This is an HTML version of an attachment to the Freedom of Information request 'Structure of Student Lifecycle Project'.
 
 
Additional information about procurement and due diligence stage of 
Student Lifecycle Project 
 
The organisational structure for the procurement and due diligence stage of 
Student Lifecycle Project and the start and end dates for each position are 
attached. 
 
The total cost to the project for staffing costs in this phase (October 2007 to 
May 2009) was £272,190. In most cases the costs related to backfill for 
departments and services from which team members were seconded. The 
only posts which were fully funded by the project were the fixed term project 
office posts. 
 
The total cost of external programme management consultancy support 
during this phase was £235,483. During the due diligence phase consultancy 
was also provided by a specialist IT consultancy working in partnership with 
the supplier. The costs of this were £293,982.