This is an HTML version of an attachment to the Freedom of Information request 'performance of Council's email filtering system'.

0x01 graphic

Item no

Report no

BT Partnership - Continuous Improvement

Finance & Resources Committee

16 June 2009

1 Purpose of report

1.1 To present plans developed in consultation with service departments for improvements over the next three years of the Council's partnership with BT. The report also highlights improvements made in the last year following formal endorsement of the extension of the partnership to 2016 as approved by Council on 21 February 2008

2 Background

2.1 The Council approved renegotiated terms of its partnership with BT in February 2006. In summary, based on successful delivery of a specified change programme over a two year period then £22.3m of cash-releasing efficiency savings would be released and the Council would extend its relationship with BT until 2016.

2.2 The change programme included refresh of both corporate and school desktop estates, new processes for managing user requests and improvements to governance and working arrangements. In parallel, the Council agreed one-off investment to refresh desktop computers within schools which were owned by the Council rather than BT.

2.3 The programme was to be judged both by delivery and results of these specific projects but also by improved user and senior management satisfaction with the ICT service.

2.4 On the 21 February 2008, the Council reviewed the success of the programme and endorsed extension of the partnership to 2016. It was agreed that BT and the Council should build on the success of the arrangements in place over the previous two years and formalise a further programme of continuous improvement.

3 Improvement Programme

3.1 Detailed consultation has been undertaken with departments and users over the last year. A programme has been designed focused around five themes:

3.2 Appendix 1 provides a list of the activities proposed against each of the themes over the next three years. Formal plans and specific measurable targets for these improvements will now be defined and reported as part of regular six monthly performance reports to Committee.

3.3 In overall terms, the design of the improvement programme requires to deliver value for both partners. In the detailed design and planning of particular workstreams this will be considered. In particular, It should be noted that significant unbudgeted investment will require to be addressed by the Council to manage obsolescence of ICT equipment in schools.

3.4 Over the last year substantial progress has been made against these themes including:

3.5 The Continuous Improvement Programme will seek to build on these successes but also provide a structured programme to communicate with ICT service users on planned development of the service.

4 Financial Implications

4.1 The programme will largely be delivered within the existing resources of the partnership. However there are significant unbudgeted financial implications to manage obsolesence of ICT equipment in schools owned by the Council over the period to 2016.

5 Recommendations

5.1 It is recommended that Finance & Resources Committee:

(i) endorse the plans to refine and build on the model of partnership working with BT; and,

(ii) note the progress made in continuous improvement over the last year.

Jim Inch

Director of Corporate Services

Appendices

Appendix 1 - Improvement Programme

Contact/tel

Wards affected

All wards

Background Papers


APPENDIX 1

PARTNERSHIP TRANSFORMATION PROGRAMME II DRAFT

Theme

Activity

Progress to date

Planned 2009/10

Planned 2010+

Leadership

Communications Plan

Communications Plan for 2009/10 agreed by JMT but this will require to be updated once overall work programme is agreed.

Delivery of communications plans including Senior Manager Event planned for May

Leadership

Review effectiveness of governance arrangements

Head of E-Gov has met HoS who value group.

BT consultancy review underway.

Complete review and present proposals to Transformation Board.

Leadership

Undertake a review of retained ICT organisation across the Council

Initial assessment undertaken and consultation on terms of reference with SCSG and Trade Unions.

Complete review and present proposals to Transformation Board and Trade Unions.

Theme

Activity

Progress to date

Planned 2009/10

Planned 2010+

Strategy

Develop ICT Work Programme from SPOW/ICT Strategy

ICT Strategy approved by SCSG and Elected Member Sounding Board. Work is being taken forward to document work programme for SCSG on 22 April.

Communicate and consult on plans prior to presentation to F&R on 13/6. Refine and review for 2010/11.

Strategy

Develop Innovation within the Partnership

Innovation Sessions have taken place in relation to Sustainability and Telecare. Workstyle business case in preparation.

Further Innovation Sessions particularly on City Vision 2030 + Visit to Adastral. Need to move one idea from forum to real delivery project. Consider potential of infrastructure refresh.

Strategy

Additional consultancy

Substantial consultancy provided for Swift, JV, Workstyle, Customer Services, E-HR, C&F Practice Team projects

Consider how consultancy can be taken forward as due to lack of investment by Council in 2008/9 no contractual requirement for support from BT

Theme

Activity

Progress to date

Planned 2009/10

Planned 2010+

Infrastructure

Desktop Refresh

Still some legacy issues with 150 machines outstanding from Refresh 1. Workstyle analysis will support next refresh being tailored to need.

Detailed design of corporate refresh.

Implementation of corporate refresh.

Infrastructure

Learning & Teaching Estate Refresh

Proposal developed by BT to meet reduced budget approved by Council. VfM assessment required.

Need to undertake detailed design work for refreshed estate within an agreed financial envelope.

Implementation of Learning & Teaching refresh.

Infrastructure

Datacentre and networks Refresh

Significant investment programme underway by BT in 21st Century MAN, F12K replacement and new SAN.

Need to agree plans and upgrade data centre infrastructure

Implementation of plans.

Infrastructure

Bandwidth increases for schools to reflect increased demand

All high schools and 12 primaries have been provided upgraded bandwidth

Upgrade of LANs in primaries through GLOW project. Provide rates for further upgrades to be funded through DSM.

Process Improvement

Targeted Improvement in Change Process

Plans have been agreed by JMT for improvement and are being closely monitored. Communicated to Department ICT Steering Groups.

Implementation and monitoring of results.

Process Improvement

Development partnership processes around capacity management to reflect ITIL best practice

Terms of Reference for Demand and Capacity Group agreed. First meeting taken place. Capacity plan for infrastructure upgrades prepared by BT.

Extend approach and formalise demand and capacity planning with reports to SCSG and JMT.

Theme

Activity

Progress to date

Planned 2009/10

Planned 2010+

Process Improvement

Develop Partnership processes around management of incidents

Formal incident management process in place with improvement actions identified which are then tracked by JMT.

Continually refine process

Process Improvement

Development partnership processes around business continuity

Creation of the Information Asset Register has provided a formal basis for understanding Council-wide the risks and to develop a programme of consultation with departments.

E-Gov will work with critical business areas to understand their business continuity plans and test that partnership agreement and SLAs meet their requirements.

Continued work with departments.

Process Improvement

Information Security processes to be updated to reflect best practice

Information Asset Register created. Security Awareness Programme underway. Information Governance Group remit agreed.

Agree proposals for laptop encryption and USB Device Control subject to funding. Further awareness programme. Information Governance Group meeting regularly.

Process Improvement

Arrangements to obtain better evidence of actual benefits realisation from business cases

BT have provided training to staff in E-Government and departments on benefits realisation.

Ensure all Project Boards focus on monitoring and tracking of benefits case.

Process Improvement

Refine and improve the effectiveness of the Joint Programme Management Office

PMO reporting and assurance taking place on monthly basis to JMT.

Refine reporting and assurance processes. Adopt model into Council Standing Orders as per recent Construction Projects report.

Service Improvement

Refinement of Granularity of Core Bill

Proposals agreed by E-Government and BT.

E-Government and Finance need to realign of central support charges.

Theme

Activity

Progress to date

Planned 2009/10

Planned 2010+

Service Improvement

Same Day Fix on Corporate Desktop

In practice, 90% of desktop fixes are delivered within 24 hours.

Formalise with new desktop SLA with service credits only applying if X% are not met within target during period. Actual % to be agreed.

Service Improvement

Reshape current support arrangements

New support arrangements in place around Oracle Financials and Web. Contact Central decommissioned.

Replace Hyperwave platform.

Service improvement

Consider potencial for increased SLAs / continuity plans for critical services

Investments in data centre by BT provide the opportunity for enhanced continuity services to be commissioned by the Council in future.

Through reviews with business areas identify within resource constraints what can be achieved.

Service Improvement

Reshape current arrangements for print to secure best value

BT have provided a proposal for combining Data Centre Printing and CEC Reprographic facility to deliver significant efficiency savings. Proposals for Online payslips developed.

CEC considering proposals but parallel work being undertaken to improve print within Revs and Bens service and to simplify Gateshead operation. Online payslips implemented.