Additional information about procurement and due diligence stage of
Student Lifecycle Project
The organisational structure for the procurement and due diligence stage of
Student Lifecycle Project and the start and end dates for each position are
attached.
The total cost to the project for staffing costs in this phase (October 2007 to
May 2009) was £272,190. In most cases the costs related to backfill for
departments and services from which team members were seconded. The
only posts which were fully funded by the project were the fixed term project
office posts.
The total cost of external programme management consultancy support
during this phase was £235,483. During the due diligence phase consultancy
was also provided by a specialist IT consultancy working in partnership with
the supplier. The costs of this were £293,982.