| SCHEMES WITH FULL APPROVAL, AS SHOWN IN MEDIUM TERM PLAN SUBMISSIONS SEPTEMBER 2007. | ||||||||||||
| Anglian Central EA | Previous Years | 2007/08 | 2008/09 | 2009/10 | 2010/11 | 2011/12 | ||||||
| Project Name | Committee Name | Coastal Erosion (CE) or Flooding (FL)? | Funding Code | Approval Status | Spend to Date (£000s) | Year 0 (£000s) | Priority Score | Year 1 (£000s) | Year 2 (£000s) | Year 3 (£000s) | Year 4 (£000s) | |
| Committed Schemes | ||||||||||||
| Ouse Washes Habitat Creation project | Anglian Central | FL | CM | A | 173 | 655 | Exempt | 1615 | 5897 | 4202 | 983 | |
| Denver Little Eyes Refurbishment, Stage 1 | Anglian Central | FL | CM | A | 109 | 624 | 41 | 20 | ||||
| Hunstanton / Heacham Beach Recycling | Anglian Central | CE | CM | A | 65 | 24 | 65 | 65 | 65 | |||
| Hunstanton/Heacham beach monitoring | Anglian Central | CE | CM | A | 35 | 24 | 35 | 35 | 35 | 5 | ||
| St Ives and the Hemingfords FAS | Anglian Central | FL | DEF | A | 5141 | 622 | 24 | 96 | 20 | |||
| Hunstanton New Defences | Anglian Central | CE | DEF | A | 9916 | 40 | 20 | 10 | ||||
| Middle Level Barrier Banks Urgent Works | Anglian Central | FL | CM | A | 1551 | 79 | 17 | 10 | ||||
| Alexandra Dock Gates ABP/EA | Anglian Central | FL | CM | A | 13 | 320 | 100 | |||||
| SCHEMES WITH FULL APPROVAL, AS SHOWN IN MEDIUM TERM PLAN SUBMISSIONS SEPTEMBER 2007. | |||||||||||||
| Anglian Northern EA | Previous Years | 2007/08 | 2008/09 | 2009/10 | 2010/11 | 2011/12 | |||||||
| Project Name | Committee Name | Coastal Erosion (CE) or Flooding (FL)? | Funding Code | Approval Status | Spend to Date (£000s) | Year 0 (£000s) | Priority Score | Year 1 (£000s) | Year 2 (£000s) | Year 3 (£000s) | Year 4 (£000s) | ||
| Committed Schemes | |||||||||||||
| Dog in a Doublet Sluice M&E Refurbishment | Anglian Northern | FL | CM | A | 300 | 36 | 765 | ||||||
| Wisbech Defences | Anglian Northern | FL | CM | A | 350 | 405 | 32 | 3542 | 4827 | 1536 | |||
| Humber Stallingborough | Anglian Northern | CE | DEF | A | 175 | 500 | 29 | 5042 | 100 | ||||
| Lincshore 2005 to 2010 | Anglian Northern | CE | DEF | A | 16651 | 8522 | 25 | 7675 | 7500 | ||||
| Northampton Flood Alleviation Scheme | Anglian Northern | FL | DEF | A | 8394 | 47 | 24 | 1 | |||||
| Weedon | Anglian Northern | FL | DEF | A | 1942 | 6 | 24 | 1 | |||||
| River Witham Phase 2 | Anglian Northern | FL | DEF | A | 171 | 73 | 22 | 2 | |||||
| River Witham Phase 3 | Anglian Northern | FL | DEF | A | 141 | 32 | 22 | 2 | |||||
| Safety Works Bridges W&N | Anglian Northern | FL | CM | A | 150 | 250 | 500 | 500 | |||||
| Tidal Nene Stabilisation | Anglian Northern | FL | CM | A | 1451 | 428 | 3 | ||||||
| SCHEMES WITH FULL APPROVAL, AS SHOWN IN MEDIUM TERM PLAN SUBMISSIONS SEPTEMBER 2007. | ||||||||||||||
| Anglian Eastern EA | Previous Years | 2007/08 | 2008/09 | 2009/10 | 2010/11 | 2011/12 | ||||||||
| Project Name | Committee Name | Coastal Erosion (CE) or Flooding (FL)? | Funding Code | Approval Status | Spend to Date (£000s) | Year 0 (£000s) | Priority Score | Year 1 (£000s) | Year 2 (£000s) | Year 3 (£000s) | Year 4 (£000s) | |||
| Committed Schemes | ||||||||||||||
| Jaywick Sea Defences - Bay 3 | Anglian Eastern | FL | DEF | A | 272 | 16 | 28 | 8170 | 31 | |||||
| Gt Yarmouth FD - Remaining Works | Anglian Eastern | FL | DEF | A | 396 | 260 | 27 | 850 | 12550 | 210 | ||||
| Southwold - Easton Bavents | Anglian Eastern | CE | DEF | A | 1878 | 85 | 23 | 10 | 1 | |||||
| Halstead (River Colne) | Anglian Eastern | FL | DEF | A | 4036 | 9 | 17 | 3 | ||||||
| Salthouse Flood Protection | Anglian Eastern | FL | CM | A | 2619 | 345 | 16 | 66 | 27 | |||||
| Minsmere Flood Management Project | Anglian Eastern | FL | CM | A | 78 | 78 | 12 | 152 | 2066 | |||||
| Happisburgh/Winterton 3B Works | Anglian Eastern | CE | CM | A | 213 | 154 | 10 | 7164 | 50 | |||||
| Walberswick to Dunwich Frontage | Anglian Eastern | FL | CM | A | 113 | 64 | 0 | 50 | 450 | 430 | ||||
| Easton Broad Flood Management Project | Anglian Eastern | FL | CM | A | 350 | 144 | 0 | 73 | ||||||
| Broadland PPPP | Anglian Eastern | FL | CM | A | 35474 | 10200 | 10400 | 11400 | 14400 | 10900 | ||||
| Broadland PPPP (over-programme) | Anglian Eastern | FL | CM | A | 2000 | |||||||||
| Ipswich FDMS: Wet Dock Gates Replacement | Anglian Eastern | FL | CM | A | 1000 | 500 | 60 | |||||||
| Ipswich FDMS: Civil Works | Anglian Eastern | FL | CM | A | 430 | 20 | ||||||||
| SCHEMES WITH FULL APPROVAL, AS SHOWN IN MEDIUM TERM PLAN SUBMISSIONS SEPTEMBER 2007. | ||||||||||||
| Midlands EA | Previous Years | 2007/08 | 2008/09 | 2009/10 | 2010/11 | 2011/12 | ||||||
| Project Name | Committee Name | Coastal Erosion (CE) or Flooding (FL)? | Funding Code | Approval Status | Spend to Date (£000s) | Year 0 (£000s) | Priority Score | Year 1 (£000s) | Year 2 (£000s) | Year 3 (£000s) | Year 4 (£000s) | |
| Committed Schemes | ||||||||||||
| GAINSBOROUGH FRONTAGES | Midlands | FL | DEF | A | 1512 | 2000 | 28 | 5560 | 7560 | |||
| GAINSBOROUGH FRONTAGES (over-programme) | Midlands | FL | DEF | A | 0 | 0 | 28 | 2000 | 0 | |||
| NOTTINGHAM TRENT LEFT BANK FAS | Midlands | FL | DEF | A | 2223 | 816 | 27 | 500 | 500 | 8000 | 13000 | |
| KEADBY TO AMCOTTS | Midlands | FL | DEF | A | 1966 | 104 | 24 | 36 | ||||
| RIVER CHELT COMBINED WORKS CONTRACT (P4-P7) | Midlands | FL | DEF | A | 11096 | 208 | 18 | 300 | ||||
| HEREFORD (BELMONT) | Midlands | FL | DEF | A | 215 | 3530 | 16 | 315 | ||||
| KEADBY PUMPING STATION (MEICA) | Midlands | FL | CM | A | 566 | 1000 | 600 | |||||
| ALKBOROUGH | Midlands | FL | DEF | A | 2257 | 402 | String Table Error | 134 | ||||
| SCHEMES WITH FULL APPROVAL, AS SHOWN IN MEDIUM TERM PLAN SUBMISSIONS SEPTEMBER 2007. | ||||||||||||
| North East - Yorkshire EA | Previous Years | 2007/08 | 2008/09 | 2009/10 | 2010/11 | 2011/12 | ||||||
| Project Name | Committee Name | Coastal Erosion (CE) or Flooding (FL)? | Funding Code | Approval Status | Spend to Date (£000s) | Year 0 (£000s) | Priority Score | Year 1 (£000s) | Year 2 (£000s) | Year 3 (£000s) | Year 4 (£000s) | |
| Committed Schemes | ||||||||||||
| Hull TSB Drive Sync | NE Yorkshire | FL | CM | A | 310 | 240 | 27 | 2830 | 2100 | |||
| Stoning - Tidal (Dales) | NE Yorkshire | FL | CM | A | 762 | 150 | 24 | 150 | 150 | 150 | 150 | |
| Wakefield (Ph 2) | NE Yorkshire | FL | DEF | A | 9963 | 250 | 19 | 800 | ||||
| Selby Tidal Defences | NE Yorkshire | FL | DEF | A | 12817 | 4321 | 18 | 115 | ||||
| SCHEMES WITH FULL APPROVAL, AS SHOWN IN MEDIUM TERM PLAN SUBMISSIONS SEPTEMBER 2007. | ||||||||||||
| North West EA | Previous Years | 2007/08 | 2008/09 | 2009/10 | 2010/11 | 2011/12 | ||||||
| Project Name | Committee Name | Coastal Erosion (CE) or Flooding (FL)? | Funding Code | Approval Status | Spend to Date (£000s) | Year 0 (£000s) | Priority Score | Year 1 (£000s) | Year 2 (£000s) | Year 3 (£000s) | Year 4 (£000s) | |
| Committed Schemes | ||||||||||||
| Stanah Sea Defences | North West | FL | DEF | A | 24 | 370 | 30 | 1135 | ||||
| Altmouth PS Urgent Works 07/08 | North West | FL | DEF | A | 13 | 1712 | 28 | 2800 | 4700 | 4758 | ||
| Altmouth PS Urgent Works 07/08 (over-programming) | North West | FL | DEF | A | 28 | 1000 | ||||||
| River Eden/Petteril Flood Defences, Carlisle | North West | FL | DEF | A | 1293 | 5123 | 24 | 59 | ||||
| Lower Lancaster FAS | North West | FL | DEF | A | 2626 | 3347 | 23 | 444 | ||||
| Thacka Beck, Penrith | North West | FL | DEF | A | 179 | 22 | 290 | 880 | 4250 | |||
| River Douglas, Wigan | North West | FL | DEF | A | 781 | 22 | 290 | 3500 | 3000 | |||
| Carlisle City & Caldew | North West | FL | DEF | F | 318 | 1297 | 20.0065454545455 * | 5400 | 9325 | 120 | ||
| Carlisle City & Caldew (over-programming) | North West | FL | DEF | F | 0 | 0 | 20.0065454545455 * | 2000 | 0 | 0 | ||
| SCHEMES WITH FULL APPROVAL, AS SHOWN IN MEDIUM TERM PLAN SUBMISSIONS SEPTEMBER 2007. | ||||||||||||||
| South West EA | Previous Years | 2007/08 | 2008/09 | 2009/10 | 2010/11 | 2011/12 | ||||||||
| Project Name | Committee Name | Coastal Erosion (CE) or Flooding (FL)? | Funding Code | Approval Status | Spend to Date (£000s) | Year 0 (£000s) | Priority Score | Year 1 (£000s) | Year 2 (£000s) | Year 3 (£000s) | Year 4 (£000s) | |||
| Committed Schemes | ||||||||||||||
| Shaldon | South West | FL | DEF | A | 376 | 308 | 23 | 183 | 3168 | 2517 | ||||
| Padstow Harbour | South West | FL | DEF | A | 1107 | 301 | 22 | 5 | ||||||
| St. Ives | South West | FL | DEF | A | 4216 | 5054 | 21 | 908 | ||||||
| Boscastle - Valency Phase 3 | South West | FL | DEF | A | 2229 | 4011 | 19 | 834 | ||||||
| Flexbury, Bude | South West | FL | DEF | A | 295 | 889 | 17 | 953 | ||||||
| SCHEMES WITH FULL APPROVAL, AS SHOWN IN MEDIUM TERM PLAN SUBMISSIONS SEPTEMBER 2007. | ||||||
| Wessex EA | 2008/09 | 2009/10 | 2010/11 | 2011/12 | ||
| Project Name | Year 1 (£000s) | Year 2 (£000s) | Year 3 (£000s) | Year 4 (£000s) | ||
| Committed Schemes | ||||||
| HILLFARRANCE SUPPLEMENTARY WORKS | Wessex FDC | 40 | ||||
| Bruton Dam Reservoir Improvements (Legal override) | Wessex FDC | 679 | 40 | |||
| Langport Lock Decommissioning 07-08 contingency | Wessex FDC | 310 | ||||
| SCHEMES WITH FULL APPROVAL, AS SHOWN IN MEDIUM TERM PLAN SUBMISSIONS SEPTEMBER 2007. | ||||||||||||||
| Southern EA | Previous Years | 2007/08 | 2008/09 | 2009/10 | 2010/11 | 2011/12 | ||||||||
| Project Name | Committee Name | Coastal Erosion (CE) or Flooding (FL)? | Funding Code | Approval Status | Spend to Date (£000s) | Year 0 (£000s) | Priority Score | Year 1 (£000s) | Year 2 (£000s) | Year 3 (£000s) | Year 4 (£000s) | |||
| Committed Schemes | ||||||||||||||
| DARTFORD CREEK BARRIER 2030 | Southern | FL | CM | A | 115 | 240 | 31 | 858 | 2459 | 20 | ||||
| PEVENSEY BAY SEA DEFENCES PPP | Southern | FL | CM | A | 11664 | 2109 | 27 | 1972 | 1972 | 1972 | 1292 | |||
| HIGH KNOCKE TO DYMCHURCH REDOUBT SD PHASES 1 & 2 | Southern | FL | DEF | A | 19171 | 11475 | 27 | 3500 | 7000 | 5000 | 3000 | |||
| HIGH KNOCKE TO DYMCHURCH REDOUBT SD PHASES 1 & 2 (over-programme) | Southern | FL | DEF | A | 27 | 1000 | ||||||||
| DENGE BEACH MANAGEMENT OPS - 08/12 PAR | Southern | FL | CM | F | 15 | 27 | 1846 | 1846 | 1846 | 1846 | ||||
| LITTLESTONE TO ST MARY'S BAY DYMCHURCH | Southern | FL | DEF | A | 8710 | 2 | 27 | 450 | 450 | |||||
| BULVERHYTHE CAPITAL MAINTENANCE 2007/08 - 2011/12 | Southern | FL | CM | E | 16 | 91 | 25 | 300 | 300 | 300 | 300 | |||
| LYMINGTON RIVER FAS | Southern | FL | DEF | A | 832 | 3383 | 23 | 30 | 5 | |||||
| R.ROTHER TIDAL WALLS IMP SCHEME (WEST) | Southern | FL | DEF | A | 9547 | 63 | 23 | 10 | ||||||
| PETT SHINGLE NOURISHMENT PH2-6 | Southern | FL | DEF | A | 10743 | 785 | 13 | 750 | 550 | 569 | 1611 | |||
| SCHEMES WITH FULL APPROVAL, AS SHOWN IN MEDIUM TERM PLAN SUBMISSIONS SEPTEMBER 2007. | ||||||||||||||
| Thames EA | Previous Years | 2007/08 | 2008/09 | 2009/10 | 2010/11 | 2011/12 | ||||||||
| Project Name | Committee Name | Coastal Erosion (CE) or Flooding (FL)? | Funding Code | Approval Status | Spend to Date (£000s) | Year 0 (£000s) | Priority Score | Year 1 (£000s) | Year 2 (£000s) | Year 3 (£000s) | Year 4 (£000s) | |||
| Committed Schemes | ||||||||||||||
| Marley Waterproofing. R39.01 | Thames | FL | CM | A | 379 | 428 | 32 | 4 | ||||||
| Marley Waterproofing, R39.02 | Thames | FL | CM | A | 275 | 369 | 32 | 11 | ||||||
| Queenhithe Wharf Frontage N230, Repair & Strength | Thames | FL | CM | A | 200 | 1317 | 30 | 15 | ||||||
| Wedges Yard Trash Screen | Thames | FL | CM | A | 115 | 80 | 30 | 350 | 10 | |||||
| Salmons Brook FAS | Thames | FL | DEF | A | 1063 | 383 | 29 | 300 | 1786 | 7316 | 1625 | |||
| Graveney Siphon & Defences | Thames | FL | CM | A | 105 | 314 | 28 | 370 | ||||||
| East Clandon Stream at Send | Thames | FL | DEF | A | 405 | 463 | 28 | 5 | ||||||
| W Enfield Flood Storage Tank Impts | Thames | FL | CM | A | 113 | 167 | 27 | 10 | ||||||
| TBAG: Thames Barrier Corrosion Protection System | Thames | FL | CM | A | 480 | 893 | 26 | 1072 | 1300 | 1450 | 2862 | |||
| TBAG TB Pier Crane Modernisation | Thames | FL | CM | A | 37 | 104 | 26 | 1230 | 900 | |||||
| TBAG Remaining BarkingBar works from TBAG Strategy | Thames | FL | CM | A | 200 | 26 | 236 | 427 | 335 | 352 | ||||
| TBAG TB Logic Control Systems Upgrade | Thames | FL | CM | A | 429 | 26 | 610 | 765 | ||||||
| TBAG TB Parvallux Replacements | Thames | FL | CM | A | 13 | 60 | 26 | 100 | 700 | 700 | ||||
| TBAG Remaing King GeorgeV works from TBAG Strategy | Thames | FL | CM | A | 50 | 26 | 128 | 285 | 187 | 63 | ||||
| TBAG TB Replacement Tools & Equipment | Thames | FL | CM | A | 211 | 52 | 26 | 85 | 87 | 89 | 91 | |||
| TBAG: TB Associated Gates Corrosion Protection Systems | Thames | FL | CM | A | 4 | 190 | 26 | 250 | ||||||
| TBAG Shift & Latch Mechanism | Thames | FL | CM | A | 160 | 88 | 26 | 88 | ||||||
| TBAG Remaining Flap works from TBAG Strategy | Thames | FL | CM | A | 25 | 26 | 69 | 79 | 4 | 4 | ||||
| TBAG Remaining Gallions works from TBAG Strategy | Thames | FL | CM | A | 31 | 26 | 21 | 31 | 31 | 31 | ||||
| TBAG Improve Comms Links to TB Assoc. Gates | Thames | FL | CM | A | 6 | 15 | 26 | 30 | ||||||
| Dartford Creek Frontage KO36 - 40 | Thames | FL | DEF | A | 3194 | 1913 | 25 | 72 | ||||||
| Moor Lane Offtake - Staines Bypass Channel | Thames | FL | CM | A | 190 | 77 | 23 | 5 | ||||||
| Erith Green Level PS | Thames | FL | DEF | A | 274 | 161 | 21 | 291 | 2913 | |||||
| Firview Close, Marlow | Thames | FL | DEF | A | 185 | 77 | 18 | 850 | 952 | 15 | ||||
| Banbury FAS | Thames | FL | DEF | A | 2886 | 319 | 18 | 1745 | 5049 | 6480 | ||||
| Cobbins Brook FAS | Thames | FL | DEF | A | 1047 | 430 | 16 | 790 | 3400 | 100 | ||||
| Silk Stream FAS | Thames | FL | CM | A | 6295 | 1671 | 16 | 78 | 18 | 13 | 10 | |||
| Colnbrook & Poyle FAS | Thames | FL | DEF | A | 1416 | 18 | 15 | 4 | 4 | |||||
| Hunton Bridge Culvert | Thames | FL | CM | A | 131 | 323 | 13 | 10 | ||||||
| Pound Lane Marlow | Thames | FL | DEF | A | 219 | 130 | 13 | 405 | 601 | |||||
| Shepperton Weir B | Thames | FL | CM | A | 3867 | 2360 | 8 | 21 | ||||||
| R Lee Hardmead & Stansted Sluices; H&S | Thames | FL | CM | A | 329181 | 402 | 10 | |||||||
| Osterley Park Trash Boom; H&S | Thames | FL | CM | A | 84 | 395 | 100 | |||||||
| West Drayton Mill and Frays Spillway; H&S | Thames | FL | CM | A | 30 | 175 | 10 | |||||||
| Mimmshall Brook D & C | Thames | FL | DEF | A | 1994 | 126 | String Table Error | 2 | ||||||
| Jubilee Riv Strande Lane Remed Wks | Thames | FL | CM | A | 306 | 100 | String Table Error | 662 | 6 | |||||
| Taplow Mill Leat | Thames | FL | DEF | A | 851 | String Table Error | 6 | |||||||
| St Catherine's Weir Reconstruction; H&S | Thames | FL | CM | A | 30 | 48 | String Table Error | 360 | ||||||
| Markyate FAS | Thames | FL | DEF | A | 4 | 6 | String Table Error | 6 | ||||||
| SCHEMES WITH FULL APPROVAL, AS SHOWN IN MEDIUM TERM PLAN SUBMISSIONS SEPTEMBER 2007. | |||||||||
| Anglian IDB | Previous Years | 2008/09 | 2009/10 | 2010/11 | 2011/12 | ||||
| Project Name | Authority Name | Coastal Erosion (CE) or Flooding (FL)? | Funding Code | Approval Status | Spend to Date (£000s) | Year 0 Allocation (£000s) | Year 1 (£000s) | Year 2 (£000s) | Year 3 (£000s) |
| Committed Schemes | |||||||||
| Strategic Improvement Scheme - St. Germans pumping station replacement | Middle Level Commissioners | FL | DEF | A | 20,050 | 10,220 | 6,397 | 1,045 | |
| SCHEMES WITH FULL APPROVAL, AS SHOWN IN MEDIUM TERM PLAN SUBMISSIONS SEPTEMBER 2007. | |||||||||
| Anglian LA Flooding | Previous Years | 2008/09 | 2009/10 | 2010/11 | 2011/12 | ||||
| Project Name | Authority Name | Coastal Erosion (CE) or Flooding (FL)? | Funding Code | Approval Status | Spend to Date (£000s) | Year 0 Allocation (£000s) | Year 1 (£000s) | Year 2 (£000s) | Year 3 (£000s) |
| Committed Schemes | |||||||||
| Southend FD Improvements, Pier to Lynton Rd | Southend on Sea BC | FL | DEF | A | 66 | 20 | 20 | ||
| SCHEMES WITH FULL APPROVAL, AS SHOWN IN MEDIUM TERM PLAN SUBMISSIONS SEPTEMBER 2007. | |||||||||
| North West LA flooding | Previous Years | 2008/09 | 2009/10 | 2010/11 | 2011/12 | ||||
| Project Name | Authority Name | Coastal Erosion (CE) or Flooding (FL)? | Funding Code | Approval Status | Spend to Date (£000s) | Year 0 Allocation (£000s) | Year 1 (£000s) | Year 2 (£000s) | Year 3 (£000s) |
| Committed Schemes | |||||||||
| Stock Beck FAS | S Lakeland | 0 | DEF | A | 3,631 | 31 | |||
| SCHEMES WITH FULL APPROVAL, AS SHOWN IN MEDIUM TERM PLAN SUBMISSIONS SEPTEMBER 2007. | |||||||||
| Wessex LA flooding | Previous Years | 2008/09 | 2009/10 | 2010/11 | 2011/12 | ||||
| Project Name | Authority Name | Coastal Erosion (CE) or Flooding (FL)? | Funding Code | Approval Status | Spend to Date (£000s) | Year 0 Allocation (£000s) | Year 1 (£000s) | Year 2 (£000s) | Year 3 (£000s) |
| Committed Schemes | |||||||||
| Weston-super-Mare Sea Defences | North Somerset Council | FL | DEF | A | 4,457 | 12,000 | 11,092 | ||
| SCHEMES WITH FULL APPROVAL, AS SHOWN IN MEDIUM TERM PLAN SUBMISSIONS SEPTEMBER 2007. | |||||||||
| Wales LA flooding | Previous Years | 2008/09 | 2009/10 | 2010/11 | 2011/12 | ||||
| Project Name | Authority Name | Coastal Erosion (CE) or Flooding (FL)? | Funding Code | Approval Status | Spend to Date (£000s) | Year 0 Allocation (£000s) | Year 1 (£000s) | Year 2 (£000s) | Year 3 (£000s) |
| Committed Schemes | |||||||||
| Ross on Wye FAS | Herefordshire Council | FL | DEF | A | 5,293 | 1,671 | 83 |
| SCHEMES WITH FULL APPROVAL, AS SHOWN IN MEDIUM TERM PLAN SUBMISSIONS SEPTEMBER 2007. | |||||||||
| North East LA Coastal Erosion | Previous Years | 2008/09 | 2009/10 | 2010/11 | 2011/12 | ||||
| Project Name | Authority Name | Coastal Erosion (CE) or Flooding (FL)? | Funding Code | Approval Status | Spend to Date (£000s) | Year 0 Allocation (£000s) | Year 1 (£000s) | Year 2 (£000s) | Year 3 (£000s) |
| Committed Schemes | |||||||||
| Newbiggin Bay Beach Recharge/Breakwater | Wansbeck DC | CE | DEF | A | 10,081 | 25 | 20 | 20 | 20 |
| Blyth South Beach Management Scheme | Blyth Valley DC | CE | DEF | A | 44 | 16 | 0 | 0 | 0 |
| SCHEMES WITH FULL APPROVAL, AS SHOWN IN MEDIUM TERM PLAN SUBMISSIONS SEPTEMBER 2007. | |||||||||
| North West LA Coastal Erosion | Previous Years | 2008/09 | 2009/10 | 2010/11 | 2011/12 | ||||
| Project Name | Authority Name | Coastal Erosion (CE) or Flooding (FL)? | Funding Code | Approval Status | Spend to Date (£000s) | Year 0 Allocation (£000s) | Year 1 (£000s) | Year 2 (£000s) | Year 3 (£000s) |
| Committed Schemes | |||||||||
| Central Area Detailed Design and Construction | Blackpool BC | CE | DEF | A | 39,550 | 14,610 | 7,970 | 0 | 0 |
| SCHEMES WITH FULL APPROVAL, AS SHOWN IN MEDIUM TERM PLAN SUBMISSIONS SEPTEMBER 2007. | |||||||||
| Wessex LA Coastal Erosion | Previous Years | 2008/09 | 2009/10 | 2010/11 | 2011/12 | ||||
| Project Name | Authority Name | Coastal Erosion (CE) or Flooding (FL)? | Funding Code | Approval Status | Spend to Date (£000s) | Year 0 Allocation (£000s) | Year 1 (£000s) | Year 2 (£000s) | Year 3 (£000s) |
| Committed Schemes | |||||||||
| BIS4 - Beach Improvement Scheme Stage 4 | Bournemouth BC | CE | CM | A | 8,970 | 994 | 1,037 | 20 | 0 |
| Poole Frontage Management Plan | Borough of Poole | CE | CM | A | 1,889 | 625 | 1,250 | 1,000 | 375 |
| SCHEMES WITH FULL APPROVAL, AS SHOWN IN MEDIUM TERM PLAN SUBMISSIONS SEPTEMBER 2007. | |||||||||
| Southern LA Coastal Erosion | Previous Years | 2008/09 | 2009/10 | 2010/11 | 2011/12 | ||||
| Project Name | Authority Name | Coastal Erosion (CE) or Flooding (FL)? | Funding Code | Approval Status | Spend to Date (£000s) | Year 0 Allocation (£000s) | Year 1 (£000s) | Year 2 (£000s) | Year 3 (£000s) |
| Committed Schemes | |||||||||
| Brighton Marina To Ovingdean Coast Protection Scheme | Brighton & Hove City C | CE | CM | A | 15,424 | 786 | 0 | 0 | 0 |
| Walmer, Kingsdown & Oldstairs Bay Beach Management Works 2007/08 | Dover DC | CE | CM | A | 1,642 | 121 | 0 | 0 | 0 |