitation, respite and day care services. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Lorayne Ferguson, 01825 768 297, [email address]
Paula Kirkland, 01273 738738, [email address] | | | | | | | | | | | | | | | |
| | Manchester: Joint Service Centre - Miles Platting (LIFT) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Other | PFI credits: | 3800000 | Date endorsed: | 39142 | | | | | | | | | | | | | | | |
| | Description: | A joint services centre facility on The Miles Platting estate to be developed by the Manchester, Salford and Trafford (MaST) LIFT Company providing a range of services including: library; community and adult education; employment advice, and Connexions services; Surestart crèche; and health services (health centre, 5 GPs, and pharmacy). | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Colleen Scott, 0161 234 1494, [email address] | | | | | | | | | | | | | | | |
| | Barnsley: Building Schools for the Future Phase 1 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 165581000 | Date endorsed: | 39114 | | | | | | | | | | | | | | | |
| | Description: | The Barnsley BSF project will be used to update all the existing school stock in the borough by 2012, creating full service Advanced Learning
Centres. The plan is to reduce the schools from 14 to 9; one school will be closed and replaced by an academy. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Steve Mair, 01226 773 634, [email address] | | | | | | | | | | | | | | | |
| | Barnsley: Building Schools for the Future Phase 2 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 158757000 | Date endorsed: | 39114 | | | | | | | | | | | | | | | |
| | Description: | 0 | | | | | | | | | | | | | | | |
| | Local Authority Contact: | | | | | | | | | | | | | | | | |
| | Tameside: Building Schools for the Future | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 128120000 | Date endorsed: | 39114 | | | | | | | | | | | | | | | |
| | Description: | The Tameside BSF Wave 3 project is a wholesale rationalisation of the secondary school estate. Ten mainstream schools will be demolished and
replaced by two Academies and five new schools. BSF funding will also be used to rebuild / refurbish three specials and a PRU. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Elaine Todd, 0161 342 3238, [email address] | | | | | | | | | | | | | | | |
| | Birmingham: Building Schools for the Future (including Primary) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 102250000 | Date endorsed: | 39083 | | | | | | | | | | | | | | | |
| | Description: | The Birmingham BSF Wave 2 project will use the standard LEP model to deliver the first of six phases of its BSF projects. In this first phase, three schools will be rebuilt with funding by PFI credits; the other eight schools will be substantially remodelled using conventional capital funding. Birmingham has also received confirmation that its second phase of BSF will be procured through Wave 5 of the BSF programme. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Peter Farrell, 0121 303 1348, [email address] | | | | | | | | | | | | | | | |
| | Wigan: Wigan: Joint Service Centre (inc library & swimming pool) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCMS & CLG Other | PFI credits: | 67000000 | Date endorsed: | 39083 | | | | | | | | | | | | | | | |
| | Description: | A Joint Service Centre (JSC) in Wigan town centre, located on either side of Wigan town hall, with the following main elements: Information and Learning Zone – incorporating a One Stop Shop and new library; Neighbourhood Zone – community-related services including Housing; Healthy Living Zone – health, social care and leisure facilities including a new swimming pool and primary care facilities. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Katherine Fairclough, 01942 827095, [email address] | | | | | | | | | | | | | | | |
| | Coventry: Childrens services (variation) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 2475000 | Date endorsed: | 39052 | | | | | | | | | | | | | | | |
| | Description: | 0 | | | | | | | | | | | | | | | |
| | Local Authority Contact: | | | | | | | | | | | | | | | | |
| | Derbyshire: Childrens services (variation) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 1950000 | Date endorsed: | 39052 | | | | | | | | | | | | | | | |
| | Description: | 0 | | | | | | | | | | | | | | | |
| | Local Authority Contact: | | | | | | | | | | | | | | | | |
| | Leeds: Childrens services (variation) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 5000000 | Date endorsed: | 39052 | | | | | | | | | | | | | | | |
| | Description: | 0 | | | | | | | | | | | | | | | |
| | Local Authority Contact: | | | | | | | | | | | | | | | | |
| | Northamptonshire: Childrens services (Variation) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 5000000 | Date endorsed: | 39052 | | | | | | | | | | | | | | | |
| | Description: | 0 | | | | | | | | | | | | | | | |
| | Local Authority Contact: | | | | | | | | | | | | | | | | |
| | Nottingham: Joint Service Centre - Bulwell (LIFT) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Other | PFI credits: | 22255000 | Date endorsed: | 39052 | | | | | | | | | | | | | | | |
| | Description: | A joint service centre in Bulwell to be developed by the Greater Nottingham LIFT Company providing a range of local authority and health services. The local authority services will include: library and one-stop information & services; youth services; indoor and outdoor games facilities; adult social services, neighbourhood and housing services (inc ALMO). | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Tanya Najuk, 07949 185417, [email address] | | | | | | | | | | | | | | | |
| | Bristol: Hengrove Park Leisure Centre | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCMS | PFI credits: | 29680000 | Date endorsed: | 39022 | | | | | | | | | | | | | | | |
| | Description: | Multi-sport centre adjacent to a community hospital and park, including a 50m swimming pool, sports hall and health & fitness faciltiies. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Stuart Woods, 0117 922 4355, [email address] | | | | | | | | | | | | | | | |
| | GLA (Transport for London): Thames Gateway Bridge | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 350000000 | Date endorsed: | 39022 | | | | | | | | | | | | | | | |
| | Description: | The TGB Scheme consists principally of a new bridge across the River Thames between Beckton and Thamesmead and the following associated highways:
• A dual carriageway for all traffic between the A406 North Circular Road (Beckton) and the A2016 Eastern Way (Thamesmead)
• A two-lane public transport highway linking local centres on either side of the river
• A footpath and separate cycle path between Woolwich Manor Way (Beckton) and Eastern Way (Thamesmead)
The overall length of the TGB Scheme is about 4.8 km, with the Bridge and its approach viaducts representing about 2 km. In addition, there will be bridge structures over the A13/A406 junction, Eric Clarke Lane, the Northern Outfall Sewer, Winsor Terrace Junction and Thamesmead Junction. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Martin Stuckey, 020 8433 6927 | | | | | | | | | | | | | | | |
| | Leeds: HRA Round 3, Little London | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing | PFI credits: | 188850000 | Date endorsed: | 39022 | | | | | | | | | | | | | | | |
| | Description: | The refurbishment (to meet Decent Homes standard) of 922 existing rented units (435 in high rise blocks) and the reprovision of 125 new build rented units. This project forms the central element of the regeneration of the Little London estate. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | | | | | | | | | | | | | | | | |
| | Worcestershire: Library + Joint Service Centre (with ODPM other) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCMS & CLG Other | PFI credits: | 36800000 | Date endorsed: | 39022 | | | | | | | | | | | | | | | |
| | Description: | Landmark city centre development including fully integrated public and university library, children's area, history centre and customer one stop service centre plus commercial uses. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Peter Parkes, 01905 766803 [email address] | | | | | | | | | | | | | | | |
| | Kent: Building Schools for the Future Phase 1 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 98840000 | Date endorsed: | 38961 | | | | | | | | | | | | | | | |
| | Description: | The Project covers the first LEP of the Building Schools for the Future programme in Kent. The PFI project includes 3 new build schools in streams 1 and 2. These streams will also include the conventional procurement of 8 schools each incorporating substantial refurbishment, remodelling and refresh with an element of new build. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Karl Limbert, 01622 221182, [email address] | | | | | | | | | | | | | | | |
| | Liverpool: Central Library & Archives | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCMS | PFI credits: | 49300000 | Date endorsed: | 38961 | | | | | | | | | | | | | | | |
| | Description: | Redevelopment of Liverpool Central Library and Archives including rebuilding of the William Brown Library, refurbishment of the library extension, renovation of the Picton, Hornby & Oak libraries plus preventative maintenance works to the historic fabric. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Joyce Little, 0151 233 6346, [email address] | | | | | | | | | | | | | | | |
| | Newham: Building Schools for the Future Phase 1 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 65470000 | Date endorsed: | 38899 | | | | | | | | | | | | | | | |
| | Description: | The Project covers the first phase of the Building Schools for the Future programme. The PFI element is for the new build of two schools (phase 1 also covers refurbishment of 6 other schools). | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Zoe Power, 020 8430 5068, [email address] | | | | | | | | | | | | | | | |
| | South Tyneside & Gateshead: Building Schools for the Future Phase 2 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 36332000 | Date endorsed: | 38899 | | | | | | | | | | | | | | | |
| | Description: | 0 | | | | | | | | | | | | | | | |
| | Local Authority Contact: | | | | | | | | | | | | | | | | |
| | Tyne and Wear, Northumberland and Durham and Darlington FRAs: North East Fire and Rescue Authorities (NEFRA) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Fire | PFI credits: | 37900000 | Date endorsed: | 38899 | | | | | | | | | | | | | | | |
| | Description: | The amalgamation, replacement and relocation of 7 fire stations to create 5 new community fire stations in the North East region. Each new fire station will have community fire safety facilities. The project will also deliver a new head quarters and stores facility for Northumberland FRA. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Alan Holmes, 0191 4441500, [email address]
Dave Jefferson, 0191 4441516, [email address] | | | | | | | | | | | | | | | |
| | Cheshire: Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 40000000 | Date endorsed: | 38838 | | | | | | | | | | | | | | | |
| | Description: | The disposal of 438,819 tonnes of Municipal Solid Waste (MSW) using MBT technology including EFW plant as part of the procurement. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Harold Collin, 01244 603559, [email address] | | | | | | | | | | | | | | | |
| | Islington: Building Schools for the Future Phase 2 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 48378000 | Date endorsed: | 38808 | | | | | | | | | | | | | | | |
| | Description: | 0 | | | | | | | | | | | | | | | |
| | Local Authority Contact: | | | | | | | | | | | | | | | | |
| | Derby: Non HRA Round 3 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing | PFI credits: | 22250000 | Date endorsed: | 38777 | | | | | | | | | | | | | | | |
| | Description: | Provision of a minimum of 175 social rented homes across the City through a combination of new-build properties that are purchased from the private sector for refurbishment. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Mike Melluish, 01332 255533, [email address] | | | | | | | | | | | | | | | |
| | Lambeth: HRA Round 3, Myatts North | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing | PFI credits: | 111000000 | Date endorsed: | 38777 | | | | | | | | | | | | | | | |
| | Description: | Proposal covers 477 homes of which 172 properties will be refurbished & 305 dwellings will be demolished & reprovided, 251 for social rent and significant remodelling of the estate & the existing open space. It will also facilitate the new build of an additional 187 units for sale, to improve the economic diversity of the community. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Tazeem Abbas, 020 7926 8317, [email address] | | | | | | | | | | | | | | | |
| | West Wiltshire: Non HRA Round 3 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing | PFI credits: | 83000000 | Date endorsed: | 38777 | | | | | | | | | | | | | | | |
| | Description: | To provide a minimum of 400 units of new build social rented housing across urban and rural areas in the district. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Chris Trowell, 01225 770360, [email address] | | | | | | | | | | | | | | | |
| | Kirklees : HRA Round 3 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing | PFI credits: | 101500000 | Date endorsed: | 38565 | | | | | | | | | | | | | | | |
| | Description: | Provision of 550 new units of affordable housing, replacing 650 old units which are no longer fit for purpose and uneconomic to refurbish to Decent Homes standard. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Mark Denton, 01484 221647 | | | | | | | | | | | | | | | |
| | Cambridgeshire, Norfolk and Suffolk Police: Three Counties Police custody centres | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | HO | PFI credits: | 87234000 | Date endorsed: | 38534 | | | | | | | | | | | | | | | |
| | Description: | Cambridgeshire, Norfolk and Suffolk have entered into a joint working agreement for the construction of nine new custody facilities. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Peter Belson, 01953 424744 | | | | | | | | | | | | | | | |
| | Leicester: Building Schools for the Future Phase 2 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 88084000 | Date endorsed: | 38473 | | | | | | | | | | | | | | | |
| | Description: | 0 | | | | | | | | | | | | | | | |
| | Local Authority Contact: | | | | | | | | | | | | | | | | |
| | Lancashire: Building Schools for the Future Phase 3 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 40475000 | Date endorsed: | 38443 | | | | | | | | | | | | | | | |
| | Description: | 0 | | | | | | | | | | | | | | | |
| | Local Authority Contact: | | | | | | | | | | | | | | | | |
| | Lewisham: Building Schools for the Future Phase 2 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 110886000 | Date endorsed: | 38443 | | | | | | | | | | | | | | | |
| | Description: | 0 | | | | | | | | | | | | | | | |
| | Local Authority Contact: | | | | | | | | | | | | | | | | |
| | Sheffield: Intermediate care resource centre (LIFT) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DH | PFI credits: | 19800000 | Date endorsed: | 38384 | | | | | | | | | | | | | | | |
| | Description: | 0 | | | | | | | | | | | | | | | |
| | Local Authority Contact: | | | | | | | | | | | | | | | | |
| | Greater Manchester Waste Disposal Authority: Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 109500000 | Date endorsed: | 38353 | | | | | | | | | | | | | | | |
| | Description: | The Disposal Authority seeks to fund the development of the capital infrastructure required to achieve a rapid improvement in household waste recycling and composting performance and otherwise to divert the bio-degradable waste that is sent to landfill. The PFI Reference Project ("Reference Project"), is designed to exceed Best Value Performance Indicators ("BVPI"), Waste Strategy 2000 ("WS 2000") targets and all of the landfill diversion targets arising as a result of the EU Landfill Directive and the Landfill Allowances Trading Scheme ("LATS"). | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Ekanem Etim-Offiong 0161 911 5122 [email address] | | | | | | | | | | | | | | | |
| | Greenwich: Building Schools for the Future | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 183510000 | Date endorsed: | 38353 | | | | | | | | | | | | | | | |
| | Description: | Rebuilding/renewal/expansion of five secondary schools under Building Schools for the Future (BSF). | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Terry Kirkpatrick, 020 8921 5513, [email address] | | | | | | | | | | | | | | | |
| | Newcastle: Building Schools for the Future Phase 2 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 62294000 | Date endorsed: | 38322 | | | | | | | | | | | | | | | |
| | Description: | 0 | | | | | | | | | | | | | | | |
| | Local Authority Contact: | | | | | | | | | | | | | | | | |
| | Newcastle: Building Schools for the Future Phase 3 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 17717000 | Date endorsed: | 38322 | | | | | | | | | | | | | | | |
| | Description: | 0 | | | | | | | | | | | | | | | |
| | Local Authority Contact: | | | | | | | | | | | | | | | | |
| | Wakefield: Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 33000000 | Date endorsed: | 38322 | | | | | | | | | | | | | | | |
| | Description: | Waste Management Programme | | | | | | | | | | | | | | | |
| | Local Authority Contact: | John S Nortcliffe, 01924 306318 | | | | | | | | | | | | | | | |
| | Leeds: 2 Joint Service Centres - Chapeltown & Harehills (LIFT) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Other | PFI credits: | 10500000 | Date endorsed: | 38292 | | | | | | | | | | | | | | | |
| | Description: | 0 | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Steven Moore, 0113 3950234, [email address] | | | | | | | | | | | | | | | |
| | Leeds: Joint Service Centre - Kirkstall (LIFT) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Other | PFI credits: | 5200000 | Date endorsed: | 38292 | | | | | | | | | | | | | | | |
| | Description: | 0 | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Steven Moore, 0113 3950234, [email address] | | | | | | | | | | | | | | | |
| | Surrey: Street lighting | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 65600000 | Date endorsed: | 38292 | | | | | | | | | | | | | | | |
| | Description: | Replacement of existing streetlight columns, illuminated signs and bollards as well as new columns | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Paul King, 020 8541 7202, [email address] | | | | | | | | | | | | | | | |
| | Birmingham: Highway maintenance | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 588000000 | Date endorsed: | 37895 | | | | | | | | | | | | | | | |
| | Description: | To improve Birmingham's road network; work will involve improvements to current street lighting service, additional street lighting columns. Users will benefit from from improved road safety and reduction in crime. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Paul O'Day, 0121 303 7412 | | | | | | | | | | | | | | | |
| | Brent: Non-HRA for people with learning difficulties | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing | PFI credits: | 26600000 | Date endorsed: | 37895 | | | | | | | | | | | | | | | |
| | Description: | Non-HRA Housing & Accommodation for People with Learning disabilities | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Gary Chase, 020 8937 2451 | | | | | | | | | | | | | | | |
| | Cumbria: Carlisle Northern Development Route | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 142800000 | Date endorsed: | 37438 | | | | | | | | | | | | | | | |
| | Description: | A 5km bypass around the western edge of Carlisle which will relieve traffic congestion in Carlisle and provide access to the new Kingmoor Park strategic employment site. Also maintenance of 150km of primary routes, including de-trunked routes in North Cumbria. | | | | | | | | | | | | | | | |
| | Local Authority Contact: | Geoff Holden, 01228 606747 | | | | | | | | | | | | | | | |
| | Newham: HRA Round 2, Forest Gate | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing | PFI credits: | 55000000 | Date endorsed: | 37438 | | | | | | | | | | | | | | | |
| | Description: | 0 | | | | | | | | | | | | | | | |
| | Local Authority Contact: | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | |
| PIPELINE PROJECT DETAILS | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | |
| | Cheshire Police: Estate Investment Programme | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | HO | PFI credits: | 125000000 | Pipeline | | | | | | | | | | | | | | | |
| | Gloucestershire Police: Estate Development Programme | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | HO | PFI credits: | 119000000 | Pipeline | | | | | | | | | | | | | | | |
| | Staffordshire Police: Staffordshire | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | HO | PFI credits: | 68700000 | Pipeline | | | | | | | | | | | | | | | |
| | West Yorkshire Police: Estate Modernisation | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | HO | PFI credits: | 177000000 | Pipeline | | | | | | | | | | | | | | | |
| | Tower Hamlets: St Clements Independent Living (LIFT) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DH | PFI credits: | 16520000 | Pipeline | | | | | | | | | | | | | | | |
| | Wolverhampton: Every Adult Matters (LIFT) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DH | PFI credits: | 29380000 | Pipeline | | | | | | | | | | | | | | | |
| | Halton: Mersey Gateway Crossing | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 209000000 | Pipeline | | | | | | | | | | | | | | | |
| | Harrow: Street lighting | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 35900000 | Pipeline | | | | | | | | | | | | | | | |
| | Hounslow: Highway maintenance | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 198000000 | Pipeline | | | | | | | | | | | | | | | |
| | Isle of Wight: Highway maintenance | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 325000000 | Pipeline | | | | | | | | | | | | | | | |
| | Nottingham: NET Line 2 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 437000000 | Pipeline | | | | | | | | | | | | | | | |
| | Sheffield: Highway maintenance | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 663800000 | Pipeline | | | | | | | | | | | | | | | |
| | Bedfordshire: Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 56000000 | Pipeline | | | | | | | | | | | | | | | |
| | Derbyshire & Derby: Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 96700000 | Pipeline | | | | | | | | | | | | | | | |
| | Dorset & Bournemouth: Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 60000000 | Pipeline | | | | | | | | | | | | | | | |
| | Essex: Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 171300000 | Pipeline | | | | | | | | | | | | | | | |
| | Gloucestershire: Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 92000000 | Pipeline | | | | | | | | | | | | | | | |
| | Hertfordshire: Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 100000000 | Pipeline | | | | | | | | | | | | | | | |
| | Hull and East Riding: Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 90000000 | Pipeline | | | | | | | | | | | | | | | |
| | Leicestershire: Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 86600000 | Pipeline | | | | | | | | | | | | | | | |
| | Lincolnshire: Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 57800000 | Pipeline | | | | | | | | | | | | | | | |
| | Milton Keynes & Northamptonshire: Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 129200000 | Pipeline | | | | | | | | | | | | | | | |
| | Norfolk: Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 77000000 | Pipeline | | | | | | | | | | | | | | | |
| | North London Waste Authority (NLWA): Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 255000000 | Pipeline | | | | | | | | | | | | | | | |
| | South London Waste Partnership: Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 52000000 | Pipeline | | | | | | | | | | | | | | | |
| | South West Devon Partnership (Plymouth, Torbay & Devon): Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 95000000 | Pipeline | | | | | | | | | | | | | | | |
| | Warwickshire, Coventry & Solihull: Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 93000000 | Pipeline | | | | | | | | | | | | | | | |
| | West of England: Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 60000000 | Pipeline | | | | | | | | | | | | | | | |
| | Barking & Dagenham: Building Schools for the Future | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 237539000 | Pipeline | | | | | | | | | | | | | | | |
| | Coventry: Building Schools for the Future | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 223884000 | Pipeline | | | | | | | | | | | | | | | |
| | Essex: Building Schools for the Future | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 167985000 | Pipeline | | | | | | | | | | | | | | | |
| | Hertfordshire: Building Schools for the Future | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 147134000 | Pipeline | | | | | | | | | | | | | | | |
| | Hull: Building Schools for the Future Phase 1 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 57292000 | Pipeline | | | | | | | | | | | | | | | |
| | Hull: Building Schools for the Future Phase 2 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 72003000 | Pipeline | | | | | | | | | | | | | | | |
| | Kent: Building Schools for the Future Phase 2 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 82552000 | Pipeline | | | | | | | | | | | | | | | |
| | Oldham: Building Schools for the Future | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 100000000 | Pipeline | | | | | | | | | | | | | | | |
| | Sheffield: Building Schools for the Future | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 40000000 | Pipeline | | | | | | | | | | | | | | | |
| | Rochdale: Joint Service Centre - Littleborough (LIFT) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCMS & CLG Other | PFI credits: | 5168000 | Pipeline | | | | | | | | | | | | | | | |
| | Lambeth: Joint Service Centre - Norwood (LIFT) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Other | PFI credits: | 14292000 | Pipeline | | | | | | | | | | | | | | | |
| | Leicester: Joint Service Centre - Southfields (LIFT) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Other | PFI credits: | 8405000 | Pipeline | | | | | | | | | | | | | | | |
| | North Tyneside: Joint Service Centre - Whitley Bay (LIFT) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Other | PFI credits: | 5500000 | Pipeline | | | | | | | | | | | | | | | |
| | Rochdale: Joint Service Centre - Middleton (LIFT) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Other | PFI credits: | 3669000 | Pipeline | | | | | | | | | | | | | | | |
| | Cheshire: Non HRA Round 5 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing | PFI credits: | 50000000 | Pipeline | | | | | | | | | | | | | | | |
| | Kent: Non HRA Round 5, Excellent Homes For All | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing | PFI credits: | 59000000 | Pipeline | | | | | | | | | | | | | | | |
| | Salford: (Pendleton) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing | PFI credits: | 121000000 | Pipeline | | | | | | | | | | | | | | | |
| | Stoke: Non HRA Round 5 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing | PFI credits: | 105000000 | Pipeline | | | | | | | | | | | | | | | |
| | GLA (London Fire Authority): Fire property | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Fire | PFI credits: | 52000000 | Pipeline | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | |
| SIGNED & OPERATIONAL PROJECT DETAILS PROJECT DETAILS | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | |
| | Amber Valley: Three leisure centres | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCMS | PFI credits: | 17470000 | Operational | | | | | | | | | | | | | | | |
| | Ashford: HRA Round 2, Stanhope | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing | PFI credits: | 40000000 | Operational | | | | | | | | | | | | | | | |
| | Avon, Somerset and Gloucester: Fire training facility | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Fire | PFI credits: | 16900000 | Operational | | | | | | | | | | | | | | | |
| | Barking & Dagenham: 1 new, 1 improved secondary school | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF & CLG Other | PFI credits: | 39760000 | Operational | | | | | | | | | | | | | | | |
| | Barnet: Street lighting | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 27770000 | Operational | | | | | | | | | | | | | | | |
| | Barnsley: Grouped schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 54000000 | Operational | | | | | | | | | | | | | | | |
| | Barnsley: Joint Service Centre - Cudworth (LIFT) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Other | PFI credits: | 5400000 | Signed | | | | | | | | | | | | | | | |
| | Bedfordshire: Mid Bedfordshire upper schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 24200000 | Operational | | | | | | | | | | | | | | | |
| | Bexley: Bexleyheath & Welling and Chislehurst & Sidcup | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 35100000 | Operational | | | | | | | | | | | | | | | |
| | Birmingham: Grouped schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 57038000 | Operational | | | | | | | | | | | | | | | |
| | Birmingham: Replacement of ten schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 50600000 | Operational | | | | | | | | | | | | | | | |
| | Bolton: Castle Hill Community Learning | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF & CLG Other | PFI credits: | 10700000 | Operational | | | | | | | | | | | | | | | |
| | Bournemouth: Library | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCMS | PFI credits: | 14990000 | Operational | | | | | | | | | | | | | | | |
| | Bradford: Building Schools for the Future Phase 1 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 111904000 | Signed | | | | | | | | | | | | | | | |
| | Breckland: New leisure centres and sports development initiatives | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCMS | PFI credits: | 9550000 | Operational | | | | | | | | | | | | | | | |
| | Brent: Relocation of Jews Free School | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 9000000 | Operational | | | | | | | | | | | | | | | |
| | Brent: Street lighting | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 7500000 | Operational | | | | | | | | | | | | | | | |
| | Brent: Willesden Sports centre & stadium | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCMS | PFI credits: | 14990000 | Operational | | | | | | | | | | | | | | | |
| | Brighton: Four secondary schools plus community library | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF & CLG Other | PFI credits: | 25300000 | Operational | | | | | | | | | | | | | | | |
| | Brighton: Library | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCMS | PFI credits: | 12759000 | Operational | | | | | | | | | | | | | | | |
| | Bristol: Building Schools for the Future | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 154990000 | Operational | | | | | | | | | | | | | | | |
| | Bristol: Grouped schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 57300000 | Operational | | | | | | | | | | | | | | | |
| | Calderdale: Four schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 53900000 | Operational | | | | | | | | | | | | | | | |
| | Cambridgeshire: “Cambridge Community Network†IT | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Other | PFI credits: | 11940000 | Operational | | | | | | | | | | | | | | | |
| | Cambridgeshire: Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 56000000 | Operational | | | | | | | | | | | | | | | |
| | Camden: Haverstock school | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 20900000 | Operational | | | | | | | | | | | | | | | |
| | Camden: HRA Pathfinder, Chalcots estate | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing | PFI credits: | 65000000 | Operational | | | | | | | | | | | | | | | |
| | Central Berkshire (Reading): Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 37000000 | Operational | | | | | | | | | | | | | | | |
| | Cheshire Police: Centralised custody facilities | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | HO | PFI credits: | 41000000 | Operational | | | | | | | | | | | | | | | |
| | Cheshire Police: Relocation of HQ and training centre | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | HO | PFI credits: | 44992297 | Operational | | | | | | | | | | | | | | | |
| | Cheshire: Ellesmere Port & Neston School | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF & CLG Other | PFI credits: | 17200000 | Operational | | | | | | | | | | | | | | | |
| | Cheshire: Non-HRA extra care | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing | PFI credits: | 55000000 | Signed | | | | | | | | | | | | | | | |
| | Cleveland & Durham Police: Firearms range | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | HO | PFI credits: | 10849000 | Operational | | | | | | | | | | | | | | | |
| | Cleveland Police: Custody & other facilities | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | HO | PFI credits: | 38300000 | Operational | | | | | | | | | | | | | | | |
| | Copeland: Office accommodation | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Other | PFI credits: | 8120000 | Operational | | | | | | | | | | | | | | | |
| | Cornwall: 32 schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 60700000 | Operational | | | | | | | | | | | | | | | |
| | Cornwall: Fire stations | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Fire | PFI credits: | 12257000 | Operational | | | | | | | | | | | | | | | |
| | Cornwall: Grouped Truro schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 71000000 | Operational | | | | | | | | | | | | | | | |
| | Cornwall: Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 45000000 | Operational | | | | | | | | | | | | | | | |
| | Coventry: Caludon Castle school | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 24300000 | Operational | | | | | | | | | | | | | | | |
| | Coventry: New homes for old | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing & DH | PFI credits: | 21647000 | Operational | | | | | | | | | | | | | | | |
| | Croydon: "Customer Focus" IT | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Other | PFI credits: | 21200000 | Operational | | | | | | | | | | | | | | | |
| | Croydon: Ashburton Learning Village | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF & DCMS | PFI credits: | 21786000 | Operational | | | | | | | | | | | | | | | |
| | Croydon: Sheltered housing & social care | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing & DH | PFI credits: | 38360000 | Signed | | | | | | | | | | | | | | | |
| | Cumbria Police: Workington police station | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | HO | PFI credits: | 7500000 | Operational | | | | | | | | | | | | | | | |
| | Darlington: Five schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 34900000 | Operational | | | | | | | | | | | | | | | |
| | Derby: Childrens services | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 2200000 | Signed | | | | | | | | | | | | | | | |
| | Derby: Grouped schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 43830000 | Operational | | | | | | | | | | | | | | | |
| | Derby: Non-HRA, social housing | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing | PFI credits: | 2805000 | Operational | | | | | | | | | | | | | | | |
| | Derby: Revenues & benefits IT | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Other | PFI credits: | 1774000 | Ended | | | | | | | | | | | | | | | |
| | Derby: Street lighting | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 35711493 | Operational | | | | | | | | | | | | | | | |
| | Derbyshire Police: Divisional HQ in Derby | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | HO | PFI credits: | 23917000 | Operational | | | | | | | | | | | | | | | |
| | Derbyshire Police: Ilkeston police station | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | HO | PFI credits: | 3774000 | Operational | | | | | | | | | | | | | | | |
| | Derbyshire: Phase 1 (two schools & one integrated facility) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 29000000 | Operational | | | | | | | | | | | | | | | |
| | Derbyshire: Phase 2 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 38200000 | Operational | | | | | | | | | | | | | | | |
| | Devon: Exeter grouped schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 79000000 | Operational | | | | | | | | | | | | | | | |
| | Doncaster: 2 secondary schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 43160000 | Signed | | | | | | | | | | | | | | | |
| | Dorset Police & Fire: Fire & police accommodation | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | HO & CLG Fire | PFI credits: | 57380000 | Signed | | | | | | | | | | | | | | | |
| | Dorset Police: Dorchester police station | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | HO | PFI credits: | 24300000 | Operational | | | | | | | | | | | | | | | |
| | Dorset: Colfox secondary school | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 15600000 | Operational | | | | | | | | | | | | | | | |
| | Dorset: Street lighting | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 31600000 | Operational | | | | | | | | | | | | | | | |
| | Dudley: Grid for Learning [Schools ICT project] | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 29550000 | Operational | | | | | | | | | | | | | | | |
| | Dudley: One secondary and one primary school / Paragon Project | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 22000000 | Operational | | | | | | | | | | | | | | | |
| | Dudley: Sedgley Health library (Multi-use facility) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DH | PFI credits: | 1486052 | Operational | | | | | | | | | | | | | | | |
| | Ealing: Grouped schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 61800000 | Operational | | | | | | | | | | | | | | | |
| | Ealing: Resource centres / Elderly Care Home | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DH | PFI credits: | 24156292 | Operational | | | | | | | | | | | | | | | |
| | Ealing: Street lighting | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 25275000 | Operational | | | | | | | | | | | | | | | |
| | Ealing: Three schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 33100000 | Operational | | | | | | | | | | | | | | | |
| | East London Waste Authority: Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 47000000 | Operational | | | | | | | | | | | | | | | |
| | East Riding of Yorkshire: Bridlington Schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 26000000 | Operational | | | | | | | | | | | | | | | |
| | East Sussex & Brighton & Hove: Waste Partnership | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 49000000 | Operational | | | | | | | | | | | | | | | |
| | East Sussex: Peacehaven schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 19000000 | Operational | | | | | | | | | | | | | | | |
| | Enfield: New secondary school (Highlands School / Worlds End Lane) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 15900000 | Operational | | | | | | | | | | | | | | | |
| | Enfield: Schools project (procured jointly with Newham) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 38800000 | Operational | | | | | | | | | | | | | | | |
| | Enfield: Street lighting | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 23700000 | Operational | | | | | | | | | | | | | | | |
| | Essex: A130 Bypass | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 97500000 | Operational | | | | | | | | | | | | | | | |
| | Essex: Clacton-on-Sea Education Project | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF & CLG Other | PFI credits: | 35700000 | Operational | | | | | | | | | | | | | | | |
| | Essex: New secondary school (Debden Park High School) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 11100000 | Operational | | | | | | | | | | | | | | | |
| | Gateshead: Schools rebuild and relocation | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 64200000 | Operational | | | | | | | | | | | | | | | |
| | GLA (London Fire Authority): Fire vehicles and equipment | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Fire | PFI credits: | 45000000 | Operational | | | | | | | | | | | | | | | |
| | Gloucestershire Police: Force HQ | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | HO | PFI credits: | 26200000 | Operational | | | | | | | | | | | | | | | |
| | Greater Manchester Fire Authority: Streford fire headquarters | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Fire | PFI credits: | 4790000 | Operational | | | | | | | | | | | | | | | |
| | Greater Manchester Police: Improved operational policing | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | HO | PFI credits: | 63000000 | Operational | | | | | | | | | | | | | | | |
| | Greenwich: Three neighbourhood resource centres | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DH | PFI credits: | 23900000 | Operational | | | | | | | | | | | | | | | |
| | Hackney: Technology learning centre (office + library/museum) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Other | PFI credits: | 14352000 | Operational | | | | | | | | | | | | | | | |
| | Hammersmith & Fulham: Care & Housing for Older People | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing & DH | PFI credits: | 12000000 | Operational | | | | | | | | | | | | | | | |
| | Haringey: Eight secondary schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 62500000 | Operational | | | | | | | | | | | | | | | |
| | Harrow: Community centres for elderly (1) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DH | PFI credits: | 2440000 | Operational | | | | | | | | | | | | | | | |
| | Harrow: Community centres for elderly (2) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DH | PFI credits: | 10000000 | Signed | | | | | | | | | | | | | | | |
| | Harrow: Revenues & benefits IT | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Other | PFI credits: | 849000 | Ended | | | | | | | | | | | | | | | |
| | Harrow: Special Schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 19500000 | Operational | | | | | | | | | | | | | | | |
| | Herefordshire & Worcestershire: Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 57361000 | Operational | | | | | | | | | | | | | | | |
| | Herefordshire: Whitecross High school | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 19500000 | Operational | | | | | | | | | | | | | | | |
| | Hertfordshire: Childrens homes & family centres | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DH | PFI credits: | 23280000 | Operational | | | | | | | | | | | | | | | |
| | Hillingdon: New secondary school (Barnhill School) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 18356000 | Operational | | | | | | | | | | | | | | | |
| | Hull: Joint Service Centre - Orchard Park (LIFT) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Other | PFI credits: | 9590000 | Signed | | | | | | | | | | | | | | | |
| | Hull: Victoria Dock, new primary school | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 3912000 | Operational | | | | | | | | | | | | | | | |
| | Isle of Wight : Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 13031000 | Operational | | | | | | | | | | | | | | | |
| | Islington: Building Schools for the Future Phase 1 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 64460000 | Signed | | | | | | | | | | | | | | | |
| | Islington: Depot services | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Other | PFI credits: | 21554000 | Operational | | | | | | | | | | | | | | | |
| | Islington: HRA Pathfinder, mainly Victorian street properties | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing | PFI credits: | 74700000 | Operational | | | | | | | | | | | | | | | |
| | Islington: HRA Round 2, street properties II | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing | PFI credits: | 165000000 | Operational | | | | | | | | | | | | | | | |
| | Islington: Street lighting | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 12166000 | Operational | | | | | | | | | | | | | | | |
| | Kent Police: Medway area police station | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | HO | PFI credits: | 23600000 | Operational | | | | | | | | | | | | | | | |
| | Kent Police: North Kent (Gravesend) police station | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | HO | PFI credits: | 45500000 | Operational | | | | | | | | | | | | | | | |
| | Kent: Grouped schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 80750000 | Operational | | | | | | | | | | | | | | | |
| | Kent: Integrated social and health services | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DH | PFI credits: | 22819902 | Operational | | | | | | | | | | | | | | | |
| | Kent: Non-HRA extra care | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing | PFI credits: | 72500000 | Signed | | | | | | | | | | | | | | | |
| | Kent: Strategic IT | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Other | PFI credits: | 7469000 | Operational | | | | | | | | | | | | | | | |
| | Kent: Swanscombe school | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 11600000 | Operational | | | | | | | | | | | | | | | |
| | Kirklees : 20 schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 59200000 | Operational | | | | | | | | | | | | | | | |
| | Kirklees : Improved SEN provision | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 25200000 | Operational | | | | | | | | | | | | | | | |
| | Kirklees : Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 33918000 | Operational | | | | | | | | | | | | | | | |
| | Knowsley: Building Schools for the Future + childrens services (£9.944m) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 259926000 | Signed | | | | | | | | | | | | | | | |
| | Lambeth: Connected learning [ICT project] | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 10748000 | Operational | | | | | | | | | | | | | | | |
| | Lambeth: Depot services | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Other | PFI credits: | 9625000 | Ended | | | | | | | | | | | | | | | |
| | Lambeth: Joint Service Centre - Streatham (LIFT) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Other | PFI credits: | 4208000 | Operational | | | | | | | | | | | | | | | |
| | Lambeth: Lilian Baylis school + Resource Centre | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 25400000 | Operational | | | | | | | | | | | | | | | |
| | Lambeth: Street lighting | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 17220000 | Operational | | | | | | | | | | | | | | | |
| | Lancashire : Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 90000000 | Operational | | | | | | | | | | | | | | | |
| | Lancashire Fire Authority: Fire stations | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Fire | PFI credits: | 5600000 | Operational | | | | | | | | | | | | | | | |
| | Lancashire: Building Schools for the Future Phase 1 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 94812000 | Signed | | | | | | | | | | | | | | | |
| | Lancashire: Building Schools for the Future Phase 2 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 111591000 | Signed | | | | | | | | | | | | | | | |
| | Lancashire: Fleetwood High School | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 13400000 | Operational | | | | | | | | | | | | | | | |
| | Leeds: Building Schools for the Future Phase 1 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 143500000 | Signed | | | | | | | | | | | | | | | |
| | Leeds: Building Schools for the Future Phases 2 & 3 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 42243000 | Signed | | | | | | | | | | | | | | | |
| | Leeds: Cardinal Heenan, replacement secondary school | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 4089058 | Operational | | | | | | | | | | | | | | | |
| | Leeds: HRA Pathfinder, Swarcliffe Estate | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing | PFI credits: | 78800000 | Operational | | | | | | | | | | | | | | | |
| | Leeds: Non HRA Round 3, (Independent Living) extra care (with DH) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing & DH | PFI credits: | 60100000 | Signed | | | | | | | | | | | | | | | |
| | Leeds: Phase 2, 10 primary schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 32000000 | Operational | | | | | | | | | | | | | | | |
| | Leeds: Phases 3&4, grouped schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 117510000 | Operational | | | | | | | | | | | | | | | |
| | Leeds: Seven schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 45200000 | Operational | | | | | | | | | | | | | | | |
| | Leeds: Street lighting | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 94600000 | Operational | | | | | | | | | | | | | | | |
| | Leicester: Building Schools for the Future Phase 1 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 63234000 | Signed | | | | | | | | | | | | | | | |
| | Leicester: Joint Service Centre - Charnwood (LIFT) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Other | PFI credits: | 2095000 | Signed | | | | | | | | | | | | | | | |
| | Leicester: Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 30841000 | Operational | | | | | | | | | | | | | | | |
| | Lewisham: 90 schools catering | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 4300000 | Operational | | | | | | | | | | | | | | | |
| | Lewisham: Building Schools for the Future Phase 1 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 118968000 | Signed | | | | | | | | | | | | | | | |
| | Lewisham: Downham lifestyles centre | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCMS | PFI credits: | 12659103 | Operational | | | | | | | | | | | | | | | |
| | Lewisham: Grouped schools modernisation project | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 60600000 | Operational | | | | | | | | | | | | | | | |
| | Lewisham: HRA Round 2, Brockley | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing | PFI credits: | 115900000 | Operational | | | | | | | | | | | | | | | |
| | Lincolnshire: Seven primary schools to address special needs | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 14100000 | Operational | | | | | | | | | | | | | | | |
| | Liverpool: Grouped schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 76000000 | Operational | | | | | | | | | | | | | | | |
| | Liverpool: Speke Forward Learning Centre (Parklands School) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF & CLG Other | PFI credits: | 20400000 | Operational | | | | | | | | | | | | | | | |
| | Manchester: Energy services | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing | PFI credits: | 3900000 | Operational | | | | | | | | | | | | | | | |
| | Manchester: Grouped schools scheme | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 35000000 | Operational | | | | | | | | | | | | | | | |
| | Manchester: HRA Pathfinder, Plymouth Grove/Stockport Road Estate | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing | PFI credits: | 36600000 | Operational | | | | | | | | | | | | | | | |
| | Manchester: HRA Round 2 (Miles Platting) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing | PFI credits: | 162000000 | Operational | | | | | | | | | | | | | | | |
| | Manchester: Street lighting | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 34100000 | Operational | | | | | | | | | | | | | | | |
| | Manchester: Temple School, replacement primary school | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 3667028 | Operational | | | | | | | | | | | | | | | |
| | Merton: Replacement of ten schools with six | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 56600000 | Operational | | | | | | | | | | | | | | | |
| | Newcastle & N Tyneside: Street lighting | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 44400000 | Operational | | | | | | | | | | | | | | | |
| | Newcastle: Building Schools for the Future Phase 1 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 51705000 | Signed | | | | | | | | | | | | | | | |
| | Newcastle: Four Secondary and Three Primary Schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 66500000 | Signed | | | | | | | | | | | | | | | |
| | Newcastle: Grouped Schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 47100000 | Operational | | | | | | | | | | | | | | | |
| | Newcastle: Joint Service Centres (LIFT) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Other | PFI credits: | 13700000 | Operational | | | | | | | | | | | | | | | |
| | Newcastle: Libraries | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCMS | PFI credits: | 40200000 | Signed | | | | | | | | | | | | | | | |
| | Newham: Achieving through innovation [ICT project] | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 14170000 | Operational | | | | | | | | | | | | | | | |
| | Newham: HRA Pathfinder, Canning Town | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing | PFI credits: | 31900000 | Operational | | | | | | | | | | | | | | | |
| | Newham: Schools project (procured jointly with Enfield) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 29050000 | Operational | | | | | | | | | | | | | | | |
| | Newham: Two new primary schools and one new secondary school | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 30000000 | Operational | | | | | | | | | | | | | | | |
| | Norfolk Police: Force HQ | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | HO | PFI credits: | 36542000 | Operational | | | | | | | | | | | | | | | |
| | Norfolk: Norwich area grouped schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 61360000 | Operational | | | | | | | | | | | | | | | |
| | Norfolk: Salt barns | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Other | PFI credits: | 1336800 | Operational | | | | | | | | | | | | | | | |
| | Norfolk: Street lighting | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 38100000 | Operational | | | | | | | | | | | | | | | |
| | North East Derbyshire: Non-HRA, social housing | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing | PFI credits: | 360545 | Operational | | | | | | | | | | | | | | | |
| | North Tyneside: Joint Service Centres - Dudley, Shiremoor (LIFT) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Other | PFI credits: | 9274000 | Operational | | | | | | | | | | | | | | | |
| | North Tyneside: Schools for the Future (4 schools) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 33500000 | Operational | | | | | | | | | | | | | | | |
| | North Wiltshire: Property accommodation | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Other | PFI credits: | 7431000 | Operational | | | | | | | | | | | | | | | |
| | North Yorkshire Fire Authority: Fire training facilities | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Fire | PFI credits: | 6630000 | Operational | | | | | | | | | | | | | | | |
| | North Yorkshire: Four primary schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 7241000 | Operational | | | | | | | | | | | | | | | |
| | Northamptonshire: 5 New Schools, 42 Refurbished and New Learning Discovery Centre | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 115900000 | Operational | | | | | | | | | | | | | | | |
| | Northamptonshire: Four elderly or mental health centres | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DH | PFI credits: | 14280000 | Operational | | | | | | | | | | | | | | | |
| | Northamptonshire: Secondary and Primary School & Community Facilities | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 23700000 | Operational | | | | | | | | | | | | | | | |
| | Northumberland: Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 40800000 | Operational | | | | | | | | | | | | | | | |
| | Northumbria Police: Stables | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | HO | PFI credits: | 1881000 | Operational | | | | | | | | | | | | | | | |
| | Norwich: "Connect" IT | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Other | PFI credits: | 12600000 | Operational | | | | | | | | | | | | | | | |
| | Nottingham: Building Schools for the Future Phase 1 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 75913000 | Signed | | | | | | | | | | | | | | | |
| | Nottingham: Joint Service Centre - Clifton & Hyson Green (LIFT) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF & CLG Other | PFI credits: | 13429000 | Operational | | | | | | | | | | | | | | | |
| | Nottingham: Nottingham Express Transit light rail scheme | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 174200000 | Operational | | | | | | | | | | | | | | | |
| | Nottinghamshire Police: Area traffic facility (accommodation & vehicles) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | HO | PFI credits: | 21460000 | Operational | | | | | | | | | | | | | | | |
| | Nottinghamshire: Bassetlaw, Phases 1 & 2 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 131620000 | Operational | | | | | | | | | | | | | | | |
| | Nottinghamshire: East Leake schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 17200000 | Operational | | | | | | | | | | | | | | | |
| | Nottinghamshire: Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 38310000 | Operational | | | | | | | | | | | | | | | |
| | Oldham: 2 secondary schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 58370000 | Operational | | | | | | | | | | | | | | | |
| | Oldham: HRA Round 2, sheltered housing | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing | PFI credits: | 132000000 | Operational | | | | | | | | | | | | | | | |
| | Oldham: Library & lifelong learning | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCMS & CLG Other | PFI credits: | 20990000 | Operational | | | | | | | | | | | | | | | |
| | Penwith: New sports and leisure and health facility | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCMS | PFI credits: | 6390000 | Operational | | | | | | | | | | | | | | | |
| | Peterborough: Secondary schools scheme | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 63740000 | Operational | | | | | | | | | | | | | | | |
| | Plymouth: Serviced accommodation & 6 primary schools + childrens services | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 49972000 | Operational | | | | | | | | | | | | | | | |
| | Portsmouth: Highway maintenance | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 121000000 | Operational | | | | | | | | | | | | | | | |
| | Portsmouth: New secondary school (Miltoncross School) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 12400000 | Operational | | | | | | | | | | | | | | | |
| | Portsmouth: Two day centres for people with learning difficulties | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DH | PFI credits: | 5323000 | Operational | | | | | | | | | | | | | | | |
| | Reading: HRA Pathfinder, North Whitley | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing | PFI credits: | 49600000 | Operational | | | | | | | | | | | | | | | |
| | Redbridge: Oaks Park School, new school | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 20000000 | Operational | | | | | | | | | | | | | | | |
| | Redcar & Cleveland: New primary schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 48970000 | Operational | | | | | | | | | | | | | | | |
| | Redcar & Cleveland: Office accommodation | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Other | PFI credits: | 13721000 | Operational | | | | | | | | | | | | | | | |
| | Redcar & Cleveland: Street lighting | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 21100000 | Operational | | | | | | | | | | | | | | | |
| | Richmond upon Thames: 6 primary schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 16772500 | Operational | | | | | | | | | | | | | | | |
| | Richmond upon Thames: Residential care homes | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DH | PFI credits: | 9535840 | Operational | | | | | | | | | | | | | | | |
| | Rochdale: Aiming High (1 Refurbishment & 3 New Build Schools) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 57548000 | Operational | | | | | | | | | | | | | | | |
| | Rochdale: Joint Service Centre - Heywood (LIFT) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Other | PFI credits: | 3004000 | Signed | | | | | | | | | | | | | | | |
| | Rotherham: 17 School (reducing to 15) Improvement Package | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 71400000 | Operational | | | | | | | | | | | | | | | |
| | Rotherham: Leisure & joint service centre | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCMS & CLG Other | PFI credits: | 24924000 | Signed | | | | | | | | | | | | | | | |
| | Salford: Schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 50230000 | Signed | | | | | | | | | | | | | | | |
| | Salford: Three Special High Schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 16200000 | Operational | | | | | | | | | | | | | | | |
| | Sandwell: Five primary schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 16894000 | Operational | | | | | | | | | | | | | | | |
| | Sandwell: HRA Pathfinder, Wednesbury South | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing | PFI credits: | 71000000 | Operational | | | | | | | | | | | | | | | |
| | Sefton: Crosby leisure centre | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCMS | PFI credits: | 6219000 | Operational | | | | | | | | | | | | | | | |
| | Selby: Non-HRA, 250 new homes | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing | PFI credits: | 6737938 | Operational | | | | | | | | | | | | | | | |
| | Sheffield: Building Schools for the Future + childrens services | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 93423000 | Signed | | | | | | | | | | | | | | | |
| | Sheffield: Office accommodation | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Other | PFI credits: | 28000000 | Operational | | | | | | | | | | | | | | | |
| | Sheffield: Phase 1, six schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 58750000 | Operational | | | | | | | | | | | | | | | |
| | Sheffield: Phase 2, two schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 31600000 | Operational | | | | | | | | | | | | | | | |
| | Sheffield: Phase 3 and pool (with DCMS) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF & DCMS | PFI credits: | 61100000 | Operational | | | | | | | | | | | | | | | |
| | Shropshire: Quality in Community services project | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DH & CLG Other | PFI credits: | 20400000 | Operational | | | | | | | | | | | | | | | |
| | Shropshire: Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 40800000 | Operational | | | | | | | | | | | | | | | |
| | Slough: Schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 48140000 | Operational | | | | | | | | | | | | | | | |
| | Solihull: Building Schools for the Future | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 86790000 | Signed | | | | | | | | | | | | | | | |
| | South Gloucestershire : Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 34300000 | Operational | | | | | | | | | | | | | | | |
| | South Tyneside & Gateshead: Building Schools for the Future Phase 1 | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 31503000 | Signed | | | | | | | | | | | | | | | |
| | South Tyneside: Bolden school (with DCMS) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF & DCMS | PFI credits: | 18663000 | Operational | | | | | | | | | | | | | | | |
| | South Tyneside: Street lighting | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 31500000 | Operational | | | | | | | | | | | | | | | |
| | South Yorkshire PTE: Doncaster interchange | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 26184000 | Operational | | | | | | | | | | | | | | | |
| | Southampton: Three secondary schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 42646000 | Operational | | | | | | | | | | | | | | | |
| | Southwark: Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 34500000 | Operational | | | | | | | | | | | | | | | |
| | Staffordshire: New children's home | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DH | PFI credits: | 5252000 | Operational | | | | | | | | | | | | | | | |
| | Staffordshire: Street lighting | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 18000000 | Operational | | | | | | | | | | | | | | | |
| | Staffordshire: Two schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 13783000 | Operational | | | | | | | | | | | | | | | |
| | Stockton-on-Tees: New primary and new secondary school / Ingleby Barwick | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 6450000 | Operational | | | | | | | | | | | | | | | |
| | Stoke: 126 schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 93000000 | Operational | | | | | | | | | | | | | | | |
| | Stoke: Joint Service Centre - Bentilee | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Other | PFI credits: | 13682000 | Operational | | | | | | | | | | | | | | | |
| | Stoke: Street lighting | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 16000000 | Operational | | | | | | | | | | | | | | | |
| | Suffolk: Fire stations | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Fire | PFI credits: | 27140000 | Signed | | | | | | | | | | | | | | | |
| | Sunderland (Tyne & Wear Fire Authority): Strategic Review of Fire Cover | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Fire | PFI credits: | 29770000 | Operational | | | | | | | | | | | | | | | |
| | Sunderland: Sandhill View school and community facilities | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF & CLG Other | PFI credits: | 17744000 | Operational | | | | | | | | | | | | | | | |
| | Sunderland: Street lighting | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 25881000 | Operational | | | | | | | | | | | | | | | |
| | Surrey : Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 85500000 | Operational | | | | | | | | | | | | | | | |
| | Surrey: Residential homes | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DH | PFI credits: | 28800000 | Operational | | | | | | | | | | | | | | | |
| | Sussex Police: Centralised custody | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | HO | PFI credits: | 1250000 | Operational | | | | | | | | | | | | | | | |
| | Sussex Police: New custody suites | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | HO | PFI credits: | 38000000 | Operational | | | | | | | | | | | | | | | |
| | Swindon: Seven new schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 62800000 | Operational | | | | | | | | | | | | | | | |
| | Tameside: Hattersley schools rationalisation | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 20900000 | Operational | | | | | | | | | | | | | | | |
| | Telford & Wrekin: Hadley Learning & Jigsaw Project | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF & DCMS | PFI credits: | 70010000 | Operational | | | | | | | | | | | | | | | |
| | Thames Valley Police: Force HQ | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | HO | PFI credits: | 10406000 | Operational | | | | | | | | | | | | | | | |
| | Torbay: Westlands & Homelands School | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 14400000 | Operational | | | | | | | | | | | | | | | |
| | Tower Hamlets: Barkantine Energy services | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing | PFI credits: | 6237000 | Operational | | | | | | | | | | | | | | | |
| | Tower Hamlets: Grouped schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 89164000 | Operational | | | | | | | | | | | | | | | |
| | Tower Hamlets: Mulberry School, secondary school and sports hall | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF & CLG Other | PFI credits: | 19300000 | Operational | | | | | | | | | | | | | | | |
| | Trafford: Sale civic centre office accommodation | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Other | PFI credits: | 6940000 | Operational | | | | | | | | | | | | | | | |
| | Uttlesford: Three new sports & leisure centres | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCMS | PFI credits: | 5790000 | Operational | | | | | | | | | | | | | | | |
| | Wakefield: Street lighting | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 16200000 | Operational | | | | | | | | | | | | | | | |
| | Walsall: Replacement of St Thomas Moore secondary school | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 8200000 | Operational | | | | | | | | | | | | | | | |
| | Walsall: Street lighting | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DfT | PFI credits: | 18600000 | Operational | | | | | | | | | | | | | | | |
| | Waltham Forest: Building Schools for the Future | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 53910000 | Signed | | | | | | | | | | | | | | | |
| | Waltham Forest: Grouped schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 53600000 | Operational | | | | | | | | | | | | | | | |
| | Waltham Forest: New secondary school (Lammas School) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 18500000 | Operational | | | | | | | | | | | | | | | |
| | Warrington: Non-HRA, Anson & Blenheim Close | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | CLG Housing | PFI credits: | 6300000 | Operational | | | | | | | | | | | | | | | |
| | Warwickshire: e-learning [ICT project] | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 10150000 | Operational | | | | | | | | | | | | | | | |
| | West Berkshire: Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 28490000 | Operational | | | | | | | | | | | | | | | |
| | West Sussex: Crawley schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 57325000 | Operational | | | | | | | | | | | | | | | |
| | West Sussex: Waste | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DEFRA | PFI credits: | 25000000 | Operational | | | | | | | | | | | | | | | |
| | Westminster: Care services | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DH | PFI credits: | 4267085 | Operational | | | | | | | | | | | | | | | |
| | Wiltshire Police: Divisional HQ (Swindon) | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | HO | PFI credits: | 23979000 | Operational | | | | | | | | | | | | | | | |
| | Wiltshire Police: Helicopters | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | HO | PFI credits: | 3053000 | Operational | | | | | | | | | | | | | | | |
| | Wiltshire: Three North Wiltshire schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 38565000 | Operational | | | | | | | | | | | | | | | |
| | Wirral: 9 schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 58500000 | Operational | | | | | | | | | | | | | | | |
| | Wolverhampton: Leisure | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCMS | PFI credits: | 10917000 | Operational | | | | | | | | | | | | | | | |
| | Worcestershire & Wolverhampton: Virtual workspace [ICT project] | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 9032000 | Operational | | | | | | | | | | | | | | | |
| | Worcestershire: Bromsgrove schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 63250000 | Operational | | | | | | | | | | | | | | | |
| | York: Three primary schools | | | | | | | | | | | | | | | |
| | Sponsoring Dept: | DCSF | PFI credits: | 15400000 | Operational | | | | | | | | | | | | | | | |