SCR Implementation project timeline
Month from start of implementation
1
2
3
4
5
6
7
8
9
Stage
0
Stage
1
Stage 2
Stage 3
Stage 4
Implementation
stages
Prepare for
Initiate
Prepare for Go Live
Go Live
Support
Implementation
Assess
Lessons Learnt /
Programme Initiation
Planning & Reporting
Readiness
Project Close
Programme
Deployment
strategies
Management
Benefits planning
Benefits realisation
Benefits
Business
strategy
Change
Establish & implement local business processes
Embed local processes
Engagement activities
Public Information Programme
Stakeholder
GP Summary
Engagement
Patient support
Creation
stategy andplan
DQ preparation
Data Quality improvements, Accreditation (GP Systems)
Ongoing support and maintenance
Go-live activities
Training preparation and delivery
Floor walking and training support
Training
Training preparation and delivery
Ongoing support and training
strategy
HealthSpace
Communications preparation
Comms strategy
Healthspace promotion activities
activities
Set up registration points
NHS number
Urgent & Unscheduled Care Setting Data Quality improvements
population
Review and implement infrastructure requirements
SCR application
Training
Floor walking and training
Training preparation and delivery
Implementation
strategy
support
Comms engagement
Create
activities
Develop
workgroups
required
Issue/update
Map, test and approve alert process
infrastructure
smartcards
PID/Business Case
SCR upload
PIP completion
complete
Gateway criteria /
Readiness Assessment
Wave approach
PCT Benefits defined
DQ Accreditation
Resource Plan
Project Close/
products required
IG process approved
Business Change Plan
Lessons Learnt
SCR/HS Communications Plan
Benefits Realisation
Plan
Programme
Communications
Information
Key:
Data quality
Business Change
Training
IT & Infrastructure
Management
& Engagement
Governance